Chattergala Pass
Chattergala Pass
Chattergala Pass
(Ministry of Defence)
Government of India
Dec 2018
INDEX
Sl. No. Content Page No.
1 Notice Inviting Tender (NIT) 2-4
2 Letter of Invitation 5-19
3 Annex -I : List of Projects along with Package Nos. 20
4 Annex-II : Procedure of Assessment of Least Cost to BRO under 20
special circumstances.
2. Proposals are hereby invited from eligible Technical Consultant for Engaging Technical
Consultant for preparation of Feasibility Study (FS) and Detailed Project Report (DPR) for
construction of Highway Tunnel including Approach Road across Chattergala Pass,
approximately in between Km 114.00 and Km 151.00 on Basoli-Bani-Bhaderwah road through
EPC Mode under Project Beacon in J & K State. The Letter of Invitation (LOI) and Terms of
Reference (ToR) including Request for Proposal (RFP) is available online on e-tender portal of
NIC https://eprocure.gov.in . The document can also be downloaded from BRO website (for
reference only). Cost of tender documents is not required to be attached/submitted with
downloaded tender.
4. All the bidders registered on Infracon shall form a Team on Infracon and which
would be assigned unique Infracon Team ID. Bidders while submitting the proposal shall
quote the Infracon Team ID.
6. The BRO has appointed Independent Monitors for this pact in consultation with the
Central Vigilance Commission (Name and Address of the Monitors as amended from time to
time, can be referred to on the MoD website at www.mod.nic.in). Following are the
independent monitors for this work:-
Sl No Name of IM E-mail ID
1 Shri Hem Kumar Pande, IAS (Retd) hempande@nic.in
Mobile No:- 9810132693
2 Shri Anjan Kumar Banerjee, IA&AS (Retd) anjan.banerjee@gov.in
Mobile No:- 8853381627
Dear Sir,
1. Introduction
1.1 The Director General Border Roads, Border Roads Organization has been entrusted with
the assignment of Engaging Technical Consultant for preparation of Feasibility Study (FS) and
Detailed Project Report (DPR) for construction of Highway Tunnel including Approach Road
across Chattergala Pass, approximately in between Km 114.00 and Km 151.00 on Basoli-Bani-
Bhaderwah road through EPC Mode under Project Beacon in J & K State, now invites proposal
from Technical consultants for carrying out detailed project report as per details given in
Annexure-1.
1.2 A brief description of the assignment and its objectives are given in the Appendix-I,
“Terms of References”.
1.3 The Director General Border Roads invites Proposals (the “Proposals”) through e-
tender (on-line bid submission) for selection of Technical Consultant (the
“Consultant”) who shall prepare DPR. A Consultant with “a Particular Team” may
submit proposals for more than one package. However, a Consultant is not allowed to
bid for a package with more than one team. For the sake of clarity, it is mentioned that
one consultant cannot submit two proposals/ bids for the same package. A consultant
(either as sole or as in JV/Association) can be awarded only up to 2 packages.
Consultants are hereby invited to submit proposals in the manner as prescribed in the
RFP. A Consultant with “a Particular Team” may submit only one “proof of eligibility
(Part 1)” and “Technical Proposal (Part II)” for any number of packages applied for by
them. However, the packages for which a Consultant with “a Particular Team” applies
should be clearly mentioned. Financial proposal for each package are to be submitted
separately. Financial proposal are only to be submitted online and no hard copy of the
financial proposal should be submitted. The most preferred bidder (H-1) for each
package would be determined on the basis of Quality and Cost as mentioned in the RFP.
Award of work to a Consultant with “a Particular Team” either as sole or as in
JV/Association shall be limited to one package only. In case, a Consultant with “a
Particular Team” turns out to be the most preferred bidder (H-1) in more than one
package, the package which is to be awarded to this Consultant with “a Particular Team”
shall be determined on the basis of least cost to Director General Border Roads (BRO)
considering the financial quote of H-1 bidder and H-2 bidder limited to those packages,
which shall be worked out as per the procedure given in the RFP. The consultants are
hereby invited to submit proposals in the manner prescribed in the RFP.
1.4 The consultants shall submit proposals either in sole capacity or in JV or in Association.
Joint Venture/Association shall not have more than two firms. Any entity which has
been barred by the Ministry of Road Transport and Highways (MORTH) or its
implementing agencies for the works of Expressways, National Highways, ISC and EI
Works and the bar subsists as on the date of application, would not be eligible to submit
the bid, either individually or as a member of a Joint Venture.
1.5 To obtain first hand information on the assignment and on the local conditions, the
consultants are encouraged to pay a visit to the client, local State PWDs and the project
site before submitting a proposal and attend a pre-proposal conference. They must fully
inform themselves of local and site conditions and take them into account in preparing
the proposal.
1.6 Financial Proposals will be opened only for the firms found to be eligible and scoring
qualifying marks in accordance with Para 5 hereof. The consultancy services will be
awarded to the highest ranking consultant on the basis of Quality and Cost.
1.7 Please note that (i) costs of preparing the proposal and of negotiating the contract,
including visits to the Client, etc., are not reimbursable as a direct cost of the
assignment; and (ii) BRO is not bound to accept any of the proposals submitted and
reserve the right to reject any or all proposals without assigning any reasons.
1.8.3 In case of Joint venture, one of the firms which preferably have relatively higher
experience will act as the lead firm representing the Joint Venture. The duties,
responsibilities and powers of such lead firm shall be specifically included in the MOU
/agreement. It is expected that the lead partner would be authorized to incur liabilities
and to receive instructions and payments for and on behalf of the Joint Venture. Payment
to be made to the JV can also be made to the account of the JV. For a JV to be eligible
for bidding, the experience of lead partner and other partner should be as indicated in
data sheet.
1.8.4 A firm can bid for a project either as a sole consultant or in the form of joint venture
with other consultant or in association with any other consultant. However, alternative
proposals i.e. one as sole or in JV with other consultant and another in association / JV
with any other consultant for the same package will be summarily rejected. In such
cases, all the involved proposals shall be rejected.
1.9 Pre-proposal conference shall be held on the date, time and venue given in Data Sheet.
1.10.1 The applicant shall furnish as part of its Proposal, a Bid Security of Rs 2,00,000 (Rupees
two lakhs only) in the form of a Bank Guarantee issued by one of the
Nationalized/Scheduled Banks in India in favour of the CE (P) BEACON payable at Sri-
Nagar (J&K) (the “Bid Security”) valid for a minimum period of 150 days (i.e.30
days beyond the validity of the bid) from the last date of submission of proposals.
This Bid Security is returnable not later than 30 (thirty) days from the date of Opening of
the Financial proposals except in case of the two highest ranked Applicants. Bid Security
of the Selected Applicant and the Second ranked Team shall be returned, upon the
Selected Applicant signing the Agreement.
1.10.2 Any bid not accompanied by the Bid Security of the required value and minimum
required validity shall be rejected by the authority as non-responsive.
1.10.3 The CE (P) Beacon shall not be liable to pay any interest on the Bid Security and the
same shall be interest free.
1.10.4 The Applicant, by submitting its Application pursuant to this RFP, shall be deemed to
have acknowledged that without prejudice to the CE (P) Beacon any other right or
remedy hereunder or in law or otherwise, the Bid Security shall be forfeited and
appropriated by the Authority as the mutually agreed pre-estimated compensation and
damage payable to the Authority for, inter alia the time, cost and effort of the CE (P)
Beacon in regard to RFP including the consideration and evaluation of the Proposal
under the following conditions :
2.1 To enable you to prepare a proposal, please find and use the attached documents listed in
the Data Sheet.
2.2 Consultants requiring a clarification of the documents must notify the Director General
Border Roads, in writing, by 15:00 Hrs, 17 Dec 2018. Any request for clarification in
writing or by tele-fax/e-mail must be sent to the address given for pre-proposal
conference as indicated in the Data Sheet. The Director General Border Roads will
replies to pre-bid queries in writing by Tele fax/E-Mail/uploaded on BRO site. Any
clarification leading to amendment to RFP will be uploaded on CPP/Infracon Portal.
2.3 At any time before the submission of proposals, the BRO may, for any reason, whether
at its own initiative or in response to a clarification requested by a Consulting firm,
modify the Documents by amendment or corrigendum. The amendment will be uploaded
on BRO website, www.bro.gov.in. The Director General Border Roads may at its
discretion extend the deadline for the submission of proposals and the same shall also be
uploaded on BRO website, www.bro.gov.in.
3. Preparation of Proposal
The proposal must be prepared in three parts viz,
Part 1 : Proof of eligibility
Part 2 : Technical Proposal
Part 3 : Financial Proposal
3.1.1 The minimum essential requirement in respect of eligibility has been indicated in the
Data Sheet. The proposal found deficient in any respect of these requirements will not be
considered for further evaluation. The following documents must be furnished in support
of proof of eligibility as per Formats given in Appendix-II:
(ii) Firm‟s relevant experience and performance for the last 10 years: Project sheets in
support of relevant experience as per Form-E2/T3 supported by the experience
certificates from clients in support of experience as specified in data sheet for the project
size preferably in terrain of similar nature as that of proposed project shall be submitted.
The experience certificate should indicate clearly the firms DPR experience in Tunnels
related to Highway/Railway/Metro project preferably in hilly terrain, details (including
configuration) of structures for hill slope stabilization, rock bolting, ground
improvement, 2/4/6 laning of highway etc. Scope of services rendered by the firm
should be clearly indicated in the certificate obtained from the client. The information
given in Form E2/T3 shall also be considered as part of Technical Proposal and shall be
evaluated accordingly.
Signature of contractor For Accepting Officer
CA NO CE (P) BEACON/ /2018-19 Srl Page No. 09
Tender No. CE (P)/BEACON/DPR CONSULTANCY/07/2018-19
The Consultants are therefore advised to see carefully the evaluation criteria for
Technical Proposal and submit the Project Sheets accordingly.
(iii) Firm‟s turnover for the last 5 years: A tabular statement as in Form E3 showing the
turnover of the applicant firm(s) for the last five years beginning with the last financial
year certified by the Chartered Account along with certified copies of the audit reports
shall be submitted in support of the turnover.
(iv) Document fee: The fee for the document is not required to be attached/submitted.
(v) Bid Security: Bank Guarantee in support of bid security for an amount specified in Data
Sheet and having validity for a minimum period of 150 days (i.e. 30 days beyond the
validity of the bid), from the last date of submission of proposals in the Form E4.
(vi) Power of Attorney on a stamp paper of Rs.100 and duly notarized authorizing to submit
the proposal.
3.1.2 The minimum essential requirement in respect of eligibility has been indicated in the
data sheet, the proposal found deficient in any respect of these requirements will not be
considered for further evaluation.
3.2.1 You are expected to examine all terms and instructions included in the Documents.
Failure to provide all requested information will be at your own risk and may result in
rejection of your proposal.
3.2.2 During preparation of the technical proposal, you must give particular attention to the
following:
3.2.3 The technical proposal shall be submitted strictly in the Formats given in Appendix- III
And shall comprise of following documents:
i) Forwarding letter for Technical proposal duly signed by the authorized person on
behalf of the bidder, as in Form-T-1
ii) Details of projects for which Technical and Financial Proposals have been
submitted by a Consultant with a particular Team as in Form-T-2
iii) Firm‟s references - Relevant Services carried out in the last seven years as per
Form-E2/T-3. This information submitted as part of Proof of Eligibility shall be
evaluated and need not be submitted again as a part of the Technical proposal
iv) Site Appreciation: limited to four A4 size pages in 1.5 space and 12 font
including photographs, if any (Form-T-4).
v) Comments on Terms of Reference: limited to two A4 size pages in 1.5 space and
12 font (Form-T-5).
vi) The composition of the proposed Team and Task Assignment to individual
personnel: Maximum three pages (Form-T-6).
vii) Proposed methodology for the execution of the services illustrated with bar
charts of activities, including any change proposed in the methodology of
services indicated in the TOR, and procedure for quality assurance: Maximum 4
pages (Form-T-7)
viii) The proposal should clearly identify and mention the details of Material Testing
lab facilities to be used by the Consultants for the project (Form-T-8). In this
connection, the proposals of the Consultants to use in-house lab facilities up to a
distance of maximum 400 km from the project site being feasible would be
accepted. For all other cases suitable nearby material Testing Laboratory shall be
proposed before Contract Agreement is executed.
ix) The proposal shall indicate as to whether the firm is having the facilities for
carrying out the following field activities or these are proposed to be outsourced
to specialized agencies in the Form- T-9.
a) Pavement Investigation
b) Geo-technical Investigation
In case the consultant envisages outsourcing any or all of the above services to the
expert agencies, the details of the same indicating the arrangement made with the
agencies need to be furnished. These agencies would however, be subject to approval
of the Director General Border Roads to ensure quality input by such agencies
during technical negotiation before award of the work. For out-sourced services,
proposed firms/consultants should have such experience on similar projects
ii. No alternative to key personnel may be proposed and only one CV may be
submitted for each position. The minimum requirements of Qualification and
Experience of all key personnel are listed in Enclosure-II of TOR. CV of a person
who does not meet the minimum experience requirement as given at enclosure-II of
TOR shall be evaluated and the marks obtained shall be taken into consideration
during evaluation of Technical Proposal (except Team leader). However if a firm
with such key personnel is declared the “most preferred bidder” for a particular
package , such key personnel should be replaced at the time of Contract
Negotiations with a person meeting requirements of Qualification and Experience
as given at enclosure-II of TOR and whose CV secures 75 % marks and above. If a
proposed key personnel does not possess the minimum (essential) educational
qualification as given at enclosure-II of TOR, Zero marks shall be assigned to such
CV and such CV shall not be evaluated further. The CV of the proposed Team
Leader should score at least 75 % marks otherwise the entire proposal shall be
considered to have failed in the evaluation of Technical Proposals and shall not
be considered for opening of Financial Proposals.
iii. Team Leader, Highway cum Pavement Engineer, Bridge Engineer, Geo-technical
cum material engineer and Senior Survey Engineer should be available from
beginning of the project. 3 Key Personnel namely Environmental Specialist,
Quantity Surveyor / Documentation expert and Traffic and safety expert are
allowed to be deployed/proposed in 2 teams at a time. If same CV is submitted by
two or more firms, zero marks shall be given for such CV for all the firms.
iv. The availability of key personnel must be ensured for the duration of the project as
per proposed work programme. If a firm claims that a key personnel proposed by
them is a permanent employee of the firm ( the personnel should have worked in
the firm continuously for a period of at least 1 year) , a certificate to the effect
along with pay slips are required to be submitted.
v. The age limit for key personnel is 70years as on the date of bid submission except
for Senior survey engineer in which case the age limit is 65 years. The proof of age
and qualification of the key personnel must be furnished in the technical proposal.
vi. An undertaking from the key personnel must be furnished that he/she will be
available for entire duration of the project assignment and will not engage
himself/herself in any other assignment during the currency of his/her assignment
on the project. After the award of work, in case of non-availability of key personnel
in spite of his/her declaration, he/she shall be debarred for a period of two years
for all projects of BRO
vii. Age limit for supporting staff to be deployed on project is 65 years as on the date
of bid submission.
viii. A good working knowledge of English Language is essential for key professional
staff on this assignment. Study reports must be in English Language.
ix. Photo, contact address and phone/mobile number of key personnel should be
furnished in the CV.
xi. It may please be noted that in case the requirement of the „Experience‟ of the
firm/consortium as mentioned in the “Proof of Eligibility‟ is met by any foreign
company, their real involvement for the intended project shall be mandatory. This can
be achieved either by including certain man-months input of key experts belonging to
the parent foreign company, or by submitting at least the draft feasibility report and
draft DPR duly reviewed by the parent firm and their paying visit to the site and
interacting with CE (P) Beacon. In case of key personnel proposed by the foreign
company, they should be on its pay roll for at least last six months (from the date
of submission).
xiii. Original Curriculum Vitae (CV) and photocopies of certificates shall be recently
signed in blue ink by the proposed key professional staff on each page and also
initialed by an authorized official of the Firm and each page of the CV must be
signed. The key information shall be as per the format. Photocopy of the CVs will
not be accepted. Unsigned copies of CVs shall be rejected.
3.2.5 The technical proposal must not include any financial information.
3.3.1 The Financial proposal should include the costs associated with the assignment. These
shall normally cover: remuneration for staff (foreign and local, in the field, office etc),
accommodation, transportation, equipment, printing of documents, surveys, geotechnical
investigations etc. This cost should be broken down into foreign and local costs. Your
financial proposal should be prepared strictly using, the formats attached in Appendix –
IV. Your financial proposal should clearly indicate the amount asked for by you without
any assumptions of conditions attached to such amounts. Conditional offer or the
proposal not furnished in the format attached in Appendix-IV shall be considered non-
responsive and is liable to be rejected.
3.3.2 The financial proposal shall take into account all types of the tax liabilities including
GST and cost of insurance specified in the Data Sheet.
3.3.3 Costs shall be expressed in Indian Rupees in case of domestic as well as for foreign
Consultant. The payments shall be made in Indian Rupees by the CE (P) Beacon and the
Consultant themselves would be required to obtain foreign currency to the extent quoted
and accepted by CE (P) Beacon. Rate for foreign exchange for payment shall be at the
rate established by RBI applicable at the time of making each payment installment on
items involving actual transaction in foreign currency. No compensation done to
fluctuation of currency exchange rate shall be made.
3.3.4 Consultants are required to charge only rental of equipments/ software(s) use so as to
economize in their financial bid.
4 Submission of Proposals
4.1 The Applicants shall submit the proposal (Proof of Eligibility and Technical Proposal) in
hard bound form with all pages numbered serially and by giving and index of submissions.
Applications submitted in other forms like spiral bound form; loose form etc shall be
rejected. Copies of Applications shall not be submitted and considered. A Consultant with
“a Particular Team” may submit only one hard copy (in original) of “proof of eligibility
(Part 1)” and “Technical Proposal (Part II)” to Director General Border Roads for all the
packages applied by them with a particular team on or before the deadline of submission
of bids. A consultant can apply for a particular package with one team only. The
packages for which a Consultant with “a Particular Team” applies should be clearly
mentioned in their proposal. However, Consultants are required to submit a copy of
Proof of Eligibility and Technical Proposal online separately for each package. Financial
proposal for each package are to be submitted separately. Financial proposal are only to
be submitted online and no hard copy of the financial proposal should be submitted.
4.2 You must submit original proposal as indicated in the Data Sheet. “Proof of Eligibility” in
original and hard bound should be enclosed in an envelope which should be marked as
“Part-I – Proof of Eligibility”. Similarly, “Technical Proposal” in original and hard bound
should be enclosed in an envelope which should be marked as “Part-II – Technical
Proposal” The proposal will be sealed in an outer envelope which will bear the address
and information indicated in the Data Sheet and shall be submitted to Director
General Border Roads on or before the deadline for submission of bids. The envelope
must be clearly marked:
5 Proposal Evaluation
5.3.2 The evaluation committee will determine whether the financial proposals are complete
(i.e. whether they have included cost of all items of the corresponding proposals ; if not,
then their cost will be considered as NIL but the consultant shall however be required to
carry out such obligations without any compensation. In case, if BRO feels that the work
cannot be carried out within overall cost of financial proposal, the proposal can be
rejected. The BRO shall correct any computational errors and correct prices in various
currencies to the single currency specified in Data Sheet. The evaluation shall exclude
those taxes (including GST), duties, fees, levies and other charges imposed under the
applicable law applied to foreign components/ resident consultants.
