Intern Report and Project
Intern Report and Project
POWER STREAM
INTERNSHIP REPORT
Name Of Students Id No
1. Woldemariam 1302399
Esuneh
1102410
2. Assaye gedif
3. Degisra 1011268
simachew
Name of mentors
1. Mr.alebachew k
2. Mr.marsilas
3. Mr.abdulkerim
DECLARATION
We declare that this Internship Report entitled “INTERNSHIP
REPORT IN DANGILA SUBSTATION.” is an original work of us
and also that submitted to Bahirdar University Institute of
Technology, Faculity of Electrical and Computer Engineering.
This internship report includes all requirements of internship
program. To accomplish this report, we have referred manuals,
different related books, EEP report papers, to have important
information on what we have done in our internship period.
ii
Bahirdar instute of technology
ACKNOWLEDGMENTS
First, we would like to thank our Almighty God for giving us strength
to accomplish our internship period and prepare our internship report
very well. In addition, we would like to thank Bahirdar University
Institute of technology for giving this chance to realize, understand
and upgrade our practical knowledge. Secondly, we would like to
thank the hosting company advisor Mr.Giwon and the substation
technicians, Mr. Siraw, Mr.fekade, Mrs. Dagnanesh, Mr. Fikremariam
and Mrs. Bizualem. Finally, we would like to thank
our academic advisors Mr.Alebachew, Mr.Marsilas,and
Mr.Abdukerim for your lovely approach for us.
iii
Bahirdar instute of technology
EXECUTIVE SUMMARY
iv
Bahirdar instute of technology
TABLE OF CONTENTS
Contents
DECLARATION................................................................................................................ 2
ACKNOWLEDGMENTS.................................................................................................. 2
EXECUTIVE SUMMARY.................................................................................................3
TABLE OF CONTENTS................................................................................................ 4
LIST OF FIGURES........................................................................................................ 7
LIST OF ACRONYMS.................................................................................................. 8
CHAPTER ONE................................................................................................................. 1
1. BACK GROUND OF THE COMPANY.................................................................1
1.1. History of the hosting company...............................................................................1
1.2. Step Up Substation.................................................................................................. 3
1.3. Step Down Substation..............................................................................................3
1.4. Vision, Mission and Objective of EEPCO............................................................... 3
1.4.1. Vision.......................................................................................................... 3
1.4.2. Mission....................................................................................................... 5
1.5. Main products or service of the substation.............................................................. 5
1.6. Main customers or the end users of its products or services....................................5
Working flow of the substation and their Diagram.........................................................8
CHAPTER TWO................................................................................................................ 9
2. OVERALL INTERNSHIP EXPERIENCE............................................................. 9
2.1. How did we get in to the company?........................................................................ 9
2.2. Work section that we have been working............................................................... 9
2.3. Objective of the Internship.................................................................................... 10
2.3.1. General Objective..................................................................................... 10
2.3.2. Specific Objective.....................................................................................10
2.4. Single line diagram of the Dangla substation........................................................ 11
2.5. Major components and their own explanations of the Danglasubstation..........13
2.5.1. Lightening arrester....................................................................................14
2.5.2. Disconecter (isolator)................................................................................15
2.5.3. Common bus bar....................................................................................... 15
2.5.4. Circuit breaker.......................................................................................... 17
Types of Circuit breaker................................................................................................17
2.5.5. Wave trap.................................................................................................. 21
v
Bahirdar instute of technology
2.5.6. Transformers............................................................................................. 22
2.5.7. Parts of power transformer....................................................................... 29
Lighting strike counter..................................................................................................41
2.6. Control Room and Protection System................................................................... 42
D.Rectifiers and Batteries............................................................................................. 45
2.7. Major Duties of the Internship...............................................................................47
2.8. Challenges we have been facing............................................................................49
2.8.1. Measures we have taken........................................................................... 49
CHAPTER THREE.......................................................................................................... 50
3. BENEFITS GAINED FROM THE INTERNSHIP............................................... 50
3.1. Improving our practical skill..................................................................................50
