2-43 Full
2-43 Full
2-43 Full
China
Bangladesh
Calcutta Myanmar
India
Thailand
Project site
Hyderabad
1.1 Background
In its 8th 5-Year Plan (FY 1992-1996), the Indian government set the targets of eliminating power
shortages, enhancing power generating facilities’ capacity utilization ratios, improving power supply
efficiency by reducing power transmission and distribution losses, ensuring fair electricity rates, and
encouraging private sector participation.
As of the end of March 1993, the installed power generation capacity in Andhra Pradesh (AP) State
was 5,080MW, of which 4,228MW was owned by the Andhra Pradesh State Electricity Board
(APSEB). This was the third-largest capacity among state electricity boards in India following
Maharashtra and Uttar Pradesh. However, looking at the supply-demand balance, the total amount of
electricity provided in FY 1993, including the power supply from central organizations such as the
National Thermal Power Corporation, was 3,920 MW, or only 80% of the estimated peak time
demand of 4,908MW. In terms of energy amount, only 26,886GWh of electricity was supplied
against the demand of 28,589GWh, causing a shortfall of 1,703GWh (6.0%). Therefore, power
supply restrictions were imposed intermittently in AP State, which impeded economic development
(especially manufacturing) in the state.
The Kothagudem “A” Thermal Power Station (60MW × 4 units) is located on the outskirts of
Paloncha, which is 230km east of Hyderabad, the capital of AP State. Since it started operations in
1966, it has been playing a central role in thermal power generation by APSEB along with the more
recently constructed Kothagudem “B” (110MW × 2 units) and “C” (110MW × 2 units) Thermal
Power Stations. However, as more than 25 years had passed since the completion, the “A” Power
Station had become so decrepit that the output had declined to 50MW/unit. Therefore, it needed
rehabilitation (modernization).
1.2 Objectives
The objective was to ease power shortages expected to continue in Andhra Pradesh State by
1
rehabilitating the boilers, turbines, and power generators of Kothagudem “A” Power Station, and
thereby contribute to economic development of the state.
1.3 Output
The planned outputs of the project were as follows:
[Thermal power generation equipment]
· Rehabilitation of 4 boilers
· Rehabilitation of 4 turbines
· Rehabilitation of 3 power generators*1
Among the total project cost of 6,262 million yen, 5,092 million yen (81% of the total project cost)
is covered by the ODA loan, consisting of the entire foreign currency portion (4,847 million yen) and
part of the local currency portion (equivalent to 245 million yen). The remaining portion is financed
by the Indian side with the executing agency’s own funds.
2.1 Relevance
At the time of appraisal, as already stated, AP State was expected to continue to suffer a power
supply shortage, and there was an urgent need to secure new power supply sources. At the same time,
as the target power station (Kothagudem “A” Power Station) was becoming decrepit, rehabilitating it
to recover its functions and have it contribute to correcting the supply and demand imbalance was
consistent with government policy. The national development plan at that time set the goal of
increasing power supply through various measures, such as “improving the capacity utilization ratio
of power generating facilities.” The “B” and “C” Power Stations at the Kothagudem Power Plant
also required rehabilitation. However, the “A” Power Station was given higher priority because it
1 One generator was excluded from the project because APSEB had already arranged to procure materials and machinery at the time
of appraisal.
2
As APSEB was divided into separate sectors due to the unbundling in 1999, the current executing agency (power generation
sector) is Andhra Pradesh Power Generation Corporation Ltd. (APGENCO).
2
was constructed seven to eleven years before the other two power stations and had deteriorated
considerably. *3 Thus, this project was highly necessary and important to fulfill beneficiaries’ needs
and government policy, and therefore the project plan was sufficiently relevant.
In its 9th 5-Year Plan (FY1997-2001), the government stated its commitment to further promoting
proper handling of electricity demand. Also, the project is consistent with the policy of developing
the electricity sector mainly in remote regions under the 10th 5-Year Plan (FY 2002-2006) as well as
the policy of increasing power generation and promoting efficient operation of the electricity system
under the AP State Electric Power Development Plan (2020). Therefore, the project has remained
highly relevant to the present.
2.2 Efficiency
2.2.1 Output
This project was implemented almost as planned.