5.3.3 The procedure as mentioned at Clauses 5.3.4, 5.4 and, 5.5 as mentioned below shall be
followed for determining the “most preferred bidder (H-1 bidder)” for this package.
5.3.4 The lowest financial proposal (FM) will be given a financial score (SF) of 100 points.
The financial scores of other proposals will be computed as follows:
SF = 100 x FM/F
(SF = Financial Score, FM= Amount of lowest bid, F= Amount of financial proposal
converted in the common currency)
S= STxT + SFxf
Where,
S = Combined Score,
ST = Technical Score out of 100
SF = Financial Score out of 100
T and f are values of weightage for technical and financial proposals respectively as
given in the Data Sheet.
5.5 For a package, a Consultant with a “particular Team” having the maximum Combined
score (S) shall be declared as the most preferred bidder (H-1).
In case work has to be awarded for multiple packages, award of work to a Consultant
with “a Particular Team” either as sole or as in JV/Association shall be limited to one
package only. At first, Consultants who become H-1 in one package each shall be
assigned the respective package. Then packages in which a Consultant with “a Particular
Team” turns out to be the most preferred bidder (H-1) in more than one package shall be
considered. In case, a Consultant with “a Particular Team” turns out to be the most
preferred bidder (H-1) in more than one package, the package which is to be awarded to this
team of a consultant shall be determined on the basis of least cost to Director General
Border Roads considering the Financial Quote of H-1 bidder and H-2 Bidder limited to
those packages. Procedure to be followed for awarding work based on QCBS including
assessment of least cost to BRO under special circumstances i.e. When a Consultant with “a
Particular Team” turns out to be the most preferred bidder (H-1) in more than one package is
given at given at Annex-II.
6. Negotiations
6.1 Prior to the expiration period of proposal validity, the Client will notify the most
preferred Consultant/Bidder i.e. the highest ranking consultant in writing by registered
letter, e-mail, or facsimile and invite him to negotiate the Contract.
6.2 Before the start of negotiations, the most preferred Consultant/Bidder (H-1) shall
be asked to give justification for the cost quoted by them to the full satisfaction of
Director General Border Roads (DGBR).
Each key personnel of the preferred consultant shall be called for interview at the time
of negotiation at the cost of consultant before the award of work.
6.3 Negotiations normally take two to three days. The aim is to reach agreement on all
points and initial a draft contract by the conclusion of Negotiations.
6.4 Negotiations will commence with discussion on technical proposal, the proposed
methodology (work plan), staffing and any suggestions made to improve the TOR, the
staffing and bar charts, which will indicate activities, periods in the field and in the home
office, staff months, logistics and reporting. The financial proposal is subject to
rationalization. Special attention will be paid to optimize the required outputs from the
Consultants within the available budget and to define clearly the inputs required from
the BRO to ensure satisfactory implementation of the Assignment.
6.5 Changes agreed upon will then be reflected in the financial proposal using proposed unit
rates.
6.6 Having selected Consultants, among other things, on the basis of an evaluation of
proposed key professional staff, the BRO expects to negotiate, within the proposal
validity period, a contract on the basis of the staff named in the proposal and, prior to
contract negotiations, will require assurances that the staff will be actually available.
The DGBR may ask to give a replacement for the key professional who has scored
less than 75% marks by a person of at least 75% score. No reduction in
remuneration would be made on account of above change.
The DGBR will not consider substitutions during contract negotiations except in cases of
incapacity of key personnel for reasons of health. Similarly, after award of contract the
DGBR expects all of the proposed key personnel to be available during implementation of
the contract. The client will not consider substitutions during contract negotiations/ contract
implementation except under exceptional circumstances. For the reason other than death/
extreme medical ground, where replacement is proposed by the Consultant due to non
availability of the originally proposed key personnel or in cases where replacement has
become necessary as a key personnel proposed by the Consultant has been found to be
unsuitable for the project by Director General Border Roads during contract negotiations
/ contract implementation , the following shall apply
(i) for total replacement up to 33% of key personnel, remuneration shall be reduced by
5%
(ii) for total replacement between 33% to 50%, remuneration shall be reduced by 10%
(iii) for total replacement beyond 50% and 66% remuneration shall be reduced by 15%
(iv) for total replacement beyond 66% of the total key personnel, the Client may initiate
action for debarment of such consultant for future projects of BRO for a period of 6
months to 24 months. If for any reason beyond the reasonable control of the
consultants, it becomes necessary to replace any of the personnel, the consultants
shall forthwith provide as a replacement a person of equivalent or better
qualification and experience.
6.7 The negotiations will be concluded with a review of the draft Contract Agreement
attached at Appendix-V. The Client and the Consultants will finalize the contract to
conclude negotiations.
6.8 If a Consultant fails to conclude the negotiations with BRO or in case a consultant
withdraws without starting / completing the negotiations with BRO, it shall attract
penalty – encashment of Bid Security submitted by the Consultant
7. Performance Security
The consultant will furnish within 15 days of the issue of Letter of Acceptance (LOA),
an unconditional Bank Guarantee from a Nationalized Bank, IDBI or ICICI/ICICI
Bank/Foreign Bank/EXIM Bank / Any Scheduled Commercial Bank approved by RBI
having a net worth of not less than 500 crore as per latest Annual Report of the Bank. In
the case of a Foreign Bank (issued by a Branch in India) the net worth in respect of
Indian operations shall only be taken into account. In case of Foreign Bank, the BG
issued by Foreign Bank should be counter guaranteed by any Nationalized Bank in
India. In case of JV, the BG shall be furnished on behalf of the JV or by the lead
member of the JVs for an amount equivalent to 10 % of the total contract value to be
received by him towards Performance Security valid for a period of two years beyond
the date of completion of services, or end of civil works contract, whichever earlier. The
Bank Guarantee will be released by CE (P) Beacon upon expiry of 2 years beyond
the date of completion of services, or end of civil works contract, whichever earlier,
provided rectification of errors if any, found during implementation of the contract
for civil work and satisfactory report by CE (P) Beacon in this regard is issued. If a
Consultant fails to submit the Performance Security (as specified above), it shall attract
penalty – encashment of Bid Security submitted by the Consultant
8. Penalty
The consultant will indemnify for any direct loss or damage that accrue due to
deficiency in services in carrying out Detailed Project Report. Penalty shall be imposed
on the consultants for poor performance/deficiency in service as expected from the
consultant and as stated in General Conditions of Contract.
9. Award of Contract
After successful Negotiations with the selected Consultant the CE (P) Beacon shall issue
letter of award and ask the Consultant to provide Performance Security as in Para 7
above. If negotiations (as per para 6 above) fail or the selected Consultant fail to provide
performance security within the prescribed time or the Consultant fail to sign the
nd
Contract Agreement within prescribed time the BRO may invite the 2 highest ranking
bidder Consultant for Contract negotiations and follow the procedure outlined in Para 6,
9 and 10 of this Letter of Invitation.
After having received the performance security and verified it, the CE (P) Beacon
(BRO) shall invite the selected bidder for signing of Contract Agreement on a date and
time convenient to both parties within 15 days of receipt of valid Performance Security.
11. The Director General Border Roads shall keep the bidders informed during the entire
bidding process and shall host the following information on its website:
i) Notice Inviting Tender (NIT)
ii) Request For Proposal (RFP)
iii) Replies to pre-bid queries, if any
iv) Amendments / corrigendum to RFP
12. Confirmation
Thanking you.
Yours sincerely,
Annex-II
Deleted
DATA SHEET
(The Name of project and Package No. should be indicated in the format given in the
technical proposal)
(ii). Limitations of the Consultant‟s Liability towards the BRO shall be as per
Clause3.4 of Draft Contract Agreement.
(iii). The risk and coverage shall be as per Clause 3.5 of Draft Contract Agreement
8. The number of copies of the proposal required to be submitted: 1 no. (ref. para 4.1)
i) Original Proposal;
ii) Documents in proof of eligibility and technical proposal as appropriate; and,
iii) Do not open, except in presence of the evaluation committee on the outer
envelope.
iv) Tender No. :----------
v) Project Name: ------------
vi) Name and Address of Consultant
12.1 First stage evaluation – eligibility requirement. (Ref Para 3.1& 5.1)
i) The sole applicant shall fulfill all the requirements given in Table-1.
(ii) In case of JV, the Lead Partner should fulfill at least 75% of all eligibility requirements
and the other partner shall fulfill at least 50% of all eligibility requirements.
(iii) If the applicant firm has / have prepared the DPR/Feasibility Study (FS)/Design
Consultancy projects solely on its own, 100%weightage shall be given. If the applicant
firm has prepared the DPR/FS projects as a
lead partner in a JV, 75% weightage shall be given. If the applicant firm have prepared the
DPR projects as the other partner (not lead partner) in a JV 50% weightage shall be given.
If the applicant firm have prepared the DPR/Feasibility Study (FS)/Design Consultancy
projects as an associate, 25% weightage shall be given.
As tunnel projects require specialized capabilities and skill sets, the following is the break-up:
1.1.1 More than 60% the indicative Length of the package 7.50
applied for
1.1.2 More than the indicative Length of the package applied 10.00
for
1.1.3 More than 2 times the indicative length of the package 12.50
applied for
1.1.4 More than 3 times the indicative length of the package 15.00
applied for
4.1 1 project
4.2 2 projects
4.3 3 projects
4.4 4 projects
4.5 5 or more projects
5 Vertical/Inclined drilling including sampling >1200 m
11
in One project
1 project 5
2 projects 8
3 or more projects 11
Max
S. No. Description
points
(i) Site Appreciation 5
(ii) Comments on TOR 5
(iii) Team Composition and Task
assignment 5
(iv) Methodology 5
Total Points 20
Rating given below shall be applicable on all above
Below Average. Average Good Excellent
50% 75% 90% 100%
The number of points assigned during the evaluation of qualification and competence of key
staff are as given below:
12.3 Detailed evaluation criteria which is to be used for evaluation of technical bids is as
indicated at Appendix-V.
The Consultant should carryout self-evaluation based on the evaluation criteria at
Appendix-V. While submitting the self-evaluation along with bid, Consultant shall
make references to the documents submitted in their proposal which have been
relied upon in self-evaluation.
Result of technical evaluation shall be made available to the bidders through e-mail
and giving opportunity to the bidders to respond within 7 days in case they have
any objection
APPENDIX I
1.2 CE (P) Beacon will be the employer and executing agency for the consultancy services
and the standards of output required from the appointed consultants are of international
level both in terms of quality and adherence to the agreed time schedule.
1.3 The Selected Consultancy firm shall prepare and submit Detailed Project Report (DPR)
for the Tunnel along with Approach Road separately.
2. Objective
2.1 The main objective of the consultancy service is to prepare detailed project report for
Construction of Tunnel along with the approach Roads, with a aim to construct/provide all
weather roads across Chattergala Pass. The approach roads would be of 4/2-lane plus
paved shoulders configuration based on the approved tunnel alignment & configuration.
The above said project site locations are Avalanche and landslide prone and Hence,
Avalanche Protection works and slope stabilization measures are required to be provided
to make it all weather road. The consultants are required to undertake detailed study in this
regard in consultation with Snow and Avalanche Study Establishment (SASE) and other
Authorities working in the region. The selected Consultant is required to establish the
technical, economical, and financial viability of the project and prepare Detailed Project
Report for development and construction of Project Tunnel and their approach roads.
2.2 The viability of the project shall be established taking into account the requirements with
regard to construction of project tunnel as per Annexure-I based on Tunnel alignment &
design, approach roads highway pavement design, avalanche protection measures,
provision of service roads wherever necessary, type of intersections, rehabilitation and
widening of existing and/or construction of new bridges and structures, Tunnel/road safety
features, quantities of various items of works, cost estimates alongwith economic analysis.
Planning for a road tunnel requires multi-disciplinary involvement and assessments, and
generally adopt the same standards as for surface roads and bridge options, with some
exceptions. Certain considerations, such as lighting, ventilation, life safety, operation and
maintenance, etc must be addressed specifically. In addition to the capital construction
cost, a life cycle cost analysis should be performed taking into account the life expectancy
of 120 years for a tunnel.
2.4 The DPR consultant should ensure detailed project preparation incorporating aspects of
value engineering, quality audit and safety audit requirement in design and
implementation. The DPR Consultant should give a certificate in the DPR that they have
addressed the safety related concern with inputs from the road safety expert (to be named).
2.5 The consultant should, along with Feasibility Report, clearly bring out through financial
analysis the preferred mode of implementation on which the Tunnel Construction Works
along with approaches are to be taken up. The consultant should also give cost estimates
along with Feasibility Report/ Detailed Project Report.
2.6 If at feasibility stage, employer desire to terminate the contract, the contract will be
terminated after payment up to that stage.
3. Scope of Services for Tunnel
3.1 The early investigations for planning and feasibility studies can be confined to information
studies and preliminary reconnaissance. Geological mapping and minimum subsurface
investigations are typically required for EIS, alternative studies and conceptual design. EIS
studies may also include limited topographical and environmental investigations to
identify potential “fatal flaws” that might stop the project at a later date. A substantial
portion of the geotechnical investigation effort should go into the Preliminary Design
Phase to refine the tunnel alignment and profile once the general corridor is selected, and
to provide the detailed information needed for design. As the final design progresses,
additional test borings might be required for fuller coverage of the final alignment and for
selected shaft and portal locations. Lastly, depending on the tunneling method selected,
additional investigations may be required to confirm design assumptions, or to provide
information for contractor design of temporary works. Figure 3-2 illustrates the flow
process of the phases of investigations.
3.2 Deleted
3.3.1 The first phase of an planning & investigation program for a road tunnel project starts with
collection and review of available information to develop an overall understanding of the
site conditions and constraints to identify existing conditions and features that may impact
the design and construction of the proposed tunnel, and can guide in planning the scope
and details of the subsurface investigation program. Published topographical,
hydrological, geological, geotechnical, environmental, zoning, and other information must
be collected, organized and evaluated. Historical seismic records, records of Avalanches &
landslides caused by earthquakes, documented by SASE and other Government Agencies
be analyzed to avoid locating tunnel portals and shafts at these potentially unstable areas.
The inversion results can be visualized in several ways. One way involves creating maps over the
investigation area that depict mean resistivity in a certain depth or elevation interval. If viewed
successively, these slices show how resistivity changes with depth in the investigation area.
Resistivity-depth sections shall also be extracted from the inverted data along profiles.
Ultimately, individual resistivities can be interpreted as different geological units (i.e. bedrock
topography). Conductive areas can be distinguished from less conductive areas. Additional
geological or geophysical surface data required for reliable interpretation must be obtained.
3.4.1.2 Interpretation and Extraction of Geological Models
The maps and vertical sections shall be interpreted by a team of geophysicist/geologist, geologists
and geotechnicians. Correlation between the resistivity models and borehole logs can provide
potential extend of weakness zones. Requirements and Positions for further subsurface
investigations with „Vertical and Inclined Coring‟ and „Horizontal and Directional Coring‟ shall
be recommended based on report given by the team.
Based on geological models developed, the Consultant shall suggest the most viable, economical
alignment after carrying out Risk Assessment.
3.5.2 Topographic data compilation
After finalisation of Alignment and Portal location, detailed topographic maps, plans and
profiles must be developed to establish primary control for final design and construction based on
a high order horizontal and vertical control field survey. As on a road tunnel system, centerline of
the roadway and centerline of tunnel may not identical because of clearance requirements for
walkways and emergency passages, A tunnel centerline developed during design should be
composed of tangent, circular, and transition spiral sections that approximate the complex
theoretical tunnel centerline within a specified tolerance. This centerline should be incorporated
into the drawings of the tunnel, and all tunnel control should be based on this centerline.
Topographical survey and mapping, structural and stratographical maps, Isopak maps,
preparation of cross sections. (Quantum of Survey shall be as per relevant Indian standard (IS
Code) or international Code (S) for high way Tunnels)
Ground marking of alignment and report on tentative tunnel alignment, section, grade,
portal positions and finding altitude and grid reference of the portal
3.5.3.1 A road tunnel cross section must be able to accommodate the horizontal and vertical
traffic clearances, as well as the other required elements. The typical cross section elements
include:
• Travel lanes
• Shoulders
• Sidewalks/Curbs
• Tunnel drainage
• Tunnel ventilation
• Tunnel lighting
• Tunnel utilities and power
• Water supply pipes for firefighting
• Cabinets for hose reels and fire extinguishers
• Signals and signs above roadway lanes
• CCTV surveillance cameras
• Emergency telephones
• Communication antennae/equipment
• Monitoring equipment of noxious emissions and visibility
Life Safety
Emergency egress illuminated signs at low level (so that they are visible in case of a fire or
smoke condition)
Additional elements conforming to IRC SP 91and other standards may also be needed under
certain design requirements and should be taken into consideration when developing the tunnel
geometrical configuration.
Clearance profile of all potential vehicles traversing the tunnel shall be established using dynamic
vehicle envelopes which consider not just the maximum allowable static envelope, but also other
dynamic factors such as bouncing, suspension failure, overhang on curves, lateral motion,
resurfacing, etc. The clearance profile should take into consideration potential future vehicle
heights, vehicle mounting on curbs, construction tolerances, and any potential ground and
structure settlement. Ventilation equipment, lighting, guide signs, and other equipment should not
encroach within the clearance profile. Vertical clearance should be selected as per IRC‟s
recommendations. The vertical clearance shall also take into consideration for future resurfacing
of the roadway once. Consideration should also be given for potential truck mounting on the
barrier in the tunnel or on low sidewalk and measures shall be used to prevent such mounting
from damaging the tunnel ceiling or tunnel system components mounted on the ceiling or the
walls.
3.6 SUB-SURFACE INVESTIGATION
Subsurface investigation is the most important type of investigations to obtain ground conditions,
as it is the principal means for:
• Defining the subsurface profile (i.e. stratigraphy, structure, and principal soil and rock types)
• Determining soil and rock material properties and mass characteristics;
• Identify geological anomalies, fault zones and other hazards (squeezing soils, methane gas, etc.)
• Defining hydrogeological conditions (groundwater levels, aquifers, hydrostatic pressures, etc.);
and
• Identifying potential construction risks.
Subsurface investigations will involve borings, sampling, in situ testing, geophysical
investigations, and laboratory material testing. These investigations shall provide factual
information about the distribution and engineering characteristics of soil, rock and groundwater at
a site, allowing an economical design, determining a reliable construction cost estimate, and
reducing the risks of construction.
Induction of a complete drilling equipment and complete set of accessories including water pumps
etc. required for the job at the tunnel site (bore hole location) in good serviceable condition for the
first time and induction of directional coring equipment in any length along the proposed
directional coring trajectory including its de-induction after completion of all works.
b) Determination of in situ stress field by over coring methods or any other techniques available
such as hydro-fracture technique.
c) Water percolation tests are to be conducted in the hole at ground level, at every six metre
depth intervals, at proposed tunnel grade level and at the junction of different lithological strata at
three different pressures as per relevant IS Codes.
d) Any deviation of holes from verticality is to be actually measured accurately and reflected.
2 (a) Bore hole locations and their depths are indicated as guide lines only. Final locations, their
dimensions, choice of field tests and their interval, choice of drilling equipment, establishing the
correct procedure for drilling, sampling and field tests including any additional holes are to be
suitably modified with approval of department.