3.2. Upgrading our theoretical knowledge....................................................................52
3.3. Improving our interpersonal communication skills............................................... 52
3.4. Improving our team playing skill...........................................................................52
3.5. In terms of improving our leadership skills........................................................... 54
3.6. In terms of understanding work ethics related issues............................................ 54
3.7. Entrepreneurship skills.......................................................................................... 56
CHAPTER FOUR............................................................................................................ 57
4. PROJECT AND CONTRIBUTION......................................................................57
4.1. Design of Underground Cable Fault Location Detector Using Microcontroller... 57
4.2. Objective of the Project......................................................................................... 59
4.2.1. General Objective..................................................................................... 59
4.2.2. Specific Objective.....................................................................................59
4.2.3. Scope of the project.................................................................................. 59
4.2.4. Significance of the Project........................................................................59
4.2.5. Problem Statement....................................................................................59
4.3. Literature Review.................................................................................................. 59
4.3.1. Early time fault location process.............................................................. 59
4.3.2. Necessary Materials..................................................................................61
4.4. Methodology..........................................................................................................63
4.5. Block diagram and Flow chart...............................................................................64
4.5.1. Block diagram...........................................................................................64
4.5.2. Block diagram description........................................................................ 65
Algorithm..................................................................................................................68
CHAPTER FIVE.............................................................................................................. 69
5. CONCLUSION AND RECOMMENDATION..................................................... 69
vi
Bahirdar instute of technology
5.1. Conclusion............................................................................................................. 69
5.2. Recommendations for the Company..................................................................... 69
REFERENCE............................................................................................................... 72
vii
Bahirdar instute of technology
LIST OF FIGURES
Figure 1.1: working flow of the substation and their diagram.................................. 5
Figure 2.1: Single line diagram of the Dangla substation......................................... 8
Figure 2.2: Lightening arrester.................................................................................. 10
Figure 2.3: Disconecter (isolator)............................................................................. 11
Figure 2.4: Common Bus Bar................................................................................... 12
Figure 2. 5: Oil circuit breaker.................................................................................. 13
Figure 2.6: SF6 circuit breaker.................................................................................. 14
Figure 2.7: Wave trap................................................................................................ 15
Figure 2. 8: Current Transformer.............................................................................. 17
Figure 2.9: Voltage Transformer............................................................................... 18
Figure 2. 10: POWER TRANSFORMER................................................................. 20
Figure 2.11: Earth transformer.................................................................................. 21
Figure 2.12: Auxiliary transformer........................................................................... 21
Figure 2.13: Tap changer........................................................................................... 23
Figure 2.14: SILICA GEL........................................................................................ 24
Figure 2.15: CONSERVATOR.................................................................................. 25
Figure 2.16: Radiator................................................................................................ 26
Figure 2.17: Oil level indicator................................................................................. 26
Figure 2.18: Winding temperature indicators............................................................ 27
Figure 2.19: oil temperature indicator....................................................................... 27
Figure 2.20: Lighting strike counter.......................................................................... 30
Figure 2.21: Control Room and Protection System.................................................. 32
Figure 2.22: Batteries................................................................................................ 33
viii
Bahirdar instute of technology
LIST OF ACRONYMS
AC Alternating Current
CB Circuit Breaker
CT Current Transformer
DC Direct Current
DS Disconecter switch
KV Kilo Volt
LA Lighting arrestor
PT Power Transformer
VT Voltage Transformer
ix
Bahirdar instute of technology
CHAPTER ONE
Now days the electrical power demand is increasing very rapidly. For
fulfilling these huge power demands the modern time requires
creation of bigger and bigger power generating stations. These power
generating stations may be hydro – electric, thermal and so on.
