Grid Compliance Study-Saudi Grid Code - Part 1
Grid Compliance Study-Saudi Grid Code - Part 1
Grid Compliance Study-Saudi Grid Code - Part 1
Agenda:-
We have taken Saudi grid code
What we are going to talking about is grid code compliance
What is the grid code
Why grid code
Why specific may be grid code give some detailed
objective and scope of these grid code
How to implement it and how to enforce it
Grid cannot be implemented without enforcement
1.)Objective of Independent power producer(Renewables):-
Objective of independent power producer is to increase the
generation so that he can make revenue
If you are asking independent power producer, to maintain
the harmonics he will not be happy,
If you want to maintain certain what say fluctuation(Ramp
up/Ramp down) and LVRT, but he will not be happy
because it will increases the cost
pg. 1 subbiahkannan
https://www.linkedin.com/in/subbiah-kannan-500148a0/
2.)Then why grid code is needed?
If you allow all the independent power producer to produce
the power at their will & with whatever the impact, the grid
is not study then grid is not going to be stable
Like that’s the reason why we made the grid code
Whenever there is the new source or demand which comes
to the grid & which makes impact on the grid
We need to study the impact of new addition or
modification these should not add harmful to the existing
grid and operations
These is the reason why we have the grid code
pg. 3 subbiahkannan
https://www.linkedin.com/in/subbiah-kannan-500148a0/
4.)What is the grid connection procedure
It means if you want to connect with the grid, what are the
procedures you need to do
5.)What is the grid connection procedure in US?
How many of known worked in the US market.
If you are worked in the US market
In US, you need a grid connection.
You need to fill in & submit the application form there will
be mention some details.
Then these grid connections request is go in queue
They will be evaluated and give approval these preliminary
these one and ask some additional information for the next
level
pg. 4 subbiahkannan
https://www.linkedin.com/in/subbiah-kannan-500148a0/
If the project is matured, then they go with some other
additional information or stuffs
So, what is the procedures for grid connection & what is
the grid impact study which we need to do
Let’s explore what is the grid impact study,
6.)What is TSP?
pg. 5 subbiahkannan
https://www.linkedin.com/in/subbiah-kannan-500148a0/
In Saudi Arabian grid code(Feb 2022), Statement:2.3.2.1
“The TSP shall develop and maintain a set of required technical
planning studies for evaluating the impact on the Grid of any
proposed Connection or modification to an existing
Connection.”
pg. 6 subbiahkannan
https://www.linkedin.com/in/subbiah-kannan-500148a0/
It is the responsibility of the regulating authority of
transmission network
“To study the impact of proposed connection or modification
connection on grid”
Which means that these document
If you are connecting new solar plant, new wind farm, new
thermal plant, even may be connecting the steel industry
What are the studies which you need to perform it is the
responsibility of transmission system provider, to have the
clear-cut guidelines what needs to be done
Providing this open document so that person who want to
connect with transmission system should follow all these
transmission protocol that’s why it is very open
7.)Grid code is applicable for which consumers?
It is applicable for consumer not really your home, but it
will be applicable for large scale consumer
For ex:-
I am constructing large scale steel industry.
I am connecting the traction substation
I am connecting to the grid to be need these
I am not connect the steel industry which has an
arc furnace which injects the heavy harmonics
to the system without grid impact study like I
cannot directly connect the steel industry to the
grid
pg. 7 subbiahkannan
https://www.linkedin.com/in/subbiah-kannan-500148a0/
It is applicable to the consumersyes, it is applicable to
the consumer
It is applicable to the sourcesyes, it is applicable to the
sources
8.)Question like it is the individual customer like individual
home to obey the Grid code?
pg. 8 subbiahkannan
https://www.linkedin.com/in/subbiah-kannan-500148a0/
Probably the commercial consumer
pg. 9 subbiahkannan
https://www.linkedin.com/in/subbiah-kannan-500148a0/
9.)Grid code is applicable for islanding?
pg. 10 subbiahkannan
https://www.linkedin.com/in/subbiah-kannan-500148a0/
Probably, the islanded system in Australia2500MW
capacity
Do you think that requirement will same.
Not why?
Probably these 500MW (or) 0.5GW is added in Indian grid
hardly anything when you compared to the existing 400GW
installed capacity
But probably means when 2500MW you are adding
500MW solar, then it is 20%
What I mean by that?
So, your studies varies depend upon
What is the existing system?
What is the capacity of proposed equipment?
It is going to remain same. Obsoletely not
By the time 2006, we model the wind turbine generator as
negative load without any inertia without any LVRT studies
& probably all the power evacuation study is done which is
approval
By the time in India, renewable installed capacity is
nothing but in today India has more than 27% of installed
capacity from renewables which is intermediate in nature.
Shall I apply the same Grid code which I have applied
during 2006 to 2022,Definitely not
what I mean Grid code compliance study ever evolving
requirements
pg. 11 subbiahkannan
https://www.linkedin.com/in/subbiah-kannan-500148a0/
This is reason why Transmission system operators(TSO)
also upgrade on the daily basis
LVRT was not the requirement for wind warms before
2006 - 2007 that’s why the wind turbine Type-1 and Wind
Turbine Type-2 is quite popular in India
“But after that LVRT is made mandatory thanks to blackout of
electricity somewhere in the world”
11.)What is LVRT?
pg. 12 subbiahkannan
https://www.linkedin.com/in/subbiah-kannan-500148a0/
Loss of generation had not been an issue when the wind
power generation was small, but due to significant growth
of wind power the sudden loss of generation may lead to
the risk of instability in grid.