2(b) The report is to bring out clearly the technical and other problems that may be encountered
during the construction and maintenance of the tunnel and also clear recommendations regarding
the feasibility of the tunnel in the prevailing conditions. Final portal locations, tunnel sections and
geometrics to be defined in this report.
2 (c) Preliminary indications of cost of the tunnel project and the time involved for the
construction to be indicated. In short, report should be self explanatory to enable the department
to take a decision regarding feasibility of the tunnel, expertise available within the country for
construction and preliminary costs for purposes of getting Administrative Approval for the works.
This report should also bring out other detailed studies involved at pre-construction stage,
construction stage and post construction stage.
Vertical and inclined test borings and soil/rock sampling are key elements of any
subsurface investigations for underground projects. The location, depth, sample types and
sampling intervals for each test boring must be finalised based on geological models developed.
In general, borings should be extended to at least 1.5 tunnel diameters below the proposed tunnel
invert. However, if there is uncertainty regarding the final profile of the tunnel, the borings should
extend at least two or three times the tunnel diameter below the preliminary tunnel invert level.
Drilling vertical holes (core drilling) one at each portal sites & at distances as laid down in
IRC:SP:91 between portal measured along the proposed tunnel alignment from any portal end
down to the tunnel grade (preferably at or near the junction of different lithological strata) which
may involved diamond drilling using NX-Bits to the extent of 400 metres for an individual hole.
Additional holes if required in this area shall be undertaken by BX- Bits, if unavoidable, will be
resorted to only with prior approval of the department.
Drilling 04 vertical boreholes of approx 400 m depth up to tunnel grade along the
alignment at suitable locations and Drilling four (4) Inclined holes (core drilling)at an angle of 30
degrees (Approx) with vertical , one at 50 mtr distance& another at 100 mtr distance from each
portal sites measured along the proposed Tunnel alignment or as required, down to the tunnel
grade as specified in IRC:SP:91 which may involve diamond drilling using NX-Bits to the extent
of 400 meters for an individual hole. The inclined drill holes must intersect the proposed tunnels
cross section at tunnel grade level (IRC:SP:91) .Additional holes if required in this area shall be
under taken . BX- Bits, if unavoidable, will be resorted to only with prior approval of the
department.
Horizontal boreholes along tunnel alignments provide a continuous record of ground conditions
and information which is directly relevant to the tunnel alignment. The location, length and
sample types along the tunnel alignment must be finalised based on geological models developed.
In rock, continuous rock core should be obtained below the surface of rock. Double and triple
tube core barrels should be used to obtain higher quality core more representative of the in situ
rock. For deeper holes, coring should be performed with the use of wire-line drilling equipment to
further reduce potential degradation of the recovered core samples. Boring shall be carried out
using at least Nx size coring bits. Core runs should be limited to a maximum length of 3 M in
moderate to good quality rock, and 2 M in poor quality rock. The rock should be logged soon
after it was extracted from the core barrel. Following information is to be noted for each core run
on the rock coring logs:
Items of particular importance to tunnel projects which greatly influence ground behaviour
and groundwater inflow during construction, and the selection of the tunneling equipment and
methods are listed below:
• Groundwater levels (general and perched levels), ground permeability (loss of drilling fluid;
rise or drop in borehole water level; etc.), and artesian conditions
• Consistency and strength of cohesive soils
• Composition, gradation and density of cohesionless soils
• Presence of lenses and layers of higher permeability soils
• Presence of gravel, cobbles and boulders, and potential for nested boulders
• Maximum cobble/boulder size from coring and/or large diameter borings (and also based
on understanding of local geology), and the unconfined compressive strength of
cobbles/boulders (from field index tests and laboratory testing of recovered samples)
• Presence of cemented soils
• Presence of contaminated soil or groundwater.
• Air quality during construction, and at portals, vent shafts and approaches of the
completed tunnel
• Maintenance of vehicular traffic and transit lines during construction
• Maintenance of utilities and other existing facilities during construction
• Access to residential and commercial properties
• Pest control during construction
• Long-term community impacts
• Long-term traffic impacts
• Temporary and permanent easements
• Tunnel fire life safety and security
• Legal and environmental constraints, enumerated in environmental statements or
reports, or elsewhere. Environmental Impact Assessment, Environmental
Management Plan and Rehabilitation and Resettlement Studies shall be carried out
by the Consultant meeting the requirements of the lending agencies like ADB/
World Bank/JICA, etc.
3.8 SEISMICITY
The release of energy from earthquakes sends seismic acceleration waves traveling
through the ground. Such transient dynamic loading instantaneously increases the shear
stresses in the ground and decreases the volume of voids within the material which leads
to an increase in the pressure of fluids (water) in pores and fractures. Thus, shear forces
increase and the frictional forces that resist them decrease. Other factors also can affect the
response of the ground during earthquakes.
• Distance of the seismic source from the project site.
• Magnitude of the seismic accelerations.
• Earthquake duration.
• Subsurface profile.
• Dynamic characteristics and strengths of the materials affected.
In addition to the distance of the seismic source to the project site, and the design
(anticipated) time history, duration and magnitude of the bedrock earthquake, the
subsurface soil profile can have a profound effect on earthquake ground motions
including the intensity, frequency content, and duration of earthquake shaking.
3.9 Deleted
3.10 The consultant shall be guided in its assignment by the Model Concession/ Contract
Agreements for EPC projects, as applicable and the Manual of Specifications and
Standards for two/ four/ six laning of highways published by IRC (IRC:SP:73 or
IRC:SP:84 or IRC:SP:87, as applicable) (the "Manual") along with relevant IRC codes for
design of long bridges.
3.11 The consultant shall prepare the bid documents including required schedules (as
mentioned above) as per EPC documents. For that it is suggested that consultant should
also go through the latest EPC documents of MoRTH before bidding the project. The
Consultant shall assist the BRO and it's Financial Consultant and the Legal Adviser by
furnishing clarifications as required for the financial appraisal and legal scrutiny of the
Project Highway and Bid Documents. Submission of reports covering all above
information including preliminary indication of cost for the Project and recommendation
for further detailed studies. Framing and submission of report covering all the following
aspects:-
(a) Preparation of preliminary design and schedule of quantities
Signature of contractor For Accepting Officer
b) Study and analysis of working faces, tunnelling method, cost analysis and types
of equipments for various operations such as drilling, blasting, mucking, haulage and
disposal of muck, fire-fighting, extrication of poisonous gases, ventilation, lighting,
side cover, power and water supply systems etc. Possibilities of using TBM are to be
evaluated with specific limitations
c) Engineering studies pertaining to leakage, de-watering, grouting, blasting,
ground acceleration due to blasting, tunnel closures supports system etc.
(d) Tentative constructions schedule including critical path analysis
(e) Listing of various codes of practice both Indian and Foreign applicable
(f) Preparation and submission of phase II report covering all the aspects of studies
and recommendations listed and specified at Sr No (a) to (j) of schedule-'A' PHASE-
II above
3.12.1 Consultant shall be responsible for sharing the findings from the preparation stages
during the bid process. During the bid process for a project, the consultant shall support
the authority in responding to all technical queries, and shall ensure participation of senior
team members of the consultant during all interaction with potential bidders including
pre-bid conference, meetings, site visits etc. In addition, the consultant shall also support
preparation of detailed responses to the written queries raised by the bidders.
ii (a) Public consultation, including consultation with Communities located along the
road, NGOs working in the area, other stake-holders and relevant Government
departments at all the different stages of assignment (such as inception stage,
feasibility stage, preliminary design stage and once final designs are concretized).
xxi. Deleted.
xxii Deleted.
xxiii. Deleted.
xxv. Preparation of social plans for the project affected people as per policy of the lending
agencies/Govt. of India R & R Policy.
4.2 While carrying out the field studies, investigations and design, the development plans being
implemented or proposed for future implementation by the local bodies, should be taken
into account. Such aspect should be clearly brought out in the reports and drawings.
4.3 Deleted.
4.4 The local and slow traffic may need segregation from the main traffic and provision of
service roads and physical barrier including fencing may be considered, wherever
necessary to improve efficiency and safety.
4.5. Standards and Codes of Practices
1. All activities related to field studies, design and documentation shall be done as per the
latest guidelines/ circulars of MoRT&H and relevant publications of the Indian Roads
Congress (IRC) and Bureau of Indian Standards (BIS). For aspects not covered by IRC and
BIS, international standards practices, may be adopted. The Consultants, upon award of the
Contract, may finalize this in consultation with CE (P) Beacon and reflect the same in the
inception report.
2. All notations, abbreviations and symbols used in the reports, documents and drawings shall
be as per IRC:71.
2. It is imperative that the QAP is approved by CE (P) Beacon before the Consultants start the
field work.
i. Climate;
ii. Road inventory
iii. Road condition, year of original construction, year and type of major
maintenance/rehabilitation works;
iv. Condition of bridges and cross-drainage structures;
v. sub-surface and geo-technical data for existing bridges;
vi. Hydrological data, drawings and details of existing bridges;
vii. Existing geological maps, catchment area maps, contour plans etc. for the project
area.
viii. Condition of existing river bank / protection works, if any.
ix. Details of sanctioned / on-going works on the stretch sanctioned by BRO/other
agencies for Tie-in purposes
x. Survey and evaluation of locally available construction materials;
xi. Historical data on classified traffic volume (preferably for 5 years or more);
xii. Origin-destination and commodity movement characteristics; if available
xiii. Speed and delay characteristics; if available;
xiv. Commodity-wise traffic volume; if available;
xv. Accident statistics; and,
xvi. Vehicle loading behavior (axle load spectrum), if available.
xvii. Type and location of existing utility services (e.g. Fibre Optical Cable, O/H and U/G
Electric, Telephone line, Water mains, Sewer, Trees etc.)
xviii. Environmental setting and social baseline of the project.
Number of Survey
Sl.NR. Description
Stations
1. Classified Traffic Volume Count 3
2. Origin-Destination and Commodity Minimum 2
Movement Characteristics
3. Axle Loading Characteristics 2
4. Intersection Volume Count All Major Intersections
5. Speed-Delay Characteristics Project Road Section
6. Pedestrian/animal cross traffic count All major inhabitations
along the highway
2. The number of survey locations indicated in the table above are indicative only.
The Consultants shall, immediately upon award of the work, submit to CE (P) Beacon
proposals regarding the total number as well as the locations of the traffic survey
stations as put of inception report. Suitable maps and charts should accompany the
proposals clearly indicating the rationale for selecting the location of survey Station
3. The methodology of collection and analysis of data, number and location of traffic
survey stations shall be finalized in consultation with CE (P) Beacon
Before validation and correction, the ATCC system shall meet the following accuracy
levels:
(a) Classification of vehicles: better than 90%
(b) Counting of vehicles: better than 95%
For verification of above accuracy levels, audit of raw ATCC shall be done on a
sampling basis.
3. ATCC systems such as Pneumatic Tube Detector, Inductive Detector Loop, Video Image
Detection, and Infrared Sensor or equivalent technologies shall be adopted.
4. The classified traffic volume count surveys shall be carried out for 7 days
(continuous, direction-wise) at the selected survey stations. The vehicle classification
system as given in relevant IRC code may be followed. However, the following
generalized classification system is suggested in view of the requirements of traffic
demand estimates and economic analysis:
5. All results shall be presented in tabular and graphical form. The survey data shall be
analyzed to bring out the hourly and daily variations. The traffic volume count per
day shall be averaged to show a weekly average daily traffic (ADT) by vehicle type.
The annual average daily traffic (AADT) shall be worked out by applying seasonal
factors.
6. The consultant shall compile the relevant traffic volume data from secondary sources
also. The salient features of traffic volume characteristics shall be brought out and
variations if any, from the traffic census carried out by the State PWD/other agencies
shall be suitably explained.
3. The data derived from the survey should be analyzed to identify requirements of
suitable remedial measures, such as construction of underpasses, fly-overs,
interchanges, grade-separated intersections along the project road alignment.
Intersections with high traffic volume requiring special treatments either presently or in
future shall be identified.
4.9.5 Axle Load Surveys
1. Axle load surveys in both directions shall be carried out at suitable location(s) in the
project road stretch on a random sample basis normally for trucks only (both empty and
loaded trucks) for 2 normal days - (24 hours) at special count stations to be finalized in
consultation with CE (P) Beacon. However, a few buses may be weighed in order to get
an idea about their loading behavior. While selecting the location(s) of axle load survey
station(s), the locations of existing bridges with load restrictions, if any, should be taken
into account and such sites should be avoided.
2. Axle load surveys shall normally be done using axle load pads or other sophisticated
instruments. The location(s) of count station(s) and the survey methodology including
the data formats and the instrument type to be used shall be finalized before taking up
the axle load surveys
3. The axle load data should be collected axle configuration-wise. The number of
equivalent standard axles per truck shall be calculated on the basis of results obtained.
The results of the survey should bring out the VDF for each truck type (axle
configuration, if the calculated VDF is found to be below the national average, then
national average shall be used. Furthermore, the data from axle load surveys should be
analyzed to bring out the Gross Vehicle Weight (GVW) and Single Axle Load (SAL)
Distributions by truck type (axle configuration).
4. The Consultant shall ascertain from local enquiries about the exceptional live loads that
have used the highway in the past in order to assess the suitability of existing bridges to
carry such loads.
2. The values of elasticity of transport demand shall be based on the prevailing practices in the
country. The Consultants shall give complete background including references for
selecting the value of transport demand elasticity.
3. It is envisaged that the project road sections covered under this TOR would be
completed and opened to traffic after 3 years. The traffic demand estimates shall be
done for a further period of 30 years from completion of two/four lane. The demand
estimates shall be done assuming three scenarios, namely, optimistic, pessimistic and
most likely traffic growth. The growth factors shall be worked out for five-yearly
intervals.
4. Traffic projections should be based on sound and proven forecasting techniques. In case
traffic demand estimated is to be made on the basis of a model, the application of the
model in the similar situation with the validation of the results should be established.
The traffic projections should also bring out the possible impact of implementation of
any competing facility in the near future. The demand estimates should also take into
account the freight and passenger traffic along the major corridors that may
interconnect with the project. Impact of toll charges on the traffic estimates should be
estimated.
Signature of contractor For Accepting Officer
CA NO CE (P) BEACON/ /2018-19 Srl Page No. 49
Tender No. CE (P)/BEACON/DPR CONSULTANCY/07/2018-19
5. The methodology for traffic demand estimates described in the preceding paragraphs is
for normal traffic only. In addition to the estimates for normal traffic, the Consultants
shall also work out the estimates for generated, induced and diverted traffic.
6. The traffic forecasts shall also be made for both diverted and generated traffic.
7. Overall traffic forecast thus made shall form the basis for the design of each pavement
type and other facilities/ancillary works.
3. The following are the set of deliverables which should be submitted after completion of
survey: (a) Raw DGPS data for the entire highway length and adjoining areas of interest
(b) Point cloud data/ Data of points captured for the entire highway length and adjoining
areas of interest (c) Topographic map of scale 1:1000 of the entire highway length and
adjoining areas of interest (d) Contour map of 50 cm of entire highway length and
adjoining areas of interest (e) Cross section of the highway at every 1 m in *.dwg format.
4. For land based surveys, Mobile LiDAR (Light Detection and Ranging) or equivalent
technology that can meet above requirements shall be adopted. For aerial based surveys,
Aerial Mobile LiDAR (Light Detection and Ranging) or equivalent technology that can
meet above requirements shall be adopted. In shadow areas such as invert levels below
culverts, where LiDAR or equivalent technologies cannot survey accurately, traditional
methods of Total Station/ Auto Level shall be used to complete the study.
5. In case of mobile LiDAR or equivalent technology, 360 degree panoramic images of the
entire highway length and adjoining areas of interest shall be submitted. In case of aerial
LiDAR or equivalent technology, ortho-images of the entire highway length and adjoining
areas of interest shall be submitted.
6. The detailed field surveys would essentially include the following activities:
i. Topographic Surveys along the Existing Right of Way (ROW): Carrying out
topographic survey using LiDAR or equivalent technology along the existing road and
realignments, wherever required and properly referencing the same with reference
pillars fixed on either side of the centre-line at safe places within the ROW
ii. The detailed field surveys would essentially include the topographic surveys along the
proposed location of bridge and alignment of approach road.
iii. The detailed topographic surveys should be carried out along the approach roads
alignment and location of bridge approved by CE (P) Beacon.
iv. Collection/ Extraction of details for all features such as structures (bridges, culverts
etc.) utilities, existing roads, electric and telephone installations (both O/H as well as
underground), huts, buildings, fencing and trees (with girth greater than 0.3metre) oil
and gas lines etc. falling within the extent of survey.
ii. In case the reconnaissance survey reveals the need for bypassing the congested
locations, the traverse lines would be run along the possible alignments in order to
identify and select the most suitable alignment for the bypass. The detailed
topographic surveys should be carried out along the bypass alignment approved by
CE (P) Beacon At locations where grade separated intersections could be the obvious
choice, the survey area will be suitably increased. Field notes of the survey should be
maintained which would also provide information about traffic, soil, drainage etc.
iii. The width of the surveyed corridor will be widened appropriately where developments
and / or encroachments have resulted in a requirement for adjustment in the
alignment, or where it is felt that the existing alignment can be improved upon through
minor adjustments.
iv. Where existing roads cross the alignments, the survey will extend a minimum of100 m
either side of the road centre line and will be of sufficient width to allow
improvements, including at grade intersection to be designed.
ii. Establishing Bench marks at site connected to GTS Bench marks at a interval of250
metres on Bench mark pillar made of RCC as mentioned above with RL and BM No.
marked on it with red paint.
iii. Boundary Pillars- Wherever there is a proposal of realignment of the existing
Highway and/or construction of New Bypasses, Consultant shall fix boundary pillars
along the proposed alignment on the extreme boundary on either side of the project
Highway at 50 m interval.
iv. Longitudinal and cross sections for major and minor streams shall cover Cross section
of the channel at the site of proposed crossing and few cross sections at suitable
distance both upstream and downstream, bed level up to top of banks and ground
levels to a sufficient distance beyond the edges of channel, nature of existing surface
soil in bed, banks & approaches, longitudinal section of channel showing site of
bridge etc. These shall be as per recommendations contained in IRC Special
Publication No. 13 (Guidelines for the Design of Small Bridges and Culverts) and
provisions of IRC:5 (“Standard Specifications & Code of Practice for Road Bridges,
Section 1 – General Features of Design”).
At feasibility study stage cross sections at 50m interval may be taken.
2. Consultant shall also map out sub-surface utilities. The following criteria shall be met by
the process of sub-surface utility mapping: (a) Coverage and mapping of all sub-surface
utilities within project RoW, especially those under additional carriageway width (b)
Accurate mapping and resolution of all sub-surface utilities up to a depth of 4 m (c)
Differentiation between sub-surface utilities such as live electric cables, metallic utilities
and other utilities (d) Sub-surface utilities radargrams further processed into utility maps
in formats such as PDF, JPEG and AutoCAD. To meet the accuracy levels, consultant
shall use Ground Penetrating Radar (GPR), Induction Locator or equivalent technologies.
3. The information collected during reconnaissance and field surveys shall be shown on a
strip plan so that the proposed improvements can be appreciated and the extent of land
acquisition with L.A schedule, utility removals of each type etc. assessed and suitable
actions can be initiated. Separate strip plan for each of the services involved shall be
prepared for submission to the concerned agency.
