MECHANICAL WORKS
Item Description Qty Unit Rate Kshs

DRAINAGE

UPVC pipework

A 100mm heavy duty golden brown pipe 6 Lm 1500 9,000

B 100mm diameter heavy duty grey pipe 3 Lm 1500 9,000

C 50mm ditto 10 Lm 1000 10,000

D 40mm ditto 0 Lm

Extra over UPVC pipework for the


following

Bends
E 100mm diameter bend 3 No. 500 1500

F 100 mm diameter Tee 3 No. 500 1500

G 50mm diameter bend 3 No. 500 1500

H Excavate for the drainage pipe to a depth


not exceeding 500mm,backfill and cutoff 30 LM 500 15,000
excess soil.

I Excavate and cutoff excess soil manhole


size 650x650mm not exceeding 1.5m
averagely 600mm constructed using
concrete blocks and install a frame
650x450mm c/w cast iron cover of the same
size making good the surrounding
3 No 10,000 30,000

Total carried to collection page 78,500


MBQ/1

Item Description Qty Unit Rate Kshs

A BIO DIGESTER

Supply and install and commission an


onsite sewer system consisting of the
following:
a) A reinforced concrete (insitu or precast)
bio digester with a capacity of 10 cubic
meters and can handle upto 200 users
complete with all accessories as Riflo
SEPTICA System or equivalent. The system
should come with a written guarantee and
functional drawings.
1 No 100,000

b) Excavations and construction of a


soak/leech field and french drain consisting
of 600mm wide trenches with depths ont
exceeding 1000mm. 22 cm 200 4400

c) Hand packed crushed stone hardcore. 20 cm 500 10,000

d) 500 gauge polythene sheeting d.p.m laid on r


blinded hardcore with 200mm side and end 21 SM 300 6300
laps.
e) grease trap 1 No 1000 1000

Total carried to collection page 121,700


MBQ/2

SUMMMARY FOR
MECHANICALWORKS

ITEM DESCRIPTION AMOUNT Ksh.

1. Carried forward from Page MBQ1


78,500

2. Carried forward from Page MBQ2


121,700

5 TOTAL CARRIED TO SUMMARY PAGE 200,200

MBQ3
PROVISIONAL SUMS
ITEM DESCRIPTION QTY UNIT RATE AMOUNT

PROVISIONAL AND PRIME COST SUMS

A Allow a Prime Cost Sum of Kshs Fifty Thousand


(50,000.00) only for Contingencies SUM 50,000.00

TOTAL FOR PROVISIONAL AND PRIME COST


SUMS 50,000.00

PS/1
SUMMARY PAGE
GRAND SUMMARY

ITEM DESCRIPTION TENDERERS SUM


(KSHS)

1 mechanical works Provisional 200,200

50,000
2 Sums PS/1

250,200
TOTAL COST CARRIED TO MAIN SUMMARY -