6 PAS. RANGKA PLAVON holow 40x40 63.00 8 Pas pagar seng penahan angin 36.00 M2 86,500.00 3,114,000.00 9 PAS, PINTU KANDANG 6.00 Unit 3,000,000.00 18,000,000.00 10 PAS. PEKERJAAN TANGGA 3.00 Unit 10,000,000.00 30,000,000.00
Terbilang : JUMLAH KONSTRUKSI 30,477,670.71
JUMLAH TOTAL 30,477,670.71 JUMLAH DIBULATKAN 30,477,000.00 18500 CV.PERMATA BINTANG MAS BENGKEL LAS KONSTRUKSI BAJA,BAJA RINGAN,TERALIS,MESIN PRODUKSI.DLL JL.RAYA JIPANG. DESA. JIPANG RT. 04 RW. 01 KECAMATAN. KARANGLEWAS KABUPATEN. BANYUMAS Tlp.081314696198
PEKERJAAN : PEMBANGUNAN GUDANG (PABRIK )
LOKASI : TIPAR .AJIBARANG MILIK : BIAYA : Rp. 716,038,000.00 TAHUN ANGGARAN : 2020
HARGA JML. HRG. JUMLAH TOTAL
SAT No. VOLUME SAT. SAT. ( . ( Rp ) ( Rp ) Rp ) A. PEKERJAAN PERSIAPAN 10,176,360.00 1 Ppembersian dan perataan 2 Pengukuran dan pemasangan bowplank 108.00 m' 38,670.00 4,176,360.00 3 Pembuatan bedeng 4,000,000.00 4 Peralatan kerja 2,000,000.00
1 Pas iwf 250,125,6,9 mm 7,104.00 kg 19,500.00 138,528,000.00 2 Pas Scoor (jangutan) 443.75 kg 19,500.00 8,653,125.00 3 Tiang & gelagar iwf 150,75,5,7mm 252.00 kg 19,500.00 4,914,000.00 4 Pas iwf 150,75,5,7 mm 840.00 kg 19,500.00 16,380,000.00 5 Platizer 6 mm 129.36 kg 19,500.00 2,522,520.00 6 Platizer 8 mm 253.00 kg 19,500.00 4,933,500.00 7 Platizer 10 mm 325.59 kg 19,500.00 6,349,005.00 8 CNP 125,50,2 mm 3,081.00 kg 19,500.00 60,079,500.00 9 Baut HTB Diam. 16mm 360.00 pcs 7,000.00 2,520,000.00 10 Baut HTB Diam. 12mm 624.00 pcs 3,500.00 2,184,000.00 11 Angkur 5/8 56.00 pcs 50,000.00 2,800,000.00 12 Trekstang Diametr 12mm 210.00 pcs 19,400.00 4,074,000.00 13 Ikat angin Ǿ16mm 12.00 pcs 291,500.00 3,498,000.00 14 Atap galv 0,3 777.60 M2 69,666.00 54,172,281.60 15 Nok atap galv 0,3 32.40 M' 60,000.00 1,944,000.00 16 Talang 64.80 M' 77,199.00 5,002,495.20 17 Pas PVC 4" Talang air 110.40 M' 98,700.00 10,896,480.00 18 Pengecatan permukaan baja dengan Zingkromate 607.50 m2 21,173.40 12,862,840.50 19 Sewa Cren 10,000,000.00
F PEKERJAAN PINTU 20,513,250.00
1 Pintu dorong plat rangka holow depan uk 600 x 300 cm 18.00 m2 759,750.00 13,675,500.00 2 Pintu dorong plat rangka holow samping uk 300 x 300 cm 9.00 m2 759,750.00 6,837,750.00
G DINDING SPANDEK 102,329,895.00
1 Pas dinding spandek Galv 0,3 Rangka CNP 100 585.00 m2 158,651.00 92,810,835.00 2 Pas keongan 60.00 m2 158,651.00 9,519,060.00 H KANOPI 15,750,000.00 1 Pas Kanopi depan Rangka CNP 125 & CNP 100 48.00 m2 250,000.00 12,000,000.00 2 Pas Kanopi samping Rangka CNP 125 & CNP 100 15.00 m2 250,000.00 3,750,000.00
Terbilang : JUMLAH 716,038,118.68
JUMLAH TOTAL 716,038,118.68 JUMLAH DIBULATKAN 716,038,000.00