Shoulder Condition
Paved: Same as for pavement
Unpaved: material loss, rut depth and corrugation,
Edge drop, mm.
Embankment Condition
general condition; and
extent of slope erosion
ii. The objective of the road and pavement condition surveys shall be to identify defects
and sections with similar characteristics. All defects shall be systematically
referenced, recorded and quantified for the purpose of determining the mode of
rehabilitation.
iii. The pavement condition surveys shall be carried out using visual means.
Supplemented by actual measurements and in accordance with the widely accepted
methodology (AASHTO, IRC, OECD, TRL and World Bank Publications) adapted to
meet the study requirements. The measurement of rut depth would be made using
standard straight edges.
iv. The shoulder and embankment conditions shall be evaluated by visual means and the
existence of distress modes (cuts, erosion marks, failure, drops) and extent (none,
moderate, frequent and very frequent) of such distress manifestations would be
recorded.
vi. Middle 200m could be considered as representative sample for each one km. of road
and incase all other things are considered similar.
Drainage Condition
General condition
Connectivity of drainage turnouts into the natural topography
Condition in cut sections
Condition at high embankments
The data obtained from the condition surveys should be analyzed and the road
segments of more or less equal performance may be identified using the criteria
given in IRC: 81-1997.
3. Pavement Roughness
i. The roughness surveys shall be carried out using Bump Integrator or similar
instrument. The methodology for the surveys shall be as per the widely used standard
practices. The calibration of the instrument shall be done as per the procedure given
in the World Bank‟s Technical Publications and duly got authenticated by
established laboratory/institution acceptable to the client
ii. The surveys shall be carried out along the outer wheel paths. The surveys shall cover
a minimum of two runs along the wheel paths for each directions.
iii. The results of the survey shall be expressed in terms of BI and IRI and shall be
presented in tabular and graphical forms. The processed data shall be analysed
using the cumulative difference approach to identify road segments homogenous
with respect to surface roughness.
iii. The deflection tests for the mainline shall be carried out at every 500 m along the
road sections covered under the study. The control section testing shall involve
carrying out deflection testing for each 100 m long homogenous road segment along
the road sections. The selection of homogenous segment shall be based on the data
derived from pavement condition surveys. The total length of such homogenous
segments shall not be less than 100 m per kilometre. The deflection measurements
for the control section testing should be at an interval of not more than 10 m.
iv. Test pits shall be dug at every 500 m and also along each homogeneous road
segment to obtain pavement composition details (pavement course, material type and
thickness) so as to be able to study if a correlation exists between deflection and
composition. If so, the relationship may be used while working out the overlay
thickness for the existing pavement.
v. Benkelman Beam Deflection surveys may not be carried out for severely distressed
sections of the road warranting reconstruction. The Consultants, immediately upon
the award of the contract, shall submit to CE (P) Beacon the scheme describing the
testing schedule including the interval. The testing scheme shall be supported by
data from detailed reconnaissance surveys.
vi. In case, the Consultants wish to use any acceptable method(s) other than Benkelman
Beam deflection technique for the evaluation of pavement strength, viz. Falling
weight deflectometer method etc. details of such methods or innovative features for
deflection testing using Benkelman Beam technique along with the methodology for
data analysis, interpretation and the use of such data for pavement overlay design
purposes using IRC or any other widely used practices, such as AASHTO guidelines,
should be got approved by CE (P) Beacon. The sources of such methods should be
properly referenced.
The Consultants shall make an inventory of all the structures (bridges, viaducts,
ROBs,/RUB and other grade separated structures, culverts, etc.) along the road under the
project. The inventory for the bridges, viaducts and ROBs shall include the parameters
required as per the guidelines of IRC-SP:35. The inventory of culverts shall be presented
in a tabular form covering relevant physical and hydraulic parameters.
4.11.4.2 Hydraulic and Hydrological Investigations
1. The hydrological and hydraulic studies shall be carried out in accordance with IRC
Special Publication No. 13 (“Guidelines for the Design of Small Bridges and Culverts”)
and IRC:5 (“Standard Specifications & Code of Practice for Road Bridges, Section I
General Feature of Design”). These investigations shall be carried out for all existing
drainage structures along the road sections under the study.
2. The consultant shall also collect information on observed maximum depth of scour.
Signature of contractor For Accepting Officer
CA NO CE (P) BEACON/ /2018-19 Srl Page No. 58
Tender No. CE (P)/BEACON/DPR CONSULTANCY/07/2018-19
3. In respect of major bridges, history of hydraulic functioning of existing bridge, if any,
under flood situation, general direction of river course through structure, afflux, extent
and magnitude of flood, effect of backwater, if any, aggradation/degradation of bed,
evidence of scour etc. shall be used to Sepment the available hydrological data. The
presence of flood control/irrigation structures, if affecting the hydraulic characteristics
like causing obliquity, concentration of flow, scour, silting of bed, change in flow levels,
bed levels etc. shall be studied and considered in design of bridges. The details of any
future planned work that may affect the river hydraulics shall be studied and considered.
4. The Consultants shall make a desk study of available data on topography(topographic
maps, stereoscopic aerial photography), storm duration, rainfall statistics, top soil
characteristics, vegetation cover etc. so as to assess the catchment areas and hydraulic
parameters for all existing and proposed drainage provisions. The findings of the desk
study would be further supplemented and Sepmented by a reconnaissance along the area.
All-important hydrological features shall be noted during this field reconnaissance.
5. The Consultants shall collect information on high flood level (HFL),low water levels
(LWL), high tide level (HTL),low tide level (LTL) where applicable, discharge velocity
etc. from available past records, local inquiries and visible signs, if any, on the structural
components and embankments. Local inquiries shall also be made with regard to the road
sections getting overtopped during heavy rains.
6. Conducting Model studies for bridges is not covered in the scope of consultancy services.
If Model study is envisaged for any bridge, requirement of the same shall be spelt out in
the RPF documents separately indicating scope and time frame of such study. Salient
features of the scope of services to be included for model study are given in the
supplement- II Terms of Reference.
4.11.4.3 Condition Surveys for Bridges, Culverts and Structures
1. The Consultants shall thoroughly inspect the existing structures and shall prepare a report
about their condition including all the parameters given in the Inspection pro-forma of
IRC-SP; 35. The condition and structural assessment survey of the bridges / culverts /
structures shall be carried out by senior experts of the Consultants.
2. For the bridges identified to be in a distressed condition based upon the visual condition
survey, supplementary testing shall be carried out as per IRC-SP:35 and IRC-SP:40.
Selection of tests may be made based on the specific requirement of the structure.
3. The assessment of the load carrying capacity or rating of existing bridges shall be carried
out under one or more of the following scenarios:
i. when the design live load is less than that of the statutory commercial
vehicle plying or likely to ply on bridge;
ii. if during the condition assessment survey and supplementary testing the
bridge is found to indicate distress of serious nature leading to doubt about
structural and / or functional adequacy, and
iii. Design live load is not known nor are the records and drawings available
4. The evaluation of the load carrying capacity of the bridge shall be carried out as per IRC-
SP:37 (“Guidelines for Evaluation of Load Carrying Capacity of Bridges”). The analytical
and correlation method shall be used for the evaluation of the load carrying capacity as far
as possible. When it is not possible to determine the load carrying capacity of the bridge
using analytical and correlation method, the same shall be carried out using load testing.
The consultant has to exhaust all other methods of evaluation of strength of bridges before
recommending to take up load testing of bridges. Road closure for testing if unavoidable
shall be arranged by CE (P) Beacon for limited duration say 12 hours or so.
5. Consultant shall carryout necessary surveys and investigations to establish the remaining
service life of each retainable bridge or structure with and without the proposed
strengthening and rehabilitation according to acceptable international practice in this
regard.
4.11.4.4 Geo-technical Investigations and Sub-Soil Exploration
1. The Consultants shall carry out geo-technical investigations and sub-surface explorations
for the proposed Bridges / Road over bridges/ tunnels/ viaducts/ interchanges etc., along
high embankments and any other location as necessary for proper design of the works and
conduct all relevant laboratory and field tests on soil and rock samples. The minimum
scope of geo-technical investigations for bridge and structures shall be as under:
S.No Description Location of Boring
1 Overall length = 6 – 30 m One abutment location and One abutment
location and at least one intermediate location
between abutments for structures having
more than one span
2 Overall length = 30 – 60 m One abutment location and at least one
intermediate location between abutments for
structures having more than one span.
3 Overall length >60 m Each abutment and each pier locations.
2. The deviation(s), if any, by the Consultants from the scheme presented above should be
approved by CE (P) Beacon.
3. However, where a study of geo-technical reports and information available from
adjacent crossings over the same waterway (existing highway and railway bridges)
indicates that subsurface variability is such that boring at the suggested spacing will be
insufficient to adequately define the conditions for design purposes, the Consultants
shall review and finalize the bore hole locations in consultation with the CE (P) Beacon
officers.
4. Geotechnical Investigations and Sub soil Explorations hall be carried out to determine
the nature and properties of existing strata in bed, banks and approaches with trial pits
and bore hole sections showing the levels, nature and properties of various strata to a
sufficient depth below the level suitable for foundations, safe intensity of pressure on
the foundation strata, proneness of site to artesian conditions, seismic disturbance and
other engineering properties of soil etc. Geotechnical investigation and Sub-soil
Exploration will be done as per IRC 78.
7. For the approach road pavement, bore holes at each major change in pavement condition
or in deflection readings or at 2 km intervals whichever is less shall be carried out to a
depth of at least 2 m below embankment base or to rock level and are to be fully logged.
Appropriate tests to be carried out on samples collected from these bore holes to determine
the suitability of various materials for use in widening of embankments or in parts of new
pavement structure.
Technical and economic feasibility of using industrial byproducts, recyclable and waste
materials shall be assessed depending on their availability in the concerned region.
2. It is to be ensured that no material shall be used from the right-of-way except by way of
leveling the ground as required from the construction point of view, or for landscaping and
planting of trees etc. or from the cutting of existing ground for obtaining the required
formation levels.
3. Environmental restrictions, if any, and feasibility of availability of these sites to
prospective civil works contractors, should be duly taken into account while selecting new
quarry locations.
4. The Consultants shall make suitable recommendations regarding making the borrow and
quarry areas after the exploitation of materials for construction of works.
5. The Material Investigation aspect shall include preparation and testing of bituminous
mixes for various layers and concrete mixes of different design mix grades using suitable
materials (binders, aggregates, sand filler etc.) as identified during Material Investigation
to conform to latest MoRT&H specification.
3. The data on accident statistics should be compiled and reported showing accident type and
frequency so that black spots are identified along the project road section. The possible
causes (such as poor geometric features, pavement condition etc.) of accidents should be
investigated into and suitable cost-effective remedial measures suggested for
implementation.
4. The detailed design for geometric elements shall cover, but not be limited to the following
major aspects:
i. horizontal alignment;
ii. longitudinal profile;
iii. cross-sectional elements, including refuge lane (50m) at every 2kms.
iv. junctions, intersections and interchanges;
v. bypasses; and,
vi. service roads as and when require i.e built up area..
5. The alignment design shall be verified for available sight distances as per the standard
norms. The provision of appropriate markings and signs shall be made wherever the
existing site conditions do not permit the adherence to the sight distance requirements as
per the standard norms.
6. The consultants shall make detailed analysis of traffic flow and level of service for the
existing road and workout the traffic flow capacity for the improved project road. The
analysis should clearly establish the widening requirements with respect to the different
horizon periods taking into account special problems such as road segments with isolated
steep gradients.
7. In the case of closely spaced cross roads the Consultant shall examine different options
such as, providing grade separated structure for some of them with a view to reduce
number of at-grade crossings, services roads connecting the cross-roads and closing access
from some of the intersections and prepare and furnish appropriate proposals for this
purpose keeping in view the cost of improvement, impact on traffic movement and
accessibility to cross roads. The detailed drawings and cost estimate should include the
provisions for realignments of the existing cross roads to allow such arrangements.
8. The Consultant shall also prepare design of grade separated pedestrian crossings (viaducts)
for large cross traffic of pedestrians and / or animals.
9. The Consultant shall also prepare details for at-grade junctions, which may be adopted as
alternative to the grade separated structures. The geometric design of interchanges shall
take into account the site conditions, turning movement characteristics, level of service,
overall economy and operational safety.
10. The Consultants shall prepare design and other details in respect of the parallel service
roads in urbanized locations and other locations to cater to the local traffic, their effect of
the viability of the project on commercial basis if service roads are constructed as part of
the project and the implications of not providing the service roads.
11. The consultant shall prepare complete road and pavement design including drainage for
new bypass option identified around congested town en-route.
2. The Consultants shall carry out detailed analysis and design for all embankments of height
greater that 6 m based on relevant IRC publications.
3. The design of embankments should include the requirements for protection works and
traffic safety features.
4.12.6 Design of Bridges and Structures
1. The data collected and investigation results shall be analyzed to determine the following:
i. HFL
ii. LWL
iii. LBL
iv. Erodibility of bed/scour level
v. Design discharge
vi. Linear waterway and effective linear waterway
vii. Likely foundation depth
viii. Safe bearing capacity
ix. Engineering properties of sub soil
x. Artesian conditions
xi. Settlement characteristics
xii. Vertical clearance
xiii. Horizontal clearance
xiv. Free board for approach road
xv. Severity of environment with reference to corrosion
xvi. Data pertaining to seismic and wind load
xvii. Requirement of model study etc.
2. The Consultant shall prepare General Arrangement Drawing (GAD) and Alignment Plan
showing the salient features of the bridges and structures proposed to be constructed /
reconstructed along the road sections covered under the Study. These salient features such
as alignment, overall length, span arrangement, cross section, deck level, founding level,
type of bridge components (superstructure, substructure, foundations, bearings, expansion
joint, return walls etc.) shall be finalized based upon hydraulic and geo-technical studies,
cost effectiveness and ease of construction. The GAD shall be supplemented by
Preliminary designs. In respect of span arrangement and type of bridge a few alternatives
with cost-benefit implications should be submitted to enable CE (P) Beacon to approve the
best alternative. After approval of alignment and GAD the Consultant shall prepare
detailed design as per IRC codes /guidelines and working drawings for all components of
bridges and structures.
3. The location of all at-grade level crossings shall be identified falling across the existing
level crossings for providing ROB at these locations. The Consultants shall prepare
preliminary GAD for necessary construction separately to the CE (P) Beacon. The
Consultant shall pursue the Indian Railways Authorities or/and any statutory authority of
State/Central Government for approval of the GAD from concerned Authorities.
4. GAD for bridges/structures across irrigation/water way channels shall be got approved
from the concerned Irrigation/Water way Authorities. Subsequent to
approval of GAD and alignment plan by CE (P) Beacon the Consultants shall prepare
detailed design as per IRC codes/guidelines for all components of the bridges and
structures.
Signature of contractor For Accepting Officer
CA NO CE (P) BEACON/ /2018-19 Srl Page No. 65
Tender No. CE (P)/BEACON/DPR CONSULTANCY/07/2018-19
5. Subsequent to the approval of the GAD and Alignment Plan by CE (P) Beacon and
Railways, the Consultant shall prepare detailed design as per IRC and Railways guidelines
and working drawings for all components of the bridges and structures. The Consultant
shall furnish the design and working drawings for suitable protection works and/or river
training works wherever required.
6. Dismantling/ reconstruction of existing structures shall be avoided as far as possible
except where considered essential in view of their poor structural conditions/ inadequacy
of the provisions etc.
7. The existing structures having inadequate carriageway width shall be
widened/reconstructed in part or fully as per the latest MoRT&H guidelines. The
Consultant shall furnish the detailed design and working drawings for carrying out the
above improvements.
8. Suitable repair / rehabilitation measures shall be suggested in respect of the existing
structures as per IRC-SP:40 along with their specifications, drawings and cost estimate in
the form of a report. The rehabilitation or reconstruction of the structures shall be
suggested based on broad guidelines for rehabilitation and strengthening of existing
bridges contained in IRC-SP:35 and IRC-SP:40.
9. Subsequent to the approval of the GAD and the alignment plan by CE (P) Beacon, detailed
design shall also be carried out for the proposed underpasses, overpasses and interchanges.
10. The Consultants shall also carry out the design and make suitable recommendations for
protection works for bridges and drainage structures.
11. In case land available is not adequate for embankment slope, suitable design for RCC
retaining wall shall be furnished. However, RES wall may also be considered depending
upon techno-economic suitability to be approved by CE (P) Beacon (BRO).
10. The consultant shall identify and plan for plantation and Transplantation of the suitable
trees along the existing highway in accordance with IRC guidelines.
11. The consultant shall assist in providing appropriate input in preparation of relevant
environment and social sections of BPIP.
Assessment on the impact of the project on the poor and vulnerable groups along
the project road corridor.
Based on the identified impacts, developing entitlement matrix for the project
affected people.
Assessment on social issues such as indigenous people, gender, HIV/AIDS,
labourers including child labour.
Implementation budgets, sources and timing of funding and schedule of tasks.
Responsibility of tasks, institutional arrangements and personnel for delivering
entitlement and plans to build institutional capacity.
Internal and external monitoring plans, key monitoring indicators and grievance
redress mechanism.
Incorporating any other suggestions of the CE (P) Beacon, till the acceptance of
the reports by the CE (P) Beacon.
The consultant would prepare the stand-alone reports as per the requirement of the
ADB/World Bank / CE (P) Beacon, as applicable, with contents as per the
following:
Executive Summary
Description of the Project
Environmental setting of the project.
Identification and categorization of the potential impacts (during pre-construction,
construction and operation periods).
Analysis of alternatives (this would include correlation amongst the finally
selected alternative alignment/routing and designs with the avoidance and
environmental management solutions).
The public consultation process.
Policy, legal and administrative framework. This would include mechanisms at the
states and national level for operational policies. This would also include a
description of the organizational and implementation mechanism recommended
for this project.
Typical plan or specific designs for all additional environmental items as
described in the scope of work.
Incorporating any other as per the suggestions of the ADB/ World Bank /
MORT&H/ CE (P) Beacon, till the acceptance of the reports by the ADB/ World
Bank / MORT&H/ CE (P) Beacon, as applicable.
EMP Reports for Contract Package based on uniform methodology and processes.
The consultant will also ensure that the EMP has all the elements for it to be a
legal document. The EMP reports would include the following:
Executive summary
Description of project
Objectives of the project.
The need for Resettlement in the Project and evaluation of measures to
minimize resettlement.
Description and results of public consultation and plans for continued
participation of PAPs.
Definition of PAPs and the eligibility criteria.
Census and survey results-number affected, how are they affected and
what impacts will they experience.
Legal and entitlement policy framework-support principles for different
categories of impact.
Arrangements for monitoring and evaluation (internal and external)
Implementation schedule for resettlement which is linked to the civil
works contract
A matrix of scheduled activities linked to land acquisition procedures to
indicate clearly what steps and actions will be taken at different stages and
the time frame
The payment of compensation and resettlement during the acquisition
process.
An itemized budget (replacement value for all assets) and unit costs for
different assets.
