Assignment One Cce3161 Y3 Cse&Cge
Assignment One Cce3161 Y3 Cse&Cge
Assignment One Cce3161 Y3 Cse&Cge
SCHOOL OF ENGINEERING
Department of Civil, Environmental and Geomatics
Engineering
The assignment will be submitted in hand written format on 21st Nov 2024.
Question One
Estimate the cost of a masonry platform 6m Χ 5m from the given drawing, specifications and
rates
Drawings
Page 1 of 4
General specifications
I. Earthwork in excavation……………4,500Rwf/Cum
II. Earthwork in filling…………………2,000Rwf/ Cum
III. Lime concrete in foundation……….. 102,500Rwf/Cum
IV. 1st class brickwork in lime mortar…. 45,000Rwf/Cum
V. 12 mm cement sand plastering 1:6…. 3,500Rwf/Sqm
VI. 2.5 cement concrete 1:2:4 floor over and including 7.5 cm lime
concrete……145,000Rwf/Sqm
VII. 2.5 cement concrete 1:2:4 Floor……………95,000Rwf/Sqm
Question Two
Prepare a detailed estimate of a shop shown in the figure below and calculate its cost with local
rates. Also find out the plinth area rate of the shop. Your Work for this part consists of the
following tasks: (1) Determine the quantities of works as per the provided BoQ. (2) Carry out the
analysis of rates (on local market) and determine the rate of each item of work in the provided
BoQ. (3) Find out the total amount of each item of work and thus the total estimated project cost.
Page 2 of 4
Plinth area =…………………….m2
Plinth area rate of the shop = Rwf…………………/m2
Page 3 of 4
Table 1: BoQ of Shop
Page 4 of 4