Upgrade Project For H-25 Gas Turbine Generator at Yokkaichi Complex of Tosoh Corporation
Upgrade Project For H-25 Gas Turbine Generator at Yokkaichi Complex of Tosoh Corporation
Upgrade Project For H-25 Gas Turbine Generator at Yokkaichi Complex of Tosoh Corporation
Manabu Hamaguchi
Kensuke Takamori
Hideaki Horiguchi
Kento Takekoshi
Takuro Aoki
Exchanger
Exchanger
Ethylene production
Ethylene production
portion of the byproduct gases generated by
the naphtha cracking furnace is used as GT fuel,
reducing flare stack gas and decreasing input Flare stack
power.
Burner Burner Backup fuel
(byproduct gases
from other processes)
Byproduct
FDF gases
(air for combustion) Other
process
Existing
GT fuel
Exhaust heat
exchanger
Exhaust
gas Intake
Boiler power
generator
Power
company grid
EMS G
Input power
DCS (existing) H-25 GT reduction
(33 MW rated output)
FDF: forced draft fan GT: gas turbine EMS: energy management system DCS: distributed control system G: generator
104.
FEATURED ARTICLES
Work planning
GT ignition
GT materials procurement
Project processes
First project Third project Fifth project Sixth project Seventh project
meeting meeting meeting meeting meeting Project completion
Fourth project meeting
meeting
FY2017 SII Second FY2017 FY2018 SII
subsidy project acceptance subsidy FY2018 acceptance
awarded meeting inspection award inspection
The Power Generation Systems Division of Hitachi’s finalization. The engineering work was done in the
Energy Business Unit served as the project manager. following order: First, pilot engineering was done to
It organized the project team, and was responsible for organize the basic plans and specifications require-
the engineering processes, work processes, customer ment drawings for the foundation work. Next came
interaction, technologies, quality guidance, and costs. It detailed equipment design engineering, followed by
also worked closely with the Utility Solutions Division purchased item procurement engineering.
of Hitachi’s Industry & Distribution Business Unit, (2) Responding to customer comments
which handled the subsidy project. Figure 2 illustrates When creating drawings for approval, several
the processes done from the time the project order rounds of comments from the customer were received
was received, up to delivery. and applied to the drawings. When comments could
not be applied, ample explanations were provided
3. 3 repeatedly. A list of the responses made to customer
Managing the Project comments was kept, and concerns and solutions were
This section discusses the policies, risk assessment, managed along with the schedule. Several rounds of
handling, and challenges that typified the project’s follow-ups were also supplied to the customer to
advanced management activities. ensure rigorous schedule management.
(1) Engineering schedule (3) Fire Service Act compliance
When creating the engineering schedule, the pro- Since they handle hazardous materials, GT power
duction processes were devised by working backward generators in Japan must be applied for under the
from processes such as on-site work, work planning, provisions of the Fire Service Act. Several problems
and trial operation planning. The deadline for com- arose in connection with the interpretation of the
pleting drawings was used as the production start- Act, but the customer and Hitachi worked together
ing point. For drawings requiring customer approval to handle them and ultimately no time was lost in
(‘drawings for approval’), the production starting passing the inspections needed to put the equipment
point was the deadline for final approval and drawing into operation.
106.
FEATURED ARTICLES
: Signal flow
CPU: central processing unit PI/O: process input/output
*1 Energy management boosted managed power output to 7.6% of the plant total, a value
that more than satisfied the 2% requirement of the subsidy application.
108.
FEATURED ARTICLES
output achieved by energy management. The energy generated by the ethylene production process as GT
management system (EMS) used was the energy and fuel. Since these gases are tied to the energy balance
equipment management service that Hitachi has reg- within the ethylene production process, there is a risk
istered as a system for the SII energy management of an energy balance breakdown in the process that
project. The service’s main features are: will prevent optimum operation if unsuitable fuel is
(1) Central management of various equipment types used for GT power generation. To ensure that the
(2) Analysis and use of gathered data energy lost to the flare stack is properly consumed
(3) Optimum equipment operation following fore- by the GT, the energy and equipment management
casts and plans service can calculate the energy balance in the pro-
The service’s functions were used to create the opti- cess to help increase the GT’s power output. The
mum operation logic for GTs fueled by byproduct operational data obtained between February 2019
gases (see Figure 7). (when operation began) and November 2019 shows
The GT power generator installed by the project that the peak power output reduction during the
is fueled by byproduct gases. The quantities and heat managed peak power time slots*2 rose to a total of
values of the generated byproduct gases vary accord- 32 GWh, already attaining the planned value of
ing to the properties and state of the naphtha used to 24 GWh (see Figure 8).
produce the ethylene. Previously, any excess byproduct
gases generated were processed by the plant’s flare
stack. The decision to use byproduct gases as GT 6. Future Business Areas
power generator fuel was reached by using Hitachi’s
energy and equipment management service to moni- Hitachi will continue to design and supply H-25
tor the measured heat values of byproduct gases emit- series industrial GTs suitable for use as distributed
ted to the atmosphere, and setting the likelihood of power supplies to domestic and overseas custom-
the need to handle variation by considering heat value ers. The power generator supplied will be tailored to
variation and usage state variation in other processes. customer facilities and needs, with a focus on highly
Conventional GT control systems assume that the energy-saving projects like the one described here.
fuel needed to generate power will be supplied. The Hitachi is confident that these activities will help
amount of fuel consumed is the amount correspond- provide the reduction in CO2 required by the world.
ing to the target power output.
*2 The hours between 8 am and 10 pm every day in the months of January, February, March,
The project’s system uses the byproduct gases July, August, September, and December.
Gas turbine power supply quantity (MWh) Managed power output during peak time slots (MWh)
Cumulative managed power output during peak time slots (MWh)
Portion delivered
by Hitachi
Finally, Figure 9 shows the plant facility after comple- Kensuke Takamori
tion of the installation work done for the project. Thermal Power Engineering Department, Thermal
Power Division, Power Generation Systems Division,
Energy Business Unit, Hitachi, Ltd. Current work and
research: Design of basic plans for gas turbine power
7. Conclusions plants.
Hideaki Horiguchi
This article has looked at how Hitachi handled the Power Generation Control System Engineering
Department, Power Generation Control System
project management work done for a gas turbine Section, Control System Platform Division, Service &
power generator project. Hitachi will continue to Platform Business Unit, Hitachi, Ltd. Current work and
research: Design of control systems for power plants.
devise and implement effective project management
activities and supply highly reliable power genera-
Kento Takekoshi
tors that satisfy requirements in areas such as pro- Utility Solutions Department, Utility Solutions
Division, Industrial Solutions & Services Business
cesses, quality, and guaranteed performance values. Division, Industry & Distribution Business Unit,
This equipment will help save energy and improve Hitachi, Ltd. Current work and research: Consulting
for energy conservation.
customer production efficiency.
Takuro Aoki
Ethylene & Energy Production Department, Yokkaichi
Manufacturing Complex, Tosoh Corporation. Current
Authors work and research: Development of energy-saving
Manabu Hamaguchi technology in ethylene manufacturing plants.
Thermal Power Business Department, Thermal
Power Division, Power Generation Systems Division,
Energy Business Unit, Hitachi, Ltd. Current work and
research: Project management for gas turbine power
plants.
110.