The rehabilitation was completed earlier than initially scheduled. According to the executing agency,
the main reason for the early completion is improving the efficiency of the procurement procedure.
In summary, the project was essentially implemented as planned, and both the project cost and
implementation period were within the initial estimated range. Therefore, the efficiency of the
project implementation was high.
3
The rehabilitation of Kothagudem “B” Power Station was completed in 2001 and that of “C” is scheduled to start in August this
year (as of the time of this survey).
3
2.3 Effectiveness
2.3.1 Operational Indicators
We obtained data on power generation, thermal efficiency, plant load factor (PLF), capacity
utilization ratio, etc. Every indicator has improved compared to before the project.
Maximum Output
As a result of rehabilitation, the output of the “A” Power Station’s four turbines had recovered to
around 60MW each, nearly the rated output level, in FY 2002.
Thermal Efficiency
Efficiency improved to 30.13% in FY 2002 and is coming close to 32.5%, the target set for this
project.
Availability Factor
The ratio was 95.10% in FY 2002. As with PLF, since the efficiency and output have increased since
rehabilitation, economical and stable operations have been realized. As a result, a
higher-than-expected availability factor has been achieved.
4
Forced Outage Rate
The forced outage rate dropped to 1.60% in FY 2002, well below the national average of 11.30% in
that year.
Comparing the data for 2002 with that for 1996, the year immediately before the rehabilitation, the
peak time power shortage was reduced from 1,110MW to 750MW and the percentage of shortage to
the peak time demand was halved from 18.1% to 9.8%.
The power surplus (power supply minus demand) improved from -2,318GWh in FY 1996 to
-1,425GWh in FY 2002, and the percentage of shortage in relation to power demand significantly
decreased from 6.4% to 2.9%.
Power generation at the sending end of Kothagudem “A” Thermal Power Station in FY 2002 was
1,702GWh, accounting for 3.6% of the total power generation in AP State.
Power Generation at the Sending End of Kothagudem “A” Thermal Power Station
Fiscal Year 1996 1997 1998 1999 2000 2001 2002
Power Generation
at the Sending End 1,270 1,111 1,062 1,478 1,558 1,613 1,702
(GWh)
Total Power
Supply in AP 33,657 38,170 40,612 45,752 46,745 46,951 47,936
State (GWh)
Percentage to the
Total Power
3.8% 2.9% 2.6% 3.2% 3.3% 3.4% 3.6%
Supply in AP
State
Shaded columns indicate the period when the rehabilitation was performed intensively. Source: APTRANSCO
5
2) Increase in power consumption per person
Power consumption per person increased from 374kWh a year at appraisal (1994) to 510kWh in FY
2001.*4
2.4 Impact
4
The Indian national average in 1999-2000 was 354kWh (Source: Annual Report on the Working of State Electricity Boards &
Electricity Departments, Planning Commission). As for the rural electrification rate, which was initially planned to be used as an
indicator, AP State had already achieved 100% by 1990.
5
Saved fuel expenses are not the only benefit of this project. Other expenses, such as operation and maintenance expenses, would
have been higher without the project. Therefore, the FIRR calculated by this method might be a little lower than the actual figure.
6
Changes in GRDP and Power Consumption in AP State
Fiscal Year 1994 1995 1996 1997 1998 1999 2000 2001
Real GRDP (10
61,114 64,729 68,809 67,866 76,116 79,605 85,522 88,765
million Rs)
Power Supply
29,979 30,918 33,657 38,170 40,612 45,752 46,745 46,951
(GWh)
Source: Statistics by AP State Government, APTRANSCO (GRDP is based on fixed prices of FY 1993)
6
Targeted about 30 residents in three locations several kilometers north, east and south of the premise of the power station.
7
power plant and related facilities. At present, about 3,000 persons in total are employed by the entire
power plant, including the power stations “A” to “C,” and 70-80% of them are local residents.
2.5 Sustainability
According to the financial statements for FY 1999, sales increased from the previous year while
expenditure increased by a larger margin due to a rise in the depreciation cost associated with
investment, resulting in an increase of the current deficit to approximately 2,040 million Rs.
