Mix Design Manual
Mix Design Manual
Mix Design Manual
5. Site Laboratory 33
7. Testing Procedures 39
8. Trouble Shooting 43
12. Annexure
1.0 Introduction
Concrete is the basic engineering material used in most of the civil engineering structures.
Its popularity as basic building material in construction is because of, its economy of use,
good durability and ease with which it can be manufactured at site. The ability to mould it into
any shape and size, because of its plasticity in green stage and its subsequent hardening to
achieve strength, is particularly useful.
Concrete like other engineering materials needs to be designed for properties like strength,
durability, workability and cohesion. Concrete mix design is the science of deciding
relative proportions of ingredients of concrete, to achieve the desired properties in the
most economical way.
With advent of high-rise buildings and pre-stressed concrete, use of higher grades of
concrete is becoming more common. Even the revised IS 456-2000 advocates use of higher
grade of concrete for more severe conditions of exposure, for durability considerations.
With advent of new generation admixtures, it is possible to achieve higher grades of concrete
with high workability levels economically. Use of mineral admixtures like fly ash, slag, meta
kaolin and silica fume have revolutionised the concrete technology by increasing strength and
durability of concrete by many folds. Mix design of concrete is becoming more relevant in the
above-mentioned scenario.
However, it should be borne in mind that mix design when adopted at site should be
implemented with proper understanding and with necessary precautions.
Durocrete mix design manual is an attempt to increase the awareness among the
users, about concrete mix design. It is made with intention of serving as ready
reckoner for personnel, implementing mix design at site.
• Better strength
• Better imperviousness and durability
• Dense and homogeneous concrete
II. Economy
It is possible to save up to 15% of cement for M20 grade of concrete with the
help of concrete mix design. In fact higher the grade of concrete more are the
savings. Lower cement content also results in lower heat of hydration and hence
reduces shrinkage cracks.
Site conditions often restrict the quality and quantity of ingredient materials.
Concrete mix design offers a lot of flexibility on type of aggregates to be used in
mix design. Mix design can give an economical solution based on the available
materials if they meet the basic IS requirements. This can lead to saving in
transportation costs from longer distances.
c) Other properties:
Mix design can help us to achieve form finishes, high early strengths for early
deshuttering, concrete with better flexural strengths, concrete with pumpability
and concrete with lower densities.
Concrete is an extremely versatile building material because, it can be designed for strength
ranging from M10 (10Mpa) to M100 (100 Mpa) and workability ranging from 0 mm slump to 150
mm slump. In all these cases the basic ingredients of concrete are the same, but it is their
relative proportioning that makes the difference.
Concrete needs to be designed for certain properties in the plastic stage as well as in the
hardened stage.
The site engineer should give following information while giving material
for mix design to the mix design laboratory: -
e) What is the degree of control at site? Following factors indicate degree of control at site: -
vi. Site laboratory – whether the site will have necessary laboratory equipment like
sieves, weighing balance etc. to check material properties.
b) Initial & Final setting time of cement: The initial setting time of cement indicates
the time after which the cement paste looses its plasticity. Operations like mixing,
placing and compaction should be completed well before the initial setting time of
cement .The minimum initial setting time specified by IS 456 –2000 (Clause 5.4.1.3
page no 14 and IS 8112-1989 page 2) is 30 minute. Most of the cements produced
today give an initial set of more than 60 minutes. Beginning of hardening of cement
paste indicates the final setting of cement. The maximum limit for final setting
permitted by IS 8112: 1989 (Clause 6.3. page 2) is 600 minute. Most of the cements
produced today give a final setting of between 3 to 5 hours. Curing can be started
after final setting of cement. The initial setting and the final setting can be extended
by use of retarders in order to avoid cold joints when lead-time for placing concrete is
longer.
B. Fine Aggregates
a) Gradation of fine aggregates: The gradation of sand is given by sieve analysis. The
sieve analysis is done by passing sand through a set of standard sieves and finding
out cumulative passing percentage through each sieve. The IS 383 – 1970 -Table 4,
clause 4.3 (refer Annexure I page no 57 of Durocrete Mix Design Manual) classifies
fine aggregates in 4 zones starting from zone I representing coarse sand, to zone IV
representing the finest sand. The limits of cumulative percentage passing for each
sieve for above zones are given in table 4 of IS 383 (refer Annexure I Page 57 of
Durocrete Mix Design Manual). The fineness of sand found by sieve analysis governs
the proportion of sand in concrete .The overall fineness of sand is given by factor
called fineness modulus. Fineness Modulus is given by division of the summation of
cumulative retained fractions for standard sieves up to 150-micron sieve size by 100.
Type of Sand - FM
b) Specific gravity of fine aggregates: This is the ratio of solid density of sand
particles to the density of water. Higher the specific gravity, heavier is the sand
particles and higher is the density of concrete. Conversely a lower specific gravity of
sand will result in lower density of concrete. Specific gravity of sand is found with help
of pycnometer bottles. The specific gravity of fine aggregates found in Pune region
varies from 2.6 to 2.8.
c) Silt Content by weight: This is found by wet-sieving of sand and material passing 75
micron sieve is classified as silt. This silt affects the workability of concrete, results in
higher water/cement ratio and lower strength. The upper limit for 75-micron sieve in
case of sand is 3% by weight. This limit has however been extended to 15% in case
of crushed sand in IS 383 – 1970 Table 1. (Refer Annexure I page 59 of Durocrete
Mix Design Manual)
C. Coarse Aggregate
a) Maximum size of coarse aggregate: Maximum size of aggregate is the standard
sieve size (40mm, 25mm, 20mm, 12.5mm, 10mm) through which at least 90% of
coarse aggregate will pass.
Maximum size of aggregate affects the workability and strength of concrete. It also
influences the water demand for getting a certain workability and fine aggregate
content required for achieving a cohesive mix. For a given weight, higher the
maximum size of aggregate, lower is the surface area of coarse aggregates and vice
versa. As maximum size of coarse aggregate reduces, surface area of coarse
aggregate increases. Higher the surface area, greater is the water demand to coat
the particles and generate workability. Smaller maximum size of coarse aggregate
will require greater fine aggregate content to coat particles and maintain
cohesiveness of concrete mix. Hence 40 mm down coarse aggregate will require
much less water than 20 mm down aggregate. In other words for the same
workability, 40mm down aggregate will have lower water/cement ratio, thus higher
strength when compared to 20mm down aggregate. Because of its lower water
demand, advantage of higher maximum size of coarse aggregate can be taken to
lower the cement consumption. Maximum size of aggregate is often restricted by
clear cover and minimum distance between the reinforcement bars. Maximum size of
coarse aggregate should be 5 mm less than clear cover or minimum distance
between the reinforcement bars, so that the aggregates can pass through the
reinforcement in congested areas, to produce dense and homogenous concrete.
It is advantageous to use greater maximum size of coarse aggregate for concrete
grades up to M 35 where mortar failure is predominant. Lower water/cement ratio will
mean higher strength of mortar (which is the weakest link) and will result in higher
strength of concrete. However, for concrete grades above M40, bond failure
becomes predominant. Higher maximum size of aggregate, which will have lower
area of contact with cement mortar paste, will fail earlier because of bond failure.
