DTS Pulikalva
DTS Pulikalva
DTS Pulikalva
(NIT)
***
A) General.
B) Tender Document
C) Preparation of Tenders
D) Submission of Tenders
4. CONDITIONS OF CONTRACT.
TENDER
A) General
B) Time for completion.
C) Quality Control
D) Cost Control
5. TECHNICAL SPECIFICATIONS
6. DRAWINGS
8. FORMATS OF SECURITIES
***
NOTICE INVITING TENDERS (NIT)
10. a) The bidders need to contact the Superintending Engineer (R&B), Nellore for information on e-procurement.
c) While registering on the e-procurement market place, bidders need to scan and upload the required documents
as per the tender requirements on to their profile.
The e-procurement market place provides an online self-service registration facility to such of the
contractors who are already registered with respective participating departments for supply of specified goods
and services. As an incentive for early registration, basic registration by suppliers, that allows them to participate
in the e-procurement process, shall be enabled on the e-procurement market place without levy of any
registration or subscription fee up to 31st March, 2003 or such later date as may be decided by the steering
committee. However, the e-procurement market place may levy charges for such value added services as may be
decided by the steering on the e-procurement as laid down in the G.O.Ms.No: 2, Information Technology and
Communication Department, Dated: 15-01-2003.
11. The transaction fee shall be paid through electronic gateway of ICICI/HDFC Banks with e-Procurement platform as
per the Government orders vide G.O.Ms.No: 13, Dated: 05-07-2006. The Department will not take any
responsibility for any delay or non-receipt.
12. a) As per the G.O.Ms.No. 174, Irrigation & CAD (PW-Reforms) Department, Dated: 01-09-2008, Submission of original
Hard Copies of the uploaded scan copies of DD/BG towards EMD by participating bidders to the tender Inviting
authority before opening of the price bid be dispensed forthwith. All the bidders shall invariably upload the
scanned copies of DD/BG in e- Procurement system and this will be the primary requirement to consider the bid
as responsive. The Department shall carry out the technical bid evaluation solely based on the uploaded
certificates/documents, DD/BG towards EMD in the e-procurement system and open the price bids of the
responsive bidders. The Department will notify the successful bidder for submission of original hard copies of all
uploaded documents, DD/BG towards EMD prior to entering into agreement.
b) The successful bidder shall invariably furnish the original DD/BG towards EMD, certificates/documents of the
uploaded scanned copies to the Tender Inviting Authority before entering into agreement either personally or
through courier or post and the receipt of the same with in the stipulated date shall be the responsibility of the
successful bidder. The Department will not take any responsibility for any delay in receipt/non-receipt of original
DD/BG towards EMD, certificates/documents, from the successful bidder before the stipulated time. On receipt of
documents, the Department shall ensure the genuinity of the DD/BG towards EMD and all other certificates /
documents uploaded by the bidder in e-Procurement system in support of the qualification criteria before
concluding the agreement.
c) If any successful bidder fails to submit the original Hard Copies of uploaded certificates/Documents, DD/BG
towards EMD with in the stipulated time or if any variation is noticed between the uploaded documents and the
hard copies submitted by the bidder, the successful bidder will be suspended from participating in the tenders on
e-Procurement platform for a period of 3 years. The e-Procurement system would deactivate the user ID of such
defaulting successful bidder based on the trigger/recommendation by the Tender Inviting Authority in the system.
Besides this, the Department shall invoke all processes of law including criminal prosecution of such defaulting
bidder as an act of extreme deterrence to avoid delays in the tender process for execution of the development
schemes taken up by the Government. The information to this extent may be displayed in the e-procurement
platform website.
13. The tenderers shall furnish a declaration in online stating that the soft copies uploaded by them are genuine. Any
incorrectness/deviation noticed will be viewed seriously and apart from cancelling the work duly forfeiting the
EMD, criminal action will be initiated including suspension of business.
i) Satisfactorily completed as Prime contractor similar single work of cost not less than Rs.72,26,628/- any
one financial year during the last five financial years i.e., from 2010-2011 to 2014-2015 updated 2015-
16
ii) Liquid assets and / or credit facilities of not less than Rs.36,13,400/-
iv) Bid capacity computed by the formula (2 AN –B) shall be greater than the ECV.
v) Should possess the Key / critical equipment (either owned or leased or to be procured against
mobilization advance)
15 The tenders will be opened by the Superintending Engineer (R&B), NELLORE or his nominee at his office in the
presence of tenderers / or their authorized representatives, on the date mentioned above.
16 The price-bids of such tenderers, who are determined to have complied with the eligibility criteria, will only be
opened.
17 If the office happens to be closed on the dates specified above, the respective activity will be performed at the
designated time on the next working day without any notification.
18 The Bidder shall authenticate the bid with his digital certificate for submitting the bid electronically on e-procurement
Platform and the bids not authenticated by Digital certificate of the bidder will not be accepted on the e-
procurement platform.
19 Any other details can be had from the Office of the Superintending Engineer(R&B), NELLORE.
20. Additional condition for execution of BT items shall be as per circular Memo No.
Circulars/DCE(N)/DEE.1/2010,Dt:18.9.2010 of the Chief Engineer (R&B) NABARD which is annexed in the Tender
Document.
21. Gradation of WMM shall be as per Circular Memo No.1814/DCE(N)/DEE.1/ AEE.2/2009, Dt:29.1.2009 of the Chief
Engineer(R&B)NABARD which is annexed in the Tender Document.
A – GENERAL
g) Reimbursable Provisions.
h) Avagahana Sadassu: Rs. 10,000
The Engineer-in-Chief (R&B), Rural Roads, Hyderabad invites tenders for the above work vide
NIT No. ENC(R&B)Rural Roads/57 / NABARD/ 2014-15,
Dated: 23-03-2015
1.1
The tenders will be opened by the Superintending Engineer (R&B), NELLORE or his nominee at his office
in the presence of tenderers or their authorised representatives, on the dates mentioned in NIT. If the Office
happens to be closed on the dates, the opening of tenders gets automatically postponed to the next working
date, the time being unaltered, unless extended on online through corrigendum.
Tenderer Superintending Engineer 6
(R&B) Circle, NELLORE
1.2 The successful tenderer is expected to complete the work within the time period specified in the NIT.
2. Firms Eligible to Tender:
2.1 The Firms who
i) Possess the valid registration in the class and category mentioned in the NIT and satisfy all the
conditions therein.
ii) Are not blacklisted or debarred or suspended by the Government for whatever the reason,
prohibiting them not to continue in the contracting business.
iii) Have complied with the eligibility criteria specified in the NIT are the eligible tenderers.
2.2 Firms Ineligible to Tender:
i) A retired officer of the Govt. of AP or Govt. of India executing works is disqualified from tendering for a
period of two years from the date of retirement without the prior permission of the Government.
ii) The Tenderer who has employed any retired officer as mentioned above shall be considered as an
ineligible tenderer.
iii) The contractor himself or any of his employees is found to be Gazetted Officer who retired from
Government Service and had not obtained permission from the Government for accepting the contractor’s
employment within a period of 2 years from the date of his retirement.
iv) The Contractor or any of his employees is found at any time after award of contract, to be such a person
who had not obtained the permission of the Government as aforesaid before submission of the tender or
engagement in the Contractor’s service.
v) Contractor shall not be eligible to tender for works in the division / circle where any of his near relatives
are employed in the rank of Assistant Engineer or Assistant Executive Engineers and above on the Engineering
side and Divisional Accounts Officer and above on the administrative side. The Contractor shall intimate the
names of persons who are working with him in any capacity or are subsequently employed. He shall also
furnish a list of Gazetted /Non-Gazetted, State Government Employees related to him. Failure to furnish such
information tenderer is liable to be removed from the list of approved contractors and his contract is liable
for cancellation.
Note: Near relatives include
1. Sons, step sons, daughters, and step daughters.
2. Son-in-law and daughter-in-law.
3. Brother-in-law and sister-in-law.
4. Brothers and Sisters.
5. Father and Mother.
6. Wife / Husband.
7. Father-in-law and Mother-in-law
8. Nephews, nieces, uncle and aunts
9. Cousins and
10. Any person residing with or dependent on the contractor.
3. Qualification data of the Tenderers
3.1 The tenderer shall furnish the following particulars in the formats enclosed, supported by documentary evidence
as specified in the formats.
a) Check slip to accompany the tender (in Annexure-I).
Attested copies of documents relating to the Registration of the firm, Registration as Civil Contractor,
Partnership deed, Articles of Association, Registration copy under AP VAT Act 2005 i.e., Taxpayer
Identification Number along with VAT clearance certificate in the prescribed proforma , Copy of
Permanent Account Number (PAN) Card and copy of Latest Income tax returns submitted along with
proof .
Note: The Partnership firms, which are registered as Contractors shall intimate the change in
partnership deed, if any, as per GO Ms No.58, I & CAD, Dated: 23-04-2002 within one month of
such change. Failure to notify the change to the registration authority in time will entail the
firms to forfeit their registration and their tender will be rejected. The intimation of change of
partners if any and the acceptance by the Registration authority may be enclosed.
b) Value of all Civil Engineering works executed every year during the last five financial years (i.e.,
from 2010-2011 to 2014-2015)in Statement-I updated to 2012-13
b) Executed in any one year, the following minimum physical quantities during the last five
financial years from 2010-2011 to 2014-2015)
a)V.C.C/VRCC/RCC/ in cum (Combined quantity) : 456 cum
b)For foundations & Sub-structure.
c) VCC/VRCC/RCC/PSC in cum (Combined quantity) : 152 Cum.
For superstructure.
d) WMM/CRMB/CRM :236 Cum
e) GSB/Granular schoulders/ :297 Cum
f) Forming Embankment/shoulders/Earth work : 2474 Cum
B) Each bidder should further demonstrate :
a) Availability {either owned with proof or leased with lease deed and proof or to be procured
against mobilization advance( the cost of equipment to be procured should be matched with
the Mobilization Advance to be given towards Machinery only and the details from whom to be
purchased along with amounts) of the following Key and Critical equipment for this work.}
b)
S. No. Equipment Type and Characteristics Minimum required
The tenderer has to submit either a certificate issued by the Executive Engineer or a
Declaration on non judicial stamp paper worth Rs 100/- as prescribed in Statement-V along
with sufficient proof of document in support of owning such as invoice / Certificate of
registration by competent authority in support of the critical equipment.
Note: The major equipment to attain the completion of works in accordance with the
prescribed construction schedule is to be shown in the above table.
d) Liquid assets and / or credit facilities of not less than Rs.3613400/- (Credit facility / letter of
credits / Solvency certificates from Nationalised Banks or any scheduled commercial bank etc).
The solvency certificate should not be earlier than 04-04-2014.
e) The tenderer shall submit the copies of documents of
i) Registration as Civil Contractor required as per NIT
ii) Registration copy under AP VAT Act 2005 i.e., Taxpayer Identification Number along with VAT
clearance certificate in the prescribed proforma
iii) PAN Card and copy of latest I.T returns submitted along with proof
iv) Necessary D.D / B.G towards E.M.D.
v) Transaction fee at 0.03% of ECV+14.00% Service tax (which includes special and Higher
education cess of 1% on service tax)on 0.03% of ECV through the electronic payment
Gateway.
f) Quality Control laboratory:
For all works costing more than Rs. 200.00 lakhs, the tenderer shall submit quality plan and also
show proof of owning quality laboratory. The following equipment is required:
Bid capacity.
The tenderer who meets the above qualification criteria and whose available bid capacity is
more than the estimated contract value will be qualified for opening of Price bid. The available
bid capacity will be calculated as under:
Where,
A= Maximum value of civil engineering works executed in its name in any one financial
year during the last five financial years (updated to current Price level) taking into account the
works completed as well as works in progress.
N= Number of years prescribed for completion of the work for which Tenders are invited
[months / 12] (12 Months)
B= Updated value (at current Price level), of all existing Commitments i.e., ongoing works,
works likely to be awarded to be executed during the next 12 Months (Period of completion for
which Tenders are invited).
Annual turn-over, cost of completed works and balance works on hand etc., shall be updated
by giving weightage of 10% per year to bring them to current price level.