Since LVRT is one of the most demanding and stringent
grid codes imposed on renewable power generation
It receives a major focus in the field of renewable energy
research
pg. 14 subbiahkannan
https://www.linkedin.com/in/subbiah-kannan-500148a0/
It is the responsibility of TSP which of the planning study
not all the study which is described in 3.3.6 that’s the
reason why I am telling
For example:
somebody connecting 10MW solarWhat are the studies
needed
If you are connecting 100MW solarThe studies may
different
If you are connecting 1000MW solarThe studies may
different
List out all the studies
Based on the capacity
Based on the voltage level
Based on the short circuit level
Based on the strength
Based on the inertia available
“Based on what is the complication of technology to come”
Probably specify what are the studies you need to do
Even today India, 15% of wind farm installed in 2000 are
operating without LVRT
“Thanks to the technology”
Type-3 and Type-4 wind turbines, recent technology of
wind turbines are come with the LVRT
pg. 15 subbiahkannan
https://www.linkedin.com/in/subbiah-kannan-500148a0/
15.)What is Duck curve?
“When you keep adding the solar then there is the famous
word called “Duck Curve”
The Duck Curve refers to a graphical representation of
electricity demand from the grid on days when renewable
energy (especially solar energy) production is high and
demand in the grid is low.
When plotted on a graph the lines and curves form a
distinctly duck-like shape.
Duck curve represents the potential for power system
instability, as the grid attempts to cope with extreme
changes in demand across different parts of the day.
As more solar energy is exported to the grid, usually across
the middle part of the day when the sun is shining, the
curves deepen.
Then, as the sun sets and solar energy is no longer being
generated, the Duck Curve typically shows extreme
changes in demand and the grid needs to ‘kick in’ suddenly
which can be difficult.
These extreme changes in demand can result in the energy
system becoming unstable.
pg. 16 subbiahkannan
https://www.linkedin.com/in/subbiah-kannan-500148a0/
16.)Explain the Duck curve with the graph
pg. 17 subbiahkannan
https://www.linkedin.com/in/subbiah-kannan-500148a0/
17.)Whether power system study is need for smaller power
plant?
It is not necessary to do all the power system studies which
listed out in section:3.3.6 for the smaller capacity of power
plant or when it is connected to the stronger grid
For Example:-
300MW solar/wind plant is connected to the stronger grid
of 400kV system which has the short circuit current of 35-
40kA it is completely different.
The same 300MW solar/wind plant is connected to the
weaker grid of 220kV system which has the short circuit
current of 3kA-4kA is different
18.) When you need to conduct more extensive planning study?
In Saudi Arabian grid code(Feb 2022), Statement:2.3.2.3
“Based on the magnitude and complexity of the
proposed user development, the TSP may need to
conduct more extensive planning studies. In such a case,
the TSP will indicate in its offer of connection this
requirement”
In the above sentence,
The magnitude is obviously important and magnitude alone
important may not be 500MW wind farm,
type-3 might be completely different of
500MW wind farm
type-4 with respect to the power quality
pg. 18 subbiahkannan
https://www.linkedin.com/in/subbiah-kannan-500148a0/
Type-4 wind farm have the different harmonics level
Type-3 wind farm have the different harmonics level
Based on the magnitude
Capacity of 300MW & 500MW or 750MW
Based on the complexity
When I say what is the technology what it is used when
proposed development of the user
“TSP may need to conduct more extensive planning studies”
19.)In India, How TSP do the study with Individual power plant
producer(IPP) when construct a new plant(solar/wind)?
TSP will ask your model
Now a days in India quite lot of people will install/sell
Power plant controller(PPC) for solar farm and wind farm
As soon as like they are proposing power plant controller
means POSCO is asking to give me the PSSe model and
need the PSCAD models
pg. 19 subbiahkannan
https://www.linkedin.com/in/subbiah-kannan-500148a0/
So, why it is needed for TSP?
Because first IPP are not aware how you are going to
control your system
But your magnitude is heavy, and the complexity is
important & that’s impact on the grid then obviously TSP
has to get your model
IPP model their power plant mathematically to
accommodate in its overall system to perform the studies
So, this extensive planning study is not necessarily the
steady state study it could be the transient stability also
20.)Why IPP shall submit their models to TSP ?
It’s because this study shall repeat by TSP
You are studying your end IPP end, concluding that you do
not have impact to the grid and applying for the grid
connectivity
But it is just not that Transmission system provider(TSP)
shall evaluate these for many other cases
That is the real reason why TSP asking the PSSe model or
PSCAD model to performing the dynamic transient study
21.)What Saudi Transmission system provider(TSP) Grid
compliance study talks about these studies?
In Saudi Arabian grid code(Feb 2022),Statement:2.3.2.4
“The user shall indicate whether it wishes the TSP to
undertake additional planning studies. The user shall bear
the full cost of the additional planning studies, if carried out
by the TSP”
pg. 20 subbiahkannan
https://www.linkedin.com/in/subbiah-kannan-500148a0/
Probably it is the Saudi policy, but the Indian policy is
different, countries to countries to vary
In Saudi, they themselves do the study TSP
In Saudi Arabia, they will be getting everything then
they will do the studies
So, Saudi TSP will be very clear, and they will be like
studying the impact of their system to what is the
critical for on their system?
pg. 21 subbiahkannan
https://www.linkedin.com/in/subbiah-kannan-500148a0/