Hence for higher grades of concrete (M40 and higher) it is advantageous to use
lower maximum size of aggregate to prevent bond failure.
c) Shape of coarse aggregate: Coarse aggregates can have round, angular, or irregular
shape. Rounded aggregates because of lower surface area will have lowest water
demand and also have lowest mortar paste requirement. Hence they will result in
most economical mixes for concrete grades up to M35. However, for concrete grades
of M40 and above (as in case of max size of aggregate) the possibility of bond failure
will tilt the balance in favour of angular aggregate with more surface area. Flaky and
elongated coarse aggregate particles not only increase the water demand but also
increase the tendency of segregation. Flakiness and elongation also reduce the
flexural strength of concrete. Specifications by Ministry of Surface Transport restrict
the combined flakiness and elongation to 30% by weight of coarse aggregates.
A. Water/cement ratio
B. Cement content
C. Relative proportion of fine & coarse aggregates
D. Use of admixtures
A. Water/cement ratio
Water to cement ratio (W/C ratio) is the single most important factor governing the strength
and durability of concrete. Strength of concrete depends upon W/C ratio rather than the
cement content. Abram’s law states that higher the water/cement ratio, lower is the strength
of concrete. As a thumb rule every 1% increase in quantity of water added, reduces the
strength of concrete by 5%. A water/cement ratio of only 0.38 is required for complete
hydration of cement. (Although this is the theoretical limit, water cement ratio lower than
0.38 will also increase the strength, since all the cement that is added, does not hydrate)
Water added for workability over and above this water/cement ratio of 0.38, evaporates
leaving cavities in the concrete. These cavities are in the form of thin capillaries. They
reduce the strength and durability of concrete. Hence, it is very important to control the
water/cement ratio on site. Every extra lit of water will approx. reduce the strength of
2
concrete by 2 to 3 N/mm and increase the workability by 25 mm. As stated earlier, the
water/cement ratio strongly influences the permeability of concrete and durability of
concrete. Revised IS 456-2000 has restricted the maximum water/cement ratios for
durability considerations by clause 8.2.4.1, table 5 (Refer Annexure VI page 78 of
Durocrete Mix Design Manual)
B. Cement content
Cement is the core material in concrete, which acts as a binding agent and imparts strength
to the concrete. From durability considerations cement content should not be reduced
3
below 300Kg/m for RCC. IS 456 –2000 (Refer annexure VI page 78 of Durocrete Mix
Design Manual) recommends higher cement contents for more severe conditions of
exposure of weathering agents to the concrete. It is not necessary that higher cement
content would result in higher strength. In fact latest findings show that for the same
water/cement ratio, a leaner mix will give better strength. However, this does not mean that
we can achieve higher grades of concrete by just lowering the water/cement ratio. This is
because lower water/cement ratios will mean lower water contents and result in lower
workability. In fact for achieving a given workability, a certain quantity of water will be
required. If lower water/cement ratio is to be achieved without disturbing the workability,
cement content will have to be increased. Higher cement content helps us in getting the
desired workability at a lower water/cement ratio. In most of the mix design methods, the
water contents to achieve different workability levels are given in form of empirical relations.
Water/cement ratios required to achieve target mean strengths are interpolated from
graphs given in IS 10262 Clause 3.1 and 3.2 fig 2 (Refer Annexure II page 61 of Durocrete
Mix Design Manual. The cement content is found as follows: -
3
Water required achieving required workability (Lit/m )
3
Cement content (Kg/m ) =
Water/cement ratio
Thus, we see that higher the workability of concrete, greater is cement content required
and vice versa. Also, greater the water/cement ratio, lower is the cement content required
and vice versa.
ii. Size & shape of coarse aggregates: Greater the size of coarse aggregate lesser is
the surface area and lesser is the proportion of fine aggregate required and vice
versa. Flaky aggregates have more surface area and require greater proportion of
fine aggregates to get cohesive mix. Similarly, rounded aggregate have lesser
surface area and require lesser proportion of fine aggregate to get a cohesive mix.
iii. Cement content: Leaner mixes require more proportion of fine aggregates than
richer mixes. This is because cement particles also contribute to the fines in
concrete.
D. Use of admixtures
Now days, admixtures are rightly considered as the fifth ingredient of concrete. The
admixtures can change the properties of concrete.
Commonly used admixtures are as follows:
Compatibility of plasticisers with the cement brand should be checked before use. Also
plasticiser should not be added in dry concrete mix.
Plasticizers are used for moderate increase of workability whereas super plasticizers are
used where very large increase in workability is required. Plasticizers are normally
lignosulphonated formaldehydes and are normally added in small dosages. This is
because large dosage can cause permanent retardation in concrete and adversely affect
its strength. Super plasticizers are naphthalene or melamine based formaldehyde. They
can be used in large dosages without any adverse effect on concrete. This is contrary to
ii. Retarders:
They are used for retarding (delaying) the initial setting time of concrete. This is
particularly required when longer placing times are desired as in case of ready mixed
concrete. Retarders are commonly used to prevent formation of cold joints when casting
large concrete. Retarders are normally added in lower dosages as large dosages can
cause permanent retardation in concrete. Retarders are recommended in case of hot
weather concreting to prevent early loss of slump. It is important to note that retarders
reduce early strength of concrete e.g. 1-day and 3-day strength. However, 28 days
strength is not affected.
iii. Accelerators
They are used for accelerating the initial strength of concrete. Typical accelerators
increase the 1-day (up to 50 %) and 3-days (up to 30 %) strength of concrete. Most of the
accelerators show little increase for 7 days strength. For this reason, accelerators are
commonly used in precast concrete elements for early removal of moulds. Accelerators
may not be much useful for early deshuttering where early strengths are required in
range of 5 to 7 days. This is because accelerators are expensive and their ability to
increase strengths decreases after 3-5 days. A better option for early deshuttering would
be the use of plasticizers, reducing the water/cement ratio and achieving a higher grade
of concrete. It is believed that accelerators may cause retrogression of strength after 28
days when compared with normal concrete.
These chemicals have double action of blocking capillary pores and reducing the size of
capillaries that may act as conduits for water. Most waterproofing agents have
plasticizing effect and help to reduce water/cement ratio. Lower water to cement ratio
results in smaller size of capillaries and improved imperviousness. In this respect, even
plasticizers will have reasonable water proofing ability. Waterproofing compounds may
not be alternative to membrane waterproofing because they can not rectify casting
defects, like honey combing, voids, cracks caused because of shrinkage. Actually normal
concrete, if cast properly with low water/cement ratio is impervious and waterproofing
compounds help to maintain low water to cement ratio.