Note:
Furnished false / fabricated particulars in the forms, statements and /annexures submitted in
proof of the qualification requirements and/or
Not turned up for entering into agreement, when called upon.
record of poor progress such as abandoning the work, not properly completing the contract,
inordinate delays in completion, litigation history or financial failures etc. and/or
participated in the previous bidding for the same work and had quoted unreasonably high
tender percentage and
even while execution of the work, if found that the work was awarded to the Contractor based
on false / fake certificates of experience, the Contractor will be blacklisted and work will be
taken over invoking clause 61 of PS to APSS.
3.4 As per G.O.Ms.No. 230, Dated: 13-08-2007, tenders with an excess of above 5% of the estimated
contract value shall be summarily rejected.
The bidder shall mandatorily pay the transaction fee to M/S C1 India through the electronic
payment Gateway. Service tax as levied by the GOI on transaction fee, electronic payment gateway
charges are to be borne by the bidders.
The Successful bidder will pay further fee @ 0.04% of ECV (Estimated contract value) payable to
Managing Director, APTS to create an e-procurement fund to be administered by APTS. (The ceiling
amount of Transaction fee for works costing ECV upto Rs 50.00 Crores is Rs 10,000.00 and for works
costing with ECV above Rs 50.00 Crores, the ceiling amount of transaction fee is Rs 25,000.00).
The above fee is payable by the successful bidder through a D.D. drawn in favour of Managing
Director, APTS, Hyderabad at the time of conclusion of the agreement. The said DD shall be sent to
Managing Director, APTS by the Superintending Engineer who is entering in to agreement with the
successful bidder.
The bank guarantee submitted by the successful bidder at the time of tender with conditional
obligations shall not be accepted and retained against EMD for performance at the time of conclusion
of contract.
Unconditional and irrevocable bank guarantee shall be paid towards EMD for the entire
specified amount at the time of concluding the agreement.
14.2 Demand Drafts / Bank Guarantees furnished towards EMD for issue of tender schedules shall be valid
for a period of six months from the date of tender notice.
14.3 The EMD of Tenderers will be returned no sooner the tenders are finalised or end date of the Tender
validity period whichever is earlier.
14.4 The 1% E.M.D. paid by the successful Tenderer at the time of submission of hard copies of Tender
documents through Demand Draft will be discharged if the Tenderer furnishes Bank Guarantee for the
full EMD of 2½% at the time of concluding agreement.
14.5 The earnest money deposited by the successful tenderer will not carry any interest and it will be dealt
with as provided in the conditions stipulated in the tender. The E.M.D. given in the form of Bank
Guarantee on a Nationalised / Scheduled commercial Bank shall be valid for the duration of contract
period plus defect liability period of two years and in case any valid extension of contract period is
granted, the validity of BG shall also be extended for the corresponding period. The Bank Guarantee on
Nationalised / Scheduled commercial Bank furnished by the tenderer towards additional security
amount shall be valid till the work is completed in all respects.
14.6 The E.M.D. shall be forfeited.
(a) if the Tenderer withdraws the Tender during the validity period of Tender.
(b) in the case of a successful Tenderer, if he fails to sign the Agreement for whatever the reason.
14.7 In consideration of the Executive Engineer / Superintending Engineer /Chief Engineer
/Commissionerate of Tenders undertaking to investigate and to take into account each tender and in
consideration of the work thereby involved, all earnest monies deposited by the tenderer will be
forfeited to the Government in the event of such tenderer either modifying or with-drawing his tender
at his instance within the said validity period of three months.
15. Signing of Tenders.
15.1 If the tender is made by an individual, it shall be signed with his full name and his address shall be
given. If it is made by a firm, it shall be signed with the co-partnership name by a member of the firm,
who shall also sign his own name, and the name and address of each member of the firm shall be given,
if the tender is made by a corporation it shall be signed by a duly authorised officer who shall produce
Tenderer Superintending Engineer 15
(R&B) Circle, NELLORE
with his tender satisfactory evidence of his authorisation. Such tendering corporation may be required
before the contract is executed, to furnish evidence of its corporate existence. Tenders signed on
behalf of G.P.A. holder will be rejected.
15.2 The Tender shall contain no alterations or additions, except those to comply with instructions issued by
the Tender Inviting Officer, or as necessary to correct errors made by the Tenderer, in which case all
such corrections shall be initialed by the person signing the Tender.
15.3 No alteration which is made by the tenderer in the contract form, the conditions of the contract, the
drawings, specifications or statements / formats or quantities accompanying the same will be
recognised; and, if any such alterations are made the tender will be void.
DECLARATION
I / WE ………………………………………………………………. have gone through carefully all the Tender conditions and solemnly
declare that I / we will abide by any penal action such as disqualification or black listing or determination of contract or
any other action deemed fit, taken by, the Department against us, if it is found that the statements, documents,
certificates produced by us are false / fabricated.
Details of value of Civil Engineering works executed in each year during the last five financial years by the
Tenderer.
a) Attach certificate(s) issued by the Executive Engineer concerned and counter signed by Superintending Engineer
showing work wise / year wise value of work done in respect of all the works executed by the Tenderer during last
five years (OR)
b) Certificate from Chartered Accountant supported with Annual Balance Sheet tallying with I.T. Clearance
certificate.
STATEMENT–II
Details of similar works completed in the Name of the Tenderer during the last five financial years.
1 2 3 4 5
Stipulated Actual date Value of work done year wise during the Total value
period of of last ‘five’ years. of work
completion completion done.
6 7 9 10 11 12 13 14
1 2 3 4 5 6 7 8
1 2010-11
2 2011-12
3 2012-13
4 2013-14
5 2014-15
Attach certificates in support of the above quantities issued by the Executive Engineer concerned and
countersigned by the Superintending Engineer duly showing the quantities executed year wise.
STATEMENT–IV
Details of works on hand and, yet to be completed as on the date of submission of the Tender and works for
which Tenders have been submitted are to be furnished.
Sl.No Name of Address of Agt. Value of Stipulated Value of Balance Anticipated Updated
work Agreement No. contract period of work Value of date of value of
Concluding & Date completion done so works to be completion balance
authority far. completed work
1 2 3 4 5 6 7 8 9 10
Attach certificates issued by the Executive Engineer concerned and countersigned by Superintending
Engineer, indicating the balance work to be done, and likely period of completion.
Signature of the Tenderer
B) Details of works for which Tenders are submitted [awarded / likely to be awarded]
1 2 3 4 5 6 7
The tenderer should furnish the information required below, regarding the availability of the equipment, required
for construction / quality control.
1 2 3 4 5 6
For all works costing more than Rs.2.00 Crores the Contractor shall submit quality plan and also show proof of
owning quality lab.
The tenderer has to submit either a certificate issued by the Executive Engineer or a Declaration on non judicial
stamp paper worth Rs 100/- as given below along with sufficient proof of document in support of owning such
as invoice / Certificate of registration by competent authority in support of the critical equipment.
DECLARATION
“I ……………………………………. do hereby solemnly affirm and declare that I /we own the following
equipment for using on the subject work and also declare that I / We will abide by any action such as
disqualification or determination of Contract or blacklisting or any action deemed fit, if the department
detects at any stage that I/we do not possess the equipment listed below.
Details of Any Is it in
S. Year of Regn.
each Capacity other working
No. purchase Number
Equipment data condition
1 2 3 4 5 6 7
STATEMENT–VI
Qualification and experience of Key Personnel proposed to be deployed for execution of the Contract.
1 2 3 4 5 6
STATEMENT - VII
1 2 3 4 5 6
To
(R&B) Circle,
NELLORE.
Sir,
I / We do hereby tender and if this tender be accepted, under take to execute the following work viz.,
“Construction of HLB across Puli Kalava at Km 12/10 of Kota-Chittamur Road in
SPSR Nellore District” as shown in the drawings and described in the specifications deposited in the office of
the Superintending Engineer, (R&B) Circle, NELLORE with such variations by way of alterations or additions to, and
omissions from the said works and method of payment as provided for in the “conditions of the contract” for the
sum of Rupees 1,44,53,256/- or such other sum as may be arrived under the clause of the standard preliminary
specifications relating to “Payment on lump-sum basis or by final measurement at unit rates”
I/WE have also quoted percentage excess or less on E.C.V., in Schedule ‘A’ Part-I, annexed (in words and
figures) for which I/We agree to execute the work when the lumpsum payment under the terms of the agreement
is varied by payment on measurement quantities.
I/WE have quoted Percentage excess or less on E.C.V., in Schedule ‘A’ Part – I both in words & figures. In
case of any discrepancy between the Percentage excess or less on E.C.V., in words and figures, the rates quoted
words only shall prevail.
I/WE agreed to keep the offer in this tender valid a period of Three month(s) mentioned in the tender
notice and not to modify the whole or any part of it for any reason within above period. If the tender is
withdrawn by me/us for any reasons whatsoever, the earnest money paid by me/us will be forfeited to
Government
I/WE hereby distinctly and expressly, declare and acknowledge that, before the submission of my/our
tender I/We have carefully followed the instructions in the tender notice and have read the A.P.S.S. and the
preliminary specifications therein and the A.P.S.S. addenda volume and that I/We have made such examination of
the contract documents and the plans, specifications and quantities and of the location where the said work is to
be done, and such investigation of the work required to be done, and in regard to the material required to be
furnished as to enable me/us to thoroughly understand the intention of same and the requirements, covenants,
agreements, stipulations and restrictions contained in the contract, and in the said plans and specifications and
distinctly agree that I/We will not hereafter make any claim or demand upon the Government based upon or
arising out of any alleged misunderstanding or misconception /or mistake on my/or our part of the said
requirement, covenants, agreements, stipulations, restrictions and conditions.
I/WE enclosed to my/our application for tender schedule a crossed demand draft
(No…………………………………………………………………………..dated:…………………..) for Rs………………………………………………..as
earnest money not to bear interest.
I/WE will employ the following technical staff for supervising the work and will see that one of them is
always at site during working hours, personally checking all items of works and paint extra attention to such works
as required special attention (eg) Reinforced concrete work.
I / WE declare that I/WE agree to recover the salaries of the technical staff actually engaged on the work
by the department, from the work bills, if I/We fail to employ technical staff as per the tender condition.
1) I/WE have not been black listed in any department in Andhra Pradesh due to any reasons.
2) I/WE have not been demoted to the next lower category for not filing the tenders after buying the tender
schedules in a whole year and my/our registration has not been cancelled for a similar default in two consecutive
years.
3) I/WE agree to disqualify me/us for any wrong declaration in respect of the above and to summarily reject my/our
tender.
Address of the Tenderer :
A. GENERAL
1. Interpretation:
1.1 In interpreting these Conditions of Contract, singular also means plural, male also means female, and vice-versa.
Headings have no significance. Works have their normal meaning under the language of the contract unless
specifically defined. The Engineers-in-charge will provide instructions clarifying queries about the conditions of
Contract.
1.2 The documents forming the Contract shall be interpreted in the following order of priority:
1) Agreement
2) Letter of Acceptance, notice to proceed with the works
3) Contractor’s Tender (Technical bid)
4) Conditions of contract
5) Specifications
6) Drawings
7) Bill of quantities (Price-bid)
8) Any other document listed as forming part of the Contract.
2. Engineer-in-Charge’s Decisions:
2.1 Except where otherwise specifically stated, the Engineer-in-charge will decide the contractual matters between
the Department and the Contractor in the role representing the Department.
3. Delegation:
3.1 The Engineer-in-charge may delegate any of his duties and responsibilities to other officers and may cancel any
delegation by an official order issued.
4. Communications:
4.1 Communications between parties, which are referred to in the conditions, are effective only when in writing. A
notice shall be effective only when it is delivered (in terms of Indian Contract Act)
5. Sub-contracting:
5.1 If the prime contractor desires to sub-let a part of the work, he should submit the same at the time of
filing tenders itself or during execution, giving the name of the proposed Sub-contractor, along with
details of his qualification and experience. The Tender Accepting Authority should verify the
experience of the Sub-contractor and if the Sub-contractor satisfies the qualification criteria in
proportion to the value of work proposed to be sub-let, he may permit the same. The total value of
works to be awarded on sub-letting shall not exceed 50% of contract value. The extent of subletting
shall be added to the experience of the sub-contractor and to that extent deducted from that of the
main contractor.
