Location: Project: Date:: Short-Circuit Report

Download as pdf or txt
Download as pdf or txt
You are on page 1of 6

Project:

ETAP Page: 1
12.6.0H
Location: Date: 13-10-2019
Contract: SN:
Engineer: Revision: Base
Study Case: SC
Filename: TUGAS BESAR_B_4 Config.: Normal

SHORT- CIRCUIT REPORT

Fault at bus: Bus3


Nominal kV = 500.000
Voltage c Factor = 1.10 (User-Defined)

Positive & Zero Sequence Impedances


Contribution 3-Phase Fault Line-To-Ground Fault Looking into "From Bus"

From Bus To Bus %V kA % Voltage at From Bus kA Symm. rms % Impedance on 100 MVA base
ID ID From Bus Symm. rms Va Vb Vc Ia 3I0 R1 X1 R0 X0

Bus3 Total 0.00 0.083 0.00 168.75 175.78 0.006 0.006 1.45E+001 1.53E+002 6.32E+003 1.37E+002

Bus2 Bus3 46.15 0.062 99.47 99.50 100.49 0.005 0.006 1.30E+001 2.05E+002 6.32E+003 1.37E+002

Bus7 Bus3 11.83 0.011 0.56 177.37 184.49 0.001 0.000 2.23E+002 1.18E+003

Bus28 Bus3 11.83 0.011 0.56 177.37 184.49 0.001 0.000 2.23E+002 1.18E+003

Gen9 Bus2 100.00 1.073 100.00 100.00 100.00 0.088 0.107 1.21E+001 2.31E+002 1.21E+001 8.50E+001

Gen13 Bus2 100.00 1.073 100.00 100.00 100.00 0.088 0.107 1.21E+001 2.31E+002 1.21E+001 8.50E+001

U1 Bus2 100.00 0.090 100.00 100.00 100.00 0.005 0.003 6.55E+001 2.75E+003 6.55E+001 2.75E+003

Bus62 Bus7 11.83 0.000 0.56 177.37 184.49 0.000 0.000

Bus48 Bus7 22.56 0.034 1.07 177.54 184.42 0.002 0.000 1.86E+002 1.05E+003

Bus63 Bus28 11.83 0.000 0.56 177.37 184.49 0.000 0.000

Bus47 Bus28 22.56 0.034 1.07 177.54 184.42 0.002 0.000 1.86E+002 1.05E+003

3-Phase L-G L-L L-L-G


Initial Symmetrical Current (kA, rms) : 0.083 0.006 0.072 0.074
Peak Current (kA), Method C : 0.207 0.015 0.181 0.184
Breaking Current (kA, rms, symm) : 0.006 0.072 0.074
Steady State Current (kA, rms) : 0.062 0.006 0.072 0.074

# Indicates a fault current contribution from a three-winding transformer


* Indicates a zero sequence fault current contribution (3I0) from a grounded Delta- Y transformer
Project:
ETAP Page: 2
12.6.0H
Location: Date: 13-10-2019
Contract: SN:
Engineer: Revision: Base
Study Case: SC
Filename: TUGAS BESAR_B_4 Config.: Normal

Fault at bus: Bus7


Nominal kV = 150.000
Voltage c Factor = 1.10 (User-Defined)

Positive & Zero Sequence Impedances


Contribution 3-Phase Fault Line-To-Ground Fault Looking into "From Bus"

From Bus To Bus %V kA % Voltage at From Bus kA Symm. rms % Impedance on 100 MVA base
ID ID From Bus Symm. rms Va Vb Vc Ia 3I0 R1 X1 R0 X0

Bus7 Total 0.00 0.209 0.00 167.43 175.42 0.017 0.017 3.34E+001 1.81E+002 6.56E+003 2.05E+002

Bus62 Bus7 2.50 0.098 0.21 167.42 175.42 0.008 0.008 1.26E+002 3.71E+002 1.37E+004 4.52E+002

Bus48 Bus7 11.51 0.036 0.63 167.66 175.36 0.002 0.000 1.86E+002 1.05E+003

Bus3 Bus7 25.93 0.077 4.61 156.71 164.51 0.007 0.009 1.37E+000 4.97E+002 1.26E+004 3.72E+002

Bus75 Bus62 5.01 0.098 0.43 167.41 175.42 0.008 0.008 1.16E+002 3.70E+002 1.37E+004 4.49E+002

Bus128 Bus62 2.50 0.000 0.21 167.42 175.42 0.000 0.000

Mtr19 Bus48 100.00 0.002 100.00 100.00 100.00 0.000 0.000 5.99E+004 8.39E+004

Mtr20 Bus48 100.00 0.002 100.00 100.00 100.00 0.000 0.000 5.99E+004 8.39E+004

Mtr21 Bus48 100.00 0.002 100.00 100.00 100.00 0.000 0.000 5.99E+004 8.39E+004

Lump14 Bus48 100.00 0.088 100.00 100.00 100.00 0.005 0.000 4.31E+002 2.88E+003

Lump15 Bus48 100.00 0.088 100.00 100.00 100.00 0.005 0.000 4.31E+002 2.88E+003

Lump16 Bus48 100.00 0.088 100.00 100.00 100.00 0.005 0.000 4.31E+002 2.88E+003

Bus2 Bus3 57.59 0.044 94.77 94.90 95.59 0.004 0.005 1.30E+001 2.05E+002 6.32E+003 1.37E+002

