SL NO Description of Item Unit RATE

Centring and shuttering :


Labour Charges for Shuttering fixing & removing work in Foundation, raft
1 slab, raft beams etc. including all support complete as per the Engineer In- SqM 280
Charge.
Labour Charges for Shuttering fixing & removing work in Retaining Wall/Any
Wall (any thickness) etc. including all support complete as per the Engineer
2 SqM 260
In-Charge. (including staging & destaging at clear heights upto 4.5m).

Labour Charges for Shuttering fixing & removing work in all type of Slab,
3 Beam, Stair etc. including all support complete as per the Engineer In-Charge. SqM 280

Labour Charges for Shuttering fixing & removing work in all type of Column
4 etc. including all support complete as per the Engineer In-Charge (including SqM 280
staging & destaging at clear heights upto 4.5m).
5 Labour Charges for Shuttering making with wooden ply & batten . SqM 60
Labour Charges for Shuttering repairing/remaking with wooden ply & batten
6 SqM 40
.
7 Labour Charges for shuttering material lifting (per lift/per floor). SqM 7
Labour Charges for Gangway making fixing & removing for all type of
8 SqM 20
structures
9 Labour Charges for slab & beam stagging & destaging. Cum 25
Labour Charges for staging & destaging above 4.5 Mtr height (for Column &
10 Cum 28
RC wall)
Labour charges for scaffolding material shifting from hutment to site Vice
11 Trip 300
versa.
Reinforcement steel :
Labour Charges for Reinforcement cutting, bending & fixing all complete for
12 all types of dia as per the Engineer in Charge. (In Raft, footing & foundation MT 5300
etc.)
Labour Charges for Reinforcement cutting, bending & fixing all complete for
13 all types of dia as per the Engineer in Charge. (In Column, Slab, Beam & Stair MT 6500
etc.)
Labour Charges for Reinforcement Lifting for all type of dia. (by tower crane
14 MT 155
any level after 1st Floor)
Labour Charges for Reinforcement Lifting for all type of dia. (by manually per
15 MT 200
floor)
Labour Charges for Reinforcement shifting for all type of dia. (by manually)
16 MT 200

Terms & condition :


1) Above rates are excluding of GST.
2) All rates are inclusive of 12% labour PF, the same will be deducted from RA Bill. Based on actual labour report. If
vendor have PF registration, then have to submit ECR challan, wages sheet as a proof of PF compliance.
3) 5% Cash Retention will be deducted from every RA Bill.
4) TDS will be deducted as per the NORMS.
5) Considering consumption of binding wire 7KG/MT as per free issue material, excess quantity will be returnable or
debitable basis as per Reconciliation.
6) Considering consumption of Nails 150 GMS/SQM Shuttering & 200 GMS/SQM for board making as per free issue
material, excess quantity will be returnable or debitable basis as per Reconciliation.
7) Safety PPE will be issued as a returnable basis & will be debited if not return after used. Also vendor have to
follow KEC HSE policy & any penalty amount will be applied if not followed by vendor.
8) Any free issue material misussed by vendor/subcontractor, then any penalty will be applied and debited from
their bill.
9) Aadhar & bank account & other required for all labour are mandatory.

You might also like