6. Other Contractors:
8.1 The Contractor shall cooperate and share the Site with other contractors, Public authorities, utilities, and the
Department. The Contractor shall also provide facilities and services for them as directed by the Engineer-in-
charge.
7. Personnel:
7.1 The Contractor shall employ the required Key Personnel named in the Schedule of Key Personnel to carry out the
functions stated in the Schedule or other personnel approved by the Engineer-in-charge. The Engineer-in-charge
will approve any proposed replacement of Key Personnel only if their qualifications, abilities, and relevant
experience are substantially equal to or better than those of the personnel listed in the Schedule.
7.2 Failure to employ the required technical personnel by the contractor action will be taken as mentioned in para 7.6
7.3 The technical personnel should be on full time and available at site whenever required by Engineer in Charge to
take instructions.
7.4 The names of the technical personnel to be employed by the contractor should be furnished in the statement
enclosed separately.
7.5 In case the contractor is already having more than one work on hand and has undertaken more than one work at
the same time, he should employ separate technical personnel on each work.
7.6 If the contractor fails to employ technical personnel the work will be suspended or department will engage a
technical personnel and recover the cost thereof from the contractor.
The arbitration shall be conducted in accordance with the provisions of Indian Arbitration and Conciliation Act
1996 or any statutory modification thereof.
The arbitrator shall state his reasons in passing the award.
Claims above Rs.50,000/-.
All claims of above Rs.50,000/- are to be settled by a Civil Court of competent jurisdiction by way of Civil suit and
not by arbitration.
A reference for adjudication under this clauses shall be made by the contractor within six months from the date of
intimating the contractor of the preparation of final bill or his having accepted payment which ever is earlier.
Whenever authorized alterations or additions made during the progress of the work are of such
a nature in the opinion of the Executive Engineer as to justify an extension of time in consequence
thereof, such extension will be granted in writing by the Engineer-in-Chief, (R&B) (RURAL ROADS) or
other competent authority when ordering such alterations or additions.
For all works costing more than Rs.2.00 Crores the Contractor shall submit quality plan and also show
proof of owning quality lab.
36.2 Recoveries to be effected from the contractors for deficient execution of work as per Circular Memo No:
12582/Vig-I/1/2005-1, Dated: 23-03-2006 communicated by the Engineer-in-Chief (R&B) Admn & Roads, vide
Memo No: 3027/QC/AEE5/DEE2/MC/2006, Dated: 28-10-2006.
The following guidelines shall be followed in regard to maintenance of quality, quantity and penalties to
be imposed for deficient execution of work on the contractors vis-à-vis the disciplinary action to be taken against
the concerned engineers.
I. FORMATION
a. Density: The density of the materials shall conform to MORTH table 300-1. The earth work shall be compacted
to the required density i.e., 95% for OMC. The determination of density shall be as per IS 2720 (Part 28).
Acceptance Criteria: The density test location shall be chosen only through random techniques as closer as
required to yield the minimum number of test results for evaluating a day’s work. At least one measurement of
density for every 1000 square meters of compacted area shall be taken. The number of tests in onset of
measurements shall be 6 (if ND tests are conducted it shall be double). If considerable variations are observed
between individual density results minimum number of tests in one set shall be increased to 10. Control shall not
be based on any one test but on the mean value of set 5-10 density determination. The mean density shall not be
less than the specified density plus [1.65-(1.65/(no. of samples) 0.5)] times the standard deviation.
b. RECOVERY FROM CONTRACTOR: If any deviation is beyond the above limit, the work shall be rejected.
Tenderer Superintending Engineer 38
(R&B) Circle, NELLORE
II. GSB / WMM / WBM
a. Thickness: The averages thickness shall be based on 5 points in a C/s for two lane and 3 points for
single lane and proportionately increased for additional lanes. (At least two cross sections in 1 Km length or
less). The average thickness shall not be less than specified thickness.
b. Over size of metal : Whenever graded metal is used.
i) No over size will be allowed over and above the range specified as per in the first sieve (top sieve).
ii) Over size in sieves other than top sieve – the difference in the rates of the metal of the specified size
and next higher size in the specified grade should be recovered for that quantity of over size metal.
iii) However if the over size in any sieve other than top sieve is found to be above 30%, metal collected
should be rejected.
c. Weight: The physical requirements shall conform to MORTH table 400-6/400-10. The density of the
compacted layer shall be at least 98% of the maximum dry density as determined for the material as per IS
2720 (Part 8). The weight of material (for WBM) shall not be less than the quantity specified in the data as per
density of metal to be recorded prior to usage. However 10% tolerance may be permitted due to crushing of
edges and corners, deviations in the measurement pit (0.5 x 0.50 m).
RECOVERIES:
1. Shortfall in thickness / quantity / weight
a) If shortfall is up to 10% in any one of the above parameter i.e., a+b+c = 10% specified oversize,
thickness / weight – in a KM Recovery @ twice the agreement rates to be effected for the deficiency.
b) If shortfall is between 10% and 20% in any one of the above parameter i.e., a+b+c = 10% to 20% specified
oversize, thickness / weight – in KM Recovery to be effected @ thrice the agreement rates for the
deficiency.
c) If shortfall is more than 20% of specified thickness / quantity / weight – the work is to be rejected and
redone.
d) In case both deficiency i.e., thickness & weight of metal is noticed, the recovery shall
be for the maximum of the two deficiencies.
III. SDBC /MSS/ BM / DBM Bituminous items :
a) Thickness : The average thickness shall be the arithmetic mean of the difference of levels
before and after construction at all grid points in that area i.e., at every 10 m c.c. longitudinally and 0.75
m and 2.75m on two lanes, 1.25 m on single lane transversely. The recovery for less thickness shall be as
under.
b) Binder quantity: The binder content shall have to be tested at the plant or mix at the time
of laying. Research carried out in the country revealed that with manage of time there would be loss of
bitumen in layer which may occur from day one. Further the testing procedure / sampling itself varies
from laboratory to laboratory, person to person and the results are subject to efficiency of the personnel
as well as equipment.
The MORTH specification gives a tolerance of + 0.30% which in fact is for the plant mix and
cannot be straight away applied for tests conducted on the surface after lapse of time. The bitumen
extraction tests shall have to be conducted as early as possible and in no care beyond 6 months.
Considering all these aspects the variations in Binder content and recoveries to be effected are:
1) 0-10% recovery to be effected @ twice the agreement.
2) 10-15% recovers to be effected @ thrice the agreement.
3) More than 15% the layer shall be rejected and re-laid.
RECOVERIES :
1. Shortfall in thickness / quantity / weight.
a) If shortfall is up to 10% in the specified thickness / quantity / weight – Recovery @ twice the
agreement rates to be effected for the deficiency in quantity.
b) If shortfall is between 10% and 20% in the specified thickness / quantity / weight – Recovery to be
effected @ thrice the agreement rates for the deficiency in quantity.
c) If shortfall is more than 20% of specified thickness / quantity / weight – the work is to be rejected
and redone.
IV. CONCRETE ITEMS:
The testing and tolerance shall be as per MORTH section 903.5. No deviations are acceptable in thickness of
PCC / all members except concrete pavements. In case of strength requirement in which established based on
concrete cores / cubes no deviation is remitted from specified strength. However if the lesser strength concrete is
allowed duly satisfying design criteria the rate of lower grade concrete or equipment to the actual strength only
shall be paid.
PAYMENT ADJUSTMENT FOR DEFICIENCY IN THICKNESS
Deficiency in the average thickness
of day’s work Percent contract unit price
Tenderer Superintending Engineer 39
(R&B) Circle, NELLORE
payable
Up to 5 mm 100
6 – 10 mm 87
11 – 15 mm 81
16 – 20 mm 75
21 – 25 mm 60
GENERAL:
1. The edges of the carriageway shall be correct within a tolerance of +/- 10mm.
2. The negative tolerance of top layer shall not be permitted in conjunction with positive tolerance of bottom
layer.
3. The QC shall inspect the work at every stage of execution particularly before laying bituminous layers &
during execution of BT layer on their own. QC is meant for quality assurance, any check after completion does
not serve the quality assurance.
The contractor shall test all the materials as per agreement specifications and results shall be
recorded duly signed by the contractor or his representative and the section officer. The name of work
and quarry location shall be clearly noted in the test reports.
36.3 The amended gradation limits with regards to Wet Mix Macadam is as under:
Ammended Table 400-11(A) Grading requirement of aggregates for Wet Mix Macadam
53.00 mm 100
45.00 mm 75-90
26.5 mm -
22.4 mm 45-70
11.2 mm 25-45
4.75 mm 20-25
2.36 mm 10-20
75 microns 0-4
No job mix where in upper limit of a particular screening and lower limit of immediately
subsequent screening as boundaries of mix is acceptable.
38.2.1 The rates shall be derived by adding to or subtracting from the agreement rate of such similar item the
cost of the difference in the quantity of materials labour between the new items and similar items in
the agreement worked out with reference to the Standard Schedule of Rates adopted in the sanctioned
estimate with which the tenders are accepted plus or minus over all tender percentage.
38.2.2 (a) Similar items but the rates of which cannot be directly deduced from the original agreement.
(b) Purely new items which do not correspond to any item in the agreement.
38.2.3 The rates of all such items shall be Estimated Rates plus or minus overall Tender premium.
39. Extra Items:
39.1 Extra items of work shall not vitiate the contract. The contractor shall be bound to execute extra items of work as
directed by the Engineer-in-Charge. The rates for extra items shall be worked out by the Executive Engineer as
per the conditions of the Contract and the same are binding on the Contractor.
39.2 The contractor shall before the 15 th day of each month, submit in writing to the Executive Engineer a statement of
extra items if any that they have executed during the preceding month failing which the contractor shall not be
entitled to claim any.
39.3 Entrustment of additional items:
39.3.1 Where ever additional items not contingent on the main work and outside the scope of original
agreement are to be entrusted to the original contractor dispensing with bids and if the value of such
items exceeds the limits upto which the officer is empowered to entrust works initially to contractor
without calling for tenders, approval of next higher authority shall be obtained. Entrustment of such
items on nomination shall be at rates not exceeding the estimated rates.
39.3.2 Entrustment of the additional items contingent on the main work will be authorised by the officers upto
the monetary limits upto which they themselves are competent to accept items in the original
agreement so long as the total amounts upto which they are competent to accept in an original
agreement rates for such items shall be worked out in accordance with the procedure (I) For all items
of work in excess of the quantities shown in the Bill of Quantities of the Tenders, the rate payable for
such items shall be estimate rates for the items (+) or (-) over all tender percentage accepted by the
competent authority.
39.3.3 Entrustment of either the additional or supplemental items shall be subject to the provisions of the
agreement entered into by a Competent Authority after the tender is accepted. The Chief Engineer
being the authority next higher to the Superintending Engineer, who entered into the agreement
approves the rate for the items / variation in quantity in the current agreement. The items shall not be
ordered by an officer on his own responsibility if the revised estimate or deviation statement providing
for the same requires the sanction of higher authority.
Note: It may be noted that the term Estimate Rate used above means the rate in the sanctioned estimate
with which the tenders are accepted, or if no such rates is available in the estimate, the rate derived
will be with reference to the Standard Schedule of Rates adopted in the sanctioned estimate with
which tenders are accepted.
a) Any section of the Permanent works in respect of which a separate time for completion is provided in the
Contract, and
b) Any substantial part of the Permanent Works which has been both completed to the satisfaction of the
Engineer-in-Charge and occupied or used by the Department.
44.1.3 If any part of the Permanent Works shall have been completed and shall have satisfactorily passed any final test
that may be prescribed by the Contract, the Engineer-in-Charge may issue such certificate, and the Contractor
shall be deemed to have undertaken to complete any outstanding work in that part of the Works during the
period of Maintenance.
45. Taxes included in the bid:
45.1.1 The percentage quoted by the contractor is exclusive of Value Added Tax (VAT) but inclusive of other taxes on all
materials that the contractor will have to purchase for performance of this contract.