Bus28 Bus3 10.02 0.020 0.85 167.40 175.42 0.002 0.003 1.15E+002 4.34E+002 1.32E+004 3.09E+002

3-Phase L-G L-L L-L-G


Initial Symmetrical Current (kA, rms) : 0.209 0.017 0.182 0.186
Peak Current (kA), Method C : 0.475 0.039 0.413 0.422
Breaking Current (kA, rms, symm) : 0.017 0.182 0.186
Steady State Current (kA, rms) : 0.139 0.017 0.182 0.186

# Indicates a fault current contribution from a three-winding transformer


* Indicates a zero sequence fault current contribution (3I0) from a grounded Delta- Y transformer
Project:
ETAP Page: 3
12.6.0H
Location: Date: 13-10-2019
Contract: SN:
Engineer: Revision: Base
Study Case: SC
Filename: TUGAS BESAR_B_4 Config.: Normal

Fault at bus: Bus41


Nominal kV = 0.400
Voltage c Factor = 1.05 (User-Defined)

Positive & Zero Sequence Impedances


Contribution 3-Phase Fault Line-To-Ground Fault Looking into "From Bus"

From Bus To Bus %V kA % Voltage at From Bus kA Symm. rms % Impedance on 100 MVA base
ID ID From Bus Symm. rms Va Vb Vc Ia 3I0 R1 X1 R0 X0

Bus41 Total 0.00 7.776 0.00 173.14 173.21 0.006 0.006 8.72E+002 1.54E+003 6.80E+006 1.18E+003

Bus42 Bus41 80.28 7.776 99.99 100.00 100.00 0.006 0.006 * 8.72E+002 1.54E+003 6.80E+006 1.18E+003

Bus40 Bus42 80.28 0.000 100.00 99.99 100.00 0.000 0.000

Bus39 Bus42 80.28 0.000 100.00 99.99 100.00 0.000 0.000

Bus43 Bus42 80.28 0.000 100.00 99.99 100.00 0.000 0.000

Bus63 Bus42 90.27 0.156 100.00 100.00 100.00 0.000 0.000 7.37E+002 2.85E+002

3-Phase L-G L-L L-L-G


Initial Symmetrical Current (kA, rms) : 7.776 0.006 6.736 6.737
Peak Current (kA), Method C : 13.190 0.010 11.426 11.428
Breaking Current (kA, rms, symm) : 0.006 6.736 6.737
Steady State Current (kA, rms) : 7.424 0.006 6.736 6.737

# Indicates a fault current contribution from a three-winding transformer


* Indicates a zero sequence fault current contribution (3I0) from a grounded Delta- Y transformer
Project:
ETAP Page: 4
12.6.0H
Location: Date: 13-10-2019
Contract: SN:
Engineer: Revision: Base
Study Case: SC
Filename: TUGAS BESAR_B_4 Config.: Normal

Fault at bus: Bus42


Nominal kV = 20.000
Voltage c Factor = 1.10 (User-Defined)

Positive & Zero Sequence Impedances


Contribution 3-Phase Fault Line-To-Ground Fault Looking into "From Bus"

From Bus To Bus %V kA % Voltage at From Bus kA Symm. rms % Impedance on 100 MVA base
ID ID From Bus Symm. rms Va Vb Vc Ia 3I0 R1 X1 R0 X0

Bus42 Total 0.00 0.785 0.00 164.63 175.53 0.090 0.090 8.47E+001 3.57E+002 9.38E+003 3.82E+002

Bus40 Bus42 0.00 0.000 101.34 95.05 100.02 0.000 0.000

Bus39 Bus42 0.00 0.000 101.34 95.05 100.02 0.000 0.000

Bus41 Bus42 0.00 0.000 101.34 95.05 100.02 0.000 0.000

Bus43 Bus42 0.00 0.000 101.34 95.05 100.02 0.000 0.000

Bus63 Bus42 50.23 0.785 30.90 141.65 150.46 0.090 0.090 8.47E+001 3.57E+002 9.38E+003 3.82E+002

Bus28 Bus63 50.64 0.054 31.06 141.64 150.47 0.006 0.006 4.29E+001 3.50E+002 1.28E+004 3.91E+002

Bus75 Bus63 50.77 0.051 31.05 141.64 150.47 0.006 0.006 9.63E+001 3.66E+002 1.34E+004 4.30E+002

3-Phase L-G L-L L-L-G


Initial Symmetrical Current (kA, rms) : 0.785 0.090 0.681 0.703
Peak Current (kA), Method C : 1.672 0.191 1.451 1.498
Breaking Current (kA, rms, symm) : 0.090 0.681 0.703
Steady State Current (kA, rms) : 0.629 0.090 0.681 0.703

