Hydropower Engineering II Module
Hydropower Engineering II Module
KOMBOLCHA INTUTE OF
TECHNOLOGY
Course Objective
In practice Hydraulic Engineers are required to design, construct and supervise various
types of Hydropower plants. The purpose of this module is to provide the students with
a solid knowledge and understanding of the principles governing the design and
analysis of the different hydropower scheme components and to provide them with an
opportunity to apply the design, construction and supervision procedures learned in
class to a "real life" Hydropower project.
Course Competencies
Students shall be able to
1. plan, design and analysis power house
2. plan, design and analysis transmission
3. plan and supervise rehabilitation and maintenance of hydropower
4. design full component of min hydropower plant
5. plan and supervise construction of hydropower plant
TABLE OF CONTENTS
1. HYDRAULIC TURBINES ......................................................................... 1
1.1 GENERAL ...............................................................................................................1
1.2 CLASSIFICATION .....................................................................................................3
1.3 CHARACTERISTICS OF TURBINES .............................................................................5
1.4 PROCEDURE IN PRELIMINARY SELECTION OF TURBINES ......................................... 17
1.5 TURBINE SCROLL CASE ......................................................................................... 19
1.6 DRAFT TUBES ....................................................................................................... 20
1.7 CAVITATION IN TURBINE & TURBINE SETTING ...................................................... 22
1.8 GENERATORS AND TURBINE CONTROLS ................................................................ 25
1.9 TURBINE CONTROL ............................................................................................... 27
2. HYDROPOWER PROJECT INVESTIGATION AND
PLANNING ....................................................................................................29
2.1 INVESTIGATION OF RESOURCES ............................................................................. 29
2.2 INVESTIGATION OF HYDROPOWER PROJECTS ......................................................... 29
2.2.1 PLANNING P ARAMETERS AND DATA...................................................................... 29
2.2.2 POWER M ARKET ................................................................................................... 30
2.2.3 SUPPLY SYSTEM:................................................................................................... 31
2.2.4 POWER M ARKET SURVEYS: ................................................................................... 32
2.2.5 DEMAND FORECAST: ............................................................................................. 32
2.3 HYDROLOGY ........................................................................................................ 33
2.3.1 FLOW DURATION STUDIES: .................................................................................... 33
2.3.2 ESTIMATION OF FLOW TO UNGAUGED SITES: .......................................................... 34
2.3.3 ENERGY AND POWER ANALYSIS USING FLOW DURATION APPROACH...................... 37
2.3.4 WATER PRESSURE OR „HEAD‟ ............................................................................... 38
2.3.5 RESIDUAL, RESERVED OR COMPENSATION FLOW .................................................... 38
2.3.6 TAIL WATER RELATIONSHIPS ................................................................................ 40
2.4 ESTIMATION OF PLANT CAPACITY AND ENERGY OUTPUT......................................... 40
2.5 RESERVOIR (STORAGE) CAPACITY ......................................................................... 47
2.5.1 AREA CAPACITY CURVES ..................................................................................... 49
2.5.2 RESERVOIR RULE CURVES .................................................................................... 49
2.5.3 EVAPORATION LOSS EVALUATION FROM RESERVOIRS............................................ 50
2.5.4 SPILLWAY DESIGN FLOOD ANALYSIS .................................................................... 50
2.6 GEOTECHNICAL STUDIES ....................................................................................... 51
2.6.1 METHODOLOGIES TO BE USED ............................................................................... 52
2.7 ENVIRONMENTAL ISSUES ...................................................................................... 53
2.8 PROJECT APPRAISAL AND SOCIO-E CONOMIC CONSIDERATIONS.............................. 54
2.9 PLANNING ............................................................................................................ 56
3. POWER PLANT STATIONS: CONVENTIONAL TYPE OF
POWER STATIONS .....................................................................................58
3.1 COMPONENTS OF HYDROPOWER PROJECTS ............................................................ 58
3.2 POWER HOUSE ...................................................................................................... 60
3.2.1 POWER HOUSE TYPES ............................................................................................ 60
3.2.2 POWER HOUSE PLANNING ..................................................................................... 61
3.2.3 COMPONENTS OF A POWER HOUSE ......................................................................... 64
i
3.3 LAYOUT AND DIMENSIONS OF POWER HOUSE ......................................................... 65
3.3.1 LAYOUT OF GENERATING UNITS FOR SMALL HYDROPOWER: .................................. 65
3.3.2 PRELIMINARY DIMENSIONS OF POWER HOUSE FOR MEDIUM AND LARGE HYDRO
(REACTION TURBINE INSTALLATION) .................................................................... 68
4. UNDER GROUND POWER HOUSE....................................................72
4.1 LOCATION OF UNDERGROUND POWER STATIONS ................................................... 72
4.2 ARRANGEMENTS OF UNDERGROUND POWER STATIONS ........................................... 73
4.3 COMPARING ABOVE–GROUND AND UNDERGROUND POWER HOUSE STATIONS
(BASICS FOR COMPARISON OF POWER STATION ALTERNATIVES).............................. 75
4.4 THE FUNCTIONS OF THE POWERHOUSE COMPLEX .................................................... 76
4.5 THE POWER HOUSE COMPLEX................................................................................ 77
4.5.1 MAIN CHARACTERISTICS OF UNDERGROUND POWER PLANTS .................................. 77
4.6 OVERALL PLANT LAYOUT ..................................................................................... 79
4.7 POWERHOUSE TUNNEL SYSTEM ........................................................................... 79
4.8 EXCAVATION EQUIPMENT AND CONSTRUCTION PROCEDURES................................. 81
4.9 TRANSFORMER ARRANGEMENTS AND LOCATIONS ................................................. 83
4.10 HYDROPOWER TUNNELS ....................................................................................... 84
4.11 ROCK STRESSES.................................................................................................... 89
4.11.1 STRESSES NEAR CORNERS ..................................................................................... 94
4.11.2 NORWEGIAN EXPERIENCE, EXAMPLES ................................................................... 98
4.11.3 ROCK STRESS MEASUREMENTS............................................................................. 98
4.11.4 MODELING ......................................................................................................... 100
4.11.5 TUNNELING METHODS ........................................................................................ 102
4.11.6 TUNNEL SUPPORTS ............................................................................................. 105
5. TRANSMISSION OF ELECTRIC POWER.......................................108
5.1 TRANSMISSION AND DISTRIBUTION (T&D) SYSTEM PLANNING ............................. 109
5.2 DESIGN PHILOSOPHY OF OVERHEAD LINES ........................................................... 111
5.3 FRAMEWORK OF A STANDARD ............................................................................. 112
5.4 RIGHT WAY OF PLANNING................................................................................... 113
5.5 TOWER SPOTTING ............................................................................................... 115
5.6 CONDITIONS INFLUENCING THE TOWER SPOTTING................................................ 115
5.7 TOWER DESIGN: (STATIC ANALYSIS AND DIMENSIONING BASED ON AGREED
STANDARDS) .................................................................................................................. 116
5.8 DESIGN OF FOUNDATIONS .................................................................................... 118
5.9 CONDUCTORS ..................................................................................................... 118
5.10 INSULATORS ....................................................................................................... 119
6. CONSTRUCTION FEATURES OF HYDROPOWER
PROJECTS ..................................................................................................120
6.1 RESERVOIRS ....................................................................................................... 120
6.2 CONCRETE DAM CONSTRUCTION ........................................................................ 122
6.3 INSTRUMENTATION OBJECTIVES AND DAM SAFETY ............................................. 129
6.4 DAM SAFETY PRINCIPLE AND CONCEPTS .............................................................. 131
ii
7. MINI HYDROPOWER PROJECT DEVELOPMENT
CONSIDERATIONS ...................................................................................134
7.1 DEFINITION ........................................................................................................ 134
7.2 ENERGY SUPPLIES IN RURAL AREAS .................................................................... 134
7.3 THE MINI HYDROPOWER DEVELOPMENT ............................................................. 135
7.4 FACTORS OF MHP DEVELOPMENT ....................................................................... 136
7.5 PREFERENTIAL POLICY FOR MHP DEVELOPMENT................................................. 137
7.6 FUNDING ............................................................................................................ 137
7.7 APPROPRIATE TECHNOLOGY FOR MHP ................................................................ 137
7.8 BENEFITS OF MHP.............................................................................................. 138
8. ENVIRONMETAL, SOCIAL AND POLITICAL FEASIBILITY
OF HYDROPOWER PROJECTS..............................................................139
8.1 RESERVOIRS ....................................................................................................... 142
8.2 WATER INTAKES, OPEN CANALS, PENSTOCKS, TAILRACES, ETC.: ........................... 142
8.3 IMPACTS ARISING FROM THE OPERATION OF THE SCHEME ..................................... 143
8.4 LANDSCAPE IMPACT ........................................................................................... 144
8.5 PRELIMINARY QUESTIONS ................................................................................... 145
8.6 CHECKLIST OF CONSIDERATIONS......................................................................... 146
8.7 EVALUATION METHODOLOGIES .......................................................................... 147
8.8 OTHER SOCIAL AND POLITICAL CONSIDERATIONS ............................................... 151
9. ECONOMIC AND FINANCIAL EVALUTION OF
HYDROPOWER PROJECTS ....................................................................153
9.1 INTRODUCTION ................................................................................................... 153
9.2 ECONOMIC AND FINANCIAL FEASIBILITY BASIC EQUATIONS CONCERNING TIME
VALUE……. ................................................................................................................... 154
9.2.1 ECONOMIC AND FINANCIAL FEASIBILITY .............................................................. 154
9.2.2 BASIC EQUATIONS CONCERNING TIME VALUE ...................................................... 155
9.3 COSTS AND BENEFITS ......................................................................................... 157
9.3.1 COSTS ................................................................................................................ 157
9.3.2 BENEFITS ........................................................................................................... 159
9.4 METHODS OF ECONOMIC APPRAISAL ....................................................... 160
9.4.1 THE NET PRESENT VALUE METHOD ...................................................................... 160
9.4.2 THE BENEFIT – COST RATIO METHOD ................................................................... 162
9.4.3 THE INTERNAL RATE OF RETURN METHOD............................................................ 163
9.5 METHODS OF FINANCIAL APPRAISAL .................................................................... 164
9.5.1 FINANCIAL CASH -FLOW ANALYSIS ....................................................................... 164
9.5.2 FINANCIAL BALANCE AND THE PAYBACK PERIOD OF THE LOAN ............................ 165
9.5.3 GENERATION COST AND PROFIT ANALYSIS ........................................................... 169
9.5.4 UNCERTAINTY ANALYSIS .................................................................................... 170
iii
Hydropower Engineering-II
1. Hydraulic Turbines
Based on the energy transfer and type of action, hydraulic machines are generally
divided in to two:
1.1. GENERAL
Hydraulic turbines may be considered as hydraulic motors or prime movers of a water
power development, which convert water energy (hydropower) in to mechanical energy
(shaft power).
The shaft power developed is used in running electricity generators directly coupled to
the shaft of the turbine, thus producing electrical power.
Activity:
Page 1
Hydropower Engineering-II
i. Water from rain and melting snow eventually reaches ponds, lakes,
reservoirs, or oceans where evaporation is constantly occurring.
iii. The flowing water causes the turbine to rotate, converting the water‟s
kinetic energy into mechanical energy.
iv. The mechanical energy produced by the turbine is converted into electric
energy by a turbine generator
Page 2
Hydropower Engineering-II
v. Inside the generator, the shaft of the turbine spins a magnet inside coils of
copper wire. It is a fact of nature that moving a magnet near a conductor
causes an electric current.
Page 3
Hydropower Engineering-II
1. Impulse Turbine:
All the available potential energy is converted in to kinetic energy with the help of
contracting nozzle/s. (eg. Pelton wheel)
2. Reaction Turbine:
The water enters to the turbine in a circumferential direction in to the scroll case and
moves into the runner through a series of guide vanes, called wicket gates.
The total energy partly converted to KE & substantial magnitude remains in the form of
PE (e.g. Francis, Kaplan, Propeller, Bulb, etc)
i) Based on head
Head is the elevation difference of reservoir water level and D/S water level.
a) Horizontal shaft
b) Vertical shaft
Page 4
Hydropower Engineering-II
P
N N
s 5
H 4
Where Ns = Specific speed
b). Turbine or synchronous speed: Since turbine & generator are fixed, the rated speed
of the turbine is the same as synchronous speed of the generator. The speed N, for
synchronous running is given by:
N 120 f
Where f = frequency cycle/sec (50-60 cycles/sec.) p
The speed of a turbine is an important parameter of design. The higher the speed, the
smaller the diameter of the turbine runner & the cheaper the generator coupled to the
turbine. High speed, however, makes a turbine more susceptible to cavitation.
c). Speed factor or peripheral coefficient,: The ratio of the peripheral speed, u, of the
bucket or vanes at the nominal diameter, D, to the theoretical velocity of water under
the effective head, H, acting on the turbine is called the speed factor or peripheral
coefficient, .
u r
But ω in rad/sec; 2 N
2gH 2 gH and r D / 2
60
DN DN
Therefore, Where, D and H in m; N in rpm
60 2gH 84.6 H
The following table suggests appropriate values of , which give the highest
efficiencies for any turbine, the head & specific speed ranges & the efficiencies of the
three main types of turbine.
Page 5
Hydropower Engineering-II
d). Runaway Speed: If the external load on the machine suddenly drops to zero (sudden
rejection) and the governing mechanism fails at the same time, the turbine will tend to
race up to the maximum possible speed, known as runaway speed. This limiting speed
under no-load, maximum-flow must be considered for safe design.
Page 6
Hydropower Engineering-II
Page 7
Hydropower Engineering-II
Where, CV is the coefficient of velocity of the jet which varies from 0.98 to 0.99.
P= ηߛQH
Where η in efficiency of the turbine, ߛis the specific weight of water, in N/m3, Q is
the flow rate in m3/S, H head in meters.
3. angle∅ߛisisthe
exitAngle ߛ- ∅ angle which varies from 10 to 20o and relation between ∅ and
ߛ=splitter
4. Diameter of the Jet (d): The diameter of the jet is obtained if flow rate is known.
Page 8
Hydropower Engineering-II
5. Speed ratio ( u/vj): The speed ratio is the ratio of the velocity (u) of the wheel at
pitch circle to theoretical velocity of the jet.
In practice the value is between 0.44 and 0.46 and average is 0.45.
6. Mean Diameter of the Wheel (D): It is the diameter between centre of the buckets.
The diameter can be obtained from peripheral velocity (u)
7. Jet ratio (m): The ratio of mean diameter of the wheel to diameter of the jet. m = D/d
8. Size of the buckets: The length, width and depth of buckets in terms of diameter of
jet‟d‟ is shown in Fig. below.