46. Price Adjustment as per G.O.Ms.No: 35, T, R&B (R-I) Department, Dated: 28-02-2006, G.O.Ms.No: 73,
T, R&B (R-I) Department, Dated: 24-04-2006, G.O.Rt.No: 175, T, R&B (R-I) Department, Dated: 19-02-
2007, G.O.Ms.No: 94, T, R&B (R.I) Department, Dated: 16-04-2008, G.O.Ms.No: 252, T,R&B (R.I)
Department, Dated: 28-08-2008 and G.O NO.1 Finance(Works&Projects-F7)Dept.dt:25-02-2012.
This Price Adjustment clause shall apply for Steel, Cement, Bitumen and P.O.L, subject to the
following conditions.
46.1 The Price Adjustment shall be both for increase and decrease in the prices for the works completed
within the original agreement period.
Price adjustment for increase or decrease in the cost of cement procured by the contractor shall be
paid in accordance with the following formula.
Vc= Increase or decrease in the cost of work done during the period under consideration due to
changes in the rates for cement.
Co= The all India average Whole sale Price Index for cement on the day 28 days prior to the closing
date of submission of Bids as published by the Ministry of Industrial Development , Government
of India, New Delhi.
Ci= The all India average Whole sale Price Index for cement on the day 28 days prior to the last date
of the measurement recorded to which a particular bill payment is related, as published by the
Ministry of Industrial Development , Government of India, New Delhi.
Pc = Percentage of cement component of the work (To be worked out for each work and
provided for in the bid document)
Price adjustment for increase or decrease in the cost of steel procured by the Contractor shall be paid
in accordance with the following formula
Vs= Increase or decrease in the cost of work done during the period under consideration due to
changes in the rates of steel.
So= The all India average Whole sale Price Index for Steel on the day 28 days prior to the closing date
of submission of Bids as published by the Ministry of Industrial Development , Government of
India, New Delhi
Si= The all India average Whole sale Price Index for Steel on the day 28 days prior to the last date of
the measurement recorded to which a particular bill payment is related, as published by the
Ministry of Industrial Development , Government of India, New Delhi.
Ps= Percentage of steel component of the work (To be worked out for each work and provided for in
the bid document)
Tenderer Superintending Engineer 44
(R&B) Circle, NELLORE
46.8 Adjustment clause for Bitumen component shall be as follows
Price adjustment for increase or decrease in the cost of bitumen shall be paid in accordance with the following
formula:
Vb= Increase or decrease in the cost of work done during the period under consideration due to
changes in the rate for bitumen.
Bo= The average Wholesale price of bitumen at the refinery on the day 28 days prior to date of
submission of Bids. The nearest refinery provided in the sanctioned estimate shall be
considered.
Bi= The average Wholesale price of bitumen at the refinery on the day 28 days prior to the last date
of measurement recorded to which a particular bill payment is related.
Pb= Percentage of bitumen component of the work. (To be worked out for each work and
provided for in the bid document)
Vf= Increase or decrease in the cost of work done during the month under consideration due to
changes in the rate for POL.
Fo= The average wholesale price of High Speed Diesel (HSD) at the existing consumer pumps of BPC
at Hyderabad on the day 28 days prior to date of submission of Bids.
Fi= The average wholesale price of High Speed Diesel (HSD) at the existing consumer pumps of
BPC at Hyderabad on the day 28 days prior to the last date of measurement recorded to
which a particular bill payment is related.
Note: The coefficient of 0.85 in the above formulae may be replaced by “1”, i.e., absolute variation of
the rate fixed by the Public Sector Under takings (PSUs) for the items as mentioned in the G.O.Ms.No.
252, T, R&B (R-I) Department, Dated: 28-08-2008, subjected to the conditions mentioned in the said
G.O.
POL 15.00%
47 Retention:
47.2 The department shall retain from each payment due to the contractor @ the rate of 7.5% of bill amount until
completion of the whole of the Works.
47.3 On completion of the whole of the Works half the total amount retained is re-paid to the Contractor and
half when the Defects Liability Period has passed and the Engineer-in-Charge has certified that all the
Defects notified by the Engineer-in-Charge to the Contractor before the end of this period have been
corrected.
47.4 On completion of the whole works, the Contractor may substitute retention money with an “on demand”
Bank Guarantee.
48 Liquidated Damages:
48.2 If for any reason, which does not entitle the contractor to an extension of item, the rate of progress of
works, or any section is at any time, in the opinion of the Superintending Engineer too slow to ensure
completion by the prescribed time or extended time for completion Superintending Engineer shall so
notify the contractor in writing and the contractor shall there upon take such steps as are necessary and
the Superintending Engineer may approve to expedite progress so as to complete the works or such
section by the prescribed time or extended time. The contractor shall not be entitled to any additional
payment for taking such steps. If as a result of any notice given by the Superintending Engineer under this
clause the contractor shall seek the Superintending Engineers permission to do any work at night or on
Sundays, if locally recognised as days or rest, or their locally recognised equivalent, such permission shall
not be unreasonably refused.
48.3 If the contractor fails to complete whole of the works or any part thereof or section of the works within
the stipulated periods of individual mile stones (including any bonafide extensions allowed by the
competent authority without levying liquidated damages), the Superintending Engineer may without
prejudice to any other method of recovery will deduct one tenth of one percent of contract value per
calendar day or part of the day for the period of delays subject to a maximum of 10% of the contract value
not as a penalty from any monies in his hands due or which may become due to the contractor. The
payment or deductions of such damages shall not relieve the contractor from his obligation to complete
the works, or from any other of his obligations and liabilities under the contract.
48.4 The liquidated damages for the whole of the work are
For milestone 1 Rs. Per day
For milestone 2 Rs. Per day
For milestone 3 Rs. Per day
For mile stone 4 Rs. Per day
The maximum amount of liquidated damages for the whole of the works is ten percent of final contract
price.
The mile stones will be filled at the time of Agreement after obtaining a Program of the work.
49 Mobilization Advance:
Tenderer Superintending Engineer 46
(R&B) Circle, NELLORE
49.2 The contractors for works exceeding more than Rs.1.00 Crore of estimated contract value are permitted to
avail the facility of mobilization advance in two installments equivalent to 10% of the contract amount (5%
for labour mobilization and 5% for machinery and equipment) named in the letter of acceptance payable
as per above. Payment of the loan will be done under separate certification by the Executive Engineer after
(I) Execution of the form of agreement by the parties there to (ii) Provisions by the contractor of the
further security in accordance with relevant condition and (iii) provision by the contractor of a Bank
Guarantee from scheduled Bank acceptable to the Executive Engineer for an amount equal to 12% (which
includes 2% for the interest charges) of a contract amount as indicated in the letter of acceptance towards
the first installment of the advance mobilization loan, such bank guarantee to remain effective until the
said advance loan has been completely repaid by the contractor out of the current earnings under the
contract and certified accordingly by the Executive Engineer The ‘Advance mobilization loan’ will be paid
in 30 days after fulfilling the above – i, ii, and iii items. Advance mobilization loan will be paid only in case
of contracts with estimated contract value exceeding Rs.100 lakhs.
49.3 A form of Bank Guarantee acceptable to Executive Engineer is indicated at page ________. The advance
mobilization loan shall be used by the contractor exclusively for mobilization expenditures, including the
acquisition of constructional plant, in connection with the works. Payment of the second installment of
advance mobilization loan equivalent to 5 percent of the contract amount will be due within a period of 9
months for local purchase of machinery and equipment and within one year in case the machinery and
equipment has to be imported under separate certification by the Engineer-in-Charge after (I) the value of
the machinery and equipment procured, and brought to site and/or ordered (satisfactory evidence to be
produced) by the contractor assessed at 100% for new machinery and 50% for old machinery brought to
site and in working condition is equivalent to 5 percent of the contract amount already paid as first
advance loan and (ii) furnishing by the contractor of a bank guarantee for an amount equal to 6 percent
(one percent towards interest) of the contract value.
49.4 Should the contractor misappropriate any portion of the advance loan, it shall become due to the
Executive Engineer and payable immediately in one lump by the contractor and no further loan will be
considered thereafter.
49.5 The above advance shall bear an interest of 10.5% per annum or Government borrowing rate for the
year 2008-09 whichever is more. The interest on the amounts paid as advance is chargeable from the
date the amount is paid. However if completion is delayed by circumstances beyond control of the
contractor for which an extension has been granted by the Executive Engineer / Superintending Engineer
the interest charges on such advances shall be waived for the period of extension.
49.6 The value of Bank Guarantee for the advance payment given to the contractor can be progressively
reduced by the amount repaid by the contractor as certified by the Executive Engineer.
49.7 Recovery of advances :
49.7.1 The advance loan together with interest at the rate specified in the above para shall be repaid within
percentages deductions from the intermediate payments under the contract. Deduction shall
commence in the next interim payment following that in which the total of all such payments to the
contractor have reached 10 percent of the contract amount and shall be made at the rate of 20 percent
of amount of all interim payments in which the loan was made together with interest payable upto that
date, until such time as the loan together with interest at the rate specified in para above shall be
completely repaid prior to the expiry of the original time for completion.
49.8 Payment of Mobilization Advance on Machinery as per Government, Finance (Works &
Projects) Department Memo 103276/F3(2)/05-3, Dated 8/12/2005
55.4 Notwithstanding the above the Department may terminate the contract for convenience.
55.5 If the Contract is terminated, the Contractor shall stop work immediately, make the Site safe and secured
leave the Site as soon as reasonably possible.
56 Payment upon Termination:
56.2 If the Contract is terminated because of a fundamental breach of Contract by the Contractor, the Engineer-
in-Charge shall issue a certificate for the value of the work done less advance payments received upon the
date of the issue of the certificate, less other recoveries due in terms of the Contract, less taxes due to be
deducted at source as per applicable law and less the percentage to apply to the work not completed.
Additional Liquidated Damages shall not apply. If the total amount due to the Department exceeds any
payment due to the Contractor the difference shall be a debt payable to the Department.
57 Property:
57.2 All materials on the Site, Plant, Equipment, Temporary Works and Works are deemed to be the property of the
Department if the Contract is terminated because of Contractor’s default.
58 Release from Performance:
58.2 If the Contract is frustrated by the outbreak of war or by any other event entirely outside the control of either the
Department or the Contractor the Engineer-in-Charge shall certify that the contract has been frustrated. The
Tenderer Superintending Engineer 49
(R&B) Circle, NELLORE
Contractor shall make the site safe and stop work as quickly as possible after receiving this certificate and shall be
paid for all works carried out before receiving it and for any work carried out after wards to which commitment was
made.
59 Water Supply:
The Contractor has to make his own arrangements for water required for the work and to the colonies and
work sites, which are to be established by the Contractor.
60 Electrical Power:
The Contractors will have to make their own arrangements for drawing electric power from the nearest
power line after obtaining permission from the Andhra Pradesh State Electricity Board at his own cost. In
case of failure of electricity, the Contractor has to make alternative arrangements for supply of electricity
by Diesel Generator sets of suitable capacity at place of work. If the supply is arranged by the
Department, necessary Tariff rates shall have to be paid based on the prevailing rates.
The contractor will pay the bills of Electricity Board for the cost of power consumed by him.
The contractor shall satisfy all the conditions and rules required as per Indian Electricity Act 1910 and
under rule –45(I) of the Indian Electricity Rules, 1956 as amended from time to time and other pertinent
rules.
The Engineer-in-Charge reserves the right to refuse permission for use of any government land for
which no claim or compensation shall be admissible to the contractor. The contractor shall, however, not
be required to pay cost or any rent for the Government land given to him.
b) The contractor shall make good to the satisfaction of the Engineer-in-Charge any damage to areas,
which he has to return or to other property or land handed over to him for purpose of this work.
Temporary structures may be erected by the contractor for storage sheds, offices, residences etc., for
non-commercial use, with the permission of the Executive Engineer on the land handed over to him at
his own cost. At the completion of the work these structures shall be dismantled site cleared and
handed over to the Executive Engineer. The land required for providing amenities will be given free of
cost from Government lands if available otherwise the contractor shall have to make his own
arrangements.
