Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

B.O.Q Serapion

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

PROJECT RENOVATION

LOCATION BLK 32 LOT 34 SOUTHRIDGE VILLAS PUROK 2 BRGY. SAN LUCAS LIPA CITY BATANGAS
OWNER LORETO E. SERAPION
SUBJECT: BILL OF QUANTITIES
ITEM NO. Particular/ Description QTY UNIT Materials Labor Cost Total
Unit Cost Amount Unit Cost Amount Unit Cost Amount
I GENERAL REQUIREMENTS
Mobilization/ Demobilization included

Sub-Total -
II SITE WORKS
2.1 Site Preparation
Survey Lay out included
2.2 Eathworks
Excavation and Trimming 8.40 - 120.00 1,008.00 120.00 1,008.00
2.3 Gravel Bedding
50mm gravel bed 1.30 1,100.00 1,429.45 100.00 129.95 1,200.00 1,559.40
Sub-Total 1,429.45 1,137.95 2,567.40
III CONCRETE WORKS
3,1 Formworks
Column 55.44 sq.m 270.00 14,968.80 130.00 7,207.20 400.00 22,176.00
BEAMS 30.78 sq.m 270.00 8,310.60 130.00 4,001.40 400.00 12,312.00
SLAB 19.00 sq.m 271.00 5,149.00 130.00 2,470.00 401.00 7,619.00
3.2 Reinforcing Bars
Footing & Wall footing 117.00 kg 40.00 4,680.00 7.00 819.00 47.00 5,499.00
Column 306.25 kg 40.00 12,249.84 7.00 2,143.72 47.00 14,393.56
Beams 1,630.78 kg 40.00 65,231.20 7.00 11,415.46 47.00 76,646.66
Slab on Grade 160.00 kg 40.00 6,400.00 7.00 1,120.00 47.00 7,520.00
.3.3 Concrete(psi)
Footing & Wall footing 3.72 cu.m 2,900.00 10,788.00 150.00 558.00 3,050.00 11,346.00
Column 2.89 cu.m 2,900.00 8,373.75 150.00 433.13 3,050.00 8,806.88
Beams 1.94 cu.m 2,900.00 5,637.60 150.00 291.60 3,050.00 5,929.20
Slab 4.40 cu.m 2,900.00 12,771.60 150.00 660.60 3,050.00 13,432.20
Sub-Total 154,560.39 31,120.11 185,680.50
IV MASONRY WORKS
4.1 CHB Laying
4" laying 74.00 sq.m 250.00 18,500.00 120.00 8,880.00 370.00 27,380.00
4.2 Plastering Works
Plastering 148.00 sq.m 75.00 11,100.00 120.00 17,760.00 195.00 28,860.00
Sub-Total 29,600.00 26,640.00 56,240.00
V METAL WORKS
5.1 Roof Framing
2"X2" x6m TUBULAR 8.00 pcs 850.00 6,800.00 500.00 4,000.00 1,350.00 10,800.00
2"x3"x12mm Thk C-Purlins 30.00 pcs 450.00 13,500.00 150.00 4,500.00 600.00 18,000.00
METAL GATE 1.00 lot 1,000.00 1,000.00 500.00 500.00 1,500.00 1,500.00
Other Consumables ( Welding Rod,. Etc.) 1.00 lot 6,000.00 6,000.00 250.00 250.00 6,250.00 6,250.00
Sub-Total 27,300.00 9,250.00 36,550.00
VI ROOFING WORKS
6.3 Roofing
Roofing Sheet GA#24 including Bended Items 5.00 sq.m 400.00 2,000.00 50.00 250.00 450.00 2,250.00
Other Accessories to complete
Others( insulation tape, Sealant,Tex Screw,
1.00
etc.) unit 6,000.00 6,000.00 250.00 250.00 6,250.00 6,250.00
Sub-Total 8,000.00 500.00 8,500.00
VII TILE WORKS
7.1 BEDROOM TILES, T&B, BALCONY 48.78 sq.m 1,000.00 48,782.50 200.00 9,756.50 1,200.00 58,539.00
Sub-Total 48,782.50 9,756.50 58,539.00
VIII Painting Works
8.1 EXTERIOR 148.00 sq.m 100.00 14,800.00 50.00 7,400.00 150.00 22,200.00
Sub-Total 14,800.00 7,400.00 22,200.00
IX DOORS AND WINDOWS
9.1 DOORS 8.00 set/s 1,500.00 12,000.00 500.00 4,000.00 2,000.00 16,000.00

Sub-Total 12,000.00 4,000.00 16,000.00


TOTAL AMOUNT 296,472.34 89,804.56 386,276.90

PREPARED BY:
0.23
ENGR. BRYAN P MAGLOYUAN
CIVIL ENGINEER

You might also like