They are chemicals that introduce small air bubbles of size less than 45microns in
concrete. These air bubbles disperse uniformly in concrete and work like ball bearings to
increase the workability of the concrete. Most of this entrained air is not expelled during
compaction and becomes a permanent part of concrete. This is unlike plasticizers whose
effect ceases after the setting of concrete. The entrained air has following advantages:
However, effect of air entrainment is to lower strength of concrete. Every 1% air entrained
can reduce the strength of concrete by 5 %. Effect of air entrainment on strength can be
negated by using lower water/cement ratio. This is possible because of high plastcizing
effect of air entrainment. Oleic Acid, Reetha powder, etc are the commonly used air
entraining agents. Air entraining agents are economically available and improve quality of
concrete. However, they should be used carefully where good concreting practices are
followed. 3 to 6 % air entrainment is commonly used in concrete. Higher air entrainment
may not result in increased beneficial effects.
The basic objective of concrete mix design is to find the most economical proportions
(Optimisation) to achieve the desired end results (strength, cohesion, workability, durability,
As mentioned earlier the proportioning of concrete is based on certain material properties
of cement, sand and aggregates. Concrete mix design is basically a process of taking trials
with certain proportions. Methods have been developed to arrive at these proportions in a
scientific manner. No mix design method directly gives the exact proportions that will
most economically achieve end results. These methods only serve as a base to start
and achieve the end results in the fewest possible trials.
The code of practice for mix design-IS 10262 clearly states following: -
The basic assumption made in mix design is that the compressive strength of workable
concretes, by and large, governed by the water/cement ratio. Another most convenient
relationship applicable to normal concrete is that for a given type, shape, size and grading
of aggregates, the amount of water determines its workability. However, there are various
other factors which affect the properties of concrete, for example the quality & quantity of
cement, water and aggregates; batching; transportation; placing; compaction; curing; etc.
Therefore, the specific relationships that are used in proportioning concrete mixes should
be considered only as the basis for trial, subject to modifications in the light of experience
as well as for the particular materials used at the site in each case.
Different mix design methods help us to arrive at the trial mix that will give us required
strength, workability, cohesion etc. These mix design methods have same common threads
in arriving at proportions but their method of calculation is different. Basic steps in mix
design are as follows:
We will now follow above steps and solve a mix design problem by different methods.
Illustration:
Consider a mix design for M30 grade of concrete, having moderate workability (Slump range
50mm to 75mm).
Material Properties
2
Cement 53 grade (Although, actual 28 days compressive strength = 63 N/mm )
Fine aggregate –
FM. = 3.26 (Zone I ) 600 micron passing = 32 %
Specific gravity = 2.75
Coarse aggregate
Concrete is designed for strength higher than characteristic strength as a margin for
statistical variation in results and variation in degree of control exercised at site. This
higher strength is defined as the target mean strength.
It is calculated as follows:
σ = Standard deviation
The values of σ are given in IS 10262 for fair, good and very good degree of control.
However, IS 456-2000 has given revised values of σ to be considered for mix design.
Better the degree of control lesser is the value of σ and lower is the target mean
strength. In other words, the ‘margin’ kept over characteristic strength is more for fair
degree of control to that of good degree of control.
Say for M30 grade of concrete, K=1.65 (for 5% failure) and Standard Deviation
2
σ = 5 N / mm .
Target Mean Strength = 30 + 1.65 * 5
2
= 38.25 N/mm
The relation between Target Mean Strength and water cement ratio for different cement
curves is given in IS 10262 Fig 2 (Refer Annexure II page 61 of Durocrete Mix Design
Manual
Once the cement curve is fixed, water/cement ratio required for achieving the target
mean strength can be interpolated (Refer Appendix B)
For Example
All the mix design methods follow same procedure up to this stage.
Most of the mix design methods find cement content with following formula:
3
Weight of Water per m
Water /cement ratio =
3
Weight of cement per m
3
Weight of Water per m
Weight of cement =
Water/cement ratio
3
Weight of water required per m also called as water demand.
ii. Aggregate properties: Fineness and silt content of fine aggregate, size, shape
and flakiness of coarse aggregate, type of aggregate e.g. crushed, uncrushed.
Different mix design methods give empirical relations to find the water demand
Say, we want to find water demand for 20 mm maximum size of crushed aggregate and
natural sand of zone II (F.M. = 3.0) for a slump range of 60 to 80 mm (compaction factor
= 0.9)
A. IS method
Refer annexure II (page no 61)
Water Demand =186 lit for compaction factor of 0.8
Add 3% water for incremental compaction factor of 0.1
Water demand = 186 + 5.58
= 191.58 Lit
These tables directly give aggregate to cement ratios from which cement content can
be calculated.
For zone II sand and grading no 2 and medium workability
Aggregate to cement ratio = 3.7 for water cement ratio of 0.45
Aggregate to cement ratio = 4.2 for water cement ratio of 0.50
Aggregate to cement ratio for w/c of 0.46 is interpolated as 3.8
3
Cement content (Kg/m ) = Plastic density /(1+Agg to cement ratio + w/c ratio)
Calculation for plastic density is shown in Sec 4.3
A. IS method
Sand % by volume for zone II sand, compaction factor 0.8 and water cement ratio 0.6 for
20mm down coarse aggregate = 35% (Refer table 2 Annexure III, page no 65 of
Durocrete Mix Design Manual)
Corrections
Correction for zone 1 sand = +1.5%
Correction for water/cement ratio of 0.46= - 3%
Net Sand content = 35=1.5-3-33.5%
Weights of fine and coarse aggregates are calculated as
V = (W +C/Sc + 1/p(fa/Sfa) ) x 1/1000
V = (W +C/Sc + 1/1-p x (Ca/Sca) ) x 1/1000
V = Absolute volume of fresh concrete i.e. (gross volume –volume of entrapped Air)
= 1-.02=0.98
W = water demand = 190Lit
C = cement content = 416Kg
p = ratio of fine aggregate to total aggregate =0.335
3
fa = total quantity of fine aggregate in Kg per m
3
ca = total quantity of coarse aggregate in Kg per m
Sc = Specific Gravity of Cement =3.15
Sfa = Specific gravity of fine aggregate =2.75
Sca = Combined Specific Gravity of Coarse aggregate (Assuming 30% of coarse
aggregate is 10mm down aggregate =2.90 x 0.7 + 2.86x 0.3=2.89
3
Fa= 606 Kg/m
3
Ca =1278Kg/m
B. DOE Method
C. ACI Method
The above proportions need to be reworked on actual plastic density of concrete which is
usually higher than 2500 for basaltic aggregates of Western Maharashtra
D. RRL Method
Refer Annexure V (page no 71)
In RRL method the relative proportion of fine aggregates is so calculated, that combined
grading of aggregates fits zone 1 or 2 of figs 1,2or 3 of Annexure 6.
A trial proportion is taken and combined gradation is worked out for e.g.
35% fine aggregate 20% 10mm down aggregate, 45% 20mm down aggregate.
Thus we find that combined gradation if plotted on fig 2 Annexure 5 goes near the lowest
curve at lowest curve on 600micron 1.18 and 2.36 fractions.
The curve can be pushed towards 2 curve (Ideal curve) by increasing the sand content.
After some trial runs it is observed that 38% Fine Aggregate, 20% 10mm down and 42%
20mm down aggregate gives grading close to curve2.