62 Roads:
In addition to existing public roads and roads Constructed by Government, if any, in work area all
additional approach roads inside work area and camp required by the Contractor shall be constructed and
maintained by him at his own cost. The layout design, construction and maintenance etc. of the roads
shall be subject to the approval of the Engineer-in-Charge. The contractor shall permit the use of these
roads by the Government free of charge.
It is possible that work at, or in the vicinity of the work site will be performed by the Government or by
other contractors engaged in work for the Government during the contract period. The contractor shall
without charge permit the government and such other contractor and other workmen to use the access
facilities including roads and other facilities, constructed and acquired by the contractor for use in the
performance of the works.
The contractor’s heavy construction traffic or tracked equipment shall not traverse any public roads or
bridges unless the contractor has made arrangement with the authority concerned. In case contractor’s
heavy construction traffic or tracked equipment is not allowed to traverse any public roads or bridges and
the contractor is required to make some alternative arrangements, no claim on this account shall be
entertained.
Labour importation and amenities to labour and contractor’s staff shall be to the contractor’s
account. His quoted percentage shall include the expenditure towards importation of labour amenities to
labour and staff;
68 Indemnity Bond:
/We …………….... Resident of ……………………………………………… do hereby bind myself to pay all the claims may
come (a) under Workmen’s Compensation Act. 1933 with any statutory modification there of and rules there
under or otherwise for or in respect of any damage or compensation payable in connection with any accident
or injury sustained (b) under Minimum wages Act 1948 (c) under payment of wages Act.1936 (d) under the
Contractor labour (Regulation and Abolition) Act. 1970 by workmen engaged for the performance of the
business relating to the above contract ie., Failing such payment of claims of workmen engaged in the above
work, I/We abide in accepting for the recovery of such claims, effected from any of my assets with the
departments.
Contractor
The employees of the Contractor and the Sub-contractor in no case shall be treated as the
Department of the Department at any point of time.
70 Salient features of some major labour laws applicable to establishment engaged in buildings and other
construction work:
(a) Workmen compensation Act 1923: The Act provides for compensation in case if injury by accident arising
out of and during the course of employment.
(b) Payment of Gratuity Act 1972: Gratuity is payable to an employee under the Act on satisfaction of certain
conditions on separation if any employee has completed 5 years service or more, or on death, the rate of
15 days wages for every completed year of service. The Act is applicable to all establishments, employing
10 or more employees.
(c) Employees P.F. and Miscellaneous provision Act 1952: The Act provides for monthly contributions by
the Department plus workers @ 10% or 8.33%. The benefits payable under the Act are:
(i) Pension or family pension on retirement or death, as the case may be.
(ii) Deposit linked insurance on the death in harness of the worker.
(iii) Payment of P.F. accumulation on retirement/death etc.,
(d) Maternity Benefit Act 1951: The Act provides for leave and some other benefits to women employees in
case of confinements or miscarriage etc.
(e) Contract Labour (Regulation & Abolition) Act 1970: The Act provides for certain welfare measures to be
provided by the contractor to contract labour and in case the Contractor fails to provide, the same are
required to be provided by the Principal Department by Law. The Principal Department is required to take
certificate of Registration and the contractor is required to take license from the designated Officer. The
Act is applicable to the establishments or Contractor of Principal Department if they employ 20 or more
contract labour.
(g) Payment of wages Act 1936: It lays down as to by what date the wages are to be paid, when it will be paid
and what deductions can be made form the wages of the workers.
(h) Equal Remuneration Act 1979: The Act provides for payment of equal wages for work of equal nature to
Male or Female workers and for not making discrimination against Female employee in the matters of
transfers, training and promotions etc.
(i) Payment of Bonus Act 1965: The Act Is applicable to all establishments employing 20 or more
employees. The Act provides for payment of annual bonus subject to a minimum of 8.33% of wages and
maximum of 20% of wages to employees drawing Rs. 3500/- per month or less. The bonus to be paid to
employees getting Rs.2500/- per months or above and upto Rs.3500/- per month shall be worked out by
taking wages as Rs.2500/- per monthly only. The Act does not apply to certain establishments. The newly
set-up establishments are exempted for five years in certain circumstances. Some of the State
Governments have reduced the employment size from 20 to 10 for the purpose of applicability of this Act.
j) Industrial Disputes Act 1947: The Act lays down the machinery and procedure for resolution of
Industrial disputes, in what situations a strike or lock- out becomes illegal and what are the requirements
for laying off or retrenching the employees or closing down the establishment.
(k) Industrial Employment (Standing Orders) Act 1946: It is applicable to all establishments employing 100 or
more workmen (employment size reduced by some of the State and Central Government to 50). The Act
provides for laying down rules governing the conditions of employment by the Department on matters
provided in the Act and get the same certified by the designated Authority.
(l) Trade Unions Act 1926: The Act lays down the procedure for registration of trade unions of workmen
and Departments. The Trade Unions registered under the act have been given certain immunities from civil
and criminal liabilities.
(m) Child Labour (Prohibition & Regulation) Act 1986: The Act prohibits employment of children below 14
years of age in certain occupations and processes and provides for regulation of employment of children in
all other occupations and processes, Employment Child Labour is prohibited in Building and Construction
Industry.
(n) Inter-State Migrant workmen’s (Regulation of Employment & Conditions of service) Act 1979: The Act
applicable to an establishment, which employs 5 or more inter-state migrant workmen through an
intermediary (who has recruited workmen in one state for employment in the establishment situated in
another State). The inter State migrant workmen, in an establishment to which this Act becomes
applicable, are required to be provided certain facilities such as housing, medical aid, travelling expenses
from home upto the establishment and back, etc.
(o) The Building and Other Construction workers (regulation of Employment and conditions of service) Act
1996 and the Cess Act of 1996: All the establishments who carryon any building or other construction work
and employs 10 or more workers are covered under this Act. All such establishments are required to pay
cess at the rate not exceeding 2% of the cost of construction as may be modified by the Government. The
Department of the establishment is required to provide safety measures at the Building or construction
work and other welfare measures, such as Canteens, First-aid facilities, Ambulance, Housing
(p) Factories Act 1948: The Act lays down the procedure for approval of plans before setting up a factory,
health and safety provisions, welfare provisions, working hours, annual earned leave and rendering
information regarding accidents or dangerous occurrences to designated authorities. It is applicable to
premises employing 10 person or more with aid of power or 20 or more persons without the aid of power
engaged in manufacturing process.
(b)The Contractor shall at all times submit details of skilled and unskilled labour and equipment employed
to the Engineer-in-Charge in prescribed proforma as he may require to assess and ensure the proper
progress of work.
(c) If the contractor does not employ the technical person agreed to on the work a fine of Rs.25,000/- will
be imposed. If he does not employ for 30 days, thereafter it becomes a fundamental breach of
contract.
74 Relationship :
Contractor shall have to furnish information along with tender, about the relationship he is having with
any officer of the Department, Government of Andhra Pradesh of the rank Assistant Engineer and above
82 Conflict of interest:
Any bribe, commission, gift or advantage given, promised or offered by on behalf of contractor or his
partner, agent or servant or any one on his behalf to any officer, servant, representatives, agents of
Engineer-in-Charge, or any persons on their behalf, in relation to the obtaining or to execution of this, or
any other contract with Engineer-in-Charge shall in addition to any criminal liability, which it may occur,
subject to the cancellation of this or all other contracts and also to payment of any loss or damage
resulting from any such cancellation. Engineer-in-Charge shall then be entitled to deduct the amount, so
payable from any money, otherwise due to the contractor under this or any other contract.
b) All contractors’ employees, representatives and sub-contractor’s employees shall wear identifications
badges provided by the contractor. Badges shall identify the contractor, showing and employee’s
number and shall be worn at all times while at the site. Individual labour will not be required to wear
identification badges.
c) All vehicles used by the contractor shall be clearly marked with contractor’s name.
d) The contractor shall be responsible for the security of the works for the duration of the contract and
shall provide and maintain continuously adequate security personnel to fulfill these obligations. The
requirements of security measures shall include, but not limited to maintenance of order on the site,
provision of all lighting, fencing, guard flagmen and all other measures necessary for the protection of
the works within the colonies, camps and elsewhere on the site, all materials delivered to the site, all
persons employed in connection with the works continuously throughout working and non working
period including nights, Sundays and holidays for duration of the contract.
b) Separate payment will not be made for the provision of fire prevention measures.
87 Sanitation:
The contractor shall implement the sanitary and watch and ward rules and regulations for all forces
employed under this contract and if the Contractor fails to enforce these rules, the Engineer-in-Charge
may enforce them at the expenses of the Contractor.
88 Training of personnel:
The contractor, shall, if and as directed by the Engineer-in-Charge provide free of any charge adequate
facilities, for vocational training of Government Officers, students, Engineers, supervisors, foremen, skilled
workmen etc. not exceeding six in number at any one time on the contractor’s work. Their salaries,
allowances etc. will be borne by the Government and the training schemes will be drawn up by the
Engineer-in-Charge in consultation with the contractor.
89 Ecological balance:
a) The contractor shall maintain ecological balance by preventing de-forestation, water pollution and
defacing of natural landscape. The contractor shall so conduct his construction operation as to prevent
any unnecessary destruction, scarring, or defacing of the natural surroundings in the vicinity of the
work. In respect of the ecological balance, Contractor shall observe the following instructions.
i) Where unnecessary destruction, scarring, damage or defacing may occur, as result of the
operation, the same shall be repaired replanted or otherwise corrected at the contractor’s
expense. The contractor shall adopt precautions when using explosives, which will prevent
scattering of rocks or other debris outside the work area. All work area including borrow areas
shall be smoothened and graded in a manner to conform to the natural appearances of the
landscape as directed by the Engineer-in-Charge.
ii) All trees and shrubbery which are not specifically required to be cleared or removed for
construction purposes shall be preserved and shall be protected from any damage that may be
caused by the contractor’s construction operation and equipment. The removal of trees and
shrubs will be permitted only after prior approval by the Engineer-in-Charge. Special care shall be
exercised where trees or shrubs are exposed to injuries by construction equipment, blasting,
excavating, dumping, chemical damage or other operation and the contractor shall adequately
protect such trees by use of protective barriers or other methods approval by the Engineer-in-
Charge. Trees shall not be used for anchorages. The contractor shall be responsible for injuries to
trees and shrubs caused by his operations. The term “injury” shall include, without limitation
bruising, scarring, tearing and breaking of roots, trunks or branches. All injured trees and shrubs
be restored as nearly as practicable without delay to their original condition at the contractor’s
expense.
(v) In conduct of construction activities and operation of equipments the contractor shall utilize
such practicable methods and devices as are reasonably available to control, prevent and
otherwise minimize the air pollution. The excessive omission of dust in to the atmosphere will not
be permitted during the manufacture, handling and storage of concrete aggregates and the
contractor shall use such methods and equipment as a necessary for collection and disposal or
prevention of dust during this operation. The contractor’s methods of storing and handling
cement shall also include means of eliminating atmospheric discharges of dust, equipment and
vehicles that give objectionable omission of exhaust gases shall not be operated. Burning of
materials resulting from clearing of trees, bushes, combustible construction materials and rubbish
may be permitted only when atmospheric conditions for burning are considered favourable.
b) Separate payment will not be made for complying with the provisions of this clause and all cost
shall be deemed to have been included in the unit rates and prices included in the contract if any
provision is not complied with within a reasonable time even after issue of a notice in this respect,
the necessary operations would be carried out by the Engineer-in-Charge at the cost of the
Contractor, Orders of the Engineer-in-Charge in this respect would be final and binding on the
contractor.
b) All the produce from such cutting of trees by the contractor shall remain the property of Government
and shall be properly stacked at site, approved by the Engineer-in-Charge. No payment whatsoever
shall be made for such cutting and its stacking by the Contractor. If any produce from such cutting is
not handed over to the Government by the contractor, he shall be charged for the same at the rates to
be decided by the Engineer-in-Charge. The recovery of this amount shall be made in full from the
intermediate bill that follows.
c) The contractor shall also make arrangements of fuel deposits for supply of required fuel for the labour
to be employed for cooking purpose at his own cost in order to prevent destruction of vegetation
growth in the surrounding area of the work site.
