Trends in Power System and Control
Trends in Power System and Control
SUBMITTED BY
S.SANDHYA RANI. S.BEULAH EVANGILINE 09471A0213 09471A0273 III-II III -II Email: sandy.sandhya25@gmail.com
NARASARAOPET- 522601
Abstract
As a consequence of deregulation, competition, and problems in securing capital outlays for expansion of the infrastructure, modern power systems are operating at ever-smaller capacity and stability margins. Traditional entities involved in securing adequate protection and control for the system may soon become inadequate, and the emergence of the new participants (non-utility generation, transmission, and distribution companies) requires coordinated approach and careful coordination of the new operating conditions. The paper reviews the key issues and design considerations for the present and new generation of SPS and emergency control schemes, and evaluates the strategies for their implementation. interchange increase, an increasingly competitive environment, and introduction of FACTS devices make the power system more complex to operate and to control, and, thus, more vulnerable to a disturbance. On the other hand, the advanced measurement and communication technology in wide area monitoring and control, FACTS devices (better tools to control the disturbance), and new paradigms (fuzzy logic and neural networks) may provide better ways to detect and control an emergency. Better detection and control strategies through the concept of wide area disturbance protection offer a better management of the disturbances and significant opportunity for higher power transfers and operating economies. Wide area disturbance protection is a concept of using system-wide information and sending selected local information to a remote location to counteract propagation of the major disturbances in the power system. With the increased availability of sophisticated computer, communication and measurement technologies, more "intelligent" equipment can be used at the local level to improve the overall emergency response. Decentralized subsystems, that can make local decisions based on local measurements and remote information (system-wide data and emergency control policies) and/or send pre-processed information to higher hierarchical levels are an economical solution to the problem. A major component of the system-wide disturbance protection is the ability to receive systemwide information and commands via the data communication system and to send selected local information to the SCADA centre. This information should reflect the prevailing state of the power system.
1. Introduction
System-wide disturbances in power systems are a challenging problem for the utility industry because of the large scale and the complexity of the power system. When a major power system disturbance occurs, protection and control actions are required to stop the power system degradation, restore the system to a normal state, and minimize the impact of the disturbance. The present control actions are not designed for a fast-developing disturbance and may be too slow. Further, dynamic simulation software is applicable only for off-line analysis. The operator must therefore deal with a very complex situation and rely on heuristic solutions and policies. Today, local automatic actions protect the system from the propagation of the fast-developing emergencies. However, local protection systems are not able to consider the overall system, which may be affected by the disturbance. The trend in power system planning utilizes tight operating margins, with less redundancy, because of new constraints placed by economical and environmental factors. At the same time, addition of non-utility generators and independent power producers, an
Proceedings of the 32nd Hawaii International Conference on System Sciences - 1999 Trends in Power System Protection and Control
Adaptive settings of frequency and frequency derivative relays may enable implementation of a frequency derivative function more effectively and reliably. This will be discused later.
decisions have to be taken locally. The relay system is preferred to be adaptive, in order to cope with system changes. To deal with out-of-step prediction, it is necessary to start with a system-wide approach, find out what sets of information are crucial, how to process information with acceptable speed and accuracy.
separation is controlled from a central site or can be predicted, an algorithm may calculate the settings and assign the appropriate load in coordination with switching actions. However, high speed communication may be required to and from the central location for fastdeveloping disturbances, such as multi-machine angular instability. Another aspect, may be adding a correction element to a scheme. If only slow speed communications are available, a fast load shedding scheme may be implemented to stop system degradation. When adequate information is available, corrective measures may be applied. If the composite system inertia constant is known, the actual power imbalance may be calculated directly from the frequency. This detection should be fast (to avoid a large frequency drop) and done at the location close to the center of inertia. High speed communications are required to initiate load shedding at different power system locations. Further, changes of load and generation, with frequency and addition, the power system imbalance changes after the Thus, relay settings should be based on the spinning reserve, total system inertia, and load characteristics and distribution. In conclusion, sophisticated models and/or high-speed communication may be required for accurate estimation of the amount and distribution of the load to be shed. If communications are available, it is easier and more reliable to calculate the amount of load to shed from the switching information and the mismatch (based on data on load and generation before the separation) in the island. To avoid disadvantages of the underfrequency load shedding and difficulties with implementing the rate-ofchange of frequency function, the automated load shedding that will reduce overloading or prevent system instability before the system is isolated is proposed as an advantageous strategy.
degree of accuracy, (1) whether an out-of-step is imminent, and (2) the boundary across which this out-ofstep will take place. This algorithm has been tested thoroughly using a Monte-Carlo-type approach. At each test, random values are assigned to line impedances, load, generator inertias, as well as disturbance location. It is found that the algorithm is capable of making accurate prediction. To illustrate how the algorithm works, consider the power system shown in Figure 1. This system is a modified version of the IEEE 39-bus test system. In Figure 1, each generator is marked with a circle, and each load with a square; the size of each symbol indicates relatively the power generated or consumed at the node. For example, Generator 34 supplies more MW to the grid than does Generator 38.