3.1 IS Method
The IS method treats normal mixes (up to M35) and high strength mixes (M40 and
above) differently. This is logical because richer mixes need lower sand content when
compared with leaner mixes. The method also gives correction factors for different w/c
ratios, workability and for rounded coarse aggregate. In IS method, the quantities of fine
and coarse aggregate are calculated with help of yield equation, which is based on
specific gravities of ingredients. Thus plastic density of concrete calculated from yield
equation can be close to actual plastic density obtained in laboratory, if specific gravities
are calculated accurately. Thus actual cement consumption will be close to that targeted
in the first trial mix itself. The water cement ratio is calculated from cement curves based
on 28 days strength of cement. This can be time consuming and impractical at times. The
IS method gives separate graphs using accelerated strength of cement with
reference mix method. This greatly reduces the time required for mix design.
The IS method suffers from following limitations: -
b. Though sand content is adjusted for lower water cement ratio there is no direct
adjustment for cement content. As discussed earlier, the cement particles act, as
fines in concrete and richer mixes often require lesser fine aggregate when
compared to leaner mixes. A mix in which cement content has been lowered by
use of plasticisers may require higher sand content to improve cohesion.
c. The IS method gives different tables for determining sand content for concrete up
to M 35 grade and above M 35 grade. There is an abrupt change in sand
content from 35% to 25% in the two tables when shifting from M 35 grade
concrete to M40 grade concrete. The change may be justified to account for
higher cement content but it should be gradual in nature.
e. The IS method does not take into account the effect of the surface texture and
flakiness of aggregate on sand and water content. It does not recommend any
corrections when crushed fine aggregate is used against natural fine aggregate
as in case of DOE method.
f. The IS method does not easily account for blending of different fine
aggregates or coarse aggregates when they individually do not conform to IS
requirements. On the other hand in RRL method, coarse sand can be blended
with fine sand or stone dust to get the required gradation (Natural sand and stone
dust will have different specific gravities). Even coarse aggregates of different
sizes, gradation and specific gravities can be blended to achieve the required
gradation in RRL method.
h. The quantities of fine aggregate and coarse aggregates are calculated from the
yield equation. The yield equation is based on concept, that volume of concrete
is summation of absolute volumes of its ingredients. Absolute volume of
ingredients are function of specific gravities of ingredients .The plastic density of
concrete if theoretically calculated on the basis of specific gravities, may not
match with that actually measured from concrete.
j. The IS method does not have an adjustment in fine aggregate content for
different levels of workability. Higher workability mixes require more fine
aggregate content to maintain cohesion of mix.
The DOE method overcomes some limitations of IS method. In DOE method, the fine
aggregate content is a function of 600micron passing fraction of sand and not the zone of
sand. The 600-micron passing fraction emerges as the most critical parameter governing
the cohesion and workability of concrete mix. Thus sand content in DOE method is more
sensitive to changes in fineness of sand when compared to the IS method. The sand
content is also adjusted as per workability of mix. It is well accepted that higher the
workability greater is the fine aggregate required to maintain cohesion in the mix. The
3
water content per m is recommended based on workability requirement given in terms of
slump and Vee Bee time. It recommends different water contents for crushed aggregates
and for natural aggregates. The quantities of fine and coarse aggregates are calculated
based on plastic density plotted from fig 4 Annexure III (page no 68). However the DOE
method allows simple correction in aggregate quantities for actual plastic density
obtained at laboratory.
a. The fine aggregates content calculated from DOE method often is on the higher
side resulting in over sandy mixes. For zone 1 coarse sand (600micron fraction
15 to 20%) the sand content may exceed 50% for moderate workability of 30mm
to 60mm slump.
b. The fine aggregate content cannot be adjusted for different cement contents.
3
Hence a rich mix with cement of 400Kg/m will have the same fine aggregate
3
proportion, as a lean mix with 300kg/m cement for given sand. Thus richer
mixes may not be as workable because of higher fines, when compared to mixes
obtained from the IS method.
c. The DOE method also does not take into account the effect of the surface texture
and flakiness of aggregate on sand and water content although it distinguishes
between crushed stone aggregates and natural aggregates.
d. The DOE method does not have a specific method of combining 10mm
aggregates with 20 mm aggregates.
e. No specific graphs are available (to estimate fine aggregate content) for
maximum size of aggregates between 20and 40 mm.
This method is based on determining the coarse aggregate content based on, dry rodded
coarse aggregate bulk density and fineness modulus of sand. Thus this method takes
into account the actual voids in compacted coarse aggregates that are to be filled by
sand cement and water. This method also gives separate tables for air-entrained
concrete. This method is most suitable for design of air-entrained concrete. This method
gives separate values of water and sand content for maximum size of aggregate up to
150mm. Hence this is most suitable method for designing plum concrete. It also gives
separate values for 12.5 & 25 mm down coarse aggregate.
This method suffers from following limitations: -
a. It gives coarse aggregate contents for sand with FM range of 2.4 to 3.0 .It is
found that sand available in many parts of India is extremely coarse with FM
more than 3.2.
b. In this method the density of fresh concrete is not given as function of specific
gravity of its ingredients. In IS and DOE method the plastic density or yield of
concrete is linked to specific gravity of ingredients.
c. The values of density of fresh concrete given in this method range from 2285
3 3
kg/m for10mm down aggregate to 2505kg/m for 150mm down coarse
aggregate. It is found that in many parts of our country, the density of fresh
concrete (plastic density) of 20 and 10 mm down aggregates vary from 2400 to
3
2600kg/m . The weights calculated from the given densities often result in higher
cement contents than that assumed.
d. The ACI method also does not take into account the effect of the surface texture
and flakiness of aggregate on sand and water content, neither does it distinguish
between crushed stone aggregates and natural aggregates.
e. The ACI method does not have a specific method of combining 10mm
aggregates with 20 mm aggregates.
f. The fine aggregate content cannot be adjusted for different cement contents.
Hence the richer mixes and leaner mixes may have same sand proportion, for a
given set of materials.
In this method, the aggregate to cement ratios are worked out on the basis of type of
aggregate, max size of aggregate and different levels of workability. The relative
proportion of aggregates is worked on basis of combined grading curves. This method
facilitates use of different types of fine and coarse aggregates in the same mix. The
relative proportion of these can be easily calculated from combined grading curves. The
values of aggregate to cement ratio are available for angular rounded or irregular coarse
aggregate.
2. All materials should be accepted only after testing and only if they meet the
acceptance criteria. Daily record of materials tested at site should be maintained at
site.
3. A site trial of mix design should be taken to ensure the suitability of mix at site.
Cubes should be cast during site trial and should be tested before commencing the
concreting work using the mix design.
4. Every mix design is specific to materials used for mix design. Hence for any minor
variation in material properties of sand, coarse aggregate received at site,
corrections in mix proportions may be necessary at the site. Following corrections
should be made regularly at site: -
a) Correction for surface moisture
b) Correction for Fineness Modulus of sand
c) Correction for size and shape of coarse aggregate
d) Correction for workability of concrete
e) Correction for Bulk density (Only in case of Volume batching)
f) Correction for yield
Daily record of corrections made in the mix proportions should be maintained in the
concreting work data sheet.