9. Number of Jets (n): Pelton wheels are single jet or multiple jets. When large power is
required the flow rate required also increases and then multiple jets required. The jet
should have sufficient spacing so that jet strikes one bucket at a time. Ordinarily not
more than four jets are provided for horizontal turbine. A vertical Pelton turbine with
six jets can be used.
Page 9
Hydropower Engineering-II
10. Number of buckets (z): The number of buckets is usually obtained from the
following empirical formula given by Taygun:
Turbines are usually coupled to an electric generator and the generator must run
at constant speed to maintain frequency of supply constant.
It is also desirable to run turbine at maximum efficiency and therefore speed
ratio u/Vj must remain same which means the jet velocity must not change.
The only way to adjust the load is to change hydraulic power input given by
p= γQH
Thus flow rate will change by changing the area of the jet or more closely the
diameter of the jet. This is accomplished by a spear valve and deflector plate
shown in Fig. below.
Page 10
Hydropower Engineering-II
Example-1. A Pelton turbine develops 8 MW under a head of 130 m at a speed of 200 rev/min.
The following are the particulars of Pelton wheel.
Determine:
–number of buckets
Page 11
Hydropower Engineering-II
Solution:
Page 12
Hydropower Engineering-II
The water after doing the work leaves through the draft tube. Essentially a
diffuser type whose area increases in the direction of the fluid flow. As area
increases velocity decreases.
A Francis turbine is suitable for medium heads (45 to 400 m) and requires a
relatively large quantity of water.
Water particle
R a d i a l v i e w
runner guide vanes and stay vanes
Page 13
Hydropower Engineering-II
The number of runner vanes varies from 16 to 24. The number of runner vanes
should be either one more or less than the number of guide vanes to avoid
periodic impact.
Francis turbine usually drives an electric generator, and hence the speed must
remain constant. Since the total head available is constant it is not desirable to
control flow rate by a valve due to hydraulic losses.
The flow rate in Francis turbine is controlled by varying the flow area in
between the adjustable guide vanes. The guide vanes are hinged at the center to
a circular ring. The area in between the vanes is varied by varying the guide
vane angle u
The regulation of guide vanes is done by servo mechanism. As load on
the turbine decreases the piston of servo mechanism Ir,l>ves to the right
and this causes the movement necessary to close the gates.
Page 14
Hydropower Engineering-II
Guide vanes
Page 15
Hydropower Engineering-II
Propeller and Kaplan turbines are axial flow reaction type turbines, suitable for
low head and high discharge.
In the propeller type only guide vanes are adjustable with fixed runner blades
while The Kaplan turbine is fitted with adjustable runner blades and both guide
vanes and runner blades act simultaneously.
Page 16
Hydropower Engineering-II
1. Net head
3. Rotational speed
4. Overall cost
1. Net head
The first criterion to take into account in the turbine's selection is the net head.
Page 17
Hydropower Engineering-II
2. Range of discharge
The range of discharge is an important factor for selecting the appropriate type
of turbine. It is necessary to know the flow regime, commonly represented by
the Flow Duration Curve (FDC)
Page 18
Hydropower Engineering-II
3. Specific speed
A scroll casing/volute is the conduit directing the water from the intake or penstock to
the runner in reaction type turbine installation.
A spiral shaped scroll case of the correct geometry ensures even distribution of water
around the periphery of the runner with the minimum possible eddy formations.
The cross-sectional area of this casing decreases uniformly along the circumference to
keep the fluid velocity constant in magnitude along its path towards the stay vane/guide
vane.
Page 19
Hydropower Engineering-II
A draft tube is a conduit discharging water from the turbine runner to the
tailrace.
The most common is elbow type which minimizes the depth of substructure compared
to vertical cone; it also has a desirable effect in directing the flow in the direction of the
tail water.
Elbow-type Draft
Tube
Page 20
Hydropower Engineering-II
Straight
Conical Draft
Tube
Tail Race
Draft tube discharges water in the tail race, which may lead it to the same
stream or to another.
The channel into which the water is discharge after passing through the
turbines is known as the Tailrace.
If the power house is close to the stream the outflow may be discharged
directly into the stream. But, when the stream is far off from the power
house, construction of tailrace channel or tunnel is necessary.
The tailrace must be designed properly and should not be neglected.
Proper design and maintenance is necessary so as to avoid excessive
aggradations (i.e. silting) or degradation (i.e. scouring) of the bed.
Page 21
Hydropower Engineering-II
When the hydrodynamic pressure in a liquid flow falls below the vapor pressure
of the liquid, there is a formation of the vapor phase.
Such phenomenon induces the formation of small individual bubbles that are
carried out of the low-pressure region by the flow and collapse in regions of
higher pressure.
The formation of these bubbles and their subsequent collapse gives rise to what
is called cavitation.
Experience shows that these collapsing bubbles create very high impulse
pressures accompanied by substantial noise (in fact a turbine undergoing
cavitation sounds as though gravel is passing through it). The repetitive action
of such collapse in a reaction turbine close to the runner blades or hub for
instance results in pitting of the material.
Cavitation results in pitting, vibration and reduction in efficiency and is
certainly undesirable.
In a relatively short time the turbine is severely damaged and will need to be
shut-off and repaired – if possible.
From the above equation the maximum permissible turbine setting Ys, max
(elevation above tail water to the center line of the propeller runners or to the bottom of
the Francis runners) can be written as (Thoma‟s formula)
If Ys is negative or positive the runner must beset below or above the tail water
respectively.
Page 22
Hydropower Engineering-II
Typical values of σc for reaction turbines, versus their specific speeds, are shown in
Table below.
The preliminary calculations of the elevation of the distributor above the tail water
level (Yt) suggest the following empirical relationships (based on knowledge of the
existing plants (Doland, 1957)):
Page 23
Hydropower Engineering-II
Example:
Page 24
Hydropower Engineering-II
Page 25
Hydropower Engineering-II
grids where their output is an insignificant proportion of the power system load. Their
efficiency is 2 to 4 per cent lower than the efficiency of synchronous generators over
the entire operating range. In general, when the power exceeds 5000 kVA a
synchronous generator is installed.
Recently, variable-speed constant-frequency systems (VSG), in which turbine speed is
permitted to fluctuate widely, while the voltage and frequency are kept constant and
undistorted, have entered the market. This system can even „‟synchronize‟‟ the unit to
the grid before it starts rotating. The key to the system is the use of a series resonant
converter in conjunction with a double feed machine. Unfortunately its cost price is still
rather high and the maximum available power too low.
The working voltage of the generator varies with its power. The standard generation
voltages are 380 V or 430 V up to 1400 kVA and at 6000/6600 for bigger installed
power. Generation at 380 V or 430 V allows the use of standard distributor
transformers as outlet transformers and the use of the generated current to feed into the
plant power system. Generating at medium voltage requires an independent transformer
MT/LT to supply the plant services.
Turbines are designed for a certain net head and discharge. Any deviation from these
parameters must be compensated for, by opening or closing control devices such as the
wicket-vanes or gate. The generator becomes overloaded and the turbine slows-down.
In this case there are basically two approaches to control the runner speed: either by
controlling the water flow to the turbine or by keeping the water flow constant and
adjusting the electric load by an electric ballast load connected to the generator
terminals.
Page 26
Hydropower Engineering-II
In the second approach it is assumed that, at full load, constant head and flow, the
turbine will operate at design speed, so maintaining full load from the generator; this
will run at a constant speed. If the load decreases the turbine will tend to increase its
speed. An electronic sensor, measuring the frequency, detects the deviation and a
reliable and inexpensive electronic load governor, switches on preset resistances and so
maintains the system frequency accurately.
The controllers that follow the first approach do not have any power limit. The
Electronic Load Governors, working according to the second approach rarely exceeds
100 kW capacities.
Page 27
Hydropower Engineering-II
The most commonly-used type is the oil-pressure governor that also uses a fly ball
mechanism lighter and more precise than that used in a purely mechanical governor.
When the turbine is overloaded, the fly balls slowdown, the balls drop, and the sleeve
of the pilot valve rise to open access to the upper chamber of the servomotor. The oil
under pressure enters the upper chamber of the servomotor to rotate the wicket-gates
mechanism and increase the flow, and consequently the rotational speed and the
frequency.
Page 28
Hydropower Engineering-II
Several planning parameters and comprehensive data and information are needed for
investigation of hydropower resources and planning of hydropower projects. The main
data are derived from:
Forecast of demand for electricity, and from studies of:
- hydrology - geology, soils and materials
- topography
Important issues, indirectly part of the planning process, are:
- environmental constraints - electricity tariffs, and tariff policy
- socio-economic considerations
Page 29
Hydropower Engineering-II
These issues influence project planning and project formulation and also contribute to
project costs
A lot of planning information can be derived from the demand curves of supply
systems. They will indicate need for regulation of watercourse contemplated for
development as they give information on the water needed for generation on a daily,
seasonal and annual basis. Such demand curves also provide data needed to determine
the size of generation, installations, and unit size and transmission facilities.
The minimum installation in the development should at least satisfy the energy and
power demand required by the load curve often termed as firm power or energy and the
maximum size can also be fixed by referring the peak demand.
140
M a x im u m
120
100
C o ld
80
60
S e a s o n a l V a r ia ti o n
40
Load (MW)
M a x im u m
20
Hot
0
0 3 6 9 12 15 18 21 24
Tim e o f O c c u r e n c e (H r s )
Page 30
Hydropower Engineering-II
“surplus” as the alternative to generation is letting the water runoff (spilling). Some of
the river discharge is by nature firm, usually the minimum flow, but its share of the
total discharge can be increased by introducing regulation of the river, i.e. provision of
storage reservoirs from which water can be drawn during dry periods.
The value of having guaranteed supply of water and the additional costs involved in
regulation is reflected in the price of electricity and firm supply commands a higher
price than secondary and surplus power and energy.
The highest priced energy, however, is often the supply termed “peaking”. By peaking
is meant the load which can be supplied to meet the variation in demand in a supply
system. It is measured as excess of the average demand over a period of time, day,
season or year.
Page 31
Hydropower Engineering-II
1400
Power Dura tion Curve
300
1200
250
1000
200
P o w e r (X 1 0 3 K W )
800
F low
150
600
0
0
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% 0% 20% 40% 60% 80% 100%
% of time f low equalled or exceeded
% tim e flow equalled or exceeded
In order to achieve a balanced and orderly development of the power supply to an area,
the planning has to be based on reliable knowledge of the market, the present and the
future demand. Power market surveys are means of evaluating the present and potential
markets for electric energy in a defined area.
The market survey will consider the effects on the use of electric energy within the
survey are of such factors as:
- geographical location - the economic status and prospective
- natural resources growth of the population
- industrial development - substitution loads
- new power uses
Page 32
Hydropower Engineering-II
2.3 Hydrology
Hydrological studies will provide data on the flow of water, one of the main parameters
used in hydropower planning.
Precipitation and hence water supply, varies widely between geographical locations,
from season to season and from year to year. Each of these variations has a profound
effect on the planning for the control and use of water resources.
The generation of hydropower does not imply consumption of water except as a result
of incidental evaporation, especially from reservoirs. The extent to which power
production will affect the use of water for other purposes will depend on a number of
factors such as:
- the location and capacity of power plants
- the nature of power to be produced, that is, RoR power, firm power or peaking
power
- the amount of fore bay and after bay regulation provided
- and the relative preference assigned to the uses of water for various purposes
The determination of the water requirement for power production is probably best
accomplished by “trial and error” methods including incremental analyses and will
require close coordination and integration of power, economic and social studies.
Hydrological data:
- `historical series of daily or monthly flows
Rainfall data:
- historical series of daily, monthly or annual total of rainfall
Basic hydrological studies are required mainly to determine water discharge and
hydraulic head.
A useful way of treating the time variability of water discharge data in hydropower
studies is by utilizing flow duration curves. A flow duration curve is a plot of flow
versus the percent of time a particular flow can be expected to be exceeded.
Methods of computing:
- rank-ordered technique - class-interval technique
Page 33
Hydropower Engineering-II
10000
Gage 4
Gage 3
1000
Gage 2
Flow
Gage 1
100
10
0 10 20 30 40 50 60 70 80 90 10
Exceedence Percentage
Page 34
Hydropower Engineering-II
The basic approach in regulated and sequential flow analysis can be explained by
referring to the physiographic layout of figure 2.4. In this case a measured record for a
considerable length of time is assumed to be available at reservoir outlet A. the
location for which flow data are needed is at point B. the flow at B is the inflow from
an area of considerable extent where there is no stream gauge record, plus inflow from
the operations of a reservoir at station A. First an estimate must be made of the average
annual runoff from area. This is done by planimetering the isohyetal map of normal
annual precipitation and getting the normal annual water input into area, the volume of
water per year.
o b t a in f r o m e n t it y
1 . R e s e rv o ir O u t fl o w
o p e r a t in g r e s e r v o ir
r e c o r
( lo c a t io n a t A )
2 . D e t e rm in e P la n im e t e r N . A . P .
m a p s a n d e s t im a t e
a v e r a g e a n n u a l
c o e f f ic ie n t o f r u n o f f .
r u n o ff fr o m u n g a u g e d
( L o c a t io n i s B
t r ib u t a ry a re a . c o n s id e r in g a r e a M )
3 . C o m p u t e
S e e s e q u e n t ia l
s e q u e n t i a l fl o w fr o m f lo w a n a ly s is
u n g a u g e d t rib u t a r y f lo w c h a r t
a r e a .
T h is is s im p le
4 . S u m o u t flo w s
s e q u e n t ia l a d d it i o n o f
fr o m u n g a u g e d c a lc u la t e d in f lo w f r o m
t r ib u t a ry a re a a n d u n g a u g e d a r e a p lu s
r e s e r v o ir o u t fl o w o b s e r v e d r e s e r v o ir
5 . P e r fo r m 6 . P e r fo r m U s e s ta n d a r d
flo w d u ra t io n o r s e q u e n t ia l h y d r o lo g ic
a n a ly s is flo w a n a ly s is t e c h n iq u e
Figure-2.4: Method for determining flow duration of regulated flow combined with un-
gagged inflow
Page 35
Hydropower Engineering-II
D i s t r ib u t io n o f f lo w a t
C h o o s e g a u g e m u s t b e
re p re s e n ta t ive r e p r e s e n t a t iv e o f
s t re a m g a u g e w h a tc a n b e e x p e c te d
s t a t io n C f ro m u n g a u g e d t r ib u t a r y
a re a M
a i = f l o w v o lu n e f o r p e r io d I
d iv id e d b y t o t a l v o lu m e f o r
e n t i r e p e r io d I t o n
w h e r e a i = in c r e m e n t a l f lo w
C o m p u t e i n c r e m e n t a l flo w f r a c t io n f o r p a r t i c u l a r p e r i o d i
f r a c t i o n fo r r e p r e s e n t a t i v e i w i l l b e s e q u e n t ia ll y e a c h
g u a g e a t s t a t io n C n u m b e r f r o m 1 to n
n = n u m b e r o f t i m e p e r i o d s in
e n t i r e r e c o r d o f f lo w s a t
s t a t io n C ( m o n t h s , d a y s )
q B M i = a iQ R m /t
w h e r e q B M i = in f lo w f r o m u n g a u g e d
t r ib u t a r y a r e a M f o r p e r io d i
C o m p u te u n g a u g e d
Q R = a v e r a g e a n n u a l r u n o f f in
t r i b u t a r y a re a i n flo w v o l u m e u n it s f o r a r e a M
m = n u m b e r o f y e a r s in e n t i r e p e r i o d
b e tw e e n i = 1 a n d i = n
t = t i m e u n it s f o r e a c h p e r i o d
P ro c e e d to s u m
w it h re u la te d
o u t f l o w s fr o m r e s e r v o i r
Figure-2.6: Flow diagram for computing sequential flow magnitudes from ungagged
tributary area.
