RINCIAN MATRIAL

PEKERJAAN : PEMBANGUNAN KANDANG AYAM UK 6M X 105M


LOKASI :
BIAYAYA : Rp. ###
TAHUN : november 2020
JUMLAH JUMLAH TOTAL
SAT
No. MATRIAL VOLUME UNIT
.
( vol ) ( TONASE )
A PEKERJAAN BANGUNAN DASAR
boplang
CAKAR AYAM
1 cor beton 0.33 24.00 7.82 5,868,000.00
cakar ayam kecil 0.02 68.00 1.09 816,000.00
pembesian 1,640.00 23,780,000.00
begisting
2 Sloof 0.24 M3 23.00 5.52
1.32 M3 2.00 2.64 8.16
pembesian dg besi 12 & 6 ulir Kg
begisting
1 Pondasi uk dalam 0,5 x 0,3 46.80 M3
2 Floor lantai 95.04 M3
3 Pas herbel 270.00 M2
B PEKERJAAN KONSTRUKSI BESI
1 PAS. ATAP 12m x 66m 319296.422888 245,219,652.78
Pas tiang iwf 250 8.00 m 12.00 bt 8.00 2,841.60 7,104.00 48,307,200.00
Pas kuda2 + kongsol iwf 250 12.00 m 12.00 bt 12.00 4,262.40 72,460,800.00
skor 250 0.75 m 18.00 1.13 399.60

tiang iwf 200 6.00 m 2.00 bt 1.00 256.00 288.20 4,352,000.00


glagar iwf 200 20.00 m 1.00 bt 1.67 32.20 547,400.00

glagar iwf 150 6.00 m 10.00 bt 5.00 840.00

Gording C 125 32.00 m 24.00 128.00 3,033.60 3,294.30 51,571,200.00


Gording C 125 6.00 m 11.00 11.00 260.70
Gording C 100 8.00 m 7.00 9.33 199.36 284.80
Gording C 100 6.00 m 4.00 4.00 85.44

pas jarum 10mm 12.00 m 20.00 bt 20.00 214.00 3,638,000.00


span mur M16 4.00 3.00 12.00 48.00 660,000.00
ikat angin Ǿ 16mm 12.00 12.00 12.00 228.00 3,876,000.00

Atap Seng Galvalum 768.00 m2 1.00 768.00 49,920,000.00


Atap kongsol Seng Galvalum 48.00 m2 1.00 48.00
nok galvalum 32.00 m 2,568,750.00
2 PAS.ANGKUR 4.00 pcs 12.00 48.00 1,920,000.00
3 Plat. PLENDES 0.09 14.00 0.44 102.07 1,735,168.75
pelekat 0.07 36.00 0.81 189.56 3,222,456.25
pelekat regel 0.03 10.00 0.11 25.92 440,677.78

siripiwf 250,plat 8mm 0.02 288.00 1.56 292.19


siripiwf 150,plat 8mm 0.01 100.00 0.26 48.70

plat d gording 6mm 0.02 154.00 0.84 116.97


plat d gording talang 6mm 0.05 12.00 0.21 29.17

siku 40x40 0.50 m 130.00 10.83 157.08

baut pelekat 5/8 x 2 12.00 30.00 360.00


baut pelekat regel5/8 x 2 6.00 12.00 72.00

baut pelekat 8/16 x 1 4.00 30.00 120.00


6 PAS. RANGKA PLAVON
holow 40x40 63.00
8 Pas pagar seng penahan angin 36.00 M2 86,500.00 3,114,000.00
9 PAS, PINTU KANDANG 6.00 Unit 3,000,000.00 18,000,000.00
10 PAS. PEKERJAAN TANGGA 3.00 Unit 10,000,000.00 30,000,000.00

Terbilang : JUMLAH KONSTRUKSI 30,477,670.71


JUMLAH TOTAL 30,477,670.71
JUMLAH DIBULATKAN 30,477,000.00
18500
CV.PERMATA BINTANG MAS
BENGKEL LAS KONSTRUKSI BAJA,BAJA RINGAN,TERALIS,MESIN PRODUKSI.DLL
JL.RAYA JIPANG. DESA. JIPANG RT. 04 RW. 01 KECAMATAN. KARANGLEWAS KABUPATEN. BANYUMAS
Tlp.081314696198

PEKERJAAN : PEMBANGUNAN GUDANG (PABRIK )


LOKASI : TIPAR .AJIBARANG
MILIK :
BIAYA : Rp. 716,038,000.00
TAHUN ANGGARAN : 2020

HARGA JML. HRG. JUMLAH TOTAL


SAT
No. VOLUME SAT. SAT. (
.
( Rp ) ( Rp ) Rp )
A. PEKERJAAN PERSIAPAN 10,176,360.00
1 Ppembersian dan perataan
2 Pengukuran dan pemasangan bowplank 108.00 m' 38,670.00 4,176,360.00
3 Pembuatan bedeng 4,000,000.00
4 Peralatan kerja 2,000,000.00

B. PEKERJAAN TANAH 57,608,276.18


1 Galian Tanah 50.05 M3 56,783.00 2,841,875.58
2 Urugan Kembali 22.52 M3 41,175.00 927,261.00
3 Urugan sirtu 240.00 M3 177,628.00 42,630,720.00
4 Urugan pasir 47.60 M3 235,471.00 11,208,419.60

