Reinforcement Detailing Column

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

8-TOR @ 150 C/C.

COLUMN SCHEDULE(M25:Fe500)
8-TOR @ 75 C/C.

COLUMN C
NUMBER
FLOOR LVL.
M25 : Fe500 , COVER = 40MM
CONFINING ZONE = 500 MM

ROOF Z1 MAIN LINK Z1 OTHERS Z2 LINKS


T8 @ 150 T8 @ 150 T8 @ 200
TO
8-TOR @ 150 C/C. 450
2ND. FLOOR
AS/SCHEDULE
LAP ZONE(Z2)

300
T16
T20

8-T16 + 2-T20
M25 : Fe500 , COVER = 40MM
CONFINING ZONE = 500 MM

8-TOR @ 75 C/C.

2ND. FLOOR Z1 MAIN LINK Z1 OTHERS Z2 LINKS


PLINTH LVL. T8 @ 150 T8 @ 150 T8 @ 200
GROUND LVL. TO
450
L0 = Shall not be less than, FOUNDATION

300
a) Larger lateral dimension of the member,
T16
b) 1/6 of clear span of member, T20
c) 450 mm.

8-T16 + 2-T20

FOUNDATION

TYPICAL DETAIL OF COLUMN


REINFORCEMENT