5. Concrete mix design assumes that aggregates used in concrete are in saturated
surface dry condition. Coarse aggregates should be wetted before concreting to
bring them in SSD condition. Since correction for surface moisture is done on sand,
water should not be spayed on sand.
6. If weigh batcher is used, its level & calibration should be checked daily before
starting the work. Calibration can easily be checked by preparing sand bags of 25
Kg & 5 Kg.
7. In case of volume batching correction for bulk density is necessary. This is because
every mix design is done by weight only. These weights are converted to volume
based on loose bulk density found at site.
8. Concrete mix design is done not only for strength but also for workability. Hence
changes in mix proportions may be necessary for changes in workability desired at
site. The slump given in mix design should never be exceeded and strictly
controlled on site. We recommend a slump reading to be taken for every 25 bags of
cement concrete.
9. Since water cement ratio not only governs the strength but also the durability of
concrete. The water cement ratio on the site should be strictly controlled. The water
cement/ratio can be controlled by maintaining the slump as per the design
specifications.
10. Use only measured cans for adding water in the mixer. Use of trapezoidal buckets
for adding water should be strictly avoided as their typical shape results in either
excess or lesser water being added to the mixer. Milk kettles are recommended
because their peculiar shape not only prevents water from falling off while addition
but also ensures speed of water addition.
11. On starting the concreting work we recommend a process of calibration of water for
first 3 batches. In this process exact quantity of water calculated after making
12. Regularly check the average weight and freshness of cement bags. Average weight
of at least 5 bags should be taken each day prior to concreting. If the average
weight of cement bags is below 49 Kgs., proper correction should be made by
reducing the weight of aggregates in order to maintain the cement consumption.
13. Mix design is based on the strength of cement tested at laboratory that is usually
fresh. If age of cement is more than 1 month or if it is not stored properly, the
strength of cement will be affected. In such cases, corrections in mix design may
be required to account for reduced strength. Such a correction may be done by
using lower cement curve in the standard graph. The effect of using a lower curve
will be, a lower water cement ratio to achieve the same strength.
14. Ensure cement stocked properly in waterproof room and is not in direct contact with
floor or the walls. Use first in first out system of keeping inventory to ensure that old
stocks of cement are not used for concreting.
15. Cubes should be cast for every batch of concrete no matter how small is the
quantity of concrete. The revised IS 456 2000 makes cube testing mandatory for
every concreting shift. The minimum frequency of samples of cubes cast is given in
IS 456 2000 Clause 15.2.2. Ensure that minimum sample of 3 cubes is always
available for 28 days testing.
16. Every sample of cube reading should always be accompanied by slump reading of
the batch from which cubes are taken. Slump reading helps us to correlate the
strength with workability. For example if it is observed that cube results are low for a
set of cubes and corresponding slump reading is found to be high, it may be
concluded that low strengths are on account of high water cement ratio. If cube
results are low for low slump reading of the batch, the problem may be with quality
of sand, aggregates or cement.
17. Standard deviation of samples of cube results should be regularly checked. The
revised IS 456 2000 assumes a standard deviation of 4 Mpa for concrete grades up
to M25 and 5 Mpa for grades above M25. Higher standard deviation mean poor
control at site on concrete operation. Acceptance criteria for accepting cube results
are given in revised IS 456 2000. The cube results should be regularly checked for
these acceptance criteria.
18. Cement consumption should be checked every day and proper record of cement
actually consumed versus the design consumption should be maintained in the
concreting work data sheet.
19. The exact cement consumption at site can be checked with help of a yield box. The
yield box is a simple rectangular box made of mild steel or plywood. The concrete
after mixing is poured in yield box and vibrated properly. The volume of concrete is
3
measured in m . Reciprocal of this volume in m3 will give cement consumption in
bags per m3 of concrete.
20. The mix design should be regularly revalidated from the laboratory for any changes
in material properties.
9. If Weigh Batcher is not available at site, then following Farmas should be made
available at site:
35 4 40 x 25 x 35
30 1 40 x 25 x 30
25 2 40 x 25 x 25
20 1 40 x 25 x 20
15 1 40 x 25 x 15
10 2 40 x 25 x 10
10. Hot plate
11. Compression testing machine.
12. A yield box of size 50cm x 50cm x 75 cm made of mild steel or plywood.
Sand contains some fraction of water as surface moisture. This moisture affects
(increases) the water cement ratio of concrete. Water cement ratio takes into account the
total water available for hydration of cement.
Water/ cement ratio = (Water added per batch + Surface moisture in sand)
Water to be added for every batch should be calculated only after deducting the surface
moisture from the water quantity of water cement ratio
Water to be added per batch = (Water/ cement ratio * 50) - (surface moisture * wt
of sand per batch)
If moisture content = 4%
Wt. Of sand = 135kgs.
Water / cement ratio = 0.55
Moisture content in sand will vary from day to day and also with different lots of sand. It is
therefore very important to make correction for moisture in sand to maintain w/c ratio. If
slump on site is kept under control, the w/c ratio is automatically controlled.
For any mix design, the coarse aggregate is considered to be in saturated surface dry
condition. Where as the metal on the site is often in bone-dry condition (especially
during summers). This dry aggregate often absorbs the water added in concrete and
reduces the workability of concrete. Correction for surface absorption is necessary to
maintain the water cement ratio.
A correction of 1% to 2 % of wt. of coarse aggregate may be made in case of bone-dry
condition of aggregate.
For example if the aggregate absorption is 2%, and total weight of aggregates is 180 Kg
then
Aggregate absorption= 0.02 * 180
= 3.6 Litres
Hence quantity of water added (From previous example) =22.1 + 3.6
=25.7 lit
How ever it is recommended that the aggregate should be wetted thoroughly before
concreting to make it in saturated surface dry condition instead of making correction for
aggregate absorption.
Hence, use 2 forms of 25litrs and one form of 30litrs. Bulk density of sand changes with
bulkage. Hence correction for bulk density of sand should be made every day.
Bulk density of metal is between 1.4 Kg/Lit to 1.5 Kg/Lit where as bulk density of sand
varies with bulkage and usually lies between 1.6 to 1.8 Kg/Lit.
This correction is done only in case of volume batching of concrete. When sand is
moist it ‘bulks’ i. e. it occupies grater volume. Hence, less weight of sand is taken in the
given volume. In other words, the bulk density of sand changes. Otherwise, volume of
sand needs to be increased in proportion of bulkage.
If correction for bulk density is done, effect of bulkage is taken care of &
correction for bulkage need not be done.
Excessive silt in sand affects the bond between cement and sand. Silt particles are finer
than 75 micron in size and have tremendous water demand. They increase the water
cement ratio required for getting the same workability. Organic and inorganic impurities
present in silt also affect the durability of concrete. This reduces the strength of concrete.
This problem is quite severe during monsoon.
