1.3 BSCQ-PQM Overview - Builders

Download as pdf or txt
Download as pdf or txt
You are on page 1of 19

Bonus Scheme for Construction Quality (BSCQ)

(for public building projects only)

Price Quality Method (PQM)


(for public building projects only)
Purpose of BSCQ

• Upgrade the quality of workmanship in the


construction industry

• Give direct incentive to contractors for


providing good quality work

• Ensure quality works for public building


projects

2
Scope
The scheme is applicable to:
• CW01* contract for new public building works valued
above $5m

• tenders called from 1 June 1998

• apply to local and foreign contractors

• Public projects with a combination of new building works


and other works (such as upgrading, alteration and
additions, etc.)

• Government funded projects

* BCA’s Construction Work Heads for General Building works

3
Other Scopes

• No BSCQ for novated contract but should


complete the CONQUAS assessment

• Re-tender contract still can qualify for BSCQ if


able to have a complete CONQUAS score

• Contracts with mixed CE & Bldg works can still


qualify for BSCQ

4
Information on BSCQ

5
https://www1.bca.gov.sg/buildsg/quality/bonus-scheme-for-construction-quality
Effective Contract / Tender Sum

• Effective Contract Sum is the proportion of the


contract sum for the new building works for
computation of bonus/discount

• Effective Tender Sum is the proportion of the tender


sum used for cost comparison / tender evaluation

• Effective Contract/Tender Sum includes Design fees,


Piling works, Foundation and M&E works

6
Incentives

• Bonus of 0.2% of the effective contract sum for


each CONQUAS point scored above the contract
Bonus Threshold Score (BTS)

• The bonus will be subjected to maximum of 3% of


the effective contract sum or S$2 million, whichever
is lower (no GST)

• Payable not later than 30 days after the DLP

• Merit points will also be given and can be used to


offset default points under Price Loading

7
Example of Bonus Calculation

• Effective contract sum = $120 million

• Bonus Threshold Score = 88.0 pts

• Actual CONQUAS score = 89.5 pts

• Bonus = (89.5-88) x 0.2% x $120 million


= $360,000

8 8
Disincentives

• Discount - deduction from payment

• Price Loading for future tenders as long as 3 years

• Downgrading - for 1 year

• Debarment - for 1 year

Check for updates at:


https://www1.bca.gov.sg/buildsg/quality/bonus-scheme-for-
construction-quality

9
Price Loading
• Based on the Default Points cumulated

• Tender sum will be loaded for tender


evaluation (only for BSCQ projects)

• Advantage for good contractor over


bad contractor in tendering

• A price-loading of 0.2% will be imposed


for each CONQUAS default point

Check for updates at:


www1.bca.gov.sg/buildsg/quality/bonus-scheme-for-construction-
quality

10
Example Application of Price-Loading

In the above example, based on the effective tender value, Firm C will be awarded
the tender at his tendered sum of $301.3 million, even though Firm A and B has
tendered lower actual prices of $301 million and $300 million respectively.
Instruction Manuals - BONUS SCHEME FOR CONSTRUCTION QUALITY (BSCQ) (mof.gov.sg)

11
Discount

• Discount will apply - if the project CONQUAS score is < stated


Discount Threshold Score (DTS)

• A discount of 0.2% of the effective contract sum will be applied for


each point scored below the applicable DTS.

• Discount will be subjected to a maximum of 3% of the effective


contract sum or S$2 million, whichever is lower

• Good practice to monitor interim CONQUAS score especially if the


estimated discount is large

12
Downgrading and Debarment

• If the contractor accumulates > 5 CONQUAS Default points for


the latest 5 contracts, it will be downgraded by one grade for up to
12-month period under BCA’s CRS

• Upon downgrading/ debarment, all merit and default points


accorded to the contractor will be set to zero

• Debarment (from MOF) will be recommended (by BCA) if the


contractor accumulates 10 or more default points in the latest 5
contracts.

13 13
Common Pitfalls

• Neglect quality standard for small value project


- same default points regardless of contract value

• No monitoring of status of CONQUAS score

• Management and Staff not aware of the impact of low


CONQUAS score

14
Price Quality Method (PQM)

• For construction tenders invited under CW01 & CW02 workheads that
are $3 million and above

• Safety performance is a mandatory Quality criterion

• New version in line with Construction Industry Transformation Map


(ITM) is effective from 31 Jan 2018

• Details at https://www1.bca.gov.sg/procurement/tender-stage/price-
quality-method-pqm-framework

15
Application of PQM
Agencies to define

• Price Productivity and Quality Weightage


• Range from 40:10:50 to 60:10:30 (depend on complexity)

• What are the Quality attributes


• Timeliness, Quality, Past performance, Track records, Project specific proposal, etc
• Mandatory min 15% for Safety performance

• Individual weightages

• Scoring method
• Benchmark Performance Method
• Ranking Method

16
Application of CONQUAS Score in PQM

Example:
• Agency set benchmark performance level:
3 projects achieving CONQUAS score 82 points or more within the past 3 years

• Maximum score for this quality attribute is 10 points

• Firms meeting requirements get 10 points

• Firms don’t meet requirements, get lower points or no points

17
Conclusion
• Looking forward, there will be greater emphasis on Quality

• Government will reward good quality contractors through:


• PQM – higher chances for contractors with proven high CONQUAS score projects to
secure contracts
• BSCQ – monetary reward for effort on current projects

• BCA initiatives to help the industry:


• CONQUAS training for Developers/Consultants/Builders (max 6 complimentary
places for each CONQUAS project)
• Customised CONQUAS training for Main Contractors and their Sub-contractors
• Certified QM/CONQUAS Manager Course
• Recognition Schemes – Certified QM/CONQUAS Manager and Supervisor

18