A sequential flows coming off area must be computed. The time increments or periods
must correspond to the records of discharge available from reservoir operation. First a
flow record at station C must be obtained and studied. The record at C is assumed to
have the same time distribution of flow as the runoff coming off area. An incremental
fraction of flow, ai, for an increment of time in the total desired time period must be
obtained for the representative gauge C. Figures 2.4 and 2.3 give flow diagrams for a
step by step procedure to calculate the sequential inflow from the un-gauged area
labeled in figure 2.5. Once the sequential flows have been calculated it is a simple
procedure to add, sequentially the flow from the un-gauged tributary to the regulated
flows.
Page 36
Hydropower Engineering-II
In regions where stream flow does not vary with respect to the contributing drainage
area flow duration curves can be plotted for the gauged sites. From these flow duration
curves are developed a family of parametric duration curves in which flow is plotted
against the average
The product of this coefficient and the computed normal annual precipitation input to
the basin and the basin area can be used to calculate the average annual discharge as:
kPA
Q
T
2.3.3. Energy and Power Analysis using Flow Duration approach
In processing regulated and unregulated flow data, it is important to recognize that in
the power equation, flow is the primary limiting factor. When a Run-Off-River type of
power study is done and a flow duration analysis is used, the capacity or size of the
hydropower units determines the maximum amount of water that will go through the
unit or units. This is dictated by the nominal runner diameter and the accompanying
outlet area and draft tube.
In the figure below Qc is the discharge capacity of the plant under the design head. This
Qc is the discharge at full gate opening of the runner under design head. Even though to
the left of Qc on the flow duration curve the stream discharge is greater, it is not
possible to pass the higher discharge through the plant. If the reservoir or pondage is
full, water must be bypassed by a spillway.
To the right of the runner discharge capacity point, Qc, it should be noted that all the
water that can go through the turbine is the amount flowing in the river at the particular
percent of time point. This shows that full-rated power production will not be produced.
With pondage it is possible to alter this for short periods of time, but the total amount
of energy output cannot be increased.
If hydraulic head and the expected losses in the penstock are known, it is possible to
generate a power duration curve from the flow duration curve.
Page 37
Hydropower Engineering-II
Page 38
Hydropower Engineering-II
100
Q (m3/s)
10
Runner Discharge Capacity point
1 Qc
0 10 20 30 40 50 60 70 80 90 100
Exceedence percentage
100
developer to keep the residual flow as small as is acceptable to the licensing authority,
since in seasons of low flow, its release may mean generation being stopped if there is
insufficient discharge to provide for the turbine. On the other hand the lack of flowing
water can endanger the life of the aquatic biota
Page 39
Hydropower Engineering-II
As release of water over spillways and other releases in to the stream immediately
below a hydropower plant are made, the tail water elevation below the outlet to the
turbine will fluctuate. Therefore, it is important to develop a tail water elevation versus
discharge curve over the complete range of flow that is to be expected. Preparing such a
curve requires an adequate contour map of the channel area and an estimation of
velocity in the channel at various stages of flow. Information on normal tail water,
maximum tail water, and minimum tail water elevations is necessary to determine
design head and to determine the appropriate turbine setting. Estimating stream channel
velocity can be made using slope-area calculations that involve conventional
Manning‟s open-channel-flow equation.
Page 40
Hydropower Engineering-II
for other design flows in order to choose, the one that yields the best results. Once the
design flow is defined (Qm-Qres), and the net head is estimated, suitable turbine types
must be identified. The suitable turbines are those for which the design flow and head
plot within the operational envelopes (figure 2.11). Every selected turbine has a
minimum technical flow (with a lower discharge the turbine either cannot operate or
has a very low efficiency) and its efficiency is a function of the operating discharge.
The gross average annual energy (E in kWh) is a function
Page 41
Hydropower Engineering-II
Page 42
Hydropower Engineering-II
Thus one must recognize that determination of plant capacity requires analyses that
vary the different parameters in equation (1.2) while applying economic analysis.
Limits of use of turbine types
For practical purposes there are some definite limits of use that need to be understood
in the selection of turbines for specific situations. Impulse turbines normally have most
economical application at head above 300 m.
For Francis turbines the units can be operated over a range of flows from approximately
50 to 115% best efficiency discharge. Below 40%, low efficiency, and rough operation
may make extended operation unwise. The upper range of flow may be limited by
instability or the generator rating and temperature rise. The approximate limits of head
range from 60 to 125% of design head.
Propeller turbines have been developed for heads from 2 to 70m but are normally used
for heads less than 30 m. For fixed blade propeller turbines the limits of flow operation
should be between 75 and 100% of best-efficiency flow. Kaplan units may be operated
between 25 and 125% of the best efficiency discharge. The head range for satisfactory
operation is from 20 to 140% of design head.
Page 43
Hydropower Engineering-II
100
90
10000
80
70
D is c h a rg e ( Q )
Available flow
60
20% 1000
50 Turbine#1
30%
40
40% Turbine#2
30 Turbine#3 100
70%
20
Turbine#4
10
0
10
0 10 20 30 40
Percen5t0of tim
60
e 70 80 90 100 10 100 1000 10000
Average annual runoff (R)
Figure-2.12: Effective use of multiple units Figure 2.13: Parametric flow duration curve
Page 44
Hydropower Engineering-II
Example is presented how to optimize the most economical installation. The computation is
done following the steps given in the flow chart. In table 2.2 the energy for each increment of
10% of the time is determined by considering the average output for the increments. The total
energy is then the sum of the 10 increments.
In table 2.2, the second row gives the value for various flow capacities for alternative sizes of
power plants. In the example the plant capacity was varied from 11.68 MW to 6.28 MW. Using
flow capacities for 0, 8, 10, 20, 30 and 40 expedience percentages, and the table was completed
to determine net annual benefits and thus most economical size of unit. This required a
determination of the project life and the discount rate for money necessary for capital
investment. The capital recovery cost was computed using a 7% discount rate and a plant life
of 40 years. The investment and annual operating costs are estimated.
The annual benefit is computed multiplying the energy produced by the unit sale value. In this
case 0.26 Birr/Kwh is used for the unit sale. Plotting annual costs and benefits against the
installed capacity will then permit a determination of the optimum plant capacity by showing
where the maximum benefit or where marginal benefit equals marginal cost. This is shown in
figure 2.15, where the optimum installation is shown as 10 MW.
Page 45
Hydropower Engineering-II
Page 46
Hydropower Engineering-II
2 . D e t e r m in e h e a d w a t e r e le v a t io n a t e a c h f lo w
c h a r a c t e r is t ic s b y f lo w d u r a t io n c u r v e . O n R u n - o f r iv e r
p la n t s t h is is o ft e n c o n s t a n t
3 . D e t e r m in e t a il w a t e r e le v a t io n a t e a c h f lo w
c h a r a c t e r is t ic s b y t h e f lo w d u r a t io n c u r v e
4 . E s t im a t e h e a d lo s s t h r o u g h h y d r o s y s te m s . T h is w ill
v a r y w it h p e n s t o c k a n d d r a f t t u b e
5 . C o m p u te a n e t h e a d f o r e a c h o f t h e flo w s
c h a r a c t e r iz e d . N o t e : a s r iv e r f lo w s in c r e a s e , t a il w a t e r
r is e s a n d r e d u c e s n e t h e a d
6 . E s t im a t e p la n t e ff ic ie n c y . T h is c a n b e m a d e
c o n s t a n t f o r p r e - f e a s i b i l it y l e v e l d e s ig n
7 . C h o o s e a w h e e l o r p la n t c a p a c it y f lo w . T h is f u ll- g a t e
f lo w w i ll b e lim it e d b y r u n n e r d ia m e t e r a n d s e le c t e d
p e n s to c k s iz e
8 . C o m p u t e p la n t d is c h a r g e a t a ll f lo w v a lu e s f o r e a c h
e x c e e d e n c e p e rc e n ta g e . N o t e : a t r iv e r f lo w s g r e a t e r
t h a n p la n t c a p a c it y t h e p la n t d is c h a r g e m a y b e le s s
th a n d e p e n d in g o n t h e n e t h e a d
9 . C o m p u te p o w e r o u tp u t a t e a c h p e r c e n t t im e u n d e r
in v e s t ig a t io n
1 0 . C o m p u t e a n n u a l e n e r g y o u t p u t f o r g iv e n p la n t
c a p a c it y . R e p e a t t h is f o r f o u r t o f iv e p la n t c a p a c it ie s .
1 1 . E s t im a t e t h e a n n u a l p la n t c o s ts f o r e a c h o f t h e
p la n t c a p a c it ie s in v e s t ig a t e d , u s in g e s t im a t in g c u r v e s .
1 2 . W it h a n n u a l e n e r g y o u t p u t c a lc u la t e p la n t b e n e f it s
b a s e d o n a v e r a g e e x p e c t e d v a lu e o f p o w e r , B ir r / K W h
1 3 . P lo t a c u r v e o r d e v e lo p t a b le t o s h o w w h e re
m a x im u m n e t b e n e f it is o b t a in e d
Page 47
Hydropower Engineering-II
S ele c t io n of M o s t E c o no m ic In s ta llat io n
1 7. 00
To t al A nn u al C os t
Annual Benefits/Cost (mBirr) 1 6. 00
1 5. 00
A nn u al be n efits
1 4. 00
A n n ua l b e ne fits
1 3. 00
1 2. 00
Tot a l A n n ua l C o s t
1 1. 00
1 0. 00
6. 00 7 . 00 8 . 00 9 .0 0 1 0. 00 11 .0 0 1 2 . 00
Ca p ac ity of H y d rop lan t (M W )
Storage(1)
Dam(2)
Appurtenant Structure: Intake andSpillage Structures:
Spillage Structure: Spillway(5)
Intake: Service Intake (3) andBottomOutlet (4)
Surveillance Structure (inDam, inFoundationaswell asValleySides)
Diversion(6)
Service Road(7)
Page 48
Hydropower Engineering-II
Mass Curve
700
600
500
e d
Accumulated Volume
Required
m e er
u
400
Lin u
l i
Storage
o q
300
d
St
Deman
200
V 400 e
d 100 R
e et
g
la
r au
m 3000 to
u S
c
c 0 2 4 6 8 10 12 14
A
200 Time
100
Figure-2.17:
0 Reservoir capacity determination: Mass Curve Procedure
0 2 4 6 8 10 12 14
Time
2.5.1 Area Capacity Curves
When releases from reservoir are made, the schedule of releases is often dictated by
considerations other than just meeting the flow demands for power production. The
needs for municipal water supply, for flood control, and for downstream irrigation use
dictates certain restraints. The restraints are conventionally taken care of by developing
reservoir operation rule curves that can guide operating personnel in making necessary
changes in reservoir water releases.
Page 49
Hydropower Engineering-II
To be effective, rule curves often require the use of rather careful and extensive
reservoir operation studies using historical flow data and estimates of demand for water
that are likely to occur in the future.
5.E+07
1.E+08
2.E+08
2.E+08
3.E+08
3.E+08
4.E+08
4.E+08
3100
3050
3000
Elevation
Elevation
2950
2900
2850
2800
3500
3000
2500
2000
1500
1000
500
.
Figure-2.18: Typical area-capacit y curve
Many hydropower developments require a dam or a diversion that blocks the normal
river flow. This then requires that provision be made for passing flood flows. Spillway
design flood analysis treats a unique type of hydrology that concerns the occurrence of
rare events of extreme flooding. Flood frequency analysis is a well-defined procedure
for spillway design flood determination. It is customary on large dams and dams where
Page 50
Hydropower Engineering-II
failure might cause a major disaster to design the spillway to pass the probable
maximum flood. For small dams, spillways are designed to pass a standard project
flood.
Page 51
Hydropower Engineering-II
Page 52
Hydropower Engineering-II
Page 53
Hydropower Engineering-II
although they may also have considerable positive effects, such as flood mitigation,
fish production, recreation facilities, water sports, etc.
The hydropower development cycle consists of three main parts, each covering on the
three periods in the life of hydropower projects:
- Preconstruction - Implementation - Operation
Development of hydropower follows well defined stages. Each stage takes the project a
step forward in the development cycle, based on the findings from the actual and
previous stages.
The major part of investigations, planning and design takes place in the first phase.
Normally, the investigation and planning of hydropower projects pass several
milestones before projects are accepted for implementation.
Page 54
Hydropower Engineering-II
Page 55
Hydropower Engineering-II
2.9 Planning
The hydropower development cycle
Pre-Feasibility Feasibility
Studies Studies
DESIGN PHASE
IMPLEMENTATION PHASE
PREFEASIBILTY
STUDIY DESIGN AND DETAIL COMMISIONING OPERATION OF
PROCUREMENT DESIGN OF WORKS INSTALLATIONS
WORK
RECONNAISSANCE
STUDIES
Page 56
Hydropower Engineering-II
Page 57
Hydropower Engineering-II
Page 58
Hydropower Engineering-II
Main components:
Dam: to create the head necessary to move turbines and impound. Storage is used to
maintain the daily or seasonal flow variations.
Penstock: conveys water from the intake structure to the power house and can take
many configurations, depending up on the projects layout. For multi-unit installations it
is often desirable to serve several Units with a single penstock, and manifolds or
bifurcation structures are provided to direct flow to individual units.
Surge tanks: Flow through a penstock can change rapidly during the operation of
power plants. As long as flow is steady and constant, pressure changes on the
conveyance conduits are minimal. However, pressure changes within the conduit
become greater as the rate of change of flow increases. This phenomenon is known as
water hammer and is caused by a change of momentum within the water column. When
there is a rapid changes in flow water hammer effects can become serious. Surge tanks
are constructed on the conduit to reduce momentum changes due to water hammer
effects.
Surge tanks are often necessary in medium and high head hydropower projects,
particularly where there is a considerable distance between the water source and power
plant. Surge tanks or chambers can also be provided on the draft tube where discharge
conduits are very long.