Depending upon the availability of resources these stations are
constructed different places. To transmit those electric power
substations are mandatory. Now a day there are many substations in
Ethiopia, from those Dangla substation is one of them. Dangla sub-
station was established in, 1976 E.C in the north western of
Amhara region with only one transformer is which converts 66kv to
15 kv.having four outgoing lines from the substation consists 15kv
each. After 23 years at 1999 anther 66/15kv step down transformer is
added, that is connected in parallel with the first transformer, for the
purpose of increasing reliability of power demands by users. Even if.
Transformer is added the substation have 4 outgoing lines having
15kv.latter on in 2005 three winding 66/33/15kv step down
transformer was installed to increase the coverage area of substation
with increasing output from the substation having additional four
33kv outgoing lines and one 15kv line .it is one of distribution
substation which receives power from bahirdar number 2 (gordema)
substations. So it is necessary to transmit these huge power blocks
from generating station to their load centers. Power is generated
comparatively in low voltage level.. For maintaining these voltage
levels and for providing greater stability a number of transformation
and switching stations have to be created in between generating
station and consumerends [1].
1.2.Step Up Substation
1.4.2. Mission
CHAPTER TWO
2. OVERALL INTERNSHIP EXPERIENCE
Key
1. Koseber 15kv
2. Injibara universty 15kv
3. Dangla15kv
4. Durbete 15kv
5. Merawi kunzila 33kv
6. Arsegmbeha 33kv
7. Quancha kuakurta 33kv
8. Shawura 33kv
9. Adiskedam 15kv
Description for
power
transformerPT1
and PT2
Apparent power (S)
=6.3MVA 66/15kv
two winding
transformer X=for
PT1=0.2% and for
PT2=0.1%
Connection Y-delta
Grounding: delta with
earthing transformer
ONAN cooling system
PT 3
S=9.3MVA
66/33/15kv three
winding transformer
Connection Y-delta
Grounding: delta with
earthing transformer
In some designs the isolator switch has the additional ability to earth
the isolated circuit by providing additional safety..
Depending upon the position in power system, the isolators can be categorized as:
1) Bus side isolator: - the isolator is directly connected with main bus
2) Line side isolator: - the isolator is situated at line side of any feeder
Bus bars receive power from incoming circuits and deliver power to
outgoing circuits. It is made of copper bar, Aluminum tube etc. In
Dangla substation bus bar is energized from Gordema substation
(Bahir Dar), Incoming 66kv by using transmission line. Bus bars can
be used to carry phase voltage in which case they must be suitably
insulated.
the bus bar itself may be not insulated but physically mounted using
an insulating material to keep it electrically separate from its support.
As we have been learnt, there are different types of circuit breakers, such as:
But, among those oil circuit breaker, SF6 circuit breaker and vacuum
circuit breaker are found in Dangla substation.
2.5.6. Transformers
Instrument transformer
Earth transformer
Auxiliary transformer
Core
Silica gel
Winding temperature indicator
Drain valve
Winding
Conservator
Radiator
Buchholz Relay
Bushing
A. Tap changer
This part of the transformer contains the assembly of the core and the
winding which is immersed in the insulation oil. It has usually
cylindrical or cubical shape dependingon transformer construction.
C. Core
Core is used to support the windings in the transformer. It also
provides a lowreluctance path to the flow of magnetic flux. It is made
up of laminated soft iron core in order to reduce eddy current loss and
Hysteresis loss.
Cores are usually circular or rectangular in shape; Diameter of the
transformer core is directly proportional to core and copper loss. If
diameter of the core is decreased, the weight of the steel in the core is
reduced which leads to less core loss of transformer and the copper
loss becomes decrease. The vice versa happen when the diameter is
increased.
D.Winding
Single phase transformer has one primary and one secondary winding.
But three- phase transformer consists of three primary and three
secondary windings which connects to each other with proper
methods. Low voltage winding is always placed inner side of core.
E.Silica gel
Silica gel breather always comes as loose item. The plastic plug
sealing on the top of the breather should be removed and fitted to the
associated pipe work. The oil cup at the bottom of the breather should
be removed, filled with transformer oil to the level indicated on it and
then re fitted to the position. Thus, the silica gel is prevented from
absorbing moisture from atmosphere. When the oil becomes
depreciate the silica gel color becomes change from pink to the blue
this indicates the oil should be changed and silica gel itself changed
in to new.