38
34
25
33
loads
30
35
36
x outage
31
32
150 100 50
#38
time, sec.
Proceedings of the of the system. Figure 2. Time domain simulation32nd Hawaii International Conference on System Sciences - 1999
Proceedings of the 32nd Hawaii International Conference on System Sciences - 1999 Trends in Power System Protection and Control
A disturbance is introduced to the system where two lines are simultaneously removed (each line is marked by an 'x' in Figure 1). This information is fed to the algorithm, which predicts that an out-of-step will occur across the line 2-25. Figure 2 reveals that the two generators 37 and 38 eventually separate from the other generators. All line angles have been checked and none but line 2-25 indicate the boundary of the out-of-step. The angle of critical line is shown in Figure 3. This confirms the result of the algorithm.
angle of critical lines 0
Mi
i
i B
Di
i
Pai (t )
where
and
-100
rotor angle and its speed relative to the synchronous reference frame, Pai(t) is the accelerating power, i.e. imbalance between the mechanical and mechanical power, Mi is the inertia constant for machine i, B is the synchronous angular frequency, and Di is the damping factor corresponding to the machine i. Swing equation can be linearized to obtain
2-25
deg.
-200 -300 0 1 2
time
A x
B u
Figure 3. Angle of critical line. Such an algorithm requires a centralized scheme and highspeed communication links across the wide system. Decentralized scheme requires communications with a central location. According to this hierarchical scheme, each regional computer issues control actions to alleviate problems that are imminent within its jurisdiction; the coordination among regions is left to the central computer.
where vector x is the vector obtained by concatenating rotor angle deviation vector and rotor speed deviation vector, and u is the vector of power imbalances for each machine. Information about possible modes of the system can now be obtained by eigenanalysis of matrix A, and its participation factors. This however, is not the only way that the information on the oscillatory modes can be obtained. In a system subject to the impulse excitation, the oscillatory modes can be determined from the power spectral density of the system response. In other words, the modes would appear as peaks of the power spectral density function of state variable x calculated as:
where F represents the Fourier transformation. Peaks of the power spectral density correspond to the modes of the interarea oscillations, and can be therefore determined from measurements of x over a time window, if we consider x as a time-frequency distribution. Descriptive (measurement) quantity we use is the machine speed. We think of interarea oscillations as energy exchanges between the groups of the machines, this energy exchange should be visible from the machine speed data. Moreover, the machine speed is easily measurable quantity, thus making a perfect candidate for
Proceedings of the 32nd Hawaii International Conference on System Sciences - 1999 Trends in Power System Protection and Control
descriptive quantity for a pattern recognition task. Algorithm we propose is following: Collect machine speed data. Perform spectrum estimation on machine speed data. Identify the frequencies of possible modes of interarea oscillations. Perform clustering on the phases of machine spectrum data at inter-area frequencies. Identify inter-area groups with clusters of phases of machine spectrum data.
machine belongs. The phase data is summarized in Table 1. Indeed, machines 1 through 8 have the phase angle of approximately 11 degrees, machines 11,12 and 13 have phase angles of approximately 3 degrees, while phase anlges of speed spectra of other machines do not belong
to any of the groups. Table 1. Phase angles of the power spectral density at the interarea oscillation mode at 0.4 Hz. We propose to use the information about groups of machines belonging to interarea modes to formulate an emergency control by modulating the admittance of the thyristor-controlled series capacitor (TCSC). The control we propose is based on the premise that we only want to enhance the stability of the system by applying the admittance adjustment control. The main control still relies on power system stabilizers, which usually perform this task very well. We would like to use the admittance control to minimize the interarea oscillations which are exhibited as the flow of energy between machines or groups thereof. We use the rate of change of machine speeds as an indication of the energy change at particular machine. In that sense, we would keep the undesirable variations of the machine velocities to their minimum, reducing the energy transfers between different groups of machines. In turn, reduced energy exchange reduces the interarea oscillations, which is the goal of our control. While this type of control does not guarantee the stability, it does guarantee that the Lyapunov exponents of a system with such control will be smaller than the ones of the system without the control. This is a result of the facts that machine states are the state variables of linearized system, and that the logarithm is a monotonous function. In that sense, the system is more stable than the system without the control.
Figure 4. Transient disturbance of the test system as described in the text below. We illustrate the performance of the algorithm on the following example: Figure 1 shows the machine speeds of the 16 machine 64-bus NPCC system subject to the fault on line between busses 28 and 29. The fault is cleared by tripping the line after three cycles but still divides machines in three groups thus producing the interarea oscillations. In this simulation we used the transient model for synchronous machines. It is obvious that the system is divided into three groups that oscillate against each other. In one group we have machines 1 through 8, in second machines 11 through 13 and all other machines oscillate by themselves. Modal analysis of the linearized system reveals five oscillatory modes under 1Hz: at 0.4150 Hz, at 0.5564 Hz, at 0.7326 Hz, at 0.8066 Hz, and one at 0.9825 Hz. Participation factor analysis indicates that machines most likely to oscillate at 0.415 Hz are machines 1 through 9 and 13 through 16. Machine 15 seems very prone to the mode at .5Hz, machines 10 through 13 are susceptible to the mode at 0.7326 Hz, and machines 14 through 16 are prone to oscillatory mode at 0.8066 Hz. We use the phase angles of the power spectral density at the given mode to determine the group to which
Proceedings of the 32nd Hawaii International Conference on System Sciences - 1999 Trends in Power System Protection and Control
Moreover, proposed type of control can be computed with a cost of QR decomposition for the matrix of sensitivity coefficients and one matrix multiplication. In addition, this type of the control guarantees the minimum energy solution, i.e. minimum per-sample change of line admittances. The stability of the control computation procedure, low computational cost, and easy parallelization of the process this algorithm very appealing for the real time applications on multiprocessor architectures.