Page 59
Hydropower Engineering-II
The selection of powerhouse configuration and structure should be based upon both
Fixed Operation and Maintenance (O&M) costs. The lower capital cost associated with
outdoor and semi-outdoor power plants is often offset by increased equipment and
Operation and Maintenance costs. The final selection of powerhouse for any given site
would be made after a detailed cost study, usually performed in the feasibility design
stage
Page 60
Hydropower Engineering-II
The basic requirement of a power house is the functional utility and the aesthetic
requirements. Planning the power house should be harmonious with the surrounding.
A power house of a hydropower may be
i. Surface Over ground power house ii. Underground power house
A surface power house has no space limitation where as an Underground power house
has space limitation. The surface power houses need an architectural planning so that
they fit in with the general landscape. If a particular area is affected by landslides and if
the underlying geology is suitable, an underground powerhouse is the obvious choice.
For low head power plant and small scale developments surface power house is the
economical choice
Design of the powerhouse is primarily a structural and architectural problem and the
size of the building is governed by the requirements to accommodate the generator, the
spiral casing and the outlet area of the draft tube.
For feasibilit y studies powerhouse layout dimensioning can be done using theoretical
and empirical relations of the power house components. For final design it so
customary for the turbine and generator manufactures to furnish dimensions for the
interiors of the spiral casing, draft tube, and generator assembly.
The following items of equipment are considered for planning and dimensioning of the
power house:
i. Hydraulic equipment:
i. Turbines iv. Governors
ii. Gate and gate valves v. Flow measuring equipment
iii. Relief valves of penstocks
ii. Electrical equipment:
i. Generator iii. Transformers, pumps, cooling
ii. Excitors systems, connections, funs and
plate forms
iv. Switching equipment:
Page 61
Hydropower Engineering-II
The machine in the power house can be either vertical mounting or horizontal
mounting. A horizontal mounting machine requires more floor space but less height. A
vertical mounting machine requires less floor space but more height. For larger
capacity installations, it is ideal choice to have vertical mounting. In general power
houses are oriented differently to accommodate excavation and site preparation
problems.
Page 62
Hydropower Engineering-II
Page 63
Hydropower Engineering-II
Page 64
Hydropower Engineering-II
Page 65
Hydropower Engineering-II
Legend
1. Inlet of spiral
case
2. Pipe bend
3. Penstock
4. Bend to draft
tube
Page 66
Hydropower Engineering-II
Generally speaking, horizontal Francis turbines are unsuitable for those cases in which
the tailrace level varies greatly during flooding. Generally, a high tailrace level can be
prevented by a water proof wall of a power house, or with a special wall or dyke behind
the power house. In this case a sump wall should be properly provided.
The width of the working bay is generally equal to about one unit bay, if the unit is
planned to be major overhauled in the power house. If the unit is planned to be major
overhauled outside the power house there can be no working bay in the power house.
The width of the unit bay is so determined that the clearance between the two units or
between the unit and the wall, should be sufficient for the erection and disassembly of
the unit, generally, about 2m. The passageway, for the operators should be 1-1.5 m, and
the clearance between the switch board / control panel and other apparatus should be at
least 2m, and that the switchboard and the wall should be about 0.8m. For the side unit,
its unit bay should have an additional width (about 1m per Units).
Page 67
Hydropower Engineering-II
The determination of the setting elevation of the turbine is very important for the
Power House design, taking in to consideration the minimum tailrace level and the
suction head of the turbine.
The height of the Power House is mainly determined by overhead craning of the
heaviest part of the unit.
3.3.2. Preliminary dimensions of power House for Medium and large Hydro
(Reaction Turbine installation)
Page 68
Hydropower Engineering-II
Page 69
Hydropower Engineering-II
3. Determination of discharge
diameter, D3 (Mosonyi‟s formula) Peripheral coefficient
H N = speed of turbine in rpm
*
D1 = N
(Entrance Diameter) 4. Guthrie Brown‟s formula
Ns
90Q 1
0.5 D3 3
D3 = 400 N
(Exit Diameter) Where, Q discharge at full load in m3/s
Bay‟s Dimension
Machine hall:
Length: the length of the machine hall depends on the number of units and the size of
machine. For vertical alignment machine the center to center distance is controlled by
the size of the scroll casing layout. Standard layout indicates a distance of 4.50 to 5.0D,
where D is the turbine out let diameter. Added to this dimension is the minimum
clearance of 2 to 3m. So, the preliminary dimension between center to center of two
units is 5.0D + 2.5m. For higher specific speed it can be 4.0D + 2.5 or smaller.
Knowing the number of machines, the total length of the machine hall can be worked
out. The additional bay for the erection loading can be one unit length.
Width: the width of the machine hall is determined by the size and clearance spacing
between the walls – needed as gangway. Since the gangway requirement is of the order
of 2.5m, as a first approximation the width of the power house can be presumed to be at
least equal to the center to center distance of two machines. Unnecessary increase in
width will increase the length of the Electrically Operated Trail (EOT) or Mechanically
Operated Trail (MOT) and the roof structure. In the Machine hall, the generator placing
is not exactly at the center of the machine hall but towards one side so as to provide
enough operation space for the crane operator.
Page 70
Hydropower Engineering-II
Height: the height of the Machine hall is fixed by the head room requirement (about 2
to 2.5m) of the crane operation. The hall must have a height which will enable the crane
to lift the rotor of the generator or the runner of the turbine clear of the floor without
any obstruction. To this clearance, space is to be added the depth of crane girder and
the head room for the operating cabin.
Loading and erection bay:
This space is required for unloading or loading heavy machines and for its erection.
Small assembly is also done on the space. The stators of the generator which come in
smaller segments are also assembled on the loading bay. The size of the erection should
be sufficient to keep the larger parts like the rotor of the generating unit.
Control bay:
The control bay houses the control equipment. It can be adjacent to the unit bay as in
most power houses. Signal is sent from the control bay to the operating bay from where
the operation control is achieved. Most of the controls are operated by remote control
from the control bay.
Service crane:
The crane should be designed for such a capacity that it can lift the heaviest component
in the power house. Normally, the heaviest part is the rotor and the stator.
Switch Yard:
This is the yard with step up transformers. This should be located near the power house.
In most cases switch yards are kept outside the power house.
Page 71
Hydropower Engineering-II
2. The generator may be in a pit but the super structure may be on the surface
3. Semi-Underground, here the generator may be located on the surface while
other units, such as turbines may be under ground
4. The power house may be placed in a cut where the stable rock exists, the units
may be placed in a cut in the rock
Page 72
Hydropower Engineering-II
According to Mosonyi, the various characteristic types and layouts of the power station
could be described with reference to head and tail water levels as follows.
Characteristics types of underground power development
i. Upstream Station or head development
ii. Downstream station or tail development
iii. Intermediate station development
iv. Diagonal Tunnel alignment with air cushion surge tank
The upstream station or Head development (Swedish type of development): in this
type of development, the power station is located close to the intake and thus water is
directly fed from the reservoir/fore bay to the generating units.
This arrangement is suitable for low head (25-50 m) and high discharge condition in
the continuously sloping or mildly rolling terrains. A surge tank could be provided at
the entrance to the tunnel to protect it from the water hammer during sudden opening
and closure of turbines.
Figure 4.1: The upstream power station or Head development (Swedish type of
development)
Page 73
Hydropower Engineering-II
Page 74
Hydropower Engineering-II
Diagonal Tunnel alignment with air cushion surge tank (Norwegian solution):
Figure 4.4: Diagonal alignment with air cushion surge tank (Norwegian Solution)
Page 75
Hydropower Engineering-II
The powerhouse is integrated as part of the dam structure, located on the surface at the
foot or adjacent to the foot of the dam or may be located underground within one of the
mountainsides/abutments. At narrow sites with favorable rock conditions and heads our
40 – 50 m, a concrete arch dam and an underground powerhouse often offer the most
cost effective solution. With less favorable rock conditions a narrow site may not be the
best dam location. In such cases wider sites allowing a surface design may offer an
alternative, which give less total costs even with significantly possible higher dam
costs. In suitable topography, which may allow a penstock and power house on the
surface without excavation of excessive open cuts, surface powerhouse may give the
cheapest solution even with excellent rock condition.
The low dam /log water way type: this type of powerhouse layout is characterized by
a low dam where most of the head is created by a long water way releasing water down
stream of natural rapids in the same river basin (Trans-basin diversion). Hydropower
plants with heads of more than 250 m will have some of these characteristics.
A powerhouse located near the intake creates layout with a long tailrace tunnel in
mountainous locations. This design requires long access tunnels and pumping of
leakage water during excavation. On the other hand there is no much risk of losing
water from a pressurized headrace tunnel. Location of the powerhouse in rock near the
intake may be dictated by topography.
Page 76
Hydropower Engineering-II
Page 77
Hydropower Engineering-II
Operational stability:
- Due to long distance from the turbine to the surge chamber, surface plants may be
unsuited for satisfying all technical criteria for stable operation. Plants with
underground powerhouse are more stable than the surface plants.
Deference, operational Reliability and personnel safety:
- As strategic infrastructure, an underground powerhouse is less vulnerable under
war like events than surface option and easier to prefect against sabotage.
Structural Design:
- Being completely fixed in its cavern, a powerhouse in the underground can be
designed very efficiently from a structural point of view, as any need for overall
support will easily be provided by the rock confinement. On the contrary, a
powerhouse on the surface may, in order to achieve appropriate safety against
sliding or uplift failure, require larger concrete volumes than what is needed for
structural reasons alone.
- Steel lining embedded in rock will have similar advantage. All reactive forces from
the pipe are transferred directly through the concrete surround to the rock. The rock
will prevent any longitudinal movement of the lining and there is no need for
expansion joints.
Operation and Maintenance:
- Embedded steel linings need less maintenance than exposal penstocks on the
surface, which are subjected to deteriorating effects from changing temperature,
sunshine, storm and rain and from frost and snow in cloud climates.
Conditions for Construction and Erection:
- Excavation for surface powerhouse will normally take less time than the access and
caverns for underground option. Therefore, construction of an underground
powerhouse will normally take longer time than surface alternatives.
Environmental impacts:
- Whether located at surface or underground, the powerhouse itself will hardly cause
serious environmental concerns. It may be assumed though, that an underground
plant, occupying less surface area, will generally get higher environmental merits
than a surface development. It causes less loss of forest or other valuable surface
assets than a surface plant and gives no negative visual impact of a penstock on the
hillside.
Page 78
Hydropower Engineering-II
The location and alignment of the power plant will depend on the conditions of rock
cover, rock type, access roads, construction admits, (Topography and geological
conditions)
- Minimum need for heavy rock support
- Adjusting the vertical alignment to follow favorable strata of sedimentary rocks
or locate the headrace as pressurized tunnel in igneous rock below weaker
sedimentary rocks
The general design criterion, which has to be satisfied at any point in an unlined
pressurized tunnel or shaft, is that the minimum principal stress in the adjacent rock
mass is higher than the maximum future water pressure.
After commissioning, the tunnel system around the powerhouse will need to serve a
different set of functions, the main ones being:
-Main access in to the powerhouse
-Branch-off tunnels to other installations like transformer cells or separate transformer
cavern, tailrace gate chamber, concrete plug with steel bulkhead, etc,
Page 79
Hydropower Engineering-II
Example:
- 45 0 inclined shaft serving for the high–voltage cable connection , for supply of
ventilation air and as alternative escape route
- Combined cavern for the main transformers and machinery for tailrace gates
and with the same cavern as the starting point for a tunnel loop for excavation
of the top heading of the powerhouse cavern
- transport access tunnel to the tailrace latter serve as surge chamber
Page 80
Hydropower Engineering-II
Figure-4.5: Plan and cross section of an underground Hydropower plants with unlined
waterways (Multipurpose tunnel layout)
A typical sequence of excavation, concrete works and erection for an underground
powerhouse with one Pelton unit is presented in the figure below.
Page 81
Hydropower Engineering-II
Page 82
Hydropower Engineering-II
Page 83
Hydropower Engineering-II
favour transformers underground, hence the transformers are located within the
machine hall or in an adjacent separate cavern.
- In a machine hall
- Between generators
- In extension of power house cavern
- In separate cavern
Tunnels of hydropower projects fall into two categories: water carrying tunnels and
service tunnels.
a) Water carrying tunnels: these include head race or power tunnels, tail race tunnels
or diversion tunnels. Flows in water tunnels are usually under pressure (pipe flow),
but sometimes free-flow (open channel flow) can be experienced, especially, in
tailrace tunnels. The design of free-flow tunnels follows the same principles as used
in the design of open canals.
- Head race tunnels: are tunnels that convey water to the surge tank. These are
pressure tunnels
- Tail race tunnels: could be free flowing or pressure tunnels depending on the
relative position of turbine setting and tail water level.
- Diversion tunnels: are constructed for the purpose of diverting the stream flow
during construction period. Normally they are not of high pressure but should have
sufficient flood carrying capacity. Such tunnels either plugged with concrete or
converted in to some use such as spillway tunnel at the completion of the project.
Page 84
Hydropower Engineering-II
Alignment: Tunnels have generally small bottom slopes, i.e. tunnels or aligned nearly
horizontal. Shaft is a tunnel with vertical alignment or inclined shaft when it is steeply
inclined to the horizontal. It is very crucial to investigate in detail the geology of the
strata through which a tunnel would be passing. Sound, homogenous, isotropic, and
solid rock formations are the most ideal ones for tunneling work.
Lining: Lining is a protective layer of concrete, R.C. or steel on the inner surface of the
tunnel to improve the efficiency and structural stability of the tunnel. Tunnels in good,
sound rock may be left unlined.
Commonly adopted shapes:
Page 85
Hydropower Engineering-II
In the case of low-pressure tunnels the tunnel surface may frequently be left unlined
except for visible fissures. A watertight lining is usually required for tunnels operating
under medium and high heads. Seepage is more likely to occur as the head increases,
water may leak through the smallest fissures and cracks. Moreover, under high-pressure
it may penetrate the otherwise watertight rock and render it permeable.
Page 86
Hydropower Engineering-II
Geometrical Shape:
- The choice of the cross-sectional profile of a tunnel depends on:
- Hydraulic considerations: Circular is preferable
- Stability considerations: Circular is preferable
- Convenience for construction: D-shaped is preferable
- Available tunneling equipment :
Longitudinal Slope: the minimum slope for a pressure tunnel is limited on the basis of
dewatering requirements. And also the longitudinal profile of the tunnel should be such
that the roof remains below the hydraulic pressure line by 1 to 2 m. Likewise, the
tunneling method and the equipment employed for transportation of the excavated
material (rail or wheel transport) can limit the maximum slope possible to provide. The
usual practice is to keep the slope of power tunnel gentle till the surge tank and then
steeper (even vertical) for the pressure shaft.