5. Estimation of Quantities and Project Costs
1. The Consultants shall prepare detailed estimates for quantities (considering
designs and mass haul diagram) and project cost for the entire project (civil packages
wise), including the cost of environmental and social safeguards proposed based on
MoRT&H‟s Standard Data Book and market rate for the inputs. The estimation of
quantities shall be based on
detailed design of various components of the projects. The estimation of quantities and
costs would have to be worked out separately for civil work Package as defined in this
TOR.
2. The Consultants shall make detailed analysis for computing the unit rates for the different
items of works. The unit rate analysis shall duly take into account the various inputs and
their basic rates, suggested location of plants and respective lead distances for
mechanized construction. The unit rate for each item of works shall be worked out in
terms of manpower, machinery and materials.
4. The project cost estimates so prepared for CE (P) Beacon /ADB/WB projects are to be
checked against rates for similar on-going works in India under CE (P) Beacon / World
Bank/ ADB financed road sector projects.
6. Viability and Financing Options
1. The Project Road should be divided into the traffic homogenous links based on the
findings of the traffic studies. The homogenous links of the Project Road should be
further subdivided into sections based on physical features of road and pavement, sub-
grade and drainage characteristics etc. The economic and commercial analysis shall be
carried out separately for each traffic homogenous link as well as for the Project Road.
2. The values of input parameters and the rationale for their selection for the economic and
commercial analyses shall be clearly brought out and got approved by CE (P) Beacon.
3. For models to be used for the economic and the commercial analyses, the calibration
methodology and the basic parameters adapted to the local conditions shall be clearly
brought out and got approved by CE (P) Beacon.
4. The economic and commercial analyses should bring out the priority of the different
homogenous links in terms of project implementation.
3. Economic Internal Rate of Return (EIRR) and Net Present Value (NPV), “with “and
“without time and accident savings” should be worked out based on these cost-benefit
stream. Furthermore, sensitivity of EIRR and NPV worked out forth different scenarios as
given under:
Scenario – I Base Costs and Base Benefits
Scenario - II Base Costs plus 15% and Base Benefits
Scenario - III Base Costs and Base Benefits minus 15%
Scenario - IV Base Costs plus 15% and Base Benefits minus 15%
The sensitivity scenarios given above are only indicative. The Consultants shall select the
sensitivity scenarios taking into account possible construction delays, construction costs
overrun, traffic volume, revenue shortfalls, operating costs, exchange rate variations,
convertibility of foreign exchange, interest rate volatility, non-compliance or default by
contractors, political risks and force majeure.
4. The economic analysis shall take into account all on-going and future road and transport
infrastructure projects and future development plans in the project area.
6.2 Financial Analysis
1. It is envisaged that the project stretch should be implemented on EPC/BOT basis,
therefore, the Consultant shall study the financial viability of the project under a
commercial format and under different user fee scenarios and funding options. The
Consultants shall submit and finalize in consultation with the CE (P) Beacon officers the
format for the analysis and the primary parameters and scenarios that should be taken into
account while carrying out the commercial analysis. The financial model so developed
shall be the property of CE (P) Beacon.
2. The Financial analysis for the project should cover financial internal rate of return,
projected income statements, balance sheets and fund flow statements and should bring
out all relevant assumptions. The sensitivity analysis should be carried out for a number
of probabilistic scenarios.
3. The financial analysis should cover identification, assessment, and mitigating measures
for all risks associated with the project. The analysis shall cover, but be not limited to,
risks related to construction delays, construction costs overrun, traffic volume, revenue
shortfalls, operating costs, exchange rate variations, convertibility of foreign exchange,
interest rate volatility, non-compliance or default by contractors, political risks and force
majeure.
4. The consultant shall suggest positive ways of enhancing the project Viability and furnish
different financial models for implementing on BOT format.
2. CE (P) Beacon shall arrange to give approval on all sketches, drawings, reports and
recommendations and other matters and proposals submitted for decision by the
Consultant in such reasonable time so as not to delay or disrupt the performance of
the Consultant‟s services
Signature of contractor For Accepting Officer
CA NO CE (P) BEACON/ /2018-19 Srl Page No. 72
Tender No. CE (P)/BEACON/DPR CONSULTANCY/07/2018-19
Preliminary design work should commence without waiting for feasibility study to be
completed. Stage 3, 5 and 6 shall run in parallel with Stage 2 and 4
9.3 Consultant shall be required to complete, to the satisfaction of the CE (P) Beacon, all the
different
stages of study within the time frame indicated in the schedule of submission in para 10
pertaining to Reports and Documents for becoming eligible for payment for any part of
the next stage.
10. Reports and Documents to be submitted by the Consultant to CE (P) Beacon
1. The Consultant shall submit to the client the reports and documents in bound volumes
(and not spiral binding form) after completion of each stage of work as per the schedule
and in the number of copies as given in Enclosure III. Further, the reports shall also be
submitted in floppy diskettes / CD‟s in addition to the hardcopies as mentioned in
Enclosure-III. Consultant shall submit all other reports mentioned specifically in the
preceding paras of the TOR.
2. The time schedule for various submissions prescribed at s.l.no.1 above shall be strictly
adhered to. No time-over-run in respect of these submissions will normally be permitted.
Consultant is advised to go through the entire terms of reference carefully and plan his work
method in such a manner that various activities followed by respective submissions as
brought out at Sl.No.1 above are completed as stipulated. Consultant is, therefore, advised
to deploy sufficient number of supporting personnel, both technical and administrative, to
undertake the project preparation activities in construction package (Section)
simultaneously. As far as possible, the proposal should include complete information such
as number of such persons, name, position, period of engagement, remuneration rate etc.
The Consultant is also advised to start necessary survey works from the beginning so as to
gain time in respect of various other activities in that stage.
STAGE 1
10.1 Quality Assurance Plan (QAP) Document
1. Immediately upon the award, the Consultants shall submit four copies of the QAP
document covering all aspects of field studies, investigations design and economic
financial analysis. The quality assurance plans/procedures for different field studies,
engineering surveys and investigation, design and documentation activities should be
presented as separate sections like engineering surveys and investigations, traffic surveys,
material geo-technical and sub-soil investigations, road and pavement investigations,
investigation and design of bridges &structures, environment and R&R assessment,
economic & financial analysis, drawings and documentation; preparation, checking,
approval and filing of calculations, identification and traceability of project documents
etc. Further, additional information as per format shall be furnished regarding the details
STAGE 2:
10.3 Feasibility Report
1. The consultant shall commence the Feasibility Study of the project in accordance with the
accepted IR for both Tunnel and Road & Bridges shall contain the following::
i. Executive summary
ii. Overview of CE (P) Beacon organization and activities, and project
financing and cost recovery mechanisms
iii. Project description including possible alternative alignments/bypasses
and technical/engineering alternatives
iv. Geology profile along the alignment based on surface geological studies.
v. Rock-Mass classification of tentative support design.
vi. Methodology adopted for the feasibility study
vii. Socioeconomic profile of the project areas
viii. Indicative design standards, methodologies and specifications
ix. Traffic surveys and analysis
x. Environmental screening and preliminary environmental assessment
xi. Initial social assessment and preliminary land acquisition/resettlement
plan
xii. Cost estimates based on preliminary rate analysis and bill of quantities
xiii. Economic and financial analysis
xiv. Conclusions and recommendations
2. Deleted
3. The basic data obtained from the field studies and investigations shall be submitted in a
separate volume as an Appendix to Feasibility Report.
4. The Final Feasibility Study Report incorporating comments, revisions and modifications
suggested by CE (P) Beacon shall be submitted within 15 days of comments from CE (P) Beacon
on draft feasibility study report.
STAGE 3:
iv. Details for various clearances such as environment and forest clearances;
v. Separate strip plan showing shifting / relocation of each utility services in
consultation with the concerned local authorities;
vi. The utility relocation plans should clearly show existing right-of-way and
pertinent topographic details including buildings, major trees, fences and
other installations such as water-mains, telephone, telegraph and electricity
poles, and suggest relocation of the services along with their crossings the
highway at designated locations as required and prepare necessary details
for submission to the Service Departments;
vii. Detail schedules for acquisition of additional land and additional properties
in consultation with the revenue authorities; and
viii. Land Acquisition Plan shall be prepared after digitization of cadastral / land
revenue maps. The digitized map shall exactly match the original map, like a
contact print, since the dimensions and area of plots, or the whole village is
to be extracted from the map itself. An accuracy of 1mm or higher in a
1:1000 scale map shall be ensured, as this translates into an accuracy of 1 m
or higher on ground.
2. The strip plans and land acquisition plan shall be prepared on the basis of data from
reconnaissance and detailed topographic surveys.
3. The Report accompanying the strip plans should cover the essential aspects as given
under:
STAGE: 4
10.7 Draft Detailed Project Report (DPR)
1. The draft DPR Submission shall consist of Construction methodology, contract
model and its merits and demerits, Main Report, Design Report, Ventilation,
Lightening and various safety measures, Report on Geo-Physical and Geo-Technical
investigations, Materials Report, Engineering Report, Drainage Design Report,
Economic and Financial Analysis Report, Environmental Assessment Report
including Resettlement Action Plan (RAP), bid Documents and Drawings.
2. The Report volumes shall be submitted as tabulated in para 10 above.
3. The Documents and Drawings shall be submitted for the Package and shall be in the
following format:
Reports
i. Volume-I, Main Report: This report will present the project background,
social analysis of the project, details of surveys and investigations carried out,
analysis and interpretation of survey and investigation data, traffic studies and
demand forecasts designs, cost estimation, environmental aspects, economic and
commercial analyses and conclusions. The report shall include Executive Summary
giving brief accounts of the findings of the study and recommendations including
reports such as General Project Description, Horizontal and Vertical Tunnel
Alignment, Typical cross section, Pavement, Tunnel Safety concept, Ventilation
Concept and design, Ventilation shafts etc., Hydraulic Design , Construction Method,
Geotechnical/Geological evaluation (Geotechnical Factual report, Geotechnical
Interpretive Report, High Resolution Satellite Imagery) and Rock Mass classification ,
Tunnel Support System, Portal Design and Construction Time, Construction Cost etc.
The Report shall also include maps, charts and diagrams showing locations and
details of existing features and the essential features of improvement and
upgrading. The Environmental Impact Assessment (EIA) Report for contract
package shall be submitted as a part of the main report.
The basic data obtained from the field studies and investigations and input data
used for the preliminary design shall be submitted in a separate volume as an
Appendix to Main Report.
ii. Volume - II, Design Report: This volume shall contain design calculations,
supported by computer printout of calculations wherever applicable. The Report
shall clearly bring out the various features of design standards adopted for the
study. The design report will be in two parts. Part-I shall primarily deal with the
design of bridges, tunnels and cross-drainage structures while Part-II shall deal
with the design of road features and pavement composition. The sub-soil
exploration report including the complete details of boring done, bore log report,
geotechnical base line report, comparison between conventional and TBM
construction, analyses and interpretation of data and the selection of design
parameters shall be included as an Appendix to the Design Report.
The detailed design for all features should be carried out as per the requirements
of the Design Standards for the project. However, there may be situations wherein
it has not been possible to strictly adhere to the design standards due to the
existing site conditions, restrictions and other considerations. The report should
clearly bring out the details of these aspect and the standards adopted.
iii. Volume - III, Materials Report: The Materials Report shall contain details
concerning the proposed borrow areas and quarries for construction materials
and possible sources of water for construction purposes. The report shall include
details on locations of borrow areas and quarries shown on maps and charts and
also the estimated quantities with mass haul diagram including possible end use
with leads involved, the details of sampling and testing carried out and results in
the form of important index values with possible end use thereof.
The materials Report shall also include details of sampling, testing and test
results obtained in respect physical properties of sub-grade soils. The information
shall be presented in tabular as well as in graphical representations and
schematic diagrams. The Report shall present soil profiles along the alignment.
The material Report should also clearly indicate the locations of areas with
problematic soils. Recommendations concerning the improvement of such soils for
use in the proposed construction works, such as stabilization (cement, lime,
mechanical) should be included in the Report.
vi. Volume - VI, Rate Analysis: This volume will present the analysis of rates for all
items of works. The details of unit rate of materials at source, carriage charges,
any other applicable charges, labour rates, machine charges as considered in
arriving at unit rates will be included in this volume. The rates for material,
labour and machinery should be based on the “Standard Data Book for Analysis
of Rates” (SoR) of Ministry of Road Transport and Highways published by Indian
Road Congress (IRC). Where the SoR rates do not cover all items for tunnel
construction works, all machinery, labour and/or material rates concerning tunnel
construction should be determined from international price data of the relevant
year and verified with actual Indian highway tunnel projects with similar layout
and boundary conditions (such as Pahtnitop Tunnel and Rohtang Tunnel).
vii. Volume - VII, Cost Estimates: This volume will present the contract package wise
cost of each item of work as well as a summary of total cost.
viii. Volume - VIII, Bill of Quantities: This volume shall contain the package-wise
detailed Bill of Quantities for all items of works.
ix. Volume - IX, Drawing Volume: All drawings forming part of this volume shall be
„good for construction‟ drawings. All plan and profile drawings will be prepared
in scale 1:250V and 1:2500H scale to cover one km in one sheet. In addition this
volume will contain „good for construction‟ drawings for the following:
General
(i)Area Map (1:200000/ 1:75000)
(ii) General Layout Tunnel – Plan view (1:10000)
(iii) General layout Tunnel- Longitudinal Section (1:10000)
(iv) Geotechnical Longitudinal Section of Tunnel with Ground condition and
support (1:10000)
(v) Tunnel System and Installations – (N.T.S)
(vi) General Construction Sequence – (N.T.S)
Geometry
(i) Typical cross Section of Tunnel, Clearance profile and installations, Jet Fan
Cabinet, clearance profile and installations , Inner Lining - (1:50)
Hydraulic System
(i) General Schematic layout, plan view (N.T.S.)
Excavation
Excavation and primary support of tunnel and ventilation shafts in all support
categories- 1:100
Ventilation shafts
Typical cross section- 1:50, 1:1000
Main & Subsidiary measuring sections- 1:100
E&M
(i) Elementary diagram of safety installations- 1:10000
(ii) Typical cross section installations: 1:100
(iii) Power supply scheme: N.T.S
(iv) Schematic Layout of technical equipment in front and in the inner area of the
tunnel - N.T.S
(v) Schematic layout of main tunnel lighting - N.T.S
(vi) Schematic diagram of video surveillance system- N.T.S
(vii) Schematic diagram of Fire alarm and detection system- N.T.S
(viii) Schematic diagram of Integrated tunnel control system- N.T.S
(xi) Operators workplaces main control center - N.T.S
Signature of contractor For Accepting Officer
CA NO CE (P) BEACON/ /2018-19 Srl Page No. 80
Tender No. CE (P)/BEACON/DPR CONSULTANCY/07/2018-19
Road Portion
Horizontal Alignment and Longitudinal Profile.
Cross-section @ 50m interval along the alignment within ROW
Typical Cross-Sections with details of pavement structure.
Detailed Working Drawings for individual Culverts and Cross Drainage
Structures.
Detailed Working Drawings for individual Bridges, tunnels and Structures
Detailed Drawings for Improvement of At-Grade and
Grade-Separated.
Intersections and Interchanges.
Drawings for Road Sign, Markings and other Facilities.
Schematic Diagrams (linear chart) indicating but be not limited to be
following:
o Widening scheme;
o Locations of median openings, intersections, interchanges,
underpasses, overpasses, bypasses;
o Locations of service roads;
o Location of traffic signals, traffic signs, road markings, safety
features; and,
o Locations of parking areas, bus bays, rest areas, if any
All drawings will be prepared in A2 size sheets. The format for plan, cross
section and profile drawings shall be finalized in consultation with the
concerned CE (P) Beacon officers. The drawings shall also include details of
all BM and reference pillars, HIP and VIP. The co-ordinates of all points
should be referenced to a common datum, preferably GTS referencing system.
The drawings shall also include the locations of all traffic safety features
including traffic signals, signs, markings, crash barriers, delineators and rest
areas, busbays, parking areas etc.
The typical cross-section drawings should indicate the scheme for future
widening of the carriageway. The proposed cross-sections of road segment
passing through urban areas should indicate the provisions for pedestrian
movements and suitable measures for surface and sub-surface drainage
and lighting, as required.
1. The Final package-wise DPR consisting of Main Report, Tunnel Design Report,
Drainage Design Report and Materials Report, incorporating all revisions deemed
relevant following receipt of the comments from CE (P) Beacon on the draft DPR
shall be submitted as per the schedule given in Enclosure-III.
STAGE: 5
10.9 Technical Schedules
1. Civil Work Contract Agreement: A civil works contract agreement shall be
submitted.
STAGE: 6
10.10 LA & Clearances II Report
2. All the necessary project related clearances such as environment, forest and
wildlife clearance from MOEF, Railways in respect of ROB/ RUBs, Irrigation
Deptt and any other concerned agencies shall be obtained by the consultant. The
final approvals shall be obtained and submitted to CE (P) Beacon so that project
implementation can straight away proceed without any hold up. For utility
clearances, consultant shall prepare draft utility shifting estimates using the latest
Schedule of Rates and obtain final approval from utility agency and CE (P)
Beacon
2. The CE (P) Beacon officers and other Government officers may visit the site at
any time, individually or collectively to acquaint/ supervise the field investigation
and survey works. CE (P) Beacon may also appoint a Proof Consultant to
supervise the work of the DPR consultant including inter-alia field investigation,
survey work, Design work and preconstruction activities
4. All equipment, software and books etc. required for satisfactory services for this
project shall be obtained by the Consultant at their own cost and shall be their
property.
1. The floppy diskettes/CD‟s containing all basic as well as the processed data
from all field studies and investigations, report, appendices, annexure,
documents and drawings shall be submitted to CE (P) Beacon at the time of
the submission of the Final Report. The data can be classified as follows:
i. Engineering Investigations and Traffic Studies: Road Inventory,
Condition, Roughness, Test Pit (Pavement composition), Benkelman Beam
Deflection, Material Investigation including test results for sub-grade soils,
Traffic Studies(traffic surveys), axle load surveys, Sub-soil Exploration,
Drainage Inventory, Inventory data for bridge and culverts indicating
rehabilitation, new construction requirement etc. in MS EXCEL or any
other format which could be imported to widely used utility packages.
ii. Rate Analysis: The Consultant shall submit the rate analysis for various
works items including the data developed on computer in this relation so
that it could be used by the Authority later for the purpose of updating the
cost of the project.
4. Consultant shall include editable soft copies of the final versions of all documents,
including but not limited to the strip plan, plan & profile drawings, cross sections
of right of way and details of structures as well as any cost workings.
SUPPLEMENT I
5. 4.5 (1) All activities related to field studies, design and documentation shall be
done as per the latest guidelines/circulars of MORT&H and relevant
publications of the Indian Roads Congress (IRC)/Bureau of Indian Standards
(BIS) for hill roads. For aspects not covered by IRC and BIS, international
standard practices, such as, British and American Standards may be adopted.
9. 4.11.2.1 (ii) Cross sections shall be taken at every 25 m. in case of hill roads and at
points of appreciable changes in soil conditions. While taking cross
sections, soil conditions shall also be recorded.
10. 4.11.3.1 (1) The inventory data shall also include:
a) General elevation of road indicating maximum & minimum heights
negotiated by main ascents & descents and total no. of ascents
&descents.
b) Details of road gradients, lengths of gentle & steep slopes, lengths &
location of stretches in unstable areas, areas with cliffs, areas with loose
rocks, land slide prone areas, snow drift prone areas, no. & location of
hairpin bends etc.
c) Details of tunnels
d) Details & types of protective structures, erosion & land slide
control/protection measures, snow drift control measures, avalanche
protection/control measures etc.