According to APERC, however, the financial conditions of the executing agency (APGENCO) and
the transmission company (APTRANSCO) have been improving since FY 1999.*9
7
The Standing Linkage Committee, consisting of representatives of the government, major producers and major consumers, meets
on a quarterly basis to discuss and determine the tariff.
8
The tariff (rupee) per kWh was 1.53 in FY 2000, 1.61 in FY 2001, and 1.83 in FY 2002. These tariffs are below the sales prices by
independent electric utility businesses in the state and electric power companies in neighboring states.
9
The person in charge (of electricity rates) at APERC said, “Subsidies from the government have also been decreasing. For the next
year, the tariff will be determined at a level that will not cause any deficit based on the cost estimates. Subsidies are expected to be
abolished in two to three years, but it will be possible to cover all expenses with sales only.”
8
Classification of Maintenance Frequency
Activities
Regular Maintenance Performed once a year for boilers, turbines, power generators
and their accessories
Predictive Maintenance Performed when necessary based on the result of daily
inspections
Preventive Maintenance Performed pursuant to instructions (manuals) of the
manufacturers
Capital Overhaul Performed once every 5 years and parts are repaired or
replaced as necessary
In summary, the power station rehabilitated under the project is sufficiently performing its expected
functions and no problem has arisen to date concerning the functioning of the facilities. Also, an
appropriate system and adequate budget are ensured for the operation and maintenance of these
facilities, and operation and maintenance activities are being carried out properly. The financial
status of the executing agency has been improving. Therefore, this project is regarded as sufficiently
sustainable.
3. Feedback
3.2 Recommendations
None.
9
Comparison of Original and Actual Scope
Item Planned Actual
(1) Output
10
Third Party Evaluator’s Opinion on
Kothagudem “A” Thermal Power Station Rehabilitation Project
Relevance
Capacity shortages are so acute in India’s power sector that any addition to generating capacity
is beneficial to the system and the economy that it serves. There are two factors that further
enhance the relevance of the project under review. At the time of the rehabilitation, the units
were thirty years old and the plant would have suffered further scaling down of capacity, even
outright scrapping in a few years’ time. By restoring the units to nearly the original designed
capacity and extending their life by 15 years at a cost of Rs. 1.848 billion, the project has
effectively postponed investment in new plant of 240 MW that, on current costs would have
consumed an outlay in excess of Rs. 10 billion. Also, the net addition of 40 MW capacity has
been achieved within an implementation period of 33 months (Feb. 1998 to October 2000),
approximately half the time that a green field project would have entailed, in Indian conditions.
The second factor of relevance relates to the changes that have occurred in India’s, and
specifically Andhra Pradesh State’s, power sector after this project was taken up for
implementation. The State power sector is now overseen by an independent regulator who has
promoted several reforms, one of them the introduction of merit order dispatch of plants, in their
order of variable cost of generation. The plant under review is operating at better than the
planned efficiency levels, which should guarantee a good ranking in this system of dispatch and
hence continued high plant utilisation.
Sustainability
The high operation indicators registered by this plant attest both to the managerial skills of the
executing agency and to the enlightened regulatory practices just referred to. Andhra Pradesh
has consistently achieved the best Plant Load Factors among all public sector thermal plants –
State as well as Central – in India for the last six years.
AP Genco’s operational and implementation strengths could be put to gainful use to the national
power sector, especially in the sector’s newly liberalized structure. The generation segment is
now opened up to free entry; phased introduction of competition is envisaged also for the
distribution segment. As an instance of well-implemented plant rehabilitation, the project under
review could serve as model to several other aging units that are marked out for renovation
across India’s power sector. The current Tenth Five-Year Plan (2002-‘07) identifies 106 thermal
units (total capacity 10,413 MW) for ‘Renovation and Modernization’ (R&M), to be taken up
based on plant-specific ‘residual life assessment studies’. Ambitious targets set for R&M in
recent Five-Year Plans have remained under-fulfilled, chiefly owing to institutional and
financing constraints. With the flexibility allowed by the new dispensation, the rehabilitated
units can now be spun off to operate as Independent Power Projects that could cater to bulk or
retail distributors and compete on cost and reliability parameters. This opens up scope for
public: private partnerships in diverse forms. Under the new law, AP Genco itself could
promote or partner such ventures not only in Andhra Pradesh but also beyond the State
boundaries.