Flow Velocity: the allowable velocities in tunnels depend upon whether it is lined or
unlined. In unlined tunnels, a velocity of 2 to 2.5 m/s is the upper limit, while in
concrete lined tunnels 4 to 5 m/s are often employed. The velocities for the pressure
shafts, which are generally steel lined, are usually higher than that in the power tunnel.
The normal range of velocities is between 5 to 8 m/s.
Rock Cover (overburden): for pressure tunnels, it is obvious that the overburden on
the roof of the tunnel serves to balance the effect of upward force due to internal
pressure. The required depth of overburden may vary for lined and unlined tunnels.
In the case of unlined tunnels, the entire internal water pressure is resisted by the
overburden rock pressure. Where a steep valley side constitutes the overburden above
the tunnel, the rule of thumb equation, H= (0.4 to 0.8)*hr has to be modified and given
by:
1 r
hw L cos
w
Where L is the shortest distance between the ground surface and the studied point of
the tunnel (or shaft) and is the average inclination of the valley side with the
horizontal (see figure below).
Page 87
Hydropower Engineering-II
r L cos w h w
hw
hr
In the case of concrete or steel lined tunnels, the linings are usually designed to carry
part or full load of the internal water pressure, and the above equations, given for
unlined tunnels, are modified accordingly in determining the required overburden
depth.
Head Loss: head losses in tunnels can be computed using Manning‟s, Darcy-
Weisbach, or Hazen-Williams formulas.
lv 2
hf n2
Manning formula: R4 / 3
l v2
h f
Darcy-Weisbach formula: 2 g Deq
l v 1.85
h f 6.84 1.17
Hazen-Williams formula (rarely used): C 1.85 Deq
Where, hf is head loss due to friction, L is tunnel length, V is mean velocity of flow, R
For a quick initial estimate of the diameter of pressure tunnels, the empirical formula
suggested by Fahlbusch can be used:
Page 88
Hydropower Engineering-II
Q 0.45
D 1.12
For steel-lined tunnels: H 0.12
Total cost
Cost
X-section
Figure 4.9: Optimum tunnel cross-section
When the virgin stresses and the geometry are known, it is in theory easy to evaluate
the magnitude and the direction of the stresses surrounding a tunnel or rock cavern. If
the rock mass properties are known, it is theoretically also relatively simple to analyze
potential stability and leakage problems caused by stresses, the need for rock support,
the possibilities for optimizing the excavation geometry, etc.
Nevertheless, empirical methods are mainly used for analyzing rock stress problems.
The reason for this is primarily the problem in obtaining reliable input parameters
which are needed for the more advanced analyses. The following parameters have been
the most difficult to quantify.
- the magnitudes and directions of the virgin rock stresses
- the properties of the in-situ rock mass, in particular the elasticity parameters
- the failure criterion of the in-situ rock mass
Page 89
Hydropower Engineering-II
Origin of Rock Stresses: the virgin stress generally represents the resultant of the
following components:
- Gravitational stresses
- Topographic stresses
- Tectonic stresses
- Residual stresses
Gravitational Stresses: this component is a result of the gravity alone. When the
surface is horizontal, the vertical gravitational stress at a depth Z is:
σ = ρ.g..Z
Where ρ.g = specific gravity of the rock
The magnitude of the total vertical stress is often identical to the magnitude of the
gravitational vertical component. However, at great depths, particularly, there are
considerable deviations from this trend.
Figure 4.10: Vertical and horizontal rock stresses as a function of depth below the rock
surface (Scandinavians Case)
In anelastic rock mass with Poisson‟s ratio of v, the horizontal stresses induced by
gravity are:
1
x y Z
Page 90
Hydropower Engineering-II
For a Poisson‟s ratio of 0.25, which is fairly common for rock masses, this means that
the horizontal stress induced by gravity is approximately 1/3 of the vertical stress.
Topographic stresses: when the surface is not horizontal, the topography will affect
the rock stress situation. Stresses caused by topographic effects are generally referred to
as topographically induced stresses or simply topographic stresses.
In high valley sides, where hydropower plants are often located, the stress situation is
totally dominated by the topographic effects. In such cases the major principal stress
(σ1) near the surface will be more or less parallel to the slope of the valley, and the
minor principal stress (σ3) will be approximately perpendicular to the slope.
Figure 4.11: Magnitudes and directions of the major and minor principal stresses in a
valley side as computed by a Finite Element Analysis
Page 91
Hydropower Engineering-II
Figure 4.12: Variation of ratio of average horizontal stress to vertical stress with depth
below surface
Residual Stresses: residual (or remnant) stresses are generally defined as stress which
has been locked in to rock material during earlier stages of its geological history. Stress
caused by contraction during cooling of a rock melt (magma) is probably the most
relevant example of this category. Vertical stresses which are abnormally high are often
explained as being caused by residual stress. Stresses Surrounding Underground
Openings
When analyzing potential problems due to rock stresses, the stress situation close to the
contour of the tunnel or rock cavern is of particular interest.
- Stresses surrounding Circular opening
The simplest case is represented by the following idealized conditions:
- Homogeneous and isotropic, elastic material
- Isotropic virgin stresses (σ1 = σ2 = σ3 = σ)
If the radius of the opening is a, the radial and tangential stresses of a cross section
(σr and σt, respectively) will be the following as function of the distance r from the
circle center.
Page 92
Hydropower Engineering-II
2
a
r ( 1 2
)
r
2
a
t ( 1 2
)
r
In the figure below these equations are shown graphically. It is particularly important to
notice the rapid increase in tangential stress close to the contour. Generally, in a case
like this, a tangential stress with a magnitude of twice the magnitude of the isostatic
stress will be induced all around the periphery.
Figure 4.13: Tangential and radial stress surrounding a circular opening in isostatic
stress field.
For an anisotropic stress condition the so-called Kirsch‟s equations are used for
evaluating the tangential stresses. According to Kirsch the tangential stress will reach
the maximum value (σt(max)) where the σ1 direction is tangent to the contour, and its
minimum value (σt(min)) where the σ3 direction is tangent. The actual values will be:
t (max) 3 1 3
t (min) 3 3 1
Figure- 4.14: The influence of rock anisotropy on the stress surrounding of a circular
opening. Potential problems due to the stresses are indicated
Page 93
Hydropower Engineering-II
The above figure illustrates that the distribution of tangential stress is strongly
influenced by the degree of stress anisotropy. If the stresses are very anisotropic the
minimum tangential stress, as illustrated, may even be negative, i.e. tensional
When the curvature radius is reduced, the magnitude of the tangential stress will
increase. This means, for instance, that the sharper the corner between the wall and the
roof of a cavern, the higher the stress concentration will be in that corner. In extreme
cases such stress concentration may reach magnitudes of more than 10 times the major
principal stress value
In cases with benches or protruding corners the stress situation will be the opposite.
Here the stabilizing stresses, or the confinement, will be reduced, and stabilit y
problems will often result.
Page 94
Hydropower Engineering-II
The detailed distribution of the tangential stress will depend mainly on the deformation
properties of the rock mass. In very jointed rock the stress peak is relatively flat, and
the maximum stress value is located relatively far from the tunnel contour. This is also
the case in typical soft rocks. In hard and elastic rocks the stress peak is much steeper,
and the maximum stress value is located close to the contour.
The magnitude of the maximum tangential stress depends in theory on the shape of the
underground opening, and not on its size. The zone of influence however will increase
with increasing size. In-situ rock stress measurements indicate that the stresses stabilize
at a constant level at a distance from the tunnel contour corresponding to approximately
half the tunnel width. The constant level corresponds to the actual virgin stress.
Page 95
Hydropower Engineering-II
In most cases a tensile jointing will not have much influence on the rock stability. For
high pressure tunnel it is more important that secondary jointing and opening of
existing joints may increase the risk of water leakages out of the tunnel.
The fracturing process is often accompanied by loud noises from the rock. A
phenomenon commonly referred to as rock burst. At moderate stress level the
fracturing will result in a loosening of thin rock slabs, often referred to as rock slabbing
or spilling. If the tangential stress is very high, the rock burst activity may be quite
dramatic. In extreme cases it may have the character of popping of large rock slabs with
considerable force and speed.
When the stresses are very high, rock bursts may be a major threat to safety if the right
type of rock support is not installed at the right moment. In such cases extensive rock
support is necessary.
Page 96
Hydropower Engineering-II
Rock burst activity is most intensive at the working face immediately after excavation.
Experience shows that the most difficult area is the section 10-20 m closest to the
working face.
In soft rocks the stress problems will not be characterized by spalling. Because of the
plastic nature of such rocks the potential problem here will be squeezing. In extreme
cases reductions of the original tunnel diameter of several tens of centimeters due to
squeezing have occurred in Central Europe.
The orientation of the major principal stress relative to the direction of major joints sets
and important structural features, such as bedding and schistosity, will have a major
influence on rock burst activity. Severe problems may occur if the schistosity runs
parallel to the tunnel axis, and the major principal stress acts perpendicular to the axis
and in the dip direction of the schistosity.
Along a tunnel there will be a certain variation in stresses, rock type and elastic
properties, and therefore also a variation in rock burst activity. Generally, there will be
a concentration of stresses in stiff rocks and considerably lower stress in softer rocks. In
gneisses, for instance it is commonly experienced that tunnel sections particularly rich
in mica are often characterized by stress relief, while the rock burst is confined to more
quartz and feldspar rich sections.
Major weakness zones may also affect the rock stress situation. As many such zones
are only able to transform shear stress to a minor extent, the principal stresses will often
be parallel and perpendicular to the zones. Hence a tunnel through a major weakness
zone may experience extensive rock spilling on one side of the zone, while the stresses
are reduced to a moderate or low level on the other side
Page 97
Hydropower Engineering-II
An Old Norwegian rule of thumb states that if heights above the tunnel of 500m or
more are reached at an angle of 250 or steeper in a valley side, one should always be
prepared for stress induced stability problems. Although this simple rule does not
consider the influence of for instance tectonic stress, it still reflects general experience
from the majority of Norwegian hydropower plants.
and perpendicular to tunnel axis. The vertical stress ( 3 ) is only one quarter of the
value of the major principal stress. And according to Kirsch‟s equation, the tangential
stress is therefore 2.75 times the maximum horizontal stress.
In water tunnels it has occasionally been experienced that spilling may continue for
many years. This long-term effect is probably caused by a combination of high stresses,
a reduction of rock strength due to water saturation, creep effects and hydraulic
pressure variations.
Page 98
Hydropower Engineering-II
Reliable information on this issue can be obtained only by carrying out rock stress
measurements.
Methods:
Throughout the years a considerable variety of different equipment for in-situ rock
stress measurements has been developed. However, for hydropower projects the
following methods are most relevant.
- Triaxial stress measurements by drill hole over coring
- Hydraulic fracturing
The drill hole over coring technique has the longest tradition, and there are several
versions of this method. Figure-4.17 illustrates the principles of the version which is
most commonly used. As can be seen, what are actually being recorded are the strains.
To be able to compute the stresses, laboratory analyses of the elastic properties have to
be carried out.
Page 99
Hydropower Engineering-II
The basic principle of hydraulic fracturing is to isolate a section of a drill hole and, by
gradually increasing the pressure of water which is pumped into the hole, to obtain
fracturing of the surrounding rock. By recording water pressure and flow, the principle
stress situation can be evaluated.
4.11.4 Modeling
For analyzing rock stresses and deformation, numerical models may be a valuable tool
.Because of the large quantities of data involved in such analyses, powerful computers
have to be used.
Principles:
Generally, there are two main categories of numerical models:
- Discontinuous
- Continuous
In discontinuous models (or” block models”) the rock mass is modeled as a system of
single blocks which interact along their edges. One fairly well known example of a
method belonging to this category is the Universal Distinct Element Code (UDEC).
Obviously; the concept of discontinuity represents certain advantages. However, as this
is quite a new category of numerical models, it has had little application up to now.
Continuous models, on the other hand, have been used on many occasions, in this
model category the rock mass is modeled as a basically continuous medium. Limited
number of discontinuities (joints .faults, etc) may also be included. Common methods
in this category are the Finite Element Method (FEM) and the Boundary Element
method (“BEM”)
The initial step of FEM-analyses is to define a geological model of the actual area. The
next step is to generate the element mesh. Based on input of rock properties and
boundary conditions the magnitudes and directions of stresses for all nodal points of the
element mesh are finally competed.
Page 100
Hydropower Engineering-II
Examples:
The basic principle of a Simple FEM- model (homogeneous and isotropic conditions) is
shown in Figure -4.13. In this model the size of the elements becomes generally smaller
close to the contour of the rock cavern which is being modeled. This is simply because
this is the area of prime interest when analyzing stability and planning rock support. A
special feature of this model is the possibility of excavation elements in the roof, thus
permitting analyses for a cavern with a curved roof as well as one with a flat roof.
The relevant mechanical parameters are given, i.e. specific gravity ( ( ) , modulus of
elasticity (E) and position’s ratio (V) need to be known. The nodal points at the bottom
of the model are free to move horizontally only, while the nodal points at the left hand
side are free to move vertically only.
Figure 4.18: Example of Finite Element model for analyzing the stresses surrounding a
planned rock cavern.
Vertically the model is loaded with gravity forces; .h. Horizontal load is applied on
the right hand side of the model, and is given as k. .h. This is both force resulting from
elastic deformation and tectonic force.
The computed directions and magnitudes of principal stresses from such model analysis
are as illustrated in Figure-4.14. Here, the magnitudes and directions of the major and
Page 101
Hydropower Engineering-II
minor principal stresses are given by the vector lengths and directions, respectively, of
each of the crosses.
Figure 4.19: Directions and magnitudes of principal stresses surrounding a rock cavern
as computed by boundary element analysis
Numerical modeling as shown by the above examples may be very useful during the
design of underground openings as well as during the planning of rock support.
Page 102
Hydropower Engineering-II
Drilling is carried out by the percussion method. The principle is to force a drill rod
with a suitable drill bit against the tunnel face, generate a stroke in order to obtain rock
spalling, and then rotate the rod before it is once again forced against the hole and a
new stroke is generated. The power for the drilling thrust and rotation is transmitted by
hydraulic systems.
Once the drilling operation is completed, charging of the drill holes with explosives
will be performed. There are different types of explosives, the most common one being
dynamite.
In rock blasting the main principle is to break the rock and push the rock fragments
towards a free surface. In a tunnel the degree of confinement of the blast volume is far
higher than in a quarry. In order to obtain a satisfactory result from a tunnel blast it is,
therefore, necessary to include the so-called “cut” in the blast hole design. These
consist of holes of larger diameter than the blast holes and are usually left unloaded.
After blasting the round, ventilation has to be carried out to lower the concentration of
blasting fumes to a satisfactory level. The fans are usually started just after the
explosion. It is very seldom possible to enter the working face area until 15-20 minutes
after the blast, but this depends on the ventilation equipment.