.
Figure 2.15: conservator
G .radiator
It is used to show the oil level in the transformer inside the conservator.
K. Drain valve
This valve is used for taking damaged oil from the oil tank for the
proper oil collection; this valve is situated under the oil tank.
L. Buchholz Relay
the pickup current Ip, then the relay operates (or trips) after a small-
time delay.
Differential Relay: Is a current operated relay that responds to the
difference betweentwo or more current above a set value. Differential
relays are commonly used for protecting generators, buses, and
transformers [4].
Lighting strike counter
We tried to relate by studying some references and asking any other coordinator
which has better experience and knowledge.
We tried to communicate all public relation officers but they couldn’t give us well
organized data. And delaying our monthly fee was unsolved.
CHAPTER THREE
Theoretical knowledge
Leadership skills
Entrepreneurship
Confidence
Effective communication
The ability to lead the workers
Punctuality and effective time management
Accountability to a given task
Punctuality
Discipline
Reliability
Honest
Cooperation
3.1.Entrepreneurship skills
Entrepreneurship is the ability and capability of someone to create
new or modified works or technologies that can add new thing for the
present. Entrepreneurship is a basis for improving the social and
economic capability of the country. Among them some are over the
internship semester we have gained the following skills under this
circumstance.
CHAPTER FOUR
4. PROJECT AND CONTRIBUTION
4.1.Design of Underground Cable Fault Location Detector Using
Microcontroller
4.1.1. Introduction
The core purpose of the electric transmission system is to move electric power from
the generating unit to different load centers. Now a day it becomes a common
method to use underground cables system instead of overhead lines especially in
urban areas, because underground cables are not affected by any adverse weather
condition such as storm, snow, heavy rainfall as well as pollution. But when the fault
occurs in underground cable it is difficult to detect the exact location of the fault for
the process of repairing that particular cable, because the entire cable should be taken
out from the ground to check and fix faults
This project uses the simple concept of Ohm’s law. When any fault like short circuit
occurs, voltage drop will vary depending on the length of fault in cable, since the
current varies. In case of fault, the voltage across series resistors changes accordingly,
which is then fed to an ADC to develop precise digital data to a programmed
microcontroller that further displays fault location in distance. The fault occurring at
what distance is shown on LCD which is interfaced with the microcontroller that is
used to make the necessary calculations.
In the underground cables basically two types of faults arise, first is open circuit
fault. These types of faults occur due to the breaking of conductor, cracks or disjoints
of conductor completely. In open circuit fault there is no current because there no
conducting complete loop for current flowing that is I=0. In this fault supply voltage
is equal to the output voltage. Short circuit fault is of two types one is symmetrical
fault and other is unsymmetrical fault. The symmetrical fault occurs due to the short
circuit of all three phase together whereas unsymmetrical fault occurs due to the short
circuit of any one phase or two phases together out of three phases.
this many problems are in counted including the damage of underground cable,
allocating extra budgets and outage ofpower for a long time.
4.2.7. Necessary Materials
1. Transformer: A transformer is static device which transfer electrical energy from
one circuit to other circuit with change in voltage or current without change in
frequency. In this project step-down transformer is used. Usually, DC voltages are
required to operate various electronic equipment and these voltages cannot be
obtained directly. Thus, the AC input at the mains supply is need to be stepped-down
to the required voltage level, and this task is accomplished by a step- down
transformer.
2. Switches: To induce faults manually in the kit, fault switches are used. About 12
fault switches are used which are arranged in three rows with each row having 4
switches. The 3 rows represent the 3 phases namely R, Y and B. The fault switches
have 2 positions-No fault position (NF) and fault position (F).
3. ADC (Analog to digital convertor): which receives input from the current
sensing circuit, converts this voltage into digital signal and feeds the microcontroller
with the signal.