The Design Standards evolved for the project shall cover all aspects of
detailed design including the design of geometric elements, pavement design,
bridges and structures, tunnels if required, traffic safety and materials.
16. 4.12.3 Wherever practicable/feasible hairpin bends and steep gradients shall be
avoided by realignments, provision of structures or any other suitable
provisions.
17. 4.12.4 While designing pavement for hill roads specific aspects relevant to hill
regions like terrain & topographic conditions, weather conditions, altitude
effects etc. shall be duly considered and suitably incorporated in design so
that pavement is able to perform well for the design traffic and service life.
Effects of factors like heavy rainfall, frost action, intensive snow and
avalanche activity, thermal stresses due to temperature difference in day
and night, damage by tracked vehicles during snow clearance operations
etc. must also be considered along with traffic intensity, its growth, axle
loads and design life.
18. 4.12.5(3) The design of embankments should include the requirements for protection
works and traffic safety features including features specific to hill roads.
19. -- Design and Drawing of Tunnels:
The Consultant shall prepare design and drawings for tunnels, if required
as per the results of feasibility study, as per the relevant specifications of
IRC:SP:91/MORT&H and other international specifications.
20. 4.12.7 a) Topography of hills generates numerous water courses and this coupled
with continuous gradients of roads in hills and high intensity of rainfall
calls for effective drainage of roads. The drainage system shall be
designed to ensure that the water flowing towards the road surface may
be diverted and guided to follow a definite path by suitable provision of
road side drains, catch water drains, interceptors etc. and flow on valley
side is controlled so that stability is not affected.
b) Further, adequate provision shall be made for sub-surface/subgrade
drainage to take care of seepage through the adjacent hill face of the
road & underground water flows.
21. 4.12.8 The Consultant shall design suitable traffic safety features and road
furniture including traffic signals, signs, markings, overhead sign boards,
crash barriers ,delineators etc. including any feature specific to hill roads.
The locations of these features shall be given in the reports and also shown
in the drawings.
22. 4.12.3 (1) The Consultant shall make suitable designs and layout for miscellaneous
SUPPLEMENT II
2. Methodology
Physical/Mathematical Model study shall be carried out at a
reputed/recognized institution. The consultant will be
responsible for identifying the institution, supplying
Information /Documents /Data required for modal studies as
indicated in para 4 below and coordinating the model study
with the institution concerned
3. Scope of Work
3.1 Physical Model study
Physical modeling with appropriate model scale for Hydraulic
and Hydrologic Investigations to :
i) Finalize span arrangement causing uniformity in flow
distribution, and work out the alignment and orientation of
river training works and bridge axis.
ii) Provide information on estimated/observed maximum
depth of scour.
iii) Provide information on required river training works for
proposed bridge
iv) Provide hydraulic design for the bridge and the required
river training works.
v) Quantify the general direction of river course through
bridge, afflux, extent and magnitude of flood, effect of
backwater, if any, aggradation/degradation of bed,
evidence of scour etc. shall be used to Sepment the
available hydrological data. The presence of flood
control/irrigation structures, if affecting the hydraulic
characteristics like causing obliquity, concentration of
flow, scour, silting of bed, change in flow levels, bed levels
etc. shall be studied and considered in Hydraulic design of
proposed bridge. The details of any planned work
viii) Size distribution of the river bed material and the bore
log data at different locations at the site of the proposed
bridge.
ix) The series of annual peak flood of the river for at least 15
years period.
SUPPLEMENT-III
ADDITIONAL REQUIREMENT OF SAFETY AUDIT
The use of checklists is highly recommended as they provide a useful “aide memoire” for the
audit team to check that no important safety aspects are being overlooked. They also give to the
project manager and the design engineer a sense of understanding of the place of safety audit in
the design process. The following lists have been drawn up based on the experience of
undertaking systematic safety audit procedures overseas. This experience indicates that extensive
lists of technical details has encouraged their use as “tick” sheets without sufficient thought being
given to the processes behind the actions. Accordingly, the checklists provide guidelines on the
principal issues that need to be examined during the course of the safety audits.
Stage F-During Feasibility Study
1. The audit team should review the proposed design from a road safety perspective and heck
the following aspects
CONTENTS ITEMS
Emergency vehicles
Public Transport
Future widening
Staging Contract
Adjacent development
A2 : Local Alignment
Visibility
New/existing road reference
Safety Aids on step hills
A3 : Junctions
Minimize potential conflicts
Layout
Visibility
A4 : Non-Motorized road
Adjacent land.
users Provision
Pedestrians
Cyclists
Non motorized Vehicles
A6 : Construction and
Buildability
operation
Operational
Network Management
1. The audit team should review the proposed check the following aspects design from a road
safety perspective and check the following aspects
Contents Items
Aspects to be checked A. Safety and operational implications of proposed alignment
and junction strategy with particular references to
expected road users and vehicle types likely to use the
road.
B. Width options considered for various sections.
C. Departures from standards and action taken.
D. Provision of pedestrians, cyclists and intermediate
transport.
E. Safety implications of the scheme beyond its physical
limits i.e. how the scheme fits into its environs and road
hierarchy
B1 : General Departure from Standards
Cross-sectional variation
Drainage
Climatic conditions
Landscaping
Services apparatus
Lay-byes
Footpath
Pedestrian crossings
Access (minimize number of private accesses)
Emergency vehicles
Public Transport
Future widening
Staging Contract
Adjacent development
B2 : Local Alignment
Visibility
New/existing road reference
Safety Aids on steep hills
B3 : Junctions
Minimize potential conflicts
Layout
Visibility
B4 : Non-Motorized road
Adjacent land.
users Provision
Pedestrians
Cyclists
Non motorized Vehicles
B5 : Signs and Lighting
Lighting
Signs/Marking
B6 : Construction and
Buildability
operation
Operational
Network Management
Stage 2 – Completion of Detailed Design
1. The audit team should satisfy itself that all issues raised at Stage 1 have been resolved.
Items may require further consideration where significant design changes have occurred.
2. If a scheme has not been subject to a stage 1 audit, the items listed in Checklists B1 to B6
should be considered together with the items listed below.
Contents Items
Aspects to be checked A. Any design changes since Stage 1.
B. The detailed design from a road safety viewpoint, including
the road safety implications of future maintenance (speed
limits; road signs and markings; visibility; maintenance of
street lighting and central reserves).
C1 : General Departure from Standards
Cross-sectional variation
Drainage
Climatic conditions
Landscaping
Services apparatus
Lay-byes
Access
Skid resistance
Agriculture
Safety fences
Adjacent development
C2 : Local Alignment
Visibility
New/existing road reference
C3 : Junctions
Layout
Visibility
Signing
Lighting
Road Marking
T,X,Y- Junction
All roundabouts
Traffic signals
C4 : Non-Motorized road
Adjacent land.
users Provision
Pedestrians
Cyclists
Non motorized Vehicles
C5 : Signs and Lighting
Advanced direction signs
Local Traffic Sings
Variable message signs
Other traffic signs
Lighting
C6 : Construction and
Buildability
operation
Operational
Network Management
Enclosure-I
MANNING SCHEDULE
1. Consultants have to provide a certificate that all the key personnel as envisaged in the
Contract Agreement have been actually deployed in the projects. They have to furnish
the certificate at the time of submission of their bills to CE (P) Beacon from time to
time.
Enclosure-II
ii) Experience
a)Total Professional Experience Min. 15 years
I Educational Qualification
Civil Engineering/Mining Engineering /Engineering
Essential
Geology
Geotechnical Engineering /Foundation
Desirable Engineering/Rock Mechanics/Geo science or
equivalent
II Essential Experience
a) Total Professional Experience Min. 15 years
(i) Professional experience in handling major tunnel
projects (Road/Rail/Metro)
(ii) Experience in major tunnel
b) Experience in Tunnel Projects construction/construction supervision projects
(Road/Rail/Metro)
(iii)Experience in preparation of DPR or Feasibility
report of major tunnel projects (Road/Rail/Metro)
(i) Professional Experience as Senior Geotechnical
Engineer
(ii) Experience as Senior Geotechnical Engineer or
similar capacity in major tunnel
construction/construction supervision projects
c) Experience in similar capacity (Road/Rail/Metro)
(iii) Experience as Senior Geotechnical Engineer or
similar capacity in preparation of DPR or Feasibility
report of major tunnel projects (Road/Rail/Metro)
(iv) Experience as Senior Geotechnical Engineer or
similar capacity in preparation of DPR/Feasibility
report of major tunnel projects (Road/Rail/Metro)
III Age Limit 70 years on the date of submission of proposal
Enclosure-II(contd.)
I Educational Qualification
Essential Degree in Electrical/Mechanical Engineering.
Post Graduation in Degree in Electrical/Mech
Desirable
Engineering
II Essential Experience
a) Total Professional Experience Min. 15 years
10 years in Tunnel Projects and should have
b) Experience in Tunnel Projects worked for atleast five years as an E&M Expert
for Tunnel Design/ Construction projects
c) Experience in similar capacity He should have handled atleast three tunneling
projects in similar capacity
III Age Limit 70 years on the date of submission of proposal
I Educational Qualification
Essential Post Graduate Degree in Geology.
Desirable Phd in Geology/Related fields.
II Essential Experience
a) Total Professional Experience Min. 15 years
He should have a minimum 10 years of professional
experience and should have involved in project
b) Experience in Tunnel Projects
preparation / DPR/ Tunnel Design for at least two
major Tunnel projects.
He should have experience in similar capacity per five
c) Experience in similar capacity years on Design/ Construction/ Supervision of Tunnel
Projects.
III Age Limit 70 years on the date of submission of proposal
I Educational Qualification
Degree or equivalent in Civil Engineering/Diploma in
Essential
Surveying.
Post Graduation in Survey Engineering/Surveying
Desirable
/Remote Sensing
II Essential Experience
a) Total Professional Experience Min. 15 years
Min. 5 years on similar projects in project preparation
b) Experience in Tunnel Projects and construction & thorough understanding of
modern computer based methods of surveying
Senior Survey Engineer for projects preparation of
c) Experience in similar capacity highway project (NH/SH/Expressways) involving
2/4/6 laning of minimum aggregate length of 80 km.
III Age Limit 65 years on the date of submission of proposal
Enclosure-II(contd.)
Environmental Expert
i) Educational Qualification
I Educational Qualification
Graduate in Civil Engineering/Material Science and
Essential
Engineering or equivalent.
Post graduation in Material Science and Engineering
Desirable
or equivalent
II Essential Experience
a) Total Professional Experience Min. 15 years
Minimum 8 years on Tunnel projects in design
b) Experience in Highway and /or construction. Experience on Tunnel
Projects
projects shall be preferred
Material Engineer on highway projects (2/4/6 lane
c) Experience in similar capacity NH/SH/Expressway) of minimum aggregate length of
80 km.
III Age Limit 70 years on the date of submission of proposal
I Educational Qualification
Essential Degree in Civil Engineering or Equivalent.
Post Graduation in Highway Engg/Transportation
Desirable
Engineering
II Essential Experience
a) Total Professional Experience Min. 15 years
b) Experience in Highway Minimum 10 years experience in pavement
Projects design and maintenance of highways
Pavement design for major highway projects (2/4/6
c) Experience in similar capacity lane NH/SH/ Expressways) of minimum aggregate
length of 80 km.
III Age Limit 70 years on the date of submission of proposal
i) Educational Qualification
Desirable
ii) Essential Experience
a) Total Professional Experience Min. 15 years
b) Experience in Highway Projects Min. 5 years in Preparation of Bill of
Quantities, Contract documents and
documentation for major highway projects
involving two/ four laning
c) Experience in similar capacity Quantity Surveyor / Documentation Expert
in highway projects (NH/SH/Expressways)
involving two/four/six laning of minimum
aggregate length of 80 km.
iii) Age Limit 70 years on the date of submission of
Proposal
Enclosure-III
3 F.S. REPORT
i) Draft Feasibility Study 4 225
Report including option
study report
ii) Comments of client 1 270
4 LA & Clearances I
Repor
t
6 Technical
Schedules
i) Draft
Technical 4 600
Schedules
iii) Final
technical 6 700
schedule
APPENDIX-II
Proof of Eligibility
Form-E1
Letter of Proposal (On Applicant‟s letter head)
(Date and Reference)
To, **********
*********
*********
With reference to your RFP Document dated ………, I/we i.e M/s-------------------------------------
--------------------------------------(Name of Bidder) h a v i n g examined all relevant documents and
understood their contents, hereby submit our Proposal for selection as Consultant. The proposal is
unconditional and unqualified.
2. All information provided in the Proposal and in the Appendices is true and correct and all
documents accompanying such Proposal are true copies of their respective originals.
3. This statement is made for the express purpose of appointment as the Consultant for the
aforesaid Project.
4. I/We shall make available to the Authority any additional information it may deem
necessary or require for supplementing or authenticating the Proposal.
5. I/We acknowledge the right of the authority to reject our application without assigning any
reason or otherwise and hereby waive our right to challenge the same on any account
whatsoever.
6. I/We certify that in the last three years, we or any of our Associates have neither failed to
perform on any contract, as evidenced by imposition of a penalty by an arbitral or judicial
authority or a judicial pronouncement or arbitration award against the Applicant, nor been
expelled from any project or contract by any public authority nor have had any contract
terminated by any public authority for breach on our part.
7. I/We understand that you may cancel the Selection Process at any time and that you are
neither bound to accept any Proposal that you may receive nor to select the Consultant,
without incurring any liability to the Applicants in accordance with Clause 1.7 of the RFP
document.
8. I/We declare that we/any member of the consortium, are/is not a Member of any other
Consortium applying for Selection as a Consultant.
9. I/We certify that in regard to matters other that security and integrity of the country, we or
any of our Associates have not been convicted by a Court of Law or indicted or adverse
orders passed by a regulatory authority which would cast a doubt on our ability to undertake
the Consultancy for the Project or which relates to a grave offence that outrages the moral
sense of the community.
10. I/We further certify that in regard to matters relating to security and integrity of the country,
we have not been charge-sheeted by any agency of the Government or convicted by a Court
of Law for any offence committed by us or by any of our Associates.
11. I/We further certify that no investigation by a regulatory authority is pending either against
us or against our Associates or against our CEO or any of our
Directors/Managers/employees.
12. I/We hereby irrevocably waive any right or remedy which we may have at any stage at law
or howsoever otherwise arising to challenge or question any decision taken by the Authority
[and/ or the Government of India] in connection with the selection of Consultant or in
connection with the Selection Process itself in respect of the above mentioned Project.
13. The Bid Security of Rs. 2,00000 (Rupees Two Lakh Only) in the form of a Bank Guarantee
is attached, in accordance with the RFP document.
14. I/We agree and understand that the proposal is subject to the provisions of the RFP document.
In no case, shall I/we have any claim or right of whatsoever nature if the Consultancy for
the Project is not awarded to me/us or our proposal is not opened or rejected.
15. I/We agree to keep this valid for 120 (One hundred and twenty) days from the Proposal
Due Date specified in the RFP.
16. A Power of Attorney in favour of the authorized signatory to sign and submit this Proposal
and documents is attached herewith.
17. In the event of my/our firm/consortium being selected as the Consultant, I/we agree to enter
into any Agreement in accordance with the form Appendix V of the RFP. We agree not to
seek any changes in the aforesaid form and agree to abide by the same.
18. I/We have studied RFP and all other documents carefully and also surveyed the Project site.
We understand that except to the extent as expressly set forth in the Agreement, we shall
have no claim, right or title arising out of and documents or information provided to us by
the Authority or in respect of any matter arising out of or concerning or relating to the
Selection Process including the award of Consultancy.
19. The Proof of Eligibility and Technical proposal are being submitted in separate covers in
hard copy and they are being submitted online also. Financial Proposal is being submitted
online only. This Proof of Eligibility read with Technical Proposal and Financial Proposal
shall constitute the Application which shall be binding on us.
20. I/We agree and undertake to abide by all the terms and conditions of the RFP Document. In
witness thereof, I/we submit this Proposal under and in accordance with the terms of the
RFP Document.
Yours faithfully,
(Signature, name and designation of the authorized signatory)
(Name and seal of the Applicant/Lead Member)
The following information should be provided in the format below for each reference assignment
for which your firm, either individually as a corporate entity or as one of the major companies
within a consortium, was legally contracted by the client:
APPENDIX-II
Form- E3
Name of Applicant:
$
Certificate from the Statutory Auditor
This is to certify that --------------(name of the Applicant) has received the payments
shown above against the respective years on account of Consultancy Services.
firm Date
$
In case he Applicant does not have a statutory auditor, it shall provide the
certificate from its chartered accountant that ordinarily audits the annual account of the Applicant.
Note:
DATE _______________
SIGNATURE OF THE BANK _______________________
SEAL OF THE BANK _____________________________
SIGNATURE OF THE WITNESS ____________________
Name and Address of the Witness ___________________
The bank guarantee shall be issued by a bank (Nationalized/Scheduled) located in India
Appendix III
(Form-T1)
TECHNICAL PROPOSAL
FROM: TO:
Sir:
I/We (name of
Bidder) Consultant/ Consultancy firm herewith enclose Technical Proposal for selection of
my/our firm/organization as Consultant for .
Yours faithfully,
Signature
Full Name
Designation
Address
(Authorized Representative)
Details of projects for which Technical and Financial Proposals have been submitted
1
2
3
4
FIRM‟S REFERENCES
Relevant Services Carried out in the Last Seven Years
Which Best Illustrate Qualifications
The following information should be provided in the format below for each reference assignment
for which your firm, either individually as a corporate entity or as one of the major companies
within a consortium, was legally contracted by the client:
Form- T4
SITE APPRECIATION
Shall give details of site as per actual site visit and data provided in RFP and collected from
site supported by photographs to demonstrate that responsible personnel of the Consultant
have actually visited the site and familiarized with the salient details/complexities and scope
of services.
Form- T5
1.
2.
3.
4.
5.
….
….
Form- T6
I. Technical/Managerial Staff
1.
2.
3.
4.
….
….
….
1.
2.
3.
4.
….
….
….
Form- T7
The approach and methodology will be detailed precisely under the following topics.
1) Composition of the team [not more than 1 page]
2) Methodology for services, surveying, data collection [not more than 2 pages]
and analysis
3) Quality Assurance system for consultancy assignment [not more than 1 page]
Form- T8
1. State whether the Applicant has in-house Material Testing Facility Available /
Outsourced / Not Available
2. In case answer to 1 is Available, attach a list of Lab equipment and facility for testing of
materials and location of laboratory
3. In case laboratory is located at a distance of more than 400 km from the project site, state
arrangements made/proposed to be made for testing of materials
Form- T9
Facility for Field investigation and Testing
2. In case answer to 1 is Available a list of field investigation and testing equipments available
in-house
4. For experience in LiDAR or equivalent technology for topographic survey, GPR and
Induction Locator or equivalent technologies for detection of sub-surface utilities and
digitization of cadastral maps for land acquisition, references need to be provided in
following format:
REFERENCES
Relevant Services Carried
Which Best Illustrate Qualifications
The following information should be provided in the format below for each reference assignment
for which your firm, either individually as a corporate entity or as one of the major companies
within a consortium, was legally contracted by the client:
Form- T10
Office Equipment and software
Form- T11
Photo
1. Proposed Position:
2. Name of Staff:
4. Nationality:
5. Educational Qualification:
(Summarize college/university and other specialized education of staff member, giving names
of schools, dates attended and degrees obtained). (Please furnish proof of qualification)
7. Publication:
(List of details of major technical reports/papers published in recognized national and
international journals)
8. Employment Record:
(Starting with present position, list in reversed order, every employment held. List all
positions held by staff member since graduation, giving dates, names of employing
organization, title of positions held and location of assignments. For experience period
of specific assignment must be clearly mentioned, also give client references, where
appropriate).