After each blast round, scaling (removing loose rocks from the roof and walls of the
tunnel) is done for the sake of safety.
The selection of equipment for mucking and hauling largely depend on the cross-
sectional area and the gradient of the tunnel. For tunnels with cross-sections smaller
than 16 m2, the only alternative for transportation is rail transport system. In larger
tunnels, wheel transport system shall be used. For wheel transport in cross-sections
between 16 and 30 m2 “niches” are required every 100 to 150 m for the purposes of
loading and turning trucks.
Page 103
Hydropower Engineering-II
A major restriction for the rail transport alternative is that the maximum gradient has to
be less than 2%. For wheel transport gradients up to 15% may be tolerated.
Use of Tunnel Boring Machines (TBM):
A tunnel boring machine (TBM) is a complex and very advanced piece of machinery
designed to excavate the entire cross-section in a single operation without the use of
explosives. Tunnels with diameters of about 1.8 m to more than 11 m have been
excavated with tunnel boring machines.
The diameter of the cutters is normally within the range of 45 to 50 cm, and the total
number of cutters varies from 20 for smallest machines to more than 70 for the largest.
Page 104
Hydropower Engineering-II
A basic philosophy in tunneling is that the extent of installed tunnel support should
reflect the actual rock conditions. In good quality rock the self-supporting capacity of
the rock mass should be used to its advantage, and the amount of tunnel support kept at
a minimum. In poor quality rock the design of support should be based on a sound
understanding of the character and extent of the stability problem.
The various geological factors which may influence the stability are:
- The strength and quality of the intact rock
- The degree of jointing and their character
- Weakness zones and faults
- Rock stresses
- Water inflow
Tunnel support may be installed either at the working face (immediate support), or
behind the face (permanent support). Whenever possible the design for the immediate
support should be chosen which makes it possible to act later as permanent support.
The following support methods are the most commonly used in hydropower tunneling
today:
- Rock bolting - Grouting
- Shotcreting - Concrete lining
Page 105
Hydropower Engineering-II
Rock Bolting:
A rock bolt is a steel bar, which is inserted into a hole drilled in a rock to improve the
rock competency. The distant end has a device which permits it to firmly anchor in the
hole and the projecting end is fitted with a plate which bears against the rock surface
(See Figure-4.16). The bolt is placed in tension between the anchor and the plate,
thereby exerting a compressive force on the rock.
Page 106
Hydropower Engineering-II
If shotcrete is applied on such zones, there will be no room for expansion of the
swelling clay, and high swelling pressure will be activated when the zones are exposed
to water. This may easily destroy the shotcrete lining.
Grouting: A grout is a mixture of cement and water forced in to rocks around the
tunnel periphery. Grouting may be performed ahead of the tunneling face (pre-
grouting) or behind the tunneling face (post-grouting). Pre-grouting is necessary in
areas where groundwater inflow makes tunnel driving difficult. Probe holes are drilled
ahead of the tunnel face to perform permeability testing before deciding the necessit y
of pre-grouting. Post-grouting is done to improve the stability of the rock mass behind
the tunnel face.
Page 107
Hydropower Engineering-II
If the power plant and the load centers are close to each other, the costs of electric power
transmission and maintenance are minimum. In most cases power plants are located in remote
areas and inside gorges which demands high cost of for transmission of electric power to the
load centers.
A design criterion of transmission lines considers:
The maximum allowable voltage variation from no load to full load
The maximum economic power loss
Protection from lightning and other damages
Structural stability in high winds (or, in temperate areas, in ice and snow)
Safety for people living and working near the lines
Underground or over ground
Over ground lines are used most often because, by using air as the cable insulator, the cable is
less expensive. Insulation can be cheap and simple. In most developing countries, un-insulated
cable is more readily available than underground.
Page 108
Hydropower Engineering-II
Un-insulated cables are exposed to lightning and to falling trees. The land close to the lines
has to be cleared of trees, and this has to be carried out periodically. The poles may also have
a finite life, and so may need replacing, perhaps every 15 years. Further, overhead lines are
less efficient than underground for a given conductor size because the wide spacing of the
conductors gives rise to inductive losses.
Underground lines have to be insulated, and protected against ground movement, ploughing,
new buildings, etc. Once installed, however, the line should run without maintenance until the
insulting material deteriorates.
High Voltage (HV) or Low Voltage (LV) lines
If transformers are used to step up the voltage to high values, the currents in the conductors are
smaller and cables are smaller. The lower cost of the cables is offset by the cost of the two
transformers needed, one at the start of the transmission line, and one at the end, to step the
voltage back down to the standard value. Additional costs for checking of ventilation or
cooling level and insulators for attachment of the cables to support poles are needed. By
contrast low voltage (LV) lines without transformers are more easily erected and maintained
by the local users of power.
measures. Hence, power system planning is based on specific objective: seeking a plan that
contributes to minimize the total socio-economical supply cost, keeping all relevant
restrictions during the period of analysis, typically 20-30 years.
Page 109
Hydropower Engineering-II
The planning process may have the following phases:
i Establishing the database
Electrical system data, i.e. description of existing system and suggested extensions
Load data, i.e. historic and present energy
consumption, description of heavy/light load
situations as well as prognoses for energy and power
Page 110
Hydropower Engineering-II
5.2 Design philosophy of overhead lines
The main parts of a power line, as
roughly shown in the figure below, are
the conductors, the supports (towers or
poles) which hold the bare conductors,
insulators needed between the
conductors and the support and shield
wires attached to tower extensions.
Towers keep the conductors at suitable
distance from the ground and other
objects (external clearances) and
mutually apart (internal clearances).
The three elements: conductors,
supports and insulators constitute the main types of components of an overhead power line. In
addition, supports need either foundations, or the lower part is buried in the ground, to keep
them in a fixed position, and hardware and clamps are used to fix the insulators between
supports and conductors. Shield wires are provided in some power lines.
The clearance has to be large enough to avoid discharge. The components must have the
mechanical strength to resist the stresses they are exposed to:-
Standards and regulations are required to layout and design overhead power lines,
which outline the criteria for electro technical and mechanical aspects. The electro
technical aspects will be to determine the voltage stresses acting on the line and to
determine the required resistance voltage. The mechanical aspects will be to determine
the loads acting on the line and to determine the strength of the various components
that will resist the stresses created by the loads.
Design philosophy and standard of overhead lines should aim in explaining the general
frame work of a power line (standard) that can be improved in line with practical and
theoretical experience.
Page 111
Hydropower Engineering-II
5.3 Framework of a standard
i Probabilistic methods :
based on statistical Knowledge of an event
E.g. a climate load that can be quantified by its yearly maximum value or the properties of a
component that can be quantified by e.g. its ultimate strength
ii Loads (Analyzing loads)
Mechanical aspects: Analyzing the loads acting on the line
- Basic loads: due to the weight of towers, conductors and hardware and to vertical and
horizontal changes to line direction
Additional loads:
- Climate loads: due to wind, ice and temperature, either separately or in combination
(statistical basis and experience)
- Special loads: to meet situations that can occur occasionally during
construction and operation
- Security loads: to withstand and satisfy requirements to the security of the
overhead line, e.g. a failure can occur due to unpredictable event,
longitudinal loads acting on a suspension tower may be due to broken
conductor under normal tension (deterministic basis)
- Safety loads: to withstand with a good safety margin for personnel working
on the transmission line
Electro technical aspects: concerning the mechanical aspects, the electrical stresses acting
on the line have be analyzed
The loads are classified as the following voltages:
- Continuous power frequency - Slow front over voltages
voltages - Fast front over voltages
- Temporary over voltages
With all loads the minimum required insulator string length and electric clearance
distances will be determined and certain measures will be taken to ensure the operation
security for safety for humans and animals.
Page 112
Hydropower Engineering-II
5.4 Right Way of planning
Lying to Transmission lines needs extensive work of panning: The planning process may
include:
Early clarification of possibilities and alternatives
Close contact with local interests and users of the areas in question
Recording of all important interests connected with the actual alternatives
Consultations where all justifiable feasible alternatives are included
In the process of planning it is very important that the planners do not choose their own
favorite alternative before all relevant information is brought forward.
i Adaptation to use of land
As a main rule, avoiding the most valuable and conflict filled areas, where satisfactory
alternatives are available should be the aim
Aim at avoiding:
Pristine areas and areas of high Land cape gems
protection value Routes with towers in cultivated fields
Large continues tracts of nature and but crossing cultivated field is
outdoor activity areas preferable to going through forest
Evaluate Border zones:
Between forest and cultivated fields
Between residential areas and other areas
Along roads (but carefully)
ii Landscape
The main rule should be that wherever possible and where solutions are otherwise acceptable,
the aim should be to find right of ways adapted to, and subordinated to the landscape.
avoid silhouettes or back ground in topography or
avoid barrier effects vegetation
avoid conspicuous effects follow existing curves in the landscape,
avoid strand zones or crossing over e.g. border zones in topography and
lakes vegetation
stay low, search for routes where the Crossing rivers, roads and traffic routes
line and especially the towers get cover should, as a main rule be perpendicular
to them.
Page 113
Hydropower Engineering-II
Take care of forest screens when Choose the upper side or inner curve
crossing or going alongside rivers and when going alongside traffic routes
traffic routes
iii Health Impacts of electric and magnetic fields
In recent years greater attention has been focused on electric and magnetic fields, both
among the general public and experts, as a result of the fear that these fields can constitute
a health risk.
Electric and magnetic fields in relation to power lines are important in this combination even
if such fields usually are weak compared to what is found in other electric sources. However,
power lines extend over larger areas and thus the public is regularly, and in some cases
permanently, exposed to the fields.
a) The electric field ( E-field)
The electric filed is designated with the latter E and is a measure of the rate of change of the
voltage when moving in a certain direction. It is measured in volts per meter (V/m).
b) The magnetic field ( B – filed)
The magnetic induction is designated with the letter B and gives the strength of the magnetic
field in the unit Tesla (T).
Page 114
Hydropower Engineering-II
5.5 Tower spotting
Tower spotting is done with the help of land surveying. During pegging of the route center
line all necessary information including measurement of crossing lines, communication lines,
houses, buildings, roads, rivers and other objects along the route and property boundaries have
to be recorded.
The pegging in principle is carried out as a polygon mesh to be able to look between each
survey instrument and back to the former.
Measuring points are taken where the route center line changes direction. The distance
between the direction pegs should not exceed 50 meters. A direction peg is located with
suitable distance between the stations, depending on the terrain type.
Side terrain is measured to both sides of the center line where the side terrain is at a higher
elevation than the center line. How far out from the center line it should be measured is
determined e.g. from phase distance and clearance required from the ground.
The choice of tower type is very important. When building wood towers, the height of the
towers is limited and so as the span length since the lengths of wood poles is a limiting factor.
Page 115
Hydropower Engineering-II
Terrain type and climatic loads will influence both span lengths and towers locations, for
instance in high mountainous areas where there often is heavy wind load. Too long length
should be avoided due to the risk of clashing between the conductors.
Overhead line supports with wood are used up to 132KV power lines. These conductors use
up to ACSR Conductor, (overall diameter 27.7mm). For larger conductors steel towers are
used. The Most commonly used wood tower for high power line is the H-frame with two legs
of round timber. The foundation is made by burying (digging down) the lower part in to the
ground. The digging depth depends on the height of the tower and diameter of the towers at
the ground surface.
When designing the towers, they have to be checked against bending and buckling.
Wood towers are usually built of timber, pressure impregnated by creosote or salt. A well-
built construction, with an impregnated tower that largely prevents water from penetrating in
to the wood can attain longer life time under normal conditions.
The towers can roughly be divided in to two types: tension towers (separating the sections)
and tangent towers. The tension towers should be rigid and able to prevent loads from one
section being transmitted to the next. The tangent towers should support the conductors within
the section.
Longitudinal loads, e.g. due to a broken conductor, will as a rule be determining for the design
of the tension towers. For tangent towers transverse wind loads are usually decisive for the
designs. When designing transmission supports, attention should be given to the fact that
different load cases can be decisive for the dimension of different parts of the tower.
Page 116
Hydropower Engineering-II
Tension towers are usually formed as so called A-towers with 2 or 3 legs. Top and base
connections must be designed for the anticipated shear forces and are carried out with the
necessary number of bolts. Alternatively, tension can be attained with guyed towers, but this
gives a less stiff construction. There are many types of tangent towers, depending on function.
Most often the so called H-frame with suspended insulator chain is used.
The mechanical design of these, i.e. clamps, insulators and suspense are implemented
according to the regulations or standards.
Steel Towers:
Computer programs are most often used to analyze the loads on steel towers (forces and
displacements)
Testing of Towers:
Even though it can be documented by means of the design that towers in a power line have the
necessary strength, it is customary to test the different tower types of a large power line in a
testing station. Loads are imposed on the towers in the suspension points for
conductors/insulators. To simulate wind loads on the tower body, loads can be applied
elsewhere in the tower.
The loads can be applied using simple weights or pulleys and hydraulic systems. During the
testing of the different load cases the loads can be applied steadily and controlled. With the
help of measuring equipment the deflection of the towers can be recorded and checked against
the loads the tower are designed for concrete poles.
Page 117
Hydropower Engineering-II
5.8 Design of foundations
The foundations of the towers may be a separate construction upon which the tower is placed
in the case of a conventional wood pole the poles themselves are dug down in to the ground.
With regard to foundations as separate parts of the tower they are usually built on steel
reinforced concrete. This type of foundation may be divided in to:
i Foundation designed to resist iii Foundation designed to resist both
compression only compression and uplift
ii Foundation designed to resist uplift iv Foundation designed to resist toppling
overturning moment
An example of type i and ii is foundations of guyed steel towers.
The columns in this case are exposed to axial compression and may rest on foundations
designed for compression only. The guy wires for this type of towers are anchored in buried
foundations (anchors) designed for tension forces only
5.9 Conductors
These carry the electrical power from one end to other for transmission and distribution.
Requirements of good conductor:
Good conductivity or low specific Not brittle
resistance Not too expensive
High tensile strength to withstand Low specific gravity for low weight
mechanical stresses
Materials may be:
i. Copper iv. Galvanized steel
ii. aluminum v. Phosphor bronze
iii. ACSR ( Aluminum conductor steel vi. Cadmium copper
core reinforced
To increase the flexibility, all conductors are stranded in which case the central layer has
successive layers 6, 12, 18, 24 wires.
Copper conductors have high electrical conductivity and tensile strength. It is non-corrosive
and free from electrolytic trouble. But it is expensive.
Page 118
Hydropower Engineering-II
Although the conductivity of aluminum conductor is 60 percent and strength is 75% to that of
copper, aluminum conductors are usually employed for carrying heavy currents for being
cheaper and lighter in weight. The disadvantage is the greater coefficient of expansion, greater
sag, low melting point, difficulty in jointing, etc. ACSR conductors are good for larger span in
general.