Since the effect of silt is to reduce the workability, if silt % at site is found to be more than
that considered in mix design, then either the same mix should be used with reduced
workability as found during calibration of water or workability should be increased by
making field corrections.
a) Increase the workability by reducing the specific surface of concrete (reducing the %
of sand, reducing % of 10mm down metal if it is flaky etc.). However, this correction
is to be done only if sand is fine or coarse aggregate is flaky and done only to the
limit of not loosing the cohesiveness of concrete mix.
b) Increase the workability by increasing the cement content. This can easily be done by
reducing the total aggregate added per batch by approx. 10kg. This should be
continued till the required workability is obtained. Sand and coarse aggregate
should be reduced proportionately. Say if we are using 40% sand as proportion of
total aggregate reduce the sand by 4kg and reduced the coarse aggregate by 6 kg.
c) By adding plasticiser – Dosage of plasticiser may be adjusted to get the required
workability. However, It is important to check the compatibility of plasticiser with
cement and also the maximum and minimum dosage of plasticisers as specified by
he manufacturers.
The fineness modulus of sand in Pune varies from 3.2 to 3.8 The IS specifies a limit of
2.2 (fine sand) to 3.2 (coarse sand) for fine aggregate. This means that sand available in
Pune is extremely coarse. This is partly because of absence of fines in the sand and 10%
to 15% is retained on 4.75mm sieve as chal or shingle present in the sand. In case of
coarse sand, a part of sand may be replaced by fine crushed sand to increase the
missing fines in concrete.
In case crushed sand is not available fine stone dust (600 μ passing more than 60 %and
150 μ passing not more than 20%) may be used to replace a part of sand. Such stone
dust should not replace more than 15 Kg of sand under normal circumstances. Strict
control on water cement ratio should be kept. Stone dust reduces the workability; hence,
the water cement ratio is likely to increase.
Take 500 gm of sand and heat it in a tray gently till sand is dry and starts flowing freely.
Surface dry sand is weighed again to find the loss in weight.
W
Surface moisture =
(500 - W)
NOTE: It is important not to over heat the sand, as it will make the sand bone dry. The
sand particles should be in saturated surface dry condition after heating. To ensure this
condition heat the sand only to the point it becomes free flowing and there is a colour
change.
Moisture in sand results in bulkage (increase in volume of sand) To get a rough estimate
of surface moisture following thumb rule may be used when sand is not extremely wet.
Moisture in Bulkage
Sand
Medium Coarse
Sand Sand
1% 8% 6%
2% 16% 12%
3% 22% 15%
4% 27% 17%
5% 29% 18%
Take 50ml. of water in 250ml. beaker and add some salt to it. Add sand to it till 100ml.
mark is reached. Again add water up to 150ml. Stir the sand well to wash it in salt water.
Keep the beaker still for 3 hours. Observe the thickness of the silt layer.
Sand with silt content greater then 8 % calculated by above method should not be used
for concreting.
In laboratory the silt % is calculated as % weight of particles finer than 75 micron. The
limit is given as 3% in IS383 (Refer Annexure I page no 59).
weight of material in kg
Bulk density =
Volume in litres
Bulk density can be measured on site by filling a standard 35 litres form with aggregate
and weighing the aggregate filled in the form.
Take 100ml. of sand in 250ml. beaker and add water so as to completely submerge the
sand. Shake the beaker well and the keep it steady for some time. Note the level to which
it settles.
Original level - New level
Bulkage % = *100
New Level
7.5 The sieve analysis of fine aggregates and the fineness modulus
Apparatus:
Set of sieves ranging 40 mm, 25 mm, 20 mm, 16 mm, 12.5 mm, 10 mm, 6.3 mm, 4.75
mm, 2.36 mm, 1.18mm, 600 μ, 300 μ, 150 μ weighing balance, heating pan and stove.
Procedure:
i. Heat 1Kg of sand on stove to remove all the moisture. This will make the
particles free from cohesion induced because of surface tension of free water in
sand.
ii. Arrange all the sieves in order of size, with largest sieve size on the top.
iii. Place weighted material on the top most sieve and shake each sieve. Shaking
shall be done with a varied motion backward and forward, left to right, circular –
clockwise, anti- clockwise with frequent jerking, so that the material is kept
moving over the sieve surface. Shaking should be done till all the particles are
given a chance to pass through the sieve.
iv. Weigh the material retained on each sieve on a weighing balance. The material
retained on each sieve after shaking represents the fraction of aggregate coarser
than the sieve size in question and finer than the sieve size above.
v. Calculate % retained and the cumulative % retained on each sieve. The
summation of the % cumulative wt retained on all the sieve sizes up to 150
micron, divided by 100 gives the fineness modulus.
vi. The sieve analysis is recorded in following table
Calculation:
Cubes of concrete should be cast for every shift of concreting work to estimate the
strength of concrete.
Concrete for filling the cubes should be taken from the middle discharge of concrete
mixer. Concrete from beginning or at the end of discharge should be avoided. Cubes
should be filled in 3 equal layers. Each layer should be uniformly tamped at least 35
times with a16mm blunt rod. The tamping should be done in such a manner that the rod
penetrates through the layer up to the lower layer. Cubes should be properly levelled and
finished using hand trowel. Cubes should be kept in shadow properly covered with wet
gunny bags. Cubes should be demoulded after 24 hours and immersed in water for
curing. It is important to keep the cubes away form the shocks or vibrations especially for
initial 3 days of casting.
We recommend that minimum 6 cubes should be taken every day and the batch of 3
cubes be tested for 7 days and 28 days respectively.
Slump test:
Slump cone for slump test, tamping rod of steel 16 mm in diameter, 0.6 m long and
rounded at one end.
Procedure:
i. The internal surface of the slump cone shall be thoroughly cleaned and should be
free from any set concrete before commencing the test. The mould should be
placed on smooth horizontal, rigid and non – absorbent surface such as carefully
levelled metal plate. The mould is firmly held in position while filling it.
ii. The mould should be filled in 4 layers each approximately one quarter of the height
of mould. Each layer shall be tamped with 25 blows. The stroke should be
nd
distributed in a uniform manner over the cross section of mould. For the 2 and
subsequent layers tamping rod should penetrate into underlying layer. The
bottom layer should be tamped throughout its depth.
iii. After the top layer has been rodded the concrete shall be struck off level with trowel
or rod. The mortar, which may have leaked out between mould and base plate,
shall be cleaned away.
iv. The mould shall be removed from concrete immediately by raising it slowly and
carefully in vertical direction. This will allow the concrete to subside and the
slump shall be measured immediately by determining the difference between
height of mould and that of highest point of slumped concrete specimen. The
above operation shall be carried out in a place free from shock or vibration.
8.6 There are cracks on the concrete surface immediately after casting.
Plastic shrinkage is the most common reason for surface cracks on concrete.
Rapid loss of moisture in the plastic stage results in plastic shrinkage cracks. The
phenomenon is common when concreting is done in windy condition. To prevent
plastic shrinkage the concrete should be covered with plastic, immediately after
casting.