# Indicates a fault current contribution from a three-winding transformer


* Indicates a zero sequence fault current contribution (3I0) from a grounded Delta- Y transformer
Project:
ETAP Page: 5
12.6.0H
Location: Date: 13-10-2019
Contract: SN:
Engineer: Revision: Base
Study Case: SC
Filename: TUGAS BESAR_B_4 Config.: Normal

Fault at bus: Bus63


Nominal kV = 150.000
Voltage c Factor = 1.10 (User-Defined)

Positive & Zero Sequence Impedances


Contribution 3-Phase Fault Line-To-Ground Fault Looking into "From Bus"

From Bus To Bus %V kA % Voltage at From Bus kA Symm. rms % Impedance on 100 MVA base
ID ID From Bus Symm. rms Va Vb Vc Ia 3I0 R1 X1 R0 X0

Bus63 Total 0.00 0.210 0.00 167.43 175.37 0.017 0.017 3.40E+001 1.80E+002 6.56E+003 2.05E+002

Bus28 Bus63 2.78 0.109 0.23 167.42 175.39 0.009 0.009 4.29E+001 3.50E+002 1.28E+004 3.91E+002

Bus75 Bus63 2.59 0.101 0.22 167.42 175.38 0.008 0.008 9.63E+001 3.66E+002 1.34E+004 4.30E+002

Bus42 Bus63 0.00 0.000 0.00 167.43 175.37 0.000 0.000

Bus47 Bus28 12.49 0.036 0.74 167.65 175.32 0.002 0.000 1.86E+002 1.05E+003

Bus3 Bus28 25.75 0.073 4.61 156.71 164.48 0.007 0.009 2.88E+001 5.20E+002 1.28E+004 3.87E+002

Bus62 Bus75 5.18 0.101 0.44 167.41 175.38 0.008 0.008 8.65E+001 3.65E+002 1.34E+004 4.27E+002

Bus68 Bus75 2.59 0.000 0.22 167.42 175.38 0.000 0.000

Bus40 Bus42 0.00 0.000 101.25 96.67 100.03 0.000 0.000

Bus39 Bus42 0.00 0.000 101.25 96.67 100.03 0.000 0.000

Bus41 Bus42 0.00 0.000 101.25 96.67 100.03 0.000 0.000

Bus43 Bus42 0.00 0.000 101.25 96.67 100.03 0.000 0.000

3-Phase L-G L-L L-L-G


Initial Symmetrical Current (kA, rms) : 0.210 0.017 0.183 0.187
Peak Current (kA), Method C : 0.471 0.039 0.409 0.419
Breaking Current (kA, rms, symm) : 0.017 0.183 0.187
Steady State Current (kA, rms) : 0.140 0.017 0.183 0.187

# Indicates a fault current contribution from a three-winding transformer


* Indicates a zero sequence fault current contribution (3I0) from a grounded Delta- Y transformer
Project:
ETAP Page: 6
12.6.0H
Location: Date: 13-10-2019
Contract: SN:
Engineer: Revision: Base
Study Case: SC
Filename: TUGAS BESAR_B_4 Config.: Normal

Fault at bus: Bus125


Nominal kV = 0.400
Voltage c Factor = 1.05 (User-Defined)

Positive & Zero Sequence Impedances


Contribution 3-Phase Fault Line-To-Ground Fault Looking into "From Bus"

From Bus To Bus %V kA % Voltage at From Bus kA Symm. rms % Impedance on 100 MVA base
ID ID From Bus Symm. rms Va Vb Vc Ia 3I0 R1 X1 R0 X0

Bus125 Total 0.00 7.776 0.00 173.14 173.21 0.006 0.006 8.72E+002 1.54E+003 6.80E+006 1.18E+003

Bus128 Bus125 80.28 7.776 99.99 100.00 100.00 0.006 0.006 * 8.72E+002 1.54E+003 6.80E+006 1.18E+003

Bus123 Bus128 80.28 0.000 100.00 99.99 100.00 0.000 0.000

Bus129 Bus128 80.28 0.000 100.00 99.99 100.00 0.000 0.000

Bus124 Bus128 80.28 0.000 100.00 99.99 100.00 0.000 0.000

Bus62 Bus128 90.27 0.156 100.00 100.00 100.00 0.000 0.000 7.37E+002 2.85E+002

3-Phase L-G L-L L-L-G


Initial Symmetrical Current (kA, rms) : 7.776 0.006 6.736 6.737
Peak Current (kA), Method C : 13.190 0.010 11.426 11.428
Breaking Current (kA, rms, symm) : 0.006 6.736 6.737
Steady State Current (kA, rms) : 7.424 0.006 6.736 6.737

# Indicates a fault current contribution from a three-winding transformer


* Indicates a zero sequence fault current contribution (3I0) from a grounded Delta- Y transformer