The Executive Engineer shall have the privilege of ordering modifications, omission or additions at
any time before the completion of the work and such orders shall not operate to annual those portions of
the specifications with which said changes do not conflict.
Engineer-in-Charge’s Decision:
It shall be accepted as in separable part of the contract that in matters regarding materials, workmanship, removal of
improper work, interpretation of the contract drawings and contract specification, mode of the procedure and the
99 Income tax:
a) During the currency of the contract deduction of income tax at 2.24% shall be made from the gross
value of each bill of the contract, the contract value of which is in excess of Rs.10,000/- for deduction of
tax at rates lower than 2.24% procedure stipulated under section 194-C(4) of Income Tax Act, 1961
shall be followed.
b) Income Tax clearance certificate should be furnished before the payment of final bill.
c) The contractor’s staff, personnel and labour will be liable to pay personnel income taxes in respect of
their salaries and wages as are chargeable under the laws and regulations for the time being in force,
and the contractor shall perform such duties in regard to such deductions thereof as may be imposed
on him by such laws and regulations
100.2 The seigniorage charges are to be recovered as provided in the agreement. Any escalation in these
charges beyond the provisions of the agreement are to be borne by the department debiting such
escalated amount to the works estimate concerned.
101 VAT:
101.1 Value added Tax (VAT) during the currency of the contract deduction towards AP-VAT Act 2005
according to which tax @ 5% on total value has to be deducted at source, while making payments to the
contractor as per Memo No. 14420/R.I(2)/08-2, Dated: 17.12.2008 of T R&B (R.I) Department.
101.2 The contractor should produce a valid VAT clearance certificate before the payment of the final bill,
otherwise payment to the contractor will be withheld.
101.3 The following clause is incorporated as per the Government instructions given in G.O.Ms. No: 141, T
(R&B) Department, Dated: 27-07-2006.
i) The contractor has to make his own arrangements for procurements, supply and use of
construction materials.
ii) All materials so procured should confirm to the relevant specifications indicated in the bidding
documents.
iii) The contractor shall follow all regulations of the Department/Government of India in respect of
import licences etc., of the procurement of the materials is through imports and he shall be
responsible for the payment of applicable duties and taxes, port clearances, inland transportation
etc.
iv) The contractor shall make his own arrangements for adequate storage of the materials.
102 (b) The Contractor shall procure the hot mix material to the work site, duly maintaining the required
laying temperature, as per the specifications.
102 An amount of 0.25% of the gross bills will be deducted from the contractors as their contribution to the
National Academy of construction, Hyderabad (As per G.O.Ms No 116, T, R&B Department, Dated: 19-05-
2007).
103 (a) The Contractor shall purchase of Bitumen/Emulsion only form the reputed firm i.e HPCL and IOCL.
They shall not be permitted to use CRMB bought private manufacturers.
(b) The Contractors shall procure Original bills towards purchase of bitumen /emulsion while submitting
the bills for payment .
Executive Engineer (R&B) Concerned should endorse the name of the work on the bills /vouchers
/invoices for which the bitumen emulsion is utilized to avoid reuse of bills on other works.
The Contractors shall order and procure the bitumen /emulsion work wise so that the contractor
obtain invoice/bills work wise and submit the same to the Executive Engineer, (R&B) Concerned while
preparing the bills.
104 The contractor shall test all the materials as per the agreement specifications and results shall be recorded
duly signed by the Contractor or his representative and the Section Officer. The name of the work and
quarry location shall be clearly noted in the test reports.
If any deficiency in the size of metal (aggregates), thickness, binder quantity, density, weight etc.,
beyond the limits/tolerances prescribed for road works are observed, necessary recoveries / penalties
will be effected as per the Circular Memo No: 12582/Vig.I/1/2005-1, Dated: 23-03-2006 of the Engineer-
in-Chief (R&B) Administration & Roads, A.P., Hyderabad
Amendment to Table 400-11 of MORT&H 4 th Revision pertaining to Gradation limits of Wet Mix Macadam
as per Circular Memo.No.1814/DCE(N)/DEE 1/AEE2/2009 dt.29.1.2009 of Chief Engineer (R&B) NABARD, A.P,
Hyderabad.
53.00mm 100mm
45.00mm 75-90
26.50mm -
22.4mm 45-70
11.20mm 24-45
4.75mm 20-25
2.36mm 10-20
75 microns 0-4
N.B :- No job mix where in upper limit of a particular screening and lower limit of immediately
DRAWINGS
GENERAL ARRANGEMENT DRAWING
1.0 DRAWINGS:
1.1 The plans enclosed with the tender are liable to the altered during execution of work as per necessity of site
conditions. The premium quoted by the contractor for various items shall hold good for execution of work even
with altered plans.
1.2 One set of drawings, on the basis of which actual execution of the work is to proceed shall be furnished
free of cost to the contractor by the Superintending Engineer / Executive Engineer progressively
according to the work program submitted by the contractor and accepted by the Superintending
Engineer / Executive Engineer. Drawings for any particular activity shall be issued to the contractor at
least 30 days in advance of the scheduled date of the start of the activity. However, no extra claims by
the contractor toward any delay in issue of drawing or issue of any revision / change to the drawings
issued earlier shall be admissible. The Superintending Engineer shall intimate the contractor 7 days in
advance regarding any delay to issue of drawings, for any particular stage of works. If work gets
effected due to delay to issue of drawings, for any particular stage of work the contractor shall be
granted extension of time in terms of condition 14.7 of tender notice.
1.3 Signed drawings above shall not be deemed to be an order for work unless they entered in the
agreement or schedule of drawings under proper alterations of the contractor and Executive Engineer
or unless they have been sent of the contractor by the Executive Engineer with a covering letter
confirming that the drawing in and authority for work in contract.
2.0 DISCREPANCIES:
2.1 In case of discrepancies between documents the following order of procedure shall apply:-
2.1.1 Between the written description of written dimensions in the drawings and the corresponding
one in the specifications, the latter shall apply.
2.1.2 Figured dimensions shall supersede scaled dimensions. The drawings on a larger scale shall
take precedence over those on a smaller scale.
2.1.3 Drawings issued as construction drawings from time to time shall supersede tender drawings
and also the correspondence drawings previously issued.
Note: The contractor should not execute any component of work without obtaining the working drawings.
Any work done without drawings shall be at the contractors responsibility only. Acceptance for
such work will be at the discretion of the Executive Engineer.
(Enclosed separately)
BILL OF QUANTITIES
PREAMBLE
1. The Bill of Quantities shall be read in conjunction with the instructions to Tenderers, General and
Special conditions of Contract Technical Specifications and Drawings.
2. The quantities given in the Bill of Quantities are estimated and provisional and are given to provide
common basis for tendering. The quantities here given are those upon which the lumpsum tender cost
of the work is based but they are subject to alterations, omissions, deductions or additions as provided
for in the conditions of this contract and do not necessarily show the actual quantities of work to be
done. The basis of payment will be actual quantities of work ordered and carried out as measured by
the Contractor and verified by the Engineer and valued at the estimate rate plus or minus tender
percentage quoted in the Bill of Quantities where applicable, and otherwise at such rates and prices as
the Engineer-in-Charge may fix within the terms of Contract.
3. The estimate rates in the Bill of Quantities shall, except in so-far as it is otherwise provided under the
Contract include cost of all constructional material, labour, machinery, transportation, erection,
maintenance, profit, taxes and duties together with all general risks, liabilities and obligations set out or
implied in the Contract.
4. The plans enclosed with the tender are liable to be altered during execution of work as per necessity of
site conditions. The Tender percentage quoted by the tenderer shall hold good for execution of work
even with altered plans.
5. The whole cost of complying with the provisions of the Contract shall be included in the estimated rates
for items provided in the Bill of Quantities and where no items are provided in the Bill of Quantities,
their cost shall be deemed to be distributed among the estimate rates entered for the related items of
work.
6. General directions and descriptions of work and materials are not necessarily repeated nor summarised
in the Bill of Quantities. References to the relevant sections of the Contract documentation shall be
made before entering estimate rate against each item in the Bill of Quantities.
7. The method of measurements of completed work for payment shall be in accordance with the relevant
MoRT&H specifications, B.I.S. Codes & A. P. S. Specifications.
8. All items of work are to be executed as per the drawings / specifications supplied with the contract
documents.
If there is any contradiction between the drawings and the text of the specifications, the later
shall prevail.
9. The Tenderer should inspect and select the quarries of his choice before he quotes the tender
percentage in the Schedule of Bill of Quantities and satisfy himself about the availability of required
quantum of materials.
10. Diversion drains should be excavated before completion of the embankments and the useful soils
should be used in the nearby embankments.
11. The actual mix proportion by weight to be adopted during execution will be got designed in the
laboratories to suit the grade of concrete and mortar to be used. It will be the responsibility of the
contractor to manufacture concrete and mortar of required strength.
18. The tenderers attention is directed to requirements for materials under the clause ‘materials and
workmanship’ in the preliminary specifications of APSS. Materials conforming to the Bureau of Indian
Standards specifications, APSS etc., shall be used on the work and the tenderers shall quote his overall
tender percentage accordingly.
19. The tenderer has to do his own testing of materials and satisfy himself that they conform to the
specifications of respective I.S.I. Codes before tendering.
20. The contractor shall himself procure the required construction materials of approved quality including
the earth for formation of embankment and water from quarries / sources of his choice. All such
24. The defect liability period of contract in terms of GO Ms.No.94, I&CAD Department, Dated: 01-07-2003
is twenty four months.
25. The estimate rates for items shown in the Schedule “A” include all construction materials. No
escalation in rates will be paid unless specified in the tender document. The tenderer has to quote an
overall tender percentage considering all the aspects of the tender to complete the finished item of
work as per the APSS / MoRT&H / B.I.S. specifications, the special specifications appended, Drawings
etc.
26. If there is any contradiction between APSS / MoRT&H and B.I.S. specifications, listed and detailed
technical specifications, the latter shall prevail.
27. In case of a job for which specifications are not available with the Schedule or in APSS / MoRT&H or
B.I.S. code and are required to be prescribed, such work shall be carried out in accordance with the
written instructions of the Engineer-in-charge.
28. The contractor should use the excavated useful soils and stone for construction purpose. Soils used for
construction either for homogeneous section in hearting or in casing zone based on the suitability will
be at free of cost and the cost of stone used for construction purpose will be recovered from the
contractor’s bill.
The contractor should quote his tender percentage keeping in view of the above aspects.
29. Additions and alternations by the Tenderer in the Schedule of quantities will disqualify the tender.
30. In the case of discrepancies between the written description of the item in the Schedule “A” and the
detailed description in the specification of the same item, the latter shall be adopted.
31. The Unit rates noted below are those governing payment of extras or deductions for omissions
according to the conditions or the contract as set-forth in the preliminary specifications of the A.P.
standard specifications and other conditions of specification of this contract.
32. It is to be expressly understood that the measured work is to be taken according to the actual
quantities when in place and finished according to the drawings or as may be ordered from time to
time by the Executive Engineer and the cost calculated by measurement or weight at their respective
rates without any additional charge for any necessary or contingent works connected works connected
Tenderer Superintending Engineer 70
(R&B) Circle, NELLORE
herewith. The Percentage Excess or less on ECV quoted are for works in situ and complete in every
respect.
33. For all items of work in excess of the quantities indicated the rates payable for such excess quantities
will be tendered rates i.e., estimate rates plus or minus tender percentage.
34. For all items of work, intermediate payment will be made provisionally as per relevant clause. Full-
accepted agreement rates will be paid only after all the items of works are completed.
35. The contractor is bound to execute all supplemental works that are found essential incidental and
inevitable during execution of main work.
36. The payment of rates for supplement items of work will be regulated as under.
Supplemental items directly deductible from similar items in the original agreement.
The rates shall be derived by adding to or subtracting from the agreement rate of such similar item the
cost of the difference in the quantity of materials labour between the new items and similar items in
the agreement worked out with reference to the schedule of rates adopted in the sanctioned estimate
with which the tenders are compared.
a) Similar items but the rates of which cannot be directly deducted from the original agreement.
b) Purely new items which do not correspond to any item in the agreement.