C. PEKERJAAN BETON 97,336,608.70


1 Lantai kerja 1.73 M3 619,159.00 1,071,145.07
2 Footplate uk. 100 X 100
Pembesian dg Besi polos 1,025.54 kg 12,844.00 13,172,035.76
Bekisting 1x pakai 42.24 M2 94,610.00 3,996,326.40
Beton Mutu Fc =19,3 Mpa ( K 225 ) 6.81 M3 783,743.00 5,337,289.83
3 Sloof uk; 15 x 20 cm
Pembesian dg Besi polos 600.70 kg 12,844.00 7,715,390.80
Bekisting 2x pakai 108.00 M2 47,305.00 5,108,940.00
Beton Mutu Fc =19,3 Mpa ( K 225 ) 5.40 M3 783,743.00 4,232,212.20
4 Kolom uk ; 10 x12 cm
Pembesian dg Besi polos 139.65 kg 12,844.00 1,793,664.60
Bekisting 2x pakai 17.60 M2 47,305.00 832,568.00
Beton Mutu Fc =19,3 Mpa ( K 225 ) 0.44 M3 783,743.00 344,846.92
5 Ring Balok Uk ; 10 x 12 cm
Pembesian dg Besi polos 321.54 kg 12,844.00 4,129,859.76
Bekisting 2x pakai 36.40 M2 47,305.00 1,721,902.00
Beton Mutu Fc =19,3 Mpa ( K 225 ) 1.09 M3 783,743.00 855,847.36
6 Cor Lantai beton Mutu Fc= 19,3 Mpa ( K225 ) 60.00 M3 783,743.00 47,024,580.00

D PEKERJAAN PASANGAN 60,009,981.50


1 Pondasi batu kali campuran 1sp : 6pp 17.50 M3 695,013.00 12,162,727.50
2 Dinding bata merah (5x11x22)cm Tebal ½batu campuran 1sp : 6pp 182.00 M2 106,899.00 19,455,618.00
3 Plesteran 1sp : 6pp Tebal 15mm 364.00 M2 48,726.00 17,736,264.00
4 Acian 364.00 M2 29,273.00 10,655,372.00

E PEKERJAAN RANGKA BAJA 352,313,747.30


1 Pas iwf 250,125,6,9 mm 7,104.00 kg 19,500.00 138,528,000.00
2 Pas Scoor (jangutan) 443.75 kg 19,500.00 8,653,125.00
3 Tiang & gelagar iwf 150,75,5,7mm 252.00 kg 19,500.00 4,914,000.00
4 Pas iwf 150,75,5,7 mm 840.00 kg 19,500.00 16,380,000.00
5 Platizer 6 mm 129.36 kg 19,500.00 2,522,520.00
6 Platizer 8 mm 253.00 kg 19,500.00 4,933,500.00
7 Platizer 10 mm 325.59 kg 19,500.00 6,349,005.00
8 CNP 125,50,2 mm 3,081.00 kg 19,500.00 60,079,500.00
9 Baut HTB Diam. 16mm 360.00 pcs 7,000.00 2,520,000.00
10 Baut HTB Diam. 12mm 624.00 pcs 3,500.00 2,184,000.00
11 Angkur 5/8 56.00 pcs 50,000.00 2,800,000.00
12 Trekstang Diametr 12mm 210.00 pcs 19,400.00 4,074,000.00
13 Ikat angin Ǿ16mm 12.00 pcs 291,500.00 3,498,000.00
14 Atap galv 0,3 777.60 M2 69,666.00 54,172,281.60
15 Nok atap galv 0,3 32.40 M' 60,000.00 1,944,000.00
16 Talang 64.80 M' 77,199.00 5,002,495.20
17 Pas PVC 4" Talang air 110.40 M' 98,700.00 10,896,480.00
18 Pengecatan permukaan baja dengan Zingkromate 607.50 m2 21,173.40 12,862,840.50
19 Sewa Cren 10,000,000.00

F PEKERJAAN PINTU 20,513,250.00


1 Pintu dorong plat rangka holow depan uk 600 x 300 cm 18.00 m2 759,750.00 13,675,500.00
2 Pintu dorong plat rangka holow samping uk 300 x 300 cm 9.00 m2 759,750.00 6,837,750.00

G DINDING SPANDEK 102,329,895.00


1 Pas dinding spandek Galv 0,3 Rangka CNP 100 585.00 m2 158,651.00 92,810,835.00
2 Pas keongan 60.00 m2 158,651.00 9,519,060.00
H KANOPI 15,750,000.00
1 Pas Kanopi depan Rangka CNP 125 & CNP 100 48.00 m2 250,000.00 12,000,000.00
2 Pas Kanopi samping Rangka CNP 125 & CNP 100 15.00 m2 250,000.00 3,750,000.00

Terbilang : JUMLAH 716,038,118.68


JUMLAH TOTAL 716,038,118.68
JUMLAH DIBULATKAN 716,038,000.00

Nb

Purwokerto, 04 Desember 2020

( SENO )