Above two tasks have to be performed with minimum change of the line admittances since the TCSC devices have range typically limited to a certain percentage of the nominal line admittance, for a variety of reasons. Above considerations exclude the apriori knowledge of the fault location. Taking into account the above consideration, selection process may be based on an extensive sensitivity analysis spanning a large number of situations, either by using some form of a composite objective function, or by applying some effective means of combinatorial optimization, such as genetic algorithms. The end result is the allocation of a limited number of TCSC controllers, which perform reasonably well over a finite set of different disturbance scenarios. The results of some comparative tests, obtained by time domain simulation on the system and fault used in Figure 4 are shown below.
dt
k 1
A'
k k
P y
where P is the sensitivity of the machine speed changes with respect to the line admittance. By setting dt 0 , the control is computed as the solution of k following equation:
P y
A'
k k
In contrast to this optimization, control of system modes would imply the minimization of . Since TCSC devices present a permanent change in the topology of a power network, their location needs to be determined before the fault has occurred. Having this in mind, TCSC selection process has to consider several criteria: Various and possibly multiple faults may happen. All machines need to be controlled at the same time to insure the control of all interarea modes (this condition may be relaxed by adaptive tracking of the interarea groups). Since all machines participating in a certain interarea mode will have similar angles and rates of change of angles (speeds), it is technically possible to use just a representative machine from a group. This may be useful in speeding up the control processing to enable real-time control.
Figure 5. Comparison of the machine #16 speeds (fault as per Figure 4): ---. -.-.Original speed in center of inertia reference frame. No control is applied. Machine #16 speed modulation control. with TCSC
solid line Machine #16 speed with both PSS and TCSC controls applied. The presented scenarios involve situations when no control was applied to the system under disturbance, and
Proceedings of the 32nd Hawaii International Conference on System Sciences - 1999 Trends in Power System Protection and Control
when group of 5 optimally selected and tuned PSS and 5 TCSC was used, both individually and together. The opportunity to speed up processing in power system stabilizing devices to enable real-time control is in the inclusion of the distributed architectures, which combine low per-unit cost with high efficiency. The control algorithm we have described in previous section can be easily implemented in the parallel architecture with great reduction of complexity and large parallel efficiency.
economical solution for the wide area problems are very attractive. Intelligent control systems (i.e. systems described in provide more secure operation and better responses, allowing utilities to operate transmission and generation margins.
7. Acknowledgement
Part of the work presented in this paper was funded by the National Science Foundation under Grant #ECS-9404895. We gratefully acknowledge this assistance.
6. Conclusion
A large disturbance such as a sudden outage of a transmission line may trigger a sequence of events leading to machine swings, voltage problem, and eventually power outage in a large area of the system. The role of a protection and control system is to timely predict the system instability, to perform actions to restore the system to a normal state and minimize the impact of the disturbance. As communication and computer technology continue to improve, and protection and control becomes more integrated, an application of adaptive system-wide protection is becoming more feasible. Since any improvement in system-wide protection and control products provides significant savings to utility, the decentralized systems that provide improved and economical solution for the system-wide disturbance problems are very attractive. Automated load shedding that will reduce overloading before the system is isolated is an improved solution in comparison to underfrequency load shedding. Although local measurements may suffice if tasks are simple (eg. protection against few contingencies only), information communicated either from central location or from remote substation seems necessary for more sophisticated requirements. Microprocessor-based coordinated protection, monitoring and control systems are the key to innovations in power system operating philosophy. The coordinated system is clearly the future of relaying technology. As communication and computer technology continue to improve, and protection and control become more integrated, the application of the adaptive wide area disturbance protection concept is becoming more feasible. Since any improvement in the wide area protection and control strategy provides significant savings to the utility, the intelligent systems that provide improved and
8. References
1 L. Cederblad and T. Cegrell, "A New Approach to Security Control of Power Systems -Local Protection Coordinated with System-Wide Operation," IFAC Symposium, Brussels, September 1988. 2 A. P. J. Malt, et al, "Computer Based Supervisory Control and Energy Management System for the City of Cape Town," IEE Proceedings, Vol. 135, pp. 41-50, January 1988. 3 Voltage Stability of Power Systems: Concepts, Analytical Tools, and Industry Experience, IEEE Publication, 90TH03582-PWR, 1990. Davos, Switzerland, Aug. 1994.