The rate of all such items shall be estimated rates plus or minus overall tender percentage.
SCHEDULE – A
ENCLOSED.
RATE OF PROGRESS
The Total Period of completion of work is 12 (Twelve) Months from the date of
entering in to Agreement to proceed including Rainy Season.
The Work Shall be programmed such as to achieve the Mile Stones as under.
Work Programme of Achieving the Mile Stones from the date of entering into Agreement including
Rainy Season.
1 2 1 2 3 4 6 7 8 9 10
I 0 to 90
days
II 91
to180
days
III 181 TO
270 days
IV 271 to
346 days
14453256
NAME OF WORK : Construction of HLB across Puli Kalava at Km 12/10 of Kota-Chittamur Road in SPSR Nellore District
PERIOD OF COMPLETION: 12 Months E.C.V RS: . 1,44,53,256/-
S.N Approximate Quantity Description of Item Morth Unit in Estimate Rate
o Specifica
tion No Amount
Figures Wo Words Figue Words Rs. Figures Words
rds s
1 2 3 4 5 6 7 8 9 10
1 1393 M3 One Earthwork excavation in soils upto SDR by mechanical means 304 1 One Rs. 31.00 Rupees 43183.00
thousand for foundations of structures as per drawing and technical (4th Cum Cubic Thirty one
three specification including setting out, construction of shoring and Revision) meter only
hundred bracing, removal of stumps and other deleterious matter, only
ninety dressing sides of bottom, back filling the excavation earth to
three cubic the extent required etc., complete for finished item of work as
meters only per MoRT&H specification 304(4th Revision)
1 2 3 4 5 6 7 8 9 10
4 220 M3 Two Vibrated cement concrete M 15 Grade Concrete using 40mm , MoRT&H One Rs. 6240.00 Rupees Six
hundred 20mm and 10mm size HBG crushed stone aggregate (Coarse Specifica Cubic thousand
twenty aggregate conforming to table 1000-1 and fine aggregate tion 1 meter two 1372800.00
cubic conforming to table 1000-2) including cost, and conveyance of 1500,170 Cum only hundred
meters only all materials to site and all labour charges for machine 0, 2100 forty only
mixing,laying in position, Compacting , Vibrating and curing (4th
including all other incidental and all other operational charges Revision)
of T&P required etc., complete as per MoRT&H Specification
1500,1700, 2100 (4th Revision) for footings of Abutments, Piers
Wing walls and Cut off walls
5 516 M3 Five Vibrated cement concrete M 15 Grade Concrete using 40mm , MoRT&H One Rs. 6240.00 Rupees Six
hundred 20mm and 10mm size HBG crushed stone aggregate (Coarse Specifica Cubic thousand
sixteen aggregate conforming to table 1000-1 and fine aggregate tion 1 meter two 3219840.00
cubic conforming to table 1000-2) including cost, and conveyance of 1500,170 Cum only hundred
meters only all materials to site and all labour charges for machine 0, 2100 forty only
mixing,laying in position, Compacting , Vibrating and curing (4th
including all other incidental and all other operational charges Revision)
of T&P required etc., complete as per MoRT&H Specification
1500,1700, 2100 (4th Revision) for Raft footing.
1 2 3 4 5 6 7 8 9 10
6 169 M3 One Vibrated cement concrete M 15 Grade Concrete using 40mm , MoRT&H One Rs. 6600.00 Rupees Six 1115400.00
hundred 20mm and 10mm size HBG crushed stone aggregate (Coarse Specifica Cubic thousand six
sixty nine aggregate conforming to table 1000-1 and fine aggregate tion 1 meter hundred
cubic conforming to table 1000-2) including cost, and conveyance of 1500,170 Cum only only
meters only all materials to site and all labour charges for machine mixing, 0, 2200
laying in position,Compacting, Vibrating and curing including all (4th
other incidental and all other operational charges of T&P Revision)
required etc., complete as per MoRT&H Specification
1500,1700, 2200 (4th Revision) for Sub structure for
abutments,Piers and wing walls
7 15 M3 Fifteen Vibrated reinforced cement concrete M 25 grade using 20mm MoRT&H One Rs. 7950.00 Rupees
cubic & 10mm HBG crushed stone aggregate (Coarse aggregate specifica Cubic Seven
meters only conforming to table 1000-1 and fine aggregate conforming to tion 1 meter thousand 119250.00
table 1000-2) including cost, and conveyance of all materials to 1500,160 Cum only nine
site and labour charges, centering, machine mixing, laying, 0,1700 & hundred
vibrating, curing etc., including other incidental hire and 2200 fifty only
operational charges of all T&P as per approved drawings and as (4th
directed during execution but excluding cost of steel and its revision
fabrication charges for finished item as per MoRT&H
specification 1500,1600,1700 & 2200 (4th revision ) and as
directed by the Engineer-in-Charge for Bed blocks & Backing
walls
1 2 3 4 5 6 7 8 9 10
8 236 M3 Two Vibrated reinforced cement concrete M 25 grade using 20mm MoRT&H One Rs. 8640.00 Rupees
specificatio
hundred & 10mm HBG crushed stone aggregate (Coarse aggregate Cubic Eight
n 1 2039040.00
thirty six conforming to table 1000-1 and fine aggregate conforming to 1500,1600, meter thousand six
cubic table 1000-2) including cost, conveyance of all materials to site 1700 and
Cum only hundred
meters only and labour charges, centering, machine mixing, laying, vibrating, as per forty only.
M.O.S.T
curing etc.,including other incidental hire and operational
DRG No
charges of all T&P etc., complete as per approved drawings and No.BD/12-
as directed during execution but excluding cost of steel and its fabrication 74A
charges for finished item as per MoRT&H specification 1500,1600,1700 and as &BD/13-
per M.O.S.T DRG No No.BD/12-74A &BD/13-74A for Deck slab 74A
9 6 M3 Six cubic Vibrated cement concrete M 15 Grade Concrete using 40mm , One Rs. 6000.00 Rupees Six
meters only 20mm and 10mm size HBG crushed stone aggregate (Coarse Cubic thousand
MoRT&H 1 36000.00
aggregate conforming to table 1000-1 and fine aggregate meter only
Specifica Cum
conforming to table 1000-2) including cost, and conveyance of only
tion
all materials to site and all labour charges for machine
1500,170
mixing,laying in position, Compacting , Vibrating and curing
0, 2100
including all other incidental and all other operational charges
(4th
of T&P required etc., complete as per MoRT&H Specification
Revision)
1500,1700, 2100 (4th Revision) for Levelling course below
approach slab.
1 2 3 4 5 6 7 8 9 10
12 103 RM One Construction of precast VRCC railing of M25grade using HBG MoRT&H 1 One Rs. 416.00 Rupees Four
crushed stone aggregate of size not exceeding 12 mm and fine Running
hundred Specifica hundred
R.M meter 42848.00
and three aggregate conforming to table 1000-2 true to line and grade, tion sixteen only.
only
tolerance of vertical RCC post not to exceed 1 in 500, centre to
running 2703,
centre spacing between vertical posts not to exceed 2000mm,
meters only 1500,
leaving adequate space between vertical posts for expansion
including cost, and conveyance of all materials to site and 1600,
labour charges, centering, machine mixing, laying, vibrating, 1700(4th
curing etc., including other incidental hire and operational Revision
charges of all T&P as per approved drawings and as directed
during execution, excluding cost of steel and its fabrication
charges as per approved drawings and technical specifications
for finished item of work as per MoRT&H Specification 2703,
1500, 1600, 1700(4th Revision) Hand rails without poot paths
Providing HYSD bars (Fe-415) of different diameters, wrought MoRT&H Rupees Sixty
and put up bars of all diameters including cost and conveyance specifica five
One
13 18 M.T Eighteen of steel to site and all labour charges for fabrication of tion 1600 1 Rs. 65180.00 thousand 1173240.00
Metric
metric reinforcement including cutting, bending, binding rods, tying &2200 tonne one
tones only M.T only
grills, placing them in position etc., complete including cost and (4th hundred
conveyance of binding wire and all handling charges and revision) eighty only
operational charges etc., and including over lapping welding if and as
required etc., complete for all R.C.C items for finished item of per
work as per standard drawings, as per the directions of the I.S.1786
Engineer-in-Charge and as per MoRT&H specification 1600 of
&2200 (4th revision) and as per I.S.1786 of 1985 for Super
structure of R.C.C items.Superstructure 1985
1 2 3 4 5 6 7 8 9 10
1 2 3 4 5 6 7 8 9 10
17 Pitching with ssrevetment with300 mm size rough stone MoRT&H One cubic Rs. 1513.00 Rupees One 15130.00
meter
including cost, and conveyance of materials to site and specifica thousand
10.00 M3 Ten cubic 1M3 only
including labour charges for packing the stones for revetment tion 2504 five
meters etc., complete for finished item of work as per MoRT&H ( 4th hundred
only. specification 2504 ( 4th revision ) and as directed by the revision thirteen
Engineer-in-Charge for Pitching of slopes for Toe wall only
1 2 3 4 5 6 7 8 9 10
18 Providing and laying filter material with Gravel underneath MoRT&H One cubic Rs. 1003.00 Rupees One
meter
pitching in slopes including cost, charges and conveyance of specifica thousand
10.00 M3 Ten cubic 1M3 only 10030.00
materials to site including labour charges etc., complete for tion 2504 three only
meters finished item of work as per MoRT&H Specification 2504 (4th ( 4th
only. Revision) and as directed by the Engineer-in-Charge under revision
Revetment
20 69.00 M3 Sixty nine Providing and laying of filter media using 50% of 150 mm IRC MORT One cubic Rs. 1740.00 Rupees One
soling stone and 50 % of 40 mm HBG metal satisfying the meter
cubic thousand
&H No. 1M3 only 120060.00
meters only requirements laid down in clause 2504.2.2 of MoRT&H seven
specifications to athickness of not less than 600mm with smaller
hundred
size towards the soil and bigger size towards the wall and 2200
forty only
provided over the entire surface behind the abutment, wing
wall and return wall to the full height compacted to a firm
Tenderer Superintending Engineer 82
(R&B) Circle, NELLORE
condition including cost and conveyance of all metal ,and all
labour charges as directed by the departmental officers as per
drawing and Technical specifications as per clause 710.1.1 of
IRC:78 and Clause 2200 of MoRT&H (4th Revision) for finished
item of work.
1 2 3 4 5 6 7 8 9 10
21 73.00 R.M Seventy Providing weep holes in VCC Abutments, Return walls and wing MoRT&H 1 One Rs. 388.00 Rupees
walls with 100mm Diameter AC pipe extending through the full running
three specifica Three
width of the structure at 1.00m C/C in both horizontal and R.M meter 28324.00
running tion 2706 only hundred
vertical direction so that the weep holes in each horizontal
meters only & 2200 eighty eight
direction is staggered from the weep holes laying above and
(4th only
below lines as shown in drawing including cost and conveyance
of the A.C pipes and labour charges for cutting to required Revision)
length, placing the pipe with a slope of about 1V : 20H towards
stream side face etc., complete for finished item of work for
weep holes as per MoRT&H specification 2706 & 2200 (4th
Revision)
22 10 Nos Ten MoRT&H 1No. One Rs. 1201.00 Rupees One 12010.00
Supplying and fixing of CI drainage spouts complete as per Specificatio Number
numbers thousand
MoRT&H Specification No.2705 and as per drawing No.BD / 1- n No.2705 only
only two
69
hundred
one only
23 381 M3 Three Providing and laying Boulder approns on river bed for protection MORTH 1M3 One cubic Rs. 1545.00 Rupees One 588645.00
hundred against scour with stone boulders weighing not less than 40 Kg Specifica metre thousand
eighty one each as per drawing and technical specifications and as per tion only five
cubic MORTH Specification No.2507.2 Boulders laid dry without wire No.2507. hundred
meters only crates 2 forty five
Tenderer Superintending Engineer 83
(R&B) Circle, NELLORE
only
1 2 3 4 5 6 7 8 9 10
24 2561 M3 Two Forming embankment with borrowed useful earth from outside MoRT&H One cubic Rs. 204.00 Rupees Two 522444.0
road boundary by mechanical means upto SDR with all leads meters
thousand specifica hundred
1M3 only
five and lifts including pre-watering of soil at borrow area, removal tion 305 and four
of top soil, excavation of soils at borrowed area, conveyance of
hundred (4th only
soil, depositing the soil on the embankment, spreading soil,
sixty one revision)
breaking clods, sectioning, grading and consolidation with 8 to
cubic 10 Tonnes Vibratory Road Roller @ OMC to meet requirement
meters only of table 300-2 of MoRT&H, including all hire and operational
charges of T&P , complete for finished item of work as per
MoRT&H specification 305 (4th revision) (Payment will be made
based on level for finished item of work).
