Method Statement for TAM Grouting
Method Statement for TAM Grouting
Project :
Kwar H.E (jammu & Kashmir)
SUBMITTED TO:
Patel Engineering Ltd.
CLIENT:
Chenab Valley Power Projects
Pvt. Ltd.
Submitted by:
Super Engineering Works
09th Novemeber 2024
A) GENERAL
B) EQUIPMENTS
S.No. Equipment
1 Air compressor - 1 No.
2 Drilling Machine - 1 No.
3 Hand drill Machine - 1 No.
4 Grouting plant - 1 No.
5 Water storage Tank - 1 No.
6 Inflatable Packers Air Pump - 1 No.
7 Bentonite mixer (500lir) - 1 No.
8 Grinding Machine - 1 No.
9 Gas Cutting Sets - 1 No.
10 Welding Machine - 1 No.
11 Single Inflatable Packers - 1 No.
12 Double Inflatable Packers - 1 No.
S.No. Manpower
1 Supervisor - 1 No.
2 Mechanical Foreman - 1 No.
3 Driver - 1 No.
4 Driller - 1 Nos.
5 Pump,Packer & Recorder Operator - 2 Nos.
6 Helper - 6 Nos.
** Sequence & nos. of man power deployment can be change as per site requirement & circumstances
D) MATERIALS
S.NO. Materials
1 114mm-150mm Temporary casing - As per site required
pipes
2 Drilling System 114-150 mm - 1No.
3 Sleeves - As per site required
4 Tools & consumables - As per site required
5 Grout Pipes - as per site required - As per site required
6 Cement - As per site required
7 Bentonite - As per site required
8 Additives - As per site required
9 Electricity & water - Required at site
Note :- Item No. 6, 7 & 8 shall be supplied by Patel engg. Ltd @ free of cost
Item No. 9 shall be supplied & provide of PEL at nearest point of work.
E) Activity
1) Preparation of Working Platform.
2) Drilling of holes with casing up to desired depth
3) Fabrication & lowering of PVC pipes.
4) Sleeve Grouting
5) Extraction of temporary Casing
6) TAM grouting
7) Quality Control
[Super Engineering Works] Page 3
1. Preparation of working platform
The Working Platform shall be prepared for Truck mounted drilling machine to
access freely at the drilling spot, Storage of water tank, Grouting Plant and Welding
machine.
2. Drilling of holes
The Drilling in the loose soil and Boulders shall be done by installing a temporary
steel casing of (About 114mm dia. to 150mm) by using special bit following the
ODEX or equivalent system. With this methodology it is possible simultaneously to
drill the hole and install the casing with Pneumatic DTH drilling Rigs. The holes will
be drilled up to one meter below the rock. Length of drilling hole shall be considered
approximately 20 m.
4. Sleeve Grouting
The Sleeve grouting design was chosen such that it will form strong enough Sleeve
around the PVC pipe and preventing the grout migration along the PVC pipes up to
ground level but shall be weak enough to be fractured by the grout when opening
particular sleeve under pressure in the stage grouting. The mix shall be computed
during trial calibration at site.
NOTE:- ** TOR (TERM OF REFERENCE) & mix grout design shall be provide by Patel Engg. Ltd as per their
objective & expected strength.
6. Tam Grouting
The purpose of grouting to form a grout curtain to control the seepage and
consolidate the terrace and filled materials below the coffer dam.
Grouting is processes of filling voids, cavities & pore in soil replace the water or air
of the previous medium with grout.
7. Quality Control
Delhi Head Office :- 3682/38, IInd Floor, Shabi Market, Mori Gate, Delhi;-110006
Factory :- HR-12, Street No. 10, Anand Parbat Industrial Area, Delhi – 110005
Godown :- Generator Factory, Near Laxmidarm Kata, Across India Oil Pump,
Auchandi Border, Haryana
Nagpur :- 19, Link Road Sadar, Nagpur – 400001
Email :- supereng33@gmail.com
Contact :- +91-9312269671, +91-9999487154,