9. Summary of the CV
(Furnish a summary of the above CV. The information in the summary shall be precise
and accurate. The information in the summary will have bearing on the evaluation of
the CV).
A) Education:
i) Field of graduation and year
ii) Field of post-graduation and year
iii) Any other specific qualification
B) Experience
i) Total experience in highways: ___ Yrs.
ii) Responsibilities held: a) ___Yrs.
b) ___Yrs.
c) ___ Yrs.
iii) Relevant experience: ___ Yrs.
Certification:
1. I am willing to work on the project and I will be available for entire duration of the
project assignment and I will not engage myself in any other assignment during the
currency of this assignment on the project
2. I, the undersigned, certify that to the best of my knowledge and belief, this biodata
correctly describes myself my qualification and my experience.
Place
Date
Note: Each page of the CV shall be signed in ink by both the staff member and the Authorized
representative of the firm. Photocopies will not be considered for evaluation.
I, …………………. (Name and Address) have not left any assignment with the consultants
engaged by MORT&H/ contracting firm (firm to be supervised now) for any continuing works of
MORT&H without completing my assignment. I will be available for the entire duration of the current
project (named…………..). If I leave this assignment in the middle of the completion of the work, I
may be debarred for an appropriate period to be decided by CE (P) Beacon. I have also no objection if
my services are extended by CE (P) Beacon for this work in future.
Appendix IV
(Form-I)
FINANCIAL PROPOSALS
FROM: TO:
Sir:
Yours faithfully,
Signature
Full Name
Designation
Address
(Authorized Representative)
* i) The Financial proposal is to be filled strictly as per the format given in CPP Portal i.e
www.eprocure.gov.in and shall be uploaded online only.
ii) Form-II, III & IV is specimen copy and not to be submitted offline (In hard copy)
Note:
No escalation will be payable during the services
Insurances shall not be allowed separately .These will be incidental to main items.
Rates for all items shall be quoted in figures as well as in words.
(Form-III)
S.No. Rate
Position Name SM Amt.(INR)
(INR)
Professional Staff
SAMPLE
Team Leader Cum Senior
1 23
Tunnel Engineer
2 Tunnel Design Expert 12
Senior Geotechnical
3 12
Engineer
Ventilation/Lightening
4 Expert (Senior E& M 6
Expert)
5 Senior Geologist 9
6 Senior Survey Engineer 12
7 Environmental Expert 6
8 Material Engineer 6
Highway cum Pavement
9 4.5
Engineer
Quantity Surveyor/
10 6
Documentation Expert
Sub-Total: 96.5
Sub-Professional Staff (To be assessed by Consultant as per requirement
of assignment)
1
2
3
4
5
6
7
Sub-Total:
TOTAL
SAMPLE
2 Typist
3 Office Boy
4 Night Watchman
Total :
Total
SAMPLE
1 Office Supplies Drafting
2 Supplies Computer
3 Running Costs
TOTAL :---------------------------
SAMPLE
13 Draft Bidding Documents 4
14 Final Detailed Project Report 6
with Bill of Quantities, Cost
Estimates, Updated Drawings etc.
15 Final EMP 6
16 Final Bidding Documents 6
Total
3 Roughness Survey
4 Axle Load Survey
5 Material Survey and Investigation
6 Sub-grade Investigation
7 Traffic Survey
8 Socio-economic & Census
Survey/Studies
9 Land Acquisition Studies
Total
Sub-soil Investigation:
The payment under this schedule will be paid based on actual quantity executed at site
Quantity Rate Amount
in in INR
INR
1 Sub-Soil Investigation for Tunnel
a) Boring in all type of strata (other than hard rock) 2000m
b) Boring in hard rock 800m
2 Directional coring in any length along the proposed directional
coring trajectory (corehole size NQ). The rate includes
transportation of all plant, manpower, drilling accessories, sampling
equipment work site, erection on site for Horizontal Directional
Coring (Soil drilling testing and rock coring), trial pit , hand
Sepuring, reinstatement of borehole etc including grouting in zones
of weakness.
2.1 Inclined soil, artificial hard material or boulder drilling and 800m
directional coring in hard rock material or boulder from the launch
site at ground level to the commencement of the HDC trajectory.
2.2 Not exceeding 100m in length from chainage 0.000 (i.e. 400m
commencement of HDC trajectory) in rock
2.3 Exceeding 100m in length but not exceeding 200m length in rock 400m
2.4 Directional coring in any length along the proposed directional 400m
coring trajectory in Material other than rock
(Form-IV)
SAMPLE Total :
Total
(Form –V)
Deleted
(i) A Firm applying should have Experience of preparation of Detailed Project Report
(DPR)/Feasibility Study (FS)/Design Consultancy for Road/Rail/ Metro tunnels of aggregate
length equal to 60% of 7.00 Km (indicative length) length of the package. Firm should have
also prepared DPR/Feasibility Study (FS)/Design Consultancy for at least one project of
Road/Rail/Metro tunnel of minimum length of 4.20 Km in last 10 years (i.e. from 2008-09
onwards).
1 2 3 5
(ii) Annual Average Turn Over for the last 3 years {In cases where, Audited/Certified copy of
Balance Sheet for the FY 2017-18 is available, last three years shall be counted from 2015-16
to 2017-18. However, where audited/certified copy of the Balance Sheet for the FY 2017-18
is not available (as certified by the Statutory auditor) then in such cases last three years shall
be considered from 2014-15 to 2016-17} of the firm from Consultancy services should be
equal to more than Rs 15 crore
Note: (i) Weightage to be given when experience by a Firm as Sole Firm/Lead Partner in a
JV/Other Partner in a JV/As Associate
No. Status of the firm in carrying out DPR/Feasibility Weightage for experience
Study (FS)/Design Consultancy
1 Sole firm 100%
2 Lead partner in a JV 75%
3 Other partner in a JV 50%
4 As Associate 25%
As tunnel projects require specialized capabilities and skill sets, the following is the break-up:
No. Status of the firm in carrying out DPR/ Weightage for experience
Feasibility Study (FS)/Design Consultancy
1 Sole firm 100%
4 As Associate 25%
2.2. Adequacy of the proposed work plan and methodology in responding to the TOR:
Max
S. No. Description points
Total Points 20
1.1 Available 0
1.2 Outsourced 0
2.4 Qualification and Competence of the Key Staff for adequacy of the Assignment. (Para 12.2
of Data Sheet and Enclosure II of TOR)
= 2 projects 6
= 3 to 5 projects 7
> 5 or more projects 8
III Employment with Firm 10
Less than 1 Year 0
1-2 years 5
more than 2 years 10
Total 100
Major Tunnel Project = having length more than 1.5 km.
<80km 0
80km-150km 14
>150km-250km 17
>250km 19
(ii) In Design/ Pavement Design of Highway Projects (2/4/6 laning of NH/SH/ 9
Expressways) in Similar Capacity – Number of Projects
2 projects 7
3- 5 projects 8
More than 5 projects 9
III Employment with Firm 10
1-2 years 5
more than 2 years 10
Total 100
Appendix VI
DRAFT
CONTRACT AGREEMENT
Between
and
For
CONTENTS
1. General Provisions
1.1 Definitions
1.2 Relation between the Parties
1.3 Law Governing the Contract
1.4 Language
1.5 Headings
1.6 Notices
1.7 Location
1.8 Authority of Member in Charge
1.9 Authorized Representatives
1.10 Taxes and Duties
2. Commencement, Completion, Modification and Termination of Contract
2.1 Effectiveness of Contract
2.2 Termination of Contract for Failure to Become Effective
2.3 Commencement of Services
2.4 Expiration of Contract
2.5 Entire Agreement
2.6 Modification
2.7 Force Majeure
2.7.1 Definition
2.7.2 No Breach of Contract
2.7.3 Measures to be Taken
2.7.4 Extension of Time
2.7.5 Payments
2.7.6 Consultation
2.8 Suspension
2.9 Termination
2.9.1 By the Client
2.9.2 By the Consultants
2.9.3 Cessation of Rights and Obligations
2.9.4 Cessation of Services
2.9.5 Payment upon Termination
2.9.6 Disputes about Events of Termination
3. Obligations of the Consultants
3.1 General
3.1.1 Standard of Performance
3.1.2 Law Governing Services
3.2 Conflict of Interests
3.2.1 Consultants not to Benefit from Commissions, discounts etc.
3.2.2 Consultants and Affiliates not to be otherwise interested in
Project
Signature of contractor For Accepting Officer
CA NO CE (P) BEACON/ /2018-19 Srl Page No. 159
Tender No. CE (P)/BEACON/DPR CONSULTANCY/07/2018-19
9 SETTLEMENT OF DISPUTES
9.1 Amicable Settlement
9.2 Dispute Settlement
IV. APPENDICES
This CONTRACT (hereinafter called the “Contract”) is made on the ----------day of the month of -----
----------2018 , between, on the one hand, The Chief Engineer, Project Beacon, Rangret, opposite
SIDCO, Distt – Badgam (J&K), Pin - 190007, (hereinafter called the “Client”) and, on the other
hand, M/s ------------------------------------------ in JV with -------------------------- and in Association with
…………………………………………….(hereinafter called the “Consultants”).
WHEREAS
(A) the Client has requested the Consultants to provide certain consulting services as
defined in the General Conditions attached to this Contract (hereinafter called the
“Services”);
(B) the Consultants, having represented to the Client that they have the required
professional skills, personnel and technical resources, have agreed to provide the
Services on the terms and conditions set forth in this Contract;
Appendix A: Terms of reference containing, inter-alia, the Description of the Services and
Reporting Requirements
Appendix B: Consultants‟ Sub consultants, Key Personnel and Sub Professional Personnel,
Task assignment, work programme, manning schedule, qualification
requirements of key personnel, and schedule for submission of various report.
2. The mutual rights and obligations of the Client and the Consultants shall be as set forth
in the Contract; in particular:
(a) The Consultants shall carry out the Services in accordance with the provisions of
the Contract; and
(b) Client shall make payments to the Consultants in accordance with the provisions
of the Contract.
IN WITNESS WHEREOF, the Parties hereto have caused this Contract to be signed in their
respective names as of the day and year first above written.
1 Signature
Name
Address
By
Authorized Representative 2. Signature
Name
Address
FOR AND ON BEHALF OF Witness
(Consultant) 1. Signature
Name
Address
By
Authorized Representative
(c) “Effective Date” means the date on which this Contract comes into force and
effect pursuant to Clause GC 2.1;
(d) “foreign currency” means any currency other than the currency of
Government;
(i) “Party”means the Client or the Consultants, as the case may be, and Parties
means both of them;
(j) “Services” means the work to be performed by the Consultants pursuant to this
Contract for the purposes of the Project, as described in Appendix A hereto;
(k) “SC” means the Special Conditions of Contract by which these General
Conditions of Contract may be amended or supplemented;
(l) “Sub Consultant” means any entity to which the Consultants subcontract any part
of the Services in accordance with the provisions of Clause GC 3.7; and
(m) “Third Party” means any person or entity other than the Government, the
Client, the Consultants or a Sub Consultant.
1.7 Location
The Services shall be performed at such locations as are specified in Letter of
Acceptance (Appendix-I) hereto and, where the location of a particular task is not so
specified, at such locations, whether in India or elsewhere, as the Client may approve.
2.6 Modification
Modification of the terms and conditions of this Contract, including any modification of
the scope of the Services, may only be made by written agreement between the Parties.
Pursuant to Clause GC 7.2 hereof, however, each party shall give due consideration to
any proposals for modification made by the other Party.
(b) Force Majeure shall not include (i) any event which is caused by the negligence
or intentional action of a Party or such Party‟s Sub Consultants or agents or
employees, nor (ii) any event which a diligent Party could reasonably have been
expected to both (A) take into account at the time of the conclusion of this
Contract and (B) avoid or overcome in the carrying out of its obligations here
under
(c) Force Majuere shall not include insufficiency of funds or failure to make any
payment required hereunder.
(a) A party affected by an event of Force Majeure shall take all reasonable measures to
remove such Party‟s inability to fulfill its obligations hereunder with a minimum of
delay.
(b) A party affected by an event of Force Majeure shall notify the other Party of such event
as soon as possible, and in any event not later than fourteen (14) days following the
occurrence of such event, providing evidence of the nature and cause of such event, and
shall similarly give notice of the restoration of normal conditions as soon as possible.
(c) The Parties shall take all reasonable measures to minimize the consequences of any
event of Force Majeure.
2.7.5 Payments
During the period of their inability to perform the Services as a result of an event of
Force Majeure, the Consultants shall be entitled to be reimbursed for additional costs
reasonably and necessarily incurred by them during such period for the purposes of the
Services and in reactivating the Services after the end of such period.
2.7.6 Consultation
Not later than thirty (30) days after the Consultants, as the result of an event of Force
Majeure, have become unable to perform a material portion of the Services, the Parties
shall consult with each other with a view to agreeing on appropriate measures to be
taken in the circumstances.
2.8 Suspension
The Client may, by written notice of suspension to the Consultants, suspend all
payments to the Consultants hereunder if the Consultants fail to perform any of their
obligations under this Contract, including the carrying out of the Services, provided that
such notice of suspension (i) shall specify the nature of the failure, and (ii) shall request
the Consultants to remedy such failure within a period not exceeding thirty (30) days
after receipt by the Consultants of such notice of suspension.
2.9 Termination
2.9.1 By the Client
The Client may, by not less than thirty (30) days‟ written notice of termination to the
Consultants (except in the event listed in paragraph (f) below, for which there shall be a
written notice of not less than sixty (60) days), such notice to be given after the
occurrence of any of the events specified in paragraphs (a) through (f) of this Clause
2.9.1, terminate this Contract:
(a) if the Consultants fail to remedy a failure in the performance of their obligations
hereunder, as specified in a notice of suspension pursuant to Clause 2.8
hereinabove, within thirty (30) days of receipt of such notice of suspension or
within such further period as the Client may have subsequently approved in
writing;
(b) if the Consultants become (or, if the Consultants consist of more than one entity,
if any of their Members becomes) insolvent or bankrupt or enter into any
agreements with their creditors for relief of debt or take advantage of any law for
the benefit of debtors or go into liquidation or receivership whether compulsory
or voluntary;
(c) if the Consultants submit to the Client a statement which has a material effect on
the rights, obligations or interests of the Client and which the Consultants know
to be false;
(d) if, as the result of Force Majeure, the Consultants are unable to perform a
material portion of the Services for a period of not less than sixty (60) days; or
(e) if the Client, in its sole discretion and for any reason whatsoever, decides to
terminate this Contract.
(b) after the termination of this Contract, such other activities as may be specified in the
SC.
3.3 Confidentiality
The Consultants, their Sub Consultants and the Personnel of either of them shall not,
either during the term or within two (2) years after the expiration of this Contract,
disclose any proprietary or confidential information relation to the Project, the Services,
this Contract or the Client's business or operations without the prior written consent of
the Client.
3.4 Liability of the Consultants
Subject to additional provisions, if any, set forth in the SC, the Consultants' liability
under this Contract shall be as provided by the Applicable Law.
3.5 Insurance to be taken out by the Consultants
The Consultants (i) shall take out and maintain, and shall cause any Sub consultants to
take out and maintain, at their (or the Sub consultants', as the case may be) own cost but
on terms and conditions approved by the Client, insurance against the risks, and for the
coverage, as shall be specified in the Special Conditions (SC), and (ii) at the Client's
request, shall provide evidence to the Client showing that such insurance has been taken
out and maintained and that the current premiums therefore have been paid.
Equipment and materials made available to the Consultants by the Client, or purchased
by the Consultants with funds provided by the Client, shall be the property of the Client
and shall be marked accordingly. Upon termination or expiration of this Contract, the
Consultants shall make available to the Client an inventory of such equipment and
materials and shall dispose of such equipment and materials in accordance with the
Client's I instructions. While in possession of such equipment and materials, the
Consultants, unless otherwise instructed by the Client in writing, shall insure them in an
amount equal to their full replacement value.
4. CONSULTANTS' PERSONNEL
4.1 General
The Consultants shall employ and provide such qualified and experienced Personnel as are
required to carry out the Services.-
4.2 Description of Personnel
(a) The titles, agreed job descriptions, minimum qualification and estimated periods of
engagement in the carrying out of the Services of each of the Consultants' Key
Professional / Sub Professional Personnel are described in Appendix B.
(b) If required to comply with the provisions of Clause 3.1.1 of this Contract, adjustments
with respect to the estimated periods of engagement of Key Professional / Sub
Professional Personnel set forth in Appendix B may be made by the Consultants by
written notice to the Client, provided
(i) that such adjustments shall not alter the originally estimated period of
engagement of any individual by more than 10% or one week, whichever is
larger, and
(ii) that the aggregate of such adjustments shall not cause payments under this
Contract to exceed the ceilings set forth in Clause 6.1 (b) of this Contract. Any
other such adjustments shall only be made with the Client's written approval.
(c) If additional work is required beyond the scope of the Services specified in Appendix
A, the estimated periods of engagement of Key Personnel set forth in Appendix B may
be increased by agreement in writing between the Client and the Consultants.
4.5.6 If any member of the approved team of a Consultant engaged by CE (P) Beacon leaves
that Consultant before completion of the job, he shall be barred for a period of 6 months
to 24 months from being engaged as a team member of any other Consultant working
(or to be appointed) for any other BRO / MORT&H projects.
4.5.7 In exceptional situations where the replacement with equivalent or better qualification is
not available, replacement with lower qualifications than the originally approved may be
accepted with reduction in remuneration as per the procedure prescribed below. This
kind of relaxation shall however, be limited to replacement of 2 key personnel only in
one consultancy contract package.
i) The new proposed personnel as a replacement has to be evaluated as per the criteria
fixed at the time of evaluation of original proposal and marks/rating and then:
-If the original personnel (included in the original proposal based on which the contract
was awarded) is to be replaced at the instruction of CE (P) Beacon and the new proposed
personnel is having less qualification/ experience i.e marks/rating (but fulfilling the
minimum requirement as per TOR), his remuneration would be reduced by 15% over
and above the stipulated conditions in the contract because of less qualified personnel.
-If the original personnel (included in Contract Agreement) is to be replaced by the
Consulting firm and the new proposed personnel is having less qualification/ experience
(marks/rating), then his remuneration would be decreased proportionally in comparison
to the marks of the original personnel. This will also take into account the contract
condition and if the proposed reduction is less than that stipulated in contract condition,
it would be as per the contract provision.
