COLLEGE OF SCIENCE AND TECHNOLOGY

SCHOOL OF ENGINEERING
Department of Civil, Environmental and Geomatics
Engineering

Y3-CSE&CGE: Individual Assignment No 1

The assignment will be submitted in hand written format on 21st Nov 2024.
Question One
Estimate the cost of a masonry platform 6m Χ 5m from the given drawing, specifications and
rates
Drawings

Page 1 of 4
General specifications

1. Foundation: Lime concrete


2. Masonry: 1st class brickwork in lime mortar
3. Flooring:
a. 2.5 cm cement concrete over 7.5 cm lime concrete
b. 2.5 cm cement concrete over wall only
4. Wall finishing : Outside walls are 12mm cement plastered 1:6
Rates

I. Earthwork in excavation……………4,500Rwf/Cum
II. Earthwork in filling…………………2,000Rwf/ Cum
III. Lime concrete in foundation……….. 102,500Rwf/Cum
IV. 1st class brickwork in lime mortar…. 45,000Rwf/Cum
V. 12 mm cement sand plastering 1:6…. 3,500Rwf/Sqm
VI. 2.5 cement concrete 1:2:4 floor over and including 7.5 cm lime
concrete……145,000Rwf/Sqm
VII. 2.5 cement concrete 1:2:4 Floor……………95,000Rwf/Sqm

Question Two

Prepare a detailed estimate of a shop shown in the figure below and calculate its cost with local
rates. Also find out the plinth area rate of the shop. Your Work for this part consists of the
following tasks: (1) Determine the quantities of works as per the provided BoQ. (2) Carry out the
analysis of rates (on local market) and determine the rate of each item of work in the provided
BoQ. (3) Find out the total amount of each item of work and thus the total estimated project cost.

You are required to use the BoQ provided to you.

Page 2 of 4
Plinth area =…………………….m2
Plinth area rate of the shop = Rwf…………………/m2

Page 3 of 4
Table 1: BoQ of Shop

S.No. Description of item Quantity Unit Rate in Rwf Amount


1. Excavation for foundations m3

2. Cement concrete in foundations (1:6:18).


m3

3. Reinforced cement concrete (1:2:4) lintels,


slabs including reinforcement up to 90
kg/cum. of concrete. m3
Damp proof course of cement concrete
4. (1:2:4), 4 cm. thick with 2 coats of bitumen,
20/30 penetration at 1.65 kg/sq.m. laid hot m2
and sanded

B.B. in cement mortar in foundations and


5. plinth. m3

6. B.B. in cement mortar in the superstructure. m3

7. Conglomerate flooring, 4 cm. thick over 10


cm. thick cement concrete (1:6:18) 10 cm. m2
thick sand.
(a) Topping, 4 cm. thick of cement (1:2:4).

8. Deodar wood doors and windows m2

9. Cement plaster 1.25 cm. thick (1:6) m2

10 Chocolate painting to Doors and windows m2


of an approved quality.
Total: Rwf

11. Provision for water supply and sanitary


arrangements @12.5%

12. Provision for electrification @7.5%

13. Provision for architectural appearance


@2%
14. Provision for unforeseen items 2%

15. Provision for P.s. and contingencies @4%

Grand Total: Rwf

Page 4 of 4