5.10 Insulators
These are provided so that there is no leakage of current to the earth through the support poles.
Porcelain, glass and steatite are used as insulators. Porcelain is (excessively widely) used as
insulator. It is dielectric strength is 60 KV per cm of thickness and compressive strength is
70,000 kg/cm2. But tensile strength is low which are about 500kg/cm2.
Steatite insulators are used in tension towers and transmission lines with sharp turn.
The types of insulators are:
Pin type Shackle type
Suspension type Stay or Egg type
Strain type
Corona
It is a phenomenon in high voltage transmission lines due to portal breakdown of air in the
vicinity of energized line. This is characterized by a violet glow around the conductor and a
hissing noise produced along the glow.
Page 119
Hydropower Engineering-II
6.1 Reservoirs
Purpose: to stabilize the flow of water in order to satisfy a varying demand from consumers or
of regulates water supplied to a river course.
Investigation of reservoir sites:
In an investigation of a potential reservoir site, consideration must be given to the amount of
rainfall, runoff, infiltration and evapotranspiration which occurs in the catchments area.
Page 120
Hydropower Engineering-II
The climatic, topographical and geological conditions are therefore important, as is the type of
vegetation cover.
Basic data for reservoir design studies:
Topographical Map Hydrological records
Leakage from reservoirs:
The most attractive site for a large impounding reservoir is a valley constricted by a gorge at
its out fall with steep banks upstream so that a small dam can impound a large volume of
water with a minimum extent of water spread. However, two other factors have to be taken in
to consideration:
i. The water tightness of the basin and ii. Bank stability
Accordingly, once the ground water conditions have been investigated an assessment can be
made of water tightness and possible ground water control measures.
Leakage from reservoirs takes the form of sudden increases in stream flow downstream of the
dam site with boils in the river and the appearance of springs on the valley sides.
Apart from the conditions in the immediate vicinity of the dam, the two factors which
determine the retention of water in reservoir basins are the piezometer conditions in, and the
natural permeability of, the floor and flanks of the basin.
For ground water condition (Knell, 1971)
i. The groundwater divide and piezometer level are at a higher elevation than that of the
proposed top water level. In this situation no significant water loss takes place.
ii. The ground water divide, but not the piezometer level, is above the top water level of
the reservoir. In these circumstances seepage can take place through the separating
ridge in to the adjoining valley.
iii. Both the ground water divide and piezometer conditions are at a lower elevation than
the top water level but higher than that of the reservoir floor. In this case the increase
in groundwater head is low and the flow from the reservoir may be initialed under
condition of low piezometer pressure in the reservoir flanks.
iv. The water table is depressed below the base of the reservoir floor. This indicates deep
drainage of the rock mass or very limited seepage.
Troubles from seepage can usually be controlled by exclusion or drainage techniques.
Page 121
Hydropower Engineering-II
Exclusions:
Cut of trenches Impervious lining – Asphalt
Grouting membrane
Clay-blanket
Grouting:
Curtain grouting
Consolidation grouting
The depth of grouting hole should be more or equal to the dam height.
Drainage gallery:
Any seepage water through the foundation will be intercepted by the drain hole and brought
up to a collection drain from where water is pumped out.
Page 122
Hydropower Engineering-II
AC T IV IT Y
T I M E S P AN (YEAR S )
S t ra t e g ic p la n n in g :
p ro je c t i n it ia t i o n
3 -2 0
F ie ld M a p p in g , s u rve y s ,
R e c o n n a is s a n c e d a t a c o l le c t io n
F e a s ib ili t y s t u d ie s Te c h n i c a l
1 -3
a n d re p o rt re s o u rc e s , o p t io n s ,
P h a s e 1 : D a m s ite R e s rvo ir s it e
e va l u a t io n e va la u t io n
2 -4
C o n firm a t i o n o f d a m
type
P h a s e 2 : D a m s it e
in ve s t i g a t io n
1 -2
D a m d e s ig n
F o u n d a t io n fe e d
C o n s t ru c t io n 2 -6
bac k
Construction of monolith can be done on either the „alternate block‟ or the „shrinkage slot‟
principle. In either method the objective is to maximize shrinkage before pouring abutting
lifts of concrete in adjacent blocks.
a) Alternate block construction adjacent pours phased to accommodate shrinkage- lag
time approximately 30-60 days.
b) Construction with contraction gaps or shrinkage slots: gaps concreted approximately
30-60 days after adjacent lifts completed.
Mass concrete in dams is not subjected to compressive stresses comparable with those
developed in most other major structures. The volume of concrete with in a dam is relatively
great, however, requiring large pours and high placing rates. Several other properties therefore
rank equally with strength as indices of quality and fitness for purpose.
Hydropower Engineering-II
Page 123
Hydropower Engineering-II
The desirable characteristics for a mass concrete for use in dam can consequently be
summarized as follows.
Satisfactory density and strength Resistance to cracking
Durability Economy
Low thermal volume change
Formwork Erection
Preparation for river diversion
Constituent Materials:
Cement:
Ordinary Portland cement is not recommended in dam construction. The resulting
temperature rise and heat gain in large pours is unacceptable in relation to consequent
problems of shrinkage, heat dissipation and cracking.
Low heat or modified Portland cement. Thermal problems can be alleviated by the use of
Pozzolana blended Portland cements. In the absence of special cements, partial replacement
with pulverized fuel ash (PFA) and /or cooling are also effective in containing heat buildup.
Aggregate :( Cheap, inert)
A maximum size of coarse aggregate of 75-100 mm is considered the optimum with rounded
or irregular natural gravels generally preferable to crushed rock aggregates. In fine aggregate
range, i.e. <4.67mm size natural sands are similarly preferable to crushed fines. Aggregates
should be clean and free from surface weathering or impurities.
Page 124
Hydropower Engineering-II
Water:
Water for use in concrete should be free of undesirable chemical contamination, including
organic contaminates. A general standard is that the water should fit for human consumption.
Admixtures:
Air entraining agent, (AEA) is added to the concrete which helps in reducing the water
contents, and handling becomes easy. Water reducing admixture (WRAs) is sometimes
employed to cut the water requirement, typically by 7-9%. They are also effective in delaying
setting time under conditions of high ambient temperatures.
Page 125
Hydropower Engineering-II
Post Cooling:
Depending on the ambient temperature, post cooling may be needed. High density
polyethylene pipes are laid between 1.0 to 1.5m interval in the lifts and ice cooled water (3-
40C) is circulated through the pipes. The period of post cooling could be as high as 6 months.
Roller Compacted concrete dam. Construction (RRCC dam):
The construction of concrete gravity dam consumed long construction time due to the slow
curing process of mass concrete to avoid thermal shrinkages. A new technology, RCC dam
construction was introduced in 1970s which offers a potential of financial benefits associated
with shortening of construction period by up to 35% combined with a lower-cost variant of
concrete for large dams.
Characteristics of Mass concrete for dams
Concrete mix
Hearting Facing
Characteristics Unit
Cement(C) +PFA(F) (kg/m3) 150-230 250-320
F/(C+F) % 20-35 0-25
Water : (C+F) ratio - 0.5-0.70 0.45-0.65
90-days compressive strength, σc MN/m2 18-30 25-40
Tensile strength, σt - 0.10-0.15 0.07-0.10
Compressive strength, σc
Unit weight, γc KN/m3 23-25
Modulus of elasticity E, GN/m2 30-45
Poisson ratio - 0.15-0.22
Shrinkage (at 1 year) % 0.02-0.05
Coefficient of thermal expansion X10-6/C 9-12
Three approaches:
RDLC- Rolled Dry Lean Concrete
RCD- Rolled –Concrete Dam (Japan) – lean hearting
RCC- Roller – Compacted Concrete – high paste content material and known to have high
PFA content
Page 126
Hydropower Engineering-II
In the construction of RCC dam the concrete is handled as an earth fill, and compacted at or
near its optimum moisture content in thin layers.
Construction in RDLC and some other RCCs permits an intensively mechanized construction
process, with concrete delivery and compaction plant. Construction joints, if considered, may
be sawn through each successive layer of concrete after placing.
The RCC approach is best suited to wide valley; giving scope for unobstructed „end-to-end‟
continues placing. The construction saving realized are at a maximum for high-volume dams
and arise from a 25-35% reduction in construction time as well as reduced unit costs for the
RCC. In its low-cost „geotechnical‟ format (e.g. RDLC). RCC is particularly suited to more
remote sites where importation of cement and/or PFA is difficult or expensive.
Number of passes of roller = compaction magnitude.
Construction of Embankment Dams:
The construction operations of embankment dams fall in to four principal groups relating to:
i. Material source development: opening out of borrow areas or quarries, installation of fixed
plants, e.g. crushers, and conveyors, construction of access and haulage roads, etc.
ii. Foundation preparation and construction: river diversion, removal of top soil and
weathered surface.
iii. Fill construction: placing to materials and compaction.
iv. Ancillary works construction: construction of spillways, stilling basins, culverts, tunnels
and outlet works.
Page 127
Hydropower Engineering-II
Page 128
Hydropower Engineering-II
iv. Control of surface erosion (precipitation or limited overtopping flows). The use of geo-
grids and mats in conjunction with natural vegetation has proved for erosion resistance.
v. Separation interlayer: geo-synthetics can be used to act as an interlayer to ensure positive
separation of fill materials, at an interface.
Page 129
Hydropower Engineering-II
Organization chart of project construction operation:
Page 130
Hydropower Engineering-II
The procedures, generally referred to as SOP‟s (Standing Operating Procedures) should also
include emergency preparedness plans and inundation mapping, the extent and nature of
inspections, hydrologic and reservoir operations, and other pertinent aspects of dam O&M.
Page 131
Hydropower Engineering-II
concepts associated with the construction of embankments and concrete structures and
with the installation of mechanical and electrical equipment
Keeping construction engineers and inspectors informed of the field control measures
and tests required to ensure quality construction
Maintaining an adequately staffed and equipped materials laboratory at the dam site to
meet the field testing requirements
Providing a formal plan for construction inspection to ensure that each facet of
essential work is accomplished in multi shift operations
Giving the Project Construction Engineer the authority to suspend work until all site
conditions different from those anticipated are evaluated and the necessary design or
construction changes are implemented
Inspection and acceptation of critical work stages, by the appropriate engineers or
geologist (design and/or technical review personnel)
Keeping a job diary and documentation that provides a complete history of the work
Providing mapping and photographic documentation of the construction progress and
of significant events; e.g., geologic maps and photographs of final treated foundations.
Existing Dams:
i. Operation and Maintenance
The operation and maintenance procedure implemented should ensure the safe operation of the
dam and provide for timely repair of facilities. The essential procedures include:
Preparing SOP‟s (Standing Operating Procedures); information on the preparation of
SOP‟s
Training personnel in both normal and emergency operation and maintenance
responsibilities and in problem detection
Maintaining a written record of reservoir, waterway, and mechanical equipment
operations and of maintenance activities
Testing full operation of spillway and outlet works gates on a regular basis, using both
primary and auxiliary power systems
Providing for public safety and for security against vandalism of essential operating
equipment
Establishing and maintaining communication links with local governmental agencies
and authorities
Page 132
Hydropower Engineering-II
Preparing and maintaining current EPP‟s (Emergency Preparedness Plan)
ii. Periodic Examinations and Evaluations
The periodic examination and evaluation of dams and reservoirs is of considerable importance
for public safety. The intent of conducting periodic examinations and evaluations is to disclose
conditions that can disrupt operations or threaten dam safety early enough for these conditions
to be corrected.
Documentation on Dams:
All significant design data, computations, and engineering and management decisions should
be documented and retained throughout the life of a dam. The documentation should cover
investigations and design, construction plans and specifications, construction history,
operation and maintenance instructions and history, instrumentation monitoring instructions,
structural behavior history, damage, repairs and improvements, and periodic examinations and
evaluations. Memoranda, reports, criteria, computations, drawings and records of all major
decisions regarding the design, construction, operation and maintenance, and safety of the dam
should be permanently retained and accessible in central file.
Page 133
Hydropower Engineering-II
7.1 Definition
Small Hydropower may be classified according to different criteria such as head, powerhouse
layout, and installed capacity. The definition may vary at different times and in different
countries implying that it has no strict definition. According to UNDO an installed capacity
between 101KW and 1000KW is defined as Mini Hydropower (MHP) development.
Page 134
Hydropower Engineering-II
world can be energized in a year. Therefore, the lack of electricity becomes a great constraint
to the rural and the national economic development of a country.
At the heart of rural electrification is the development of commercial energy owing to some
historic factors, vast rural areas are completely cut off from the national economy. Most
energy consumption in rural areas is still from biomass and electricity occupies only a small
portion of the energy consumed.
In our country more than 80% of the population is scattered in the country side consuming
88.4% of the Biomass energy out of 94.5% of Biomass energy consumption in the country
(1996- statistics). On the other hand 751.128 metric ton of fuel oil was consumed out of which
only about 8% of the fuel oil was consumed by rural energy consumption. This shows that the
imposition on the financial balance of the country is high but urban and industrial centers are
using large proportion of imported energy sources. Such disproportionate energy allocation
leads to an increase in fire wood consumption in rural areas resulting in soil erosion and loss
as well as a decrease in soil fertility and damage to the environment. Therefore, the promotion
of rural commercial energy is a critical decision for our nation.
Those who are in favor of using conventional energy think that it all the total fire wood
consumption in rural areas of the world is replaced by oil, about 0.2 billion tons of oil will be
needed annually occupying only 7% of the total oil production in the world. So shortage of
energy in rural areas is actually is an issue of poverty rather than an energy issue.
Page 135
Hydropower Engineering-II
The main advantages of MHP are:
its suitably for decentralized development, fully using local materials and appropriate
technology with the participation of local people,
its mature technology and small investment risk,
its low operating costs easy maintenance and reliable power supply
little environmental impact during construction with some positive impact on the
environment
the obvious social benefit to a developing local economy and improvements in the
material and spiritual life of local residents
Hence, it is pointed out in a United Nations report that as a clean and renewable energy SHP
or MHP ought to be developed as a priority for its maximum economic benefits as well as its
multi purposes, such as irrigation water supply, fish breeding and ecological effects.
For developing countries, the maximum capacity of the rural industrial equipment is generally
less than 100KW and rural industries can be energized by MHP if MHP resources are
abundant in the region. For instance in China the unit cost of MHP is around $650– 00 and its
M&O cost is much less than that of diesel or coal fueled plants. Therefore China has gone to
great efforts to develop SHP and MHP, and „‟to get richness by constructing MPH‟‟ has
become the common experience in hilly regions of china.