4. Microcontroller: the microcontroller is the flash type reprogrammable
microcontroller in which we can program it with our objectives. It forms part of the
controlling unit and makes necessary calculations regarding the distance of the fault.
5. Relays: which is sensing device which senses the fault &send a trip signal to
circuit breaker to isolate the faulty section. A relay is automatic device by means of
which an electrical circuit is indirectly controlled & is governed by change in the
same or another electrical circuit.
6. LCD (Liquid Crystal Display) screen: is an electronic display module and find a
wide range of applications. LCD display interfaced to the microcontroller which
shows the status of the cable of each phase and the distance of the cable at the
particular phase, in case of any fault. A 16x2 LCD display (it can display 16
characters per line and there are 2 such lines) is used in this project.
4.3.Methodology
This project is proposed with four parts: DC power supply part, cable part, controlling
part, display part. DC power supply part consist of ac supply is step-down transformer,
bridge - rectifier converts ac signal to dc & regulator is used to produce constant dc
voltage. The cable part is denoted by set of resistors along with switches. Current
sensing part of cable representedas set of resistors &switches are used as fault creators
to indicate the fault at each location. This part senses the change in current by sensing
the voltage drop. Next is controlling part which consist of analog to digital convertor
which receives input from the current sensing circuit, converts this voltage into digital
signal and feeds the microcontroller with the signal. The microcontroller also forms
part of the controlling unit and makes necessary calculations regarding the distance of
the fault. The display part consists of the LCD display interfaced to the microcontroller
which shows the status of the cable of each phase and the distance of the cable at the
particular phase, in case of any fault. So, in this project I pass through many
procedures as listed below in order to develop and comprise varies component for
whole design completion of this task.
Step 1: Firstly, necessary data, such as the environments in which this type of fault
normally occurred, duration of the fault, effect of the fault on different sectors and the
loss of the company
, needs to be collected and have a deep study about
the project.Step 2: Select appropriate components
Step 3: Then make a model which shows the application of
the circuit.Step 4: After that assemble all the components to
make a circuit.
Step 4: Develop and simulate code program
Step 5: finally, Conclude about the project based on the result of the test
any of the switches, they impose conditions like line to ground, line to line and line to
line to line fault as per the switch operation. As a result of the fault, there is a change
in voltage value. This voltage value measured across the resistance is fed to the ADC.
The converting unit is a microcontroller that include analog to digital converter for
converting analog signal of sensing unit and converting it into digital form for
operating of microcontroller. The microcontroller does the processing for estimating
the exact point at which fault occurs. It also operates rely for protecting the system
from the effects of fault and provide protection to each phase. In the end, the
displaying unit associated with microcontroller is used for determining the distance of
fault in the underground cable and also the type of fault by
Algorithm
CHAPTER FIVE
5. CONCLUSION AND RECOMMENDATION
5.1.Conclusion
The internship program has been a helpful experience in exposing us
to the real engineering work. Internship provides many benefits not
only for interns, but also for hosting companies. Since the interns
could be parts of the employment, they could be an additional man
power. It can also be an exciting event to put theoretical knowledge
into practice. It had ups and downs but at the end it left us with
knowledge. And also the role of the internship in introducing students
with practical work experience and other personal and professional
skills provided that it is perceived and run in the right way both by
the university and the hosting company. In our internship at EEP that
we spent four months, we have got so many practical experiences and
knowledge’s as well as we meet a good person.
The company has no reference book which gives the full information
about the background of substation (company).
the company the earthing transformers that gards (protects) the two
power transformers (66/15kv) is not functional, hence we
recommend the company should maintain or installed new earthing
transformer In.
REFERENCE
[1] Dangla substation manual how to operate and the working
principles ofequipment’s.
[2] http://www.eepco.gov.et.com
[3] Walter A. Elmore. Protective Relaying Theory& Applications.
[4] Theraja “A Text Book of Electrical Technology “, volume1, 2, 3.
[5] Guile, A; Paterson (1977). Electrical power systems, volume I. Pergamon
p.331