9.8 Can crushed sand make as good a concrete as that made from
natural sand? How does it affect the economy of mix design?
Crushed sand can make as good a concrete as that made of natural sand .In fact use of
crushed sand will become inevitable in near future because of dwindling sources of natural
sand. Crushed sand particle though shaped, does not have the spherical shape of natural
sand. Hence the crushed sand will have greater water demand than that of natural sand
resulting in slightly higher cement consumption. However, if crushed sand is properly graded
with adequate fines the mix may have lower water demand when compared to poorly graded
natural sand. Besides crushed sand can afford better control on gradation when compared to
natural sand. Hence crushed sand may become an economical option if good quality natural
sand is not available.
External Factors
i. Sulphate attack
ii. Chloride attack
iii. Carbonation
iv. Effervescence (Leaching)
v. Shrinkage / Creep
vi. Alkali Aggregate Reaction
i. Sulphate attack
Remedy:
Remedy:
Avoid:
iii. Carbonation
5 0.5 4
10 2 16
15 4 36
20 7 64
Remedy:
Effect
a) Increase Permeability of concrete.
b) Reduces the PH of concrete – enhancing corrosion.
c) Affects the aesthetics of concrete surface.
Remedy
a) Use of low water/ cement ratio.
b) Use of Puzzolonic materials.
v. Shrinkage
• Plastic shrinkage
• Drying Shrinkage
Effect:
a) Cracking
Remedy:
a) Early curing
b) Protecting concrete from Wind/ Sun.
c) Wetting of Aggregates / Subgrade.
Remedy
Fly ash, known also as pulverized – fuel ash, is the ash precipitated electro-statically from
the exhaust fumes of coal-fired power stations, and is the most common artificial
pozzolana. During combustion of powdered coal in modern power plants, as coal passes
through high temperature zone in the furnace, the volatile matter & carbon are burned off,
where as most of the mineral impurities, such as clays, quartz, and feldspar, will melt at
high temperature. The fused matter will be quickly transported to lower temperature
zones where it solidifies as spherical particles of glass. Some of the mineral matter
agglomerates forming bottom ash, but most of it flies out with the flue gas stream and is
called fly ash. This ash is subsequently removed from the gas by electrostatic
precipitators.
The free lime generated as a result of hydration is water-soluble and tends to leach out.
This makes concrete porous and more vulnerable to further attack from water and other
chemicals.
The reactive silica present in fly ash converts free lime into calcium silicate
hydrates, which is insoluble in water and possesses cementitious properties. It
leads to further gain of strength at later ages in concrete. The IS allows upto 35%
replacement of cement by fly ash.
The fly ash particles are spherical (which is advantageous from the water requirement
point of view) and are of least the same fineness as cement (although with fewer fine
particles) so that the silica is readily available for reaction.
The pozzolanic activity of fly ash is in no doubt, but it is essential that it has a constant
fineness and a constant carbon content. The two are often interdependent since the
carbon particles tend to be coarser. Modern boiler plant produce fly ash with a carbon
content of about 3 percent but much higher values are encountered in fly ash from older
plants. British Standard BS 3892: 1965 lays down a maximum loss of ignition of 7
percent, but probably a carbon content upto 12 percent is acceptable. It is not clear why
carbon may be harmful but, of course, it is not pozzolanic and is therefore no more than a
filler The importance of uniformity of properties of fly ash can not be overestimated, as
otherwise it is difficult to maintain the uniformity of the resulting concrete. British Standard
BS 3892: 1965 specifies three zones of fineness so that uniform supply can be assured.
Portland- pozzolana cements show also good resistance to sulphate attack and to some
other destructive agents. This is so because the pozzolanic reaction leaves less lime to
be leached out and also reduces the permeability of concrete. It should be remembered
that pozzolanas vary very considerably in their effects, both good and bad, and it is
advisable to test any untried pozzolanic material in combination with the cement and
aggregate, which are to be used in actual construction. The use of fly ash with sulphate-
resisting Portland cement is not allowed according to British code of Practice CP
110:1972 and BS 5328:1976 when resistance to sulphate attack is required. This view is
not necessarily correct.
When pozzolanas are used as a partial replacement for cement, the cement and
pozzolanas are batched separately and mixed with the other ingredients in the concrete
mixer. The required properties of pozzolanas for such a purpose are prescribed by ASTM
Standard C 618-78.
With replacement, concrete mixes have a lower early strength than when Portland
cement is used, but beyond about three months there is no less of strength. With lean
mixes, there may even be a long-term gain of strength due to the replacement. If equal
early strength is required and pozzolana to be used (e.g. because of alkali-aggregate
reactivity) then addition of pozzolana rather than replacement of cement is necessary.
Because the continuing formation of hydrates fills the pores and also because of
the absence of free lime which could be leached out, partial replacement of
Portland cement by pozzolana reduces the permeability of concrete: a 7 to 10- fold
reduction has been reported. The US Government encourages the use of fly ash
in all appropriate construction involving the Federal Funds.
11.3 Applications
A) Improvement in workability
With fresh concrete mixtures that show a tendency to bleed or segregate, it is well known that
incorporation of finely divided Flyash generally improves workability by reducing the size and
volume of voids. It will also enhance cohesiveness of freshly made concrete. The small size
and the glassy texture of fly ashes makes it possible to reduce the amount of water required
for a given consistency. In a review paper on the use of fly ashes it was reported in one case
that a concrete made by substituting 30% of cement with a Canadian flyash required 7% less
water.
D) Environmental Considerations
Not only is the manufacture of Portland cement highly energy intensive it also is a significant
contributor of the green house gases.
The production of every tonne of Portland cement contributes about one tonnes of CO2 into
the atmosphere. Minor amount of NO2 and CH4 are also released into the atmosphere. The
total CO2 emissions per tone of cement range from about 1.1 tones of CO2 from the wet
process to 0.89 tonnes from a precalcination kiln. Hence every tonne of cement replaced by
fly ash, saves the environment from release of approximately one tonne of CO2 in the
atmosphere.
Thus today environmental and energy considerations also advocate use of fly ash in
concrete.
Source: Refer Table No. 4 (Clause 4.3) Page no. 11 of IS 383 -1970
Source: IS383 – 1970 TABLE 5 page 11 (Clause 4.4) All in Aggregate Grading
Quality of aggregates:
Note I –
The presence of mica in fine aggregate has been found to reduce considerably the durability and
compressive strength of concrete and further investigations are underway to determine extent of
mica. It is advisable. Therefore, to investigate the mica content of fine aggregate and make
suitable allowances for the possible reduction in the strength of the concrete or mortar.
Note II –
The aggregate shall not contain harmful organic impurities (tested in accordance with IS 2386
Part II –1963) insufficient quantities to affect adversely the strength or durability of concrete. A
fine aggregate which fails in the test for organic impurities may be used, provided that when
tested for the effect of organic impurities on the strength of the Mortar, the relative strength at 7
and 28 days, reported in accordance with IS 2386 Part VI –1963, is not less than 95 %.