It will be ensured that the new proposed personnel should score at least 75% of the
marks of the originally approved key personnel. Both the Consulting firm and the
proposed personnel should give the undertaking in the format available in Form VII of
Appendix II along with the replacement CV.
ii) The CV should be signed by personnel and the consulting firm in every page. If the CV is
found incorrect at later date, the personnel accepted would be removed from the assignment
and debarred from further CE (P) Beacon works for an appropriate period to be decided by
CE (P) Beacon and the new proposed personnel in place of removed personnel would be
paid 15% less salary than the original personnel. 15% reduction in the salary will be imposed
as penalty for submitting the incorrect information. This penalty will be imposed only once.
If the same consulting firm submits incorrect information again second time, necessary
action will be taken by CE (P) Beacon to blacklist the firm.
5.5 Payment
In consideration of the Services performed by the Consultants under this Contract, the
Client shall make to the Consultants such payments and in such manner as is provided by
Clause 6 of this Contract.
(a) The Client shall cause to be paid to the Consultants an advance payment as specified in
the SC, and as otherwise set forth below. The advance payment will be due after
provision by the Consultants to the Client of a bank guarantee by a bank acceptable to the
Client in an amount (or amounts) and in a currency (or currencies) specified in the SC,
such bank guarantee (i) to remain effective until the advance payment has been fully set
off as provided in the SC, and ii) in such form as the Client shall have approved in
writing.
Payment as %
S.No Item of contract
value
1 Submission of final Inception Report 5%
2 Topographical survey of corridor including 10%
walk over survey by geologist
3 Conduct of Vertical and Horizontal drilling 20%
with sampling
4 Submission of final Alignment Report 10%
5 Submission of final Feasibility Report 5%
6 Submission of final Land Acquisition
10%
Report
7 Submission of clearance proposals 5%
8 Submission of Draft DPR 10%
9 Approval of Final DPR 10%
10 Approval of Technical Schedules 5%
11 Retention to be released after 2 years 10%
Total: 100%
Note: Consultants have to provide a certificate that all key personnel as envisaged in the
Contract Agreement has been actually deployed in the project. They have to submit this
certificate at the time of submission of bills to CE (P) Beacon from time to time.
(c) No payment shall become eligible for the next stage till the consultant completes to the
satisfaction of the client the work pertaining to the preceding stage. The payment for the
work of sub-soil investigation (Boring)will be as per plan approved by the client and will
be paid as per actual at the rates quoted by the consultants .The payment for the quantity
given by the client for boring will be deemed to be included in the above mentioned
payment schedule. Any adjustment in the payment to the consultants will be made in the
final payment only.
(d) The Client shall cause the payment of the Consultants in Para 6.4 (b) above as given in
schedule of payment within thirty (30) days after the receipt by the Client of bills.
Interests at the rate specified in the SC shall become payable as from the above due date
on any amount due by, but not paid on, such due date.
(e) The final payment under this Clause shall be made only after the final report and a final
statement, identified as such, shall have been submitted by the Consultants and approved
as satisfactory by the Client. The Services shall be deemed completed and finally
accepted by the Client and the final report and final statement shall be deemed approved
by the Client as satisfactory one hundred and eighty (180) calendar days after receipt of
the final report and final statement by the Client unless the Client, within ninety(90) day
period, gives written the final notice to the Consultants specifying in detailed deficiencies
in the services, report or final statement. The Consultants shall thereupon promptly
make any
necessary corrections, and upon completion of such corrections, the foregoing process
shall repeated. Any amount which the Client has paid or caused to be paid in accordance
with this Clause in excess of the amounts actually payable in accordance with the
provisions of this Contract shall be reimbursed by the Consultants to the Client within
thirty (30) days after receipt by the Consultants of notice thereof. Any such claim by the
Client for reimbursement must be made within twelve (12) calendar months after receipt
by the Client of a final report and a final statement approved by the Client in accordance
with the above.
(f) All payments under this Contract shall be made to the account of the Consultants specified
in the SC.
7. Responsibility for Accuracy of Project Documents
7.1 General
7.1.1 The Consultant shall be responsible for accuracy of the data collected, by him directly
or procured from other agencies/authorities, the designs, drawings, estimates and all
other details prepared by him as part of these services. He shall indemnify the CE (P)
Beacon (BRO) against any inaccuracy in the work which might surface during
implementation of the project. The Consultant will also be responsible for correcting, at
his own cost and risk, the drawings including any re-survey / investigations and
correcting layout etc. if required during the execution of the Services.
7.1.2 The Consultant shall be fully responsible for the accuracy of design and drawings of the
bridges and structures. All the designs and drawings for bridges and structures
including all their components shall be fully checked by a Senior Engineer after
completion of the designs. All drawings for bridges and structures shall be duly signed
by the (a) Designer, (b) Senior Checking Engineer, and (c) Senior Bridge / Structure
Expert. The designs and drawings not signed by the three persons mentioned above
shall not be accepted. The Consultant shall indemnify the Client against any inaccuracy
/ deficiency in the designs and drawings of the bridges and structures noticed during the
construction and even thereafter and the Client shall bear no responsibility for the
accuracy of the designs and drawings submitted by the Consultants.
7.1.3 The survey control points established by the Consultant shall be protected by the
Consultants till the completion of the Consultancy Services.
7.2. Retention Money
An amount equivalent to 10% of the contract value shall be retained at the end of the
contract for accuracy of design and quantities submitted and the same will be released
after the completion of civil contract works or after 3 years from completion of
consultancy services, whichever is earlier. The retention money will however be
released by the Client on substitution by Bank Guarantee of the same amount valid up
to the period as above.
7.3. Penalty
7.3.1. Penalty for Error/Variation
i) If variation in any of the main quantities of work like earth work including sub
grade, GSB, WMM, Bituminous works (BM/DBM/AC/BC),drains, total concrete
quantities and reinforcing steel in bridge works or overall project cost, found during
execution is more than +/- 15%, the penalty equivalent to 5% of the contract value
shall be imposed. For this purpose retention money equivalent to 5% of the contract
value will be forfeited. This shall exclude any additional/deletion of items/works
ordered during the execution.
ii) For inaccuracies in survey/investigation/design work the penalties shall be imposed
as per details given in Table below:
The Parties undertake to act in good faith with respect to each other‟s rights under this
Contract and to adopt all reasonable measures to ensure the realization of the objectives
of this Contract.
8.2 Operation of the Contract
The Parties recognize that it is impractical in this Contract to provide for every
contingency which may arise during the life of the Contract, and the Parties hereby agree
that it is their intention that this Contract shall operate fairly as between them, and
without detriment to the interest of either of them, and that, if during the term of this
Contract either Party believes that this Contract is operating unfairly, the Parties will use
their best efforts to agree on such action as may be necessary to remove the cause or
causes of such unfairness, but no failure to agree on any action pursuant to this Clause
shall give rise to a dispute subject to arbitration in accordance with Clause 9 hereof.
9. SETTLEMENT OF DISPUTES
9.1 Amicable Settlement
The Parties shall use their best efforts to settle amicably all disputes arising out of or in
connection with this Contract or the interpretation thereof.
9.2 Dispute Settlement
Any dispute between the Parties as to matters arising pursuant to this Contract which
cannot be settled amicably within thirty (30) days after receipt by one Party of the other
Party‟s request for such amicable settlement may be submitted by either Party for
settlement in accordance with the provisions specified in the SC.
iii) Length of Bypass / realignment shall not be treated as additional to the existing
length of the highway for the purpose of change / variation in length.
Increase/decrease in length on account of bypasses/realignment shall not be
considered as change of scope. However, the total length of the project highway
(including bypasses and realignment) along the finally approved alignment shall be
compared with the indicative length in the RFP for the purpose of variation.
1.1(a) The words “in the Government‟s country” are amended to read “in INDIA”
1.8 Entity to Act as Member in charge (In case of Joint Venture of Consultants) with or
without an Associate:
- ………………………..
1.9 The Authorized Representatives are:
b) The consultant will furnish within 15 days of the issue of letter of acceptance, an
unconditional Bank Guarantee from a Nationalized Bank, IDBI or ICICI/ICICI
Bank/Foreign Bank/EXIM Bank / Any Scheduled Commercial Bank approved by RBI
having a net worth of not less than 500 crore as per latest Annual Report of the Bank. In
the case of a Foreign Bank (issued by a Branch in India) the net worth in respect of Indian
operations shall only be taken into account. In case of Foreign Bank, the BG issued by
Foreign Bank should be counter guaranteed by any Nationalized Bank in India. In case of
JV, the BG shall be furnished on behalf of the JV or lead partner of JV for an amount
equivalent to 10 %of the total contract value to be received by him towards Performance
Security valid for a period of three years beyond the date of completion of services.
2.2 The time period shall be “Twenty Four months” or such other time period as the parties
may agree in writing.
2.3 The time period shall be “fifteen days” or such other time period as the Parties may agree
in writing.
2.4 The time period shall be 24 months or such other time period as the parties may agree in
writing.
(a) Except in case of negligence or willful misconduct on the part of the Consultants or on the
part of any person or firm acting on behalf of the Consultants in carrying out the Services,
the Consultants, with respect to damage caused by the Consultants to the Client‟s
property, shall not be liable to the Client:
(b) This limitation of liability shall not affect the Consultants‟ liability, if any, for damage to
Third Parties caused by the Consultants or any person or firm acting on behalf of the
Consultants in carrying out the Services.
(b) Third Party liability insurance with a minimum coverage, for Rs. 1.00 million for the period of
consultancy.
(c) (i) The Consultant shall provide to CE (P) Beacon Professional Liability Insurance (PLI) for a period
of Five years beyond completion of Consultancy services or as per Applicable Law, whichever is
higher.
(ii) The Consultant will maintain at its expense PLI including coverage for errors and omissions
caused by Consultant‟s negligence in the performance of its duties under this agreement, (A) For
the amount not exceeding total payments for Professional Fees and Reimbursable Expenditures
made or expected to be made to the Consultants hereunder OR (B) the proceeds, the
Consultants may be entitled to receive from any insurance maintained by the Consultants to cover
such a liability, whichever of (A) or (B) is higher.
(iii) The policy should be issued only from an Insurance Company operating in India.
(iv) The policy must clearly indicate the limit of indemnity in terms of “Any One Accident” (AOA)
and “Aggregate limit on the policy” (AOP) and in no case should be for an amount less than stated
in the contract.
(v) If the Consultant enters into an agreement with CE (P) Beacon in a joint venture or „in
association‟, the policy must be procured and provided to CE (P) Beacon by the joint venture/in
association entity and not by the individual partners of the joint venture/ association.
(vi) The contract may include a provision thereby the Consultant does not cancel the policy midterm
without the consent of Employer. The insurance company may provide an undertaking in this
regard.
(d) Employer‟s liability and workers‟ compensation insurance in respect of the Personnel of the
Consultants and of any Sub consultant, in accordance with the relevant provisions of the Applicable
Law, as well as, with respect to such Personnel, any such life, health, accident, travel or other
insurance as may be appropriate; and all insurances and policies should start from the date of
commencement of services and remain effective as per relevant requirements of contract agreement.
3.9 The Consultants shall not use these documents for purposes unrelated to this Contract without the
prior written approval of the Client.
4.6 The person designated as Team Leader cum Senior Highway Engineer in Appendix B shall serve in
that capacity, as specified in Clause 4.6.
6.1 (b) The ceiling amount in local currency is Rs……… Excluding GST)
9.2 Disputes shall be settled by arbitration in accordance with the following provisions:
(a) The parties shall make efforts to agree to the sole Arbitrator of an Engineer Officer to be appointed by
Director General Border Roads; or in his absence the officer officiating as the DGBR and waive
applicability of Sub Section-12 of Arbitration and Concillation Act 1996 and amendment thereto for
purpose by an express agreement in writing. However, if such an attempt does not succeeded within 30
days then Indian Road Congress will be approached to appointment an Engineer Officer as Arbitrator.
(b) Where the Parties agree that the dispute concerns a technical matter, they may agree to
appoint a sole arbitrator or, failing agreement on the identity of such sole arbitrator within thirty
(30) days after receipt by the other Party of the proposal of a name for such an appointment by
the Party who initiated the proceedings, either Party may apply to the President, Indian Roads
Congress, New Delhi, for a list of not fewer than five nominees and, on receipt of such list, the
Parties shall alternately strike names there from, and the last remaining nominee on the list shall
be the sole arbitrator for the matter in dispute. If the last remaining nominee has not been
determined in this manner within sixty (60) days of the date of the list, the president, Indian Roads
Congress, New Delhi, shall appoint, upon the request of either Party and from such list or
otherwise, a sole arbitrator for the matter in dispute.
(b) Where the Parties do not agree that the dispute concerns a technical matter, the Client and the
Consultants shall each appoint one arbitrator, and these two arbitrators shall jointly appoint a third
arbitrator, who shall chair the arbitration panel. If the arbitrators named by the Parties do not
succeed in appointing a third arbitrator within thirty (30) days after the later of the two arbitrators
named by the Parties has been appointed, the third arbitrator shall, at the request of either Party, be
appointed by Secretary, the Indian Council of Arbitration, New Delhi.
(c) If, in a dispute subject to Clause SC 9.2.1 (b), one Party fails to appoint its arbitrator within thirty
(30) days after the other Party has appointed its arbitrator, the Party which has named an arbitrator may
apply to the Secretary, Indian Council of Arbitration, New Delhi, to appoint a sole arbitrator for the matter
in dispute, and the arbitrator appointed pursuant to such application shall be the sole arbitrator for that
dispute.
(a) Arbitration proceedings shall be conducted in accordance with procedure of the Arbitration &
Conciliation Act 1996, of India
(b) The arbitrator shall give reasons for the award in each and every case irrespective of the value
of the claims or counter claims.
(c) The award shall be made within a period of twelve months from date of appointment of
arbitrator i.e. date of receipt of order on appointment by the arbitrator.
(d) The parties may by concerned extend the periods for making award for a further period not
exceeding six months.
(e) If the award is not made within the above specified period or the extended period, the mandate
of the arbitrator shall terminate unless the court has either prior to or on expiry of the period so
specified extended the period.
(f) If agreed by both the parties in writing fast tract procedure as stipulated at article 29 (b) of
Arbitration and Conciliation Act 1996 and amended thereto may also be followed to resolve the
dispute.
(g) No suspension of work on Account of Arbitration: the reference to the Arbitration shall
proceed not withstanding that works shall not then be or alleged to be complete, provided always
that the obligations of the arbitration being conducted during the progress of work. Neither party
shall be entitled to suspend the work to which the dispute relates on account of arbitration.
If for any reason an arbitrator is unable to perform his function, a substitute shall be appointed in
the same manner as the original arbitrator.
The sole arbitrator or the third arbitrator appointed pursuant to paragraphs (a) through (c) of Clause
8.2.1 hereof shall be an internationally recognized legal or technical expert with extensive
experience in relation to the matter in dispute.
9.2.5 Miscellaneous
(a) Proceedings shall, unless otherwise agreed by the Parties, be held at a place as fixed by the
arbitrator at his discretion.
(b) The appropriate Court of Sri Nagar (Jammu & Kashmir) shall alone has jurisdiction to decide any
dispute arising out of or in respect of this contract.
(c) The English language shall be the official language for all purposes; and [Note: English language
may be changed to any other Language, with the agreement of both the Parties.]
(d) The decision of the sole arbitrator or of a majority of the arbitrators (or of the third arbitrator if
there is no such majority) shall be final and binding and shall be enforceable in any court of competent
jurisdiction, and the Parties hereby waive any objections to or claims of immunity in respect of such
enforcement.
(e) The maximum amount payable per Arbitrator in Arbitration clauses shall be as under
(f) In exceptional cases, such as cases involving major legal implications/ wider ramifications/ higher
financial stakes etc., a special fee structure could be fixed in consultation with the Contractor/ Supervision
Consultants and with the specific approval of the CE (P) Beacon before appointment of the Arbitrator,
Appendix A
Terms of reference containing, inter alia, the Description of the Services and Reporting Requirement
Appendix B
Appendix C
The Consultant‟s personnel shall normally work for 8 hours in a day and six days a week. Normally
Sundays shall be closed for working. In addition they shall also be allowed to avail holidays as observed
by the Client‟s office in the relevant state without deduction of remunerations. In case any person is
required to work on Sunday or Holiday due to exigency of work, he/she shall be given compensatory leave
within the next 15 days.
Appendix D
Duties of Client
______________________________________________________________________________
Appendix E
Cost Estimate
Appendix F
Appendix - I
Format for Bank Guarantee for Performance Security (For individual work)
BANK GUARANTEE FOR PERFORMANCE SECURITY
To,
The Chief Engineer
Project Beacon
Rangret, opposite SIDCO
Distt – Badgam (J&K)
Pin - 190007
In consideration of “CE (P) Beacon” (hereinafter referred as the “Client”, which expression shall, unless
repugnant to the context or meaning thereof include its successors, administrators and assigns) having
awarded to M/s.………………………………………………having its office at
……………….. (Hereinafter referred to as the “Consultant” which expression shall repugnant to the
context or meaning thereof, include its successors, administrators, executors and assigns), a contract by
issue of client‟s Contract Agreement no. / Letter of Acceptance No.……………….. dated ………………
and the same having been unequivocally accepted by the Consultant, resulting in a Contract valued at
Rs…………../- (Rupees….………………….) excluding GST for “Engaging Technical Consultant for
preparation of Feasibility Study (FS) and Detailed Project Report (DPR) for construction of Highway
Tunnel including Approach Road across Chattergala Pass, approximately in between Km 114.00 and Km
151.00 on Basoli-Bani-Bhaderwah road through EPC Mode under Project Beacon in J & K State” in
the states of……….under Contract Package No. …. (Hereinafter called the “Contract”), and
the Consultant having agreed to furnish a Bank Guarantee to the Client as “Performance Security as
stipulated by the Client in the said contract for performance of the above Contract amounting to
Rs.……………./- (Rupees…………………………………….).
The Client shall have the fullest liberty without affecting in any way the liability of the Bank under this
Guarantee, from time to time to vary or to extend the time for performance of the contract by the
Consultant. The Client shall have the fullest liberty without affecting this guarantee, to postpone from time
to time the exercise of any powers vested in them or of any right which they might have against the
consultant and to exercise the same at any time in any
manner, and either to enforce or to forbear to enforce any covenants, contained or implied, in the Contract
between the Client and the Consultant any other course or remedy or security available to the Client. The
bank shall not be relieved of its obligations under these presents by any exercise by the Client of its liberty
with reference to the matters aforesaid or any of them or by reason of any other act or forbearance or other
acts of omission or commission on the part of the Client or any other indulgence shown by the Client or by
any other matter or thing whatsoever which under law would but for this provision have the effect of
relieving the Bank.
The Bank also agrees that the Client at its option shall be entitled to enforce this Guarantee against the
Bank as a principal debtor, in the first instance without proceeding against the Consultant and
notwithstanding any security or other guarantee that the Client may have in relation to the Consultant‟s
liabilities.
c) We are liable to pay the guaranteed amount or any part thereof under this Bank Guarantee
only and only if you serve upon us a written claim or demand on or before ……………(date of
expiry of Guarantee).
NOTE:
(i) The bank guarantee(s) contains the name, designation and code number of the
officer(s) signing the guarantee(s).
(ii) The address, telephone no. and other details of the Head Office of the Bank as well as of
issuing branch should be mentioned on the covering letter of issuing Branch.
(iii) The bank guarantee for Rs. 10,000 and above is signed by at least two officials (or as per the
norms prescribed by the RBI in this regard).