1 2 3 4 5 6 7 8 9 10
28 1881 M2 One Providing and applying tack coat with bitumen Emulsion MoRT&H 1M2` One Rs 9.70 Rupees Nine 18245.70
square
thousand (Medium settting) (Bulk) using Emulsion pressure distributor at Specifica and paise
meters
eight the rate of 0.20 kgs per sqm on the prepared tion 503 only seventy only
hundred bituminous/granular surface cleaned with mechanical broom (4th
Tenderer Superintending Engineer 86
(R&B) Circle, NELLORE
eighty one for finished item of work as per MoRT&H Specification 503 (4th revision)
square revision) and as directed by the Engineer-in-Charge.
meters only
29 1881 M2 One Providing and laying of close graded premix surfacing material MoRT&H 1M2` One Rs. 187.00 Rupees One
square
thousand (Mixed seal surfacing)of 25 mm thickness by hot mix plant using Specifica hundred 351747.00
meters
eight hard blasted crushed aggregate of 13.2mm to 0.09mm (Type B) tion 512 only eighty seven
hundred (4th only
as per table 500.2.6 of specification 512 of MORTH (4th
eighty one Revision)
revision ) working out to 0.3375 Cum /10 Sqm premixed with
square
meters only bituminous binder 60/70 grade working out to 23.75 Kg per 10
sqm area including cost of all materials and transporting the Hot
mix to work site laying with mechanical paver finished to the
required grade level and alignment rolling with smooth wheeled
vibratory and tandem rollers to achieve the desired compaction
as per MoRT&H Specific ation 512 (4th Revision) complete for
finished item of work in all respects as directed by Engineer-in-
charge.
Total No. of items 29 ( Twenty Total Rupees One Crore Forty four lakhs fifty three thousand Total Rs. 1,44,53,256/
nine only) two hundred fifty six only. -
BILL OF QUANTITIES
Part-II
Details of Maximum amount reimbursable to the Contractor.
1) The tenderers are eligible for reimbursement of amounts towards Avagahana Sadassu not exceeding the amounts indicated above.
2) The rates mentioned in Bill of Quantities (Part-I) are including overhead charges and contractors profit but excluding VAT as per G.O.Ms.No: 141, T(R&B)
Department, Dated: 27-07-2006. The items covered under overhead charges are as per the MoRT&H standard data book for analysis of rates (First revision).
3) As the overhead charges include engaging technical persons by the contractor and Work insurance, no reimbursement for these will be made separately.
4) The Contractor has to take Policies and certificates of insurance and they shall be delivered to the Superintending Engineer at the time of concluding
Agreement. Failing to comply with the above, the Engineer-in-Charge shall take insurance policy at the cost of Contractor duly deducting the premium from the
Contractor bills.
5) If the contractor fails to employ technical persons, the work will be suspended or department will engage technical persons and recover the cost thereof from the contractor.
I/We ………………… do hereby express my willingness to execute the aforesaid work as per the conditions, standards, specifications, rules, regulations, etc.,
stipulated in the tender documents.
a) at an overall tender percentage of ………% (in figures) …………………………….(in words) Excess/ less over estimated value or at Estimate rates.
WHEREAS ……………………………………………………….. (Name of the Contractor) (here in after called “the Tenderer”) has
submitted his tender response to NIT No………………………. dated:…………………… for the work “
………………………………………………………………………………………………..” (Name of work) (hereinafter called “the tender”).
SEALED with the Common Seal of the Bank this …………….. day of ……………..200….
(1) If after Tender opening the tenderer withdraws or modifies his Bid during the period of bid validity
specified in the Form of Tender.
(2) If the Tenderer having been notified of the acceptance of his bid by the Department during the
period of validity.
(a) fails or refuses to execute the Form of Agreement in accordance with the Instructions to
Tenderers, if required; or
(b) fails or refuses to furnish the balance EMD and additional performance Security in accordance
with the instructions of Tenderers.
We undertake to pay to the Department up to the above amount upon receipt of his first
written demand, without the Department having to substantiate his demand, provided that in
his demand the Department will note the amount claimed by him is due to him owning to the
occurrence of one or both of the two conditions, specifying the occurred condition or
conditions.
This Guarantee will remain in force up to and including the date** …………………… after the dead
line for submission of Tenders as such deadline is stated in the Instructions to Tenders or as it
may be extended by the Department, notice of which extension(s) to the Bank is hereby
waived. Any demand in respect of this Guarantee should reach the Bank not later than the
above date.
WITNESS……………….. SEAL………………………………………………..
--------------------------------------------------------------------------------------------------------
* The Tenderer should insert the amount of the EMD in words and figures denominated in Indian
Rupee. This figure should be the same as shown in the NIT.
** 6 months for the deadline date for submission of Tender. Date should be inserted by the
Department before the Tender documents are issued.
WHEREAS__________________________________________________ ________
_____________________________________________________________________ _____ __
_____________________(name and address of Contractor ) (hereinafter called “the Contractor”) has undertaken, in
pursuance of Contract No. ________ dated: ____________ to execute the work of _________________ [name of
work];
AND WHEREAS it has been stipulated by you in the said Contract that the Contractor shall furnish
you with a Bank Guarantee by a Schedule bank for the sum specified therein as balance EMD / EMD for
compliance with his obligations in accordance with the Contract;
AND WHEREAS we have agreed to give the Contractor such a Bank Guarantee;
NOW THEREFORE we hereby affirm that we are the Guarantor and responsible to you, on behalf of
the Contractor, up to a total of _____________________ [amount of guarantee]
_________________________________ [in words], such sum being payable and we undertake to pay you,
upon your first written demand and without cavil or argument, any sum or sums within the limits of
________________________ [amount of guarantee] as aforesaid without your needing to prove or to show
grounds or reasons for your demand for the sum specified therein.
We hereby waive the necessity of your demanding the said debt from the Contractor before
presenting us with the demand.
This guarantee shall be valid upto ……………………….. i.e., until 28 days from the date of expiry of the
Defects Liability period.
Name of Bank_____________________________________
Address__________________________________________
Date_____________________________________________
AND WHEREAS we have agreed to give the Contractor such a Bank Guarantee;
NOW THEREFORE we hereby affirm that we are the Guarantor and responsible to you, on behalf of
the Contractor, up to a total of Rs._____________________ [amount of guarantee]
_________________________________ [in words], such sum being payable and we undertake to pay you,
upon your first written demand and without cavil or argument, any sum or sums within the limits of
________________________ [amount of guarantee] as aforesaid without your needing to prove or to show
grounds or reasons for your demand for the sum specified therein.
We hereby waive the necessity of your demanding the said debt from the Contractor before
presenting us with the demand.
We further agree that no change or addition to or other modification of the terms of the Contract or
of the Works to be performed thereunder or of any of the contract documents which may be made between
you and the Contractor shall in any way release us from any liability under this guarantee, and we hereby
waive notice of any such change, addition or modification.
This guarantee shall be valid upto and until 28 days from the date completion.
Name of Bank_____________________________________
Address__________________________________________
Date_____________________________________________
To
________________________________
________________________________
________________________________
Gentlemen:
In accordance with the provisions of the Conditions of Contract, Mobilisation advance for the
above-mentioned Contract, _________ _________________ [name and address of Contractor]
(hereinafter called “the Contractor”) shall deposit with ______________________ [name of Department]
a bank guarantee to guarantee his proper and faithful performance under the said Contract for an amount
of Rs.___________[amount of guarantee] 1 _____________________ ____ ______ ____ ______________(in
words).
We further agree that no change or addition to or other modification of the terms of the Contract
or of works to be performed thereunder or of any of the Contractor documents which may be made
between ____________________[name of Department] and the Contractor, shall in any way release us
from any liability under this guarantee, and we hereby waive notice of any such change, addition or
modification.
1
An amount shall be inserted by the bank representing the amount of the Advance Payment, and denominated in Indian
Rupees.
Yours truly,
Address:_____________________
Date:_____________________
2. Address :-
3. Tin :-
The above dealer has filed returns up to date (Month & Year ) and has paid Taxes due
there in.
The dealer has no pending arrears under APVAT Act 2005, CST ACT 1956 and
APGST ACT 1957, A.P.Entry Tax Act as on date.
This certificate is valid upto a period of Twelve months from the date of issue.
Date :
Place:
Assessing authority
Sub: (R&B) Department – NABARD works – Execution of bituminous items of work – Location of
HMP and temperature of mix – Certain instructions issued - Regarding
Ref: Arising
******
All the Superintending Engineers (R&B) dealing with NABARD works are informed that NABARD
officials had inspected certain works recently. They observed that in certain cases the location of the HMP is
at large distance to the work site due to which the temperature of the mix is not being followed.
In view of that all the Superintending Engineers (R&B) dealing with NABARD works are requested
to follow the instructions given below for all ongoing as well as future works.
1. The execution staff should make a practice to ensure the required temperatures of the mix. They shall
record the temperature of the mix at (i) the HMP, (ii) the time of coming to site, (iii) laying and (iv)
rolling.
2. In case of sub-base layers, the material shall be done mechanically by the mix-in-place method using
a rotavator or similar approved equipment and shall be spread with the help of motor grader of
adequate capacity.
3. The material for WMM shall be mixed using pug mill or pan type mixer of concrete batching plant.
The temperatures of mixes as per MORT&H (4th revision) are tabulated below:
(60/70 gr bitu)
All the Superintending Engineers are requested to execute the works strictly adhering to
the above instructions and as per MORT&H specifications in toto. All the Superintending Engineers
and Executive Engineers are instructed to inspect the HMPs in their jurisdictions before starting of
works. The Superintending Engineers shall give suitable instructions to all the field officers under
their respective jurisdictions in this regard.
Before starting of any BT work the Superintending Engineer and Executive Engineer
should inspect the HMP proposed for executing any particular work and satisfy themselves about the
temperatures attainable as prescribed above. They should individually submit a certificate clearly
delineating the motorable distance between HMP and site of work. It is observed and out of
experience in the past maintenance of above temperatures is virtually not possible in case the HMP is
located farther than 70 Km from site of work.
In the light of above experience the Superintending Engineers have to be cautious before
submitting these certificates and scrupulously follow the instructions failing which stringent
disciplinary action will be initiated against defaulters without any further notice.
NABARD
Copy to the Chief Engineer (R&B), Quality Control and Member COT with a request to give suitable
instructions to the QC staff to follow the above mentioned observations during their inspections and
give specific report about the compliance.
Circular Memo No: 1814 / DCE(N) / DEE 1 / AEE 2 / 2009 Dated : 29.01.2009
Sub: NABARD Works – RIDF-XIV – RIDF XIV(RIAD) – Wet Mix Macadam – Amendment to Table
400-11 of MORT&H for gradation limits – regarding
Ref: Arising
*** ***
All the Superintending Engineer(R&B) dealing with NABARD works are informed that an amendment
has been issued by the undersigned to the table 400-11 of MORT&H (4 th revision) pertaining to gradation
limits of Wet Mix Macadam proposed to be used in all NABARD works henceforth.
53.00 mm 100
45.00 mm 75-90
26.5 mm -
22.4 mm 45-70
11.2 mm 25-45
4.75 mm 20-25
2.36 mm 10-20
75 microns 0-4
N.B: No job mix where in upper limit of a particular screening and lower limit of
immediately subsequent screening as boundaries of mix is acceptable.
Further the Superintending Engineers are requested to mention the amended table 400-11(A) in the
technical specifications also.
NABARD
To