Page 136
Hydropower Engineering-II
7.5 Preferential policy for MHP development
For instance in china, the government has stipulated a series of preferential policies to promote
SHP development as follows:
The “three self-policy“, namely self-construction, self-management and self-consumption;
which means that the people who invested in and constructed SHP stations have the right
to manage the plant to use, to use the output of SHP plant and to obtain benefits from the
station
“Further developing SHP with benefits from existing stations which means that the
benefits of SHP should be reinvested to further develop SHP should be reinvested to
further develop SHP plants or local grids
Local grids can have their own supply area and unified management system of generation,
distribution and power supply and be connected to and mutually aided by large (or
national) grids
The government gives preferential loans and exemption to SHP developers
7.6 Funding
Generally speaking the unit cost of SHP or MHP is greater than that of medium and large
hydropower plants and its initial investment is a great burden for local developers. The
funding of SHP or MHP should mainly be self-generated and be based on the particular
conditions of a country. In any case a feasibility study of the project is first required for the
developer or owner so as to make the right decision.
The funds for SHP or MHP can be gathered from:
some subsidies or preferential loans from central and local governments
loans from banks
investment from industrial consumers and local people
Page 137
Hydropower Engineering-II
some practical devices, such as ELC (Electric Load Control), a simplified govern or
(operator), auto-valves with counterweight and automatic controllers have been invented
which reduces the operating cost and improved operation
Substituting electricity for fire wood gives positive effect by reducing deforestation and,
hence, conserving the ecological environment as well as improving the hygiene of rural
people.
Page 138
Hydropower Engineering-II
Impacts of hydropower schemes are highly location and technology specific. A high mountain
diversion scheme, being situated in a highly sensitive area is more likely to generate impact
than an integral low-head scheme in a valley. Diversion projects in mountains use the large
change in elevation of a river as it flows downstream. The tail water from the power plant then
reenters the river, and entire areas of the river may be bypassed by a large volume of water,
when the plant is in operation. Given below is a description of possible impacts. However it is
not certain that all or most of this list of descriptions will be applicable to a specific project. In
the list are identified the event, persons or things affected, impact and priority at local and
national levels.
Page 139
Hydropower Engineering-II
In operation:
Flow alteration
Fish Loss of habitat High
Plants Loss of habitat Medium
Birds Loss of habitat Medium
Wildlife Loss of habitat Medium
Page 140
Hydropower Engineering-II
Electricity transmission:
On the construction:
Accidents
Minor injuries Medium
Workers
Major injuries High
Workers
Death High
Workers
Jobs created and increased income
Local and national
General public
employment benefits High
On the operation:
Page 141
Hydropower Engineering-II
Physical presence Loss of future production Low
Forestry Visual intrusion Medium
General public Injury, death Medium
Birds
General public
Nonexistent accidents Major injuries Negligible
Accidents on maintenance of
transmission lines Minor injuries Negligible
General public
8.1 Reservoirs
The impacts generated by the construction of a dam and the creation of the adjoining reservoir
include the loss of ground, the construction and opening of construction roads, working
platforms, excavation works, blasting which are dependent on the dam size. Other non-
negligible impacts are the barrier effect and the alteration of flow consequent to a river
regulation that did not exist before.
Page 142
Hydropower Engineering-II
restored as soon as possible. In any case these impacts are always transitory and do not
constitute a serious obstacle to the administrative authorization procedure.
In view of its protective role against riverine erosion it is wise to restore and reinforce the river
bank vegetation that may have been damaged during construction of the hydraulic structures.
It should be noted that the ground should be re-vegetated with indigenous species, better
adapted to the local conditions.
The impact assessment study should take count of the effects of excess excavated material in
the stream. To mitigate the impacts the traffic operation, avoiding of excavated material
should be carefully planned prior to construction.
On the positive side it should be noted that the increase in the level of activity in an area
usually economically depressed, by using local manpower and small local subcontractors
during the construction phase is to be welcomed.
Page 143
Hydropower Engineering-II
Precision manufactured gears in the speed increaser
Turbine casings and speed increaser casings strongly stiffened to avoid resonance and
vibrations
Anchoring of the turbine by special anti-shrinking concrete to ensure the monolithic
condition between hydro unit and foundation block
Turbine ballasting with large masses of concrete to reduce to a minimum the vibrations
amplitude
Each of the components that comprise a hydro scheme - powerhouse, weir, spillway, penstock,
intake, tailrace, and substation and transmission lines - has potential to create a change in the
visual impact of the site by introducing contrasting forms, lines, color or textures. The design,
location, and appearance of any one feature may well determine the level of public acceptance
for the entire scheme.
The penstock is usually the main cause of annoyance. Its layout must be carefully studied
using every natural feature - rocks, ground, and vegetation - to cover it and painting it if there
is no other solution so as to minimize contrast with the background. If the penstock can be
buried, this is usually the best solution. Expansion joints and concrete anchor blocks can then
be reduced or eliminated; the ground is returned to its original state and the pipe does not form
a barrier to the passage of wild life.
The powerhouse, with the intake, the penstock tailrace and transmission lines must be
skillfully inserted into the landscape. Any mitigation strategies should be incorporated in the
project, usually without too much extra cost to facilitate permit approval.
Page 144
Hydropower Engineering-II
8.5 Preliminary Questions
In assessing the feasibility of hydro power developments, it is important to consider early the
social, political, and environmental feasibility at a proposed site or in a resource area that has
potential sites. The purpose of such an evaluation is to determine whether there are restraints
due to social concerns such as disruption of peoples' lives or the existing economy,
institutional or legal restraints: and/or environmental concerns that will make proceeding with
development unwise. Further, it is important to quantify the restraints to determine whether
more time should be devoted to the study of social, political, or environmental acceptability
and whether mitigation can be provided so that a hydro plant can be economically installed
and operated.
Activity:
-When do you think that, the Environmental feasibility will be assessed?
-Whom do you think that, the responsible that should do the Evaluation?
Page 145
Hydropower Engineering-II
8.6 Checklist of Considerations
In referring to the assessment of social, political, and environmental feasibility, the words used
to refer to the variables in the appraisal include such words as factors, parameters, issues, and
considerations. Important in the evaluation is first to develop a comprehensive checklist of the
considerations that need to be assessed. This hopefully will ensure that none of the
considerations will be overlooked. The degree of sophistication with which one weighs and
determines the impact of hydropower development on various factors being considered will be
quite site specific and depend on time and funding limitations. The following is a
comprehensive checklist that might be used in developing and using methodologies.
i. Natural considerations:
a. Terrestrial
Soils Seismic activity
Landforms
b. Hydrological
Surface water levels Ground water levels
Surface water quantities Groundwater quantities
Surface water quality Groundwater quality
c. Biological
Vegetation Birds
Fish and aquatic life Terrestrial animals
d. Atmospheric
Air quality Air movement
ii. Cultural and human considerations:
a. Social
Scenic views and vistas Rare and unique species
Open-space qualities Health and safety
Historical and archaeological Ambient noise level
sites Residential integrity
b. Local economy
Employment (short-term) Housing (short-term)
Employment (long-term) Housing (long-term)
Page 146
Hydropower Engineering-II
Fiscal effects on local Business-activity
government
c. Land use and land value
Agricultural Industrial
Residential Other (public domain, public
Commercial areas)
d. Infrastructure
Transportation Government service
Utilities Educational opportunity and
Waste disposal facilities
e. Recreation
Hunting Boating Pick-nicking
Fishing Swimming Hiking/biking
Impact matrix approach technique requires the development of a matrix in which certain
activities or actions are arrayed against the various considerations. If the environmental impact
appraisal is very broad, it can include the social, political, and economic issues that must be
weighed. The actions or activities for planning, development, and operating a hydropower
development are arrayed on the vertical scale of a matrix table and the various social, political,
and environmental considerations are arrayed on the horizontal scale.
The practice is to enter into the matrix table a symbol to indicate the extent, to which a
specific activity or sub activity will affect the particular consideration or sub factor. The entry
can be qualitatively expressed in a scaling or rating approach by assigning the symbols,
indicating the impacts have significant, limited and insignificant impacts on the resources area.
This implies the evaluator has good understanding of the base considerations as they exist or
are expected to exist before construction and development proceeds. Naturally, this takes on a
Page 147
Hydropower Engineering-II
subjective weighing because it is not always easy to document why a particular entry was
made. It implies a weighing of impact before and after development and even at stages during
construction.
Another technique that has been used in siting highways (Oglesby, Bishop, and Willike,
1970), in a water resource planning effort (Bishop, 1972), and in an appraisal of recreational
water bodies (Milligan and Warnick, 1973) is a factor profile analysis. This is a graphical
representation of subjective scaling of the impact or importance of various considerations on
the overall feasibility of development. Feasibility should be considered from four principal
areas of concern: (1) engineering and technological feasibility, (2) social acceptability, (3)
environmental acceptability, and (4) economic feasibility. Figure 8.3 arrays the considerations
environmental evaluation in just three main categories and thirteen sub factors. In Figure B, a
bar graph has been developed for each of the sub factors of the major considerations. This
requires the subjective scaling of impact the hydropower development will have either during
construction or during operation, or both. A magnitude representation from 0 to -10 and 0 to
+10 is made of each of the sub factors in the factor profile. This scaling is here referred to as
an attribute number. Note that it can be either negative or positive, or both. For instance, a
hydropower development might disrupt fish habitat by decreasing flows during certain times
and cause a valuation of a negative entry in the factor profile. At the same time the flow
release might improve the flows at other times, making a positive entry on the factor profile.
Guidelines and ways of consistently arriving at the attribute number is the challenging
problem. Here is where it is important to call on the help of professionals to develop the
guidelines or scaling the attribute number and actually making the assessment.
Page 148
Hydropower Engineering-II
Considerations of Impact
Flood control □ □ □
Impoundment ◙ □
control
Worker & □
equipment access
Security & safety □
Page 149
Figure 8.3: Example of factor profile for evaluating impact of hydropower development
on environmental acceptability
To illustrate the technique more fully, a factor profile for just one category of the cultural
and human considerations has been developed and presented in Figure 8.3. This is the
social category with thirteen sub factors. Guidelines for assigning numerical value for the
attribute numbers of two of the considerations are given below.
Page 150
Figure 8.4: Example factor profile for evaluating impact of hydropower development on
social conditions.
For open-space qualities:
If several thousand acres of open space is inundated and penstock and canals cross and
mar the open nature of the area, a-10 could be assigned.
If a large area of open space is inundated, a -7 could be assigned.
If a limited area of open space is disrupted, a -3 could be assigned.
If no apparent change will occur in the open-space area, a 0 could be assigned.
If impoundment and control of stream allows use of open space and new vegetation
creates a more open and attractive area, a +5 could be assigned.
The factor profile can give a Visual representation of restraints. If desired, it is possible to
sum the various values of attribute numbers. It is also possible to give added weight to
certain of the considerations by giving a weighting factor to a given consideration or sub
factor.
Page 151
Legal Considerations:
Legal considerations are important in the appraisal of social and political feasibility of
hydropower developments: water rights, regional state regulatory permits, and federal
licensing.
Depending on the state involved, there are other legal requirements that must be met and
require attention even at the feasibility study level. Typical of these requirements are
stream channel alteration permits, public utility certificates for study of need and
convenience, state environmental impact statements, and proof of compliance with state
water quality standards. Because of the direct impact of hydropower developments on the
stream's fishery resources, there always should be requirements and political acceptance
that must be sought from the legal authority. These problems must be addressed as the
planning proceeds.
Page 152
9. ECONOMIC AND FINANCIAL EVALUTION OF
HYDROPOWER PROJECTS
9.1. Introduction
After our technical deliberations, we arrive at the economic and financial appraisal.
The objective of an economic and financial appraisal are first to provide an economic basis
for deciding whether or not to implement a project, and secondly to examine promising
development alternative in an economic respect to determine which is the most attractive
An economic appraisal is based on the benefits and costs from the viewpoint of society as
a whole, while a financial appraisal is viewed from the perspective of the project sponsor,
and states whether the tangible value of the output of the project will be sufficient to
amortize (pay back) the project loan, pay operation and maintenance cost, and meet the
interest on other financial obligations.
Page 153
Information from financing: fund sources and funding; its yearly installment during
construction; interest rate; the basic economic and financial discount rate and rate of
escalation.
.
Information on Alternative Energy Sources: construction costs; energy costs, operation
and maintenance costs, fuel prices, etc.
Information on Socio-Economic elements: institutions; codes; policies and other socio-
economic factors concerning the environment industrial and agricultural productivities,
etc.
Information on Other Cost Rates, e.g. fees necessary for a license and low producers;
categories of taxes and their rates; rates of insurance etc.
Economic and financial appraisals are two aspects defining the project feasibility in respect
of economics. The project sponsor pursuing maximum profits may ignore the
environmental impact or may harm the national interest, which will lead to the project
would be financially infeasible on one hand, on the other hand the project would be
financially infeasible owing to the large discrepancy between theoretical energy costs and
actual tariffs. Therefore the justification for financial feasibility becomes difficult. The
project sponsor should take measure to strive to reduce investment costs, seek loans with a
low interest, change the ways of funding, etc.
Page 154
Economic analysis deals primarily with the development and applications of benefit cost
analysis, which is the most frequently, used procedure for project economic evaluation.
Economic feasibility is considered from the stand point of the sponsor. When total benefits
accruing from the project exceed the total costs incurred, the project is regarded as
economically feasible.
Page 155
Present Value:
This is the value obtained by discounting all future costs and revenues into the present
timeframe so that they can be compared on a current monetary basis. The sum of these
values represents the net present value.
Annual Equivalent Value:
This is the capital value of an annuity, the cumulated present values of which (in n years)
equals the total initial capital cost, or the capital is recovered in n years by an annual
equivalent value under a given discount rate.
P F / 1 i ,
n
(9.2)
Where 1 /(1 i) n the present–value factor with a single payment
3. The uniform payment future–value equation
F A1 i n 1] / i, (9.3)
Page 156
n
n
A P * i 1 i / 1 i 1 , (9.6)
Figure 9.1 shows the cash flow and the relationship between P, A, n and F.
Equations (9.2) and (9.5) are also suitable for the present–value calculation of benefit.
9.2.1 Costs
Capital costs: This is the sum of money invested in a project (including its interest during
construction) before its completion. Accordingly, the project sponsor will return the money
from the energy sales to pay back the initial expenditure and operating costs, and at the
same time retain the remaining profit for himself.
In general the capital cost of preliminary design is classified by the following items:
Civil engineering;
Electro-mechanical equipment and its installation;
Equipment such as the gate, hoist, penstock and its installation;
Temporary engineering;
Compensation for filling the reservoir;
Other expenses, e.g. administration of the construction unit, operation preparation,
scientific research, exploration and design, construction monitoring , establishment of
the base of the construction enterprises, legal procedures, certificates, taxes and
insurance,
Reservation for unforeseen expenditures;
Interest during the construction period;
Page 157
Table 9.1: An example for estimating