Relation between free water/cement ratio and concrete strength at 28 days for different
cement curves:
Fig.1
70.0
60.0
F
E
28 - Day Concrete Strength, N/mm 2
50.0
D
C
40.0
B
A
30.0
20.0
10.0
0
0.30 0.35 0.40 0.45 0.50 0.55 0.60 0.65
3
Nominal maximum size of Water content per m of concrete Kg
aggregate, mm
i) For different types of coarse and fine aggregate, the free water content is
estimated as 2/3 W FA + 1/3 W CA
where,
W FA = free water content appropriate to the type of the fine aggregate, and
W CA = free water content appropriate to the type of the coarse aggregate
ii) Values interpolated for 25 mm maximum size of aggregate.
15
15 15
15 40 40
40
60 80
60 40
60 80
60 80 100
80 100
100 100
0.2 0.4 0.6 0.8 0.2 0.4 0.6 0.8 0.2 0.4 0.6 0.8 0.2 0.4 0.6 0.8
Free-water/cement ratio
Fig 2
μ sieve.
Recommended proportions of fine aggregate passing a 600μ
15
15
15
15 40
40 40
40 60
60 60
60 80 100
80
80 80 100
100 100
0.2 0.4 0.6 0.8 0.2 0.4 0.6 0.8 0.2 0.4 0.6 0.8 0.2 0.4 0.6 0.8
Free-water/cement ratio
Fig 3
μ sieve.
Recommended proportions of fine aggregate passing a 600μ
15
15
15
15 40
40
40 40 60
60
60
60 80
80 80
100
80
100 100
100
0.2 0.4 0.6 0.8 0.2 0.4 0.6 0.8 0.2 0.4 0.6 0.8 0.2 0.4 0.6 0.8
Free-water/cement ratio
Table 1 Approximate mixing water requirements for different slumps and maximum
size of aggregate
3
Slump Water, kg/m of concrete, for the maximum sizes of coarse
Mm aggregates
10 12.5 20 25 40 50 70 150
mm mm mm mm mm mm mm mm
NON-AIRENTRAINED CONCRETE
30 To 50 205 200 185 180 160 155 145 125
80 to 100 225 215 200 195 175 170 160 140
150 to 180 240 230 210 205 185 180 170 -
Approximate 3 2.5 2 1.5 1 0.5 0.3 0.2
entrapped air
content,
percent
Source: ACI Manual 21.1.81
Notes:
i) The above values are maximum for reasonably well-shaped angular
coarse aggregate graded within acceptable limits.
ii) The quantities of mixing water can be used to compute cement factors
for trial batches.
iii) For aggregate greater than 40 mm, the slump values are based on
slump tests after removal of particles greater than 40 mm by wet
screening.
Maximum size Volume of dry rodded coarse aggregate per unit volume of
of aggregate concrete for different fineness moduli of sand
Notes :
I) These volumes are selected from empirical relationships to produce concrete with a
degree of workability suitable for usual RC construction; for less workable concrete,
such as that required for concrete pavements they may be increased by about 10
percent; for more workable concrete, such as that required for pumped concrete, they
may be decreased by about 10 percent.
ii) Fineness modulus of sand = sum of cumulative ratios retained on sieves with square
openings of about 0.15, 0.3, 0.6, 1.18, 2.36 and 4.75 mm
Table 1
Aggregate – Cement Ratios for Different Degrees of Workability, Water – Cement Ratios
and Gradings – for 40 – mm Rounded Gravel Aggregate
Table 2
Aggregate – Cement Ratios for Different Degrees of Workability, Water – Cement Ratios
and Gradings – for 40 – mm Crushed Rock Aggregate
Table 4
Aggregate – Cement Ratios for Different Degrees of Workability, Water – Cement Ratios
and Gradings – for 20 – mm Crushed Rock Aggregate
Aggregate – Cement Ratios for Different Degrees of Workability, Water – Cement Ratios
and Gradings – for 10 – mm Rounded Gravel Aggregate
Table 6
Aggregate – Cement Ratios for Different Degrees of Workability, Water – Cement Ratios
and Gradings – for 10 – mm Crushed Rock Aggregate
Fig-1
100
75
67
60
59
52 50
47
44
38 36
30 31 32
23 24 25 24
15 17
11 12 12
5 7 7
2
3
0
150 mm 300 mm 600 mm 1.18 mm 2.26 mm 4.75 mm 10 mm 20 mm 40 mm
I S sleve designation
75
65
55
48
45
42 42
34 35 35
28 28 30
27
21 23
21
14 16
12
9
2
150 mm 300 mm 600 mm 1.18 mm 2.26 mm 4.75 mm 10 mm 20 mm
I S sleve designation
75
60 60
45 45 45
37
34 33 30
28 26
20 20
19
14 16
12
6 6
3
0
150 mm 300 mm 600 mm 1.18 mm 2.26 mm 4.75 mm 10 mm
I S sleve designation
Note: In the absence of established value of standard deviation, the values given in Table 8 may
be assumed, and attempt should be made to obtain results of 30 samples as early as possible to
establish the value of standard deviation.
1. Concrete mix proportioning (Ref : IS 456 2000 Point no.9 Page No. 22)
Design mix concrete is preferred to nominal mix. If design mix concrete cannot be used
for any reason on the work for grades of M 20 or lower, nominal mixes may be used with
the permission of engineer-in-charge, which, however, is likely to involve a higher cement
content.
3 Batching.
To avoid confusion and error in batching, consideration should be given to using the
smallest practical number of different concrete mixes on any site or in any one plant. In
batching concrete, the quantity of both cement and aggregate shall be determined by
mass; admixture, if solid, by mass; liquid admixture may however be measured in volume
or mass; water shall be weighed or measured by volume in a calibrated tank. (See also
IS 4925)
3.1.1 Except where it can be shown to the satisfaction of the engineer-in-charge that
supply of properly graded aggregate of uniform quality can be maintained over a
period of work, the grading of aggregate should be controlled by obtaining the
coarse aggregate in different sizes and blending them in the right proportions
when required, the different sizes being stocked-piled for several hours
preferably a day before use. The grading of coarse and fine aggregate should e
checked as frequently as possible, the frequency for the job being determined by
the engineer-in-charge to ensure that the specified grading is maintained.
3.1.2 The accuracy of the measuring equipment shall be within ± 2 percent of the
quantity of cement being measured and within ± 3 percent of the quantity of
aggregate, admixtures and water being measured.
Forms shall not be released until the concrete has achieved strength of at least twice the
stress to which the concrete may be subjected at the time of removal of formwork. The
strength referred to shall be that of concrete using the same cement and aggregates and
admixtures, if any, with the same proportions and cured under conditions of temperature
and moisture similar to those existing on the work.
Compressive strength
33 Grade 43 Grade 53 Grade
2
3 days (N/mm ) 16 23 27
2
7 days (N/mm ) 22 33 37
2
28 days (N/mm ) 33 43 53
Setting time
Initial setting time Minimum 30 minute
Final setting time Maximum 600 minute
Soundness
By Le-Chatlier’s method Maximum 10 mm
By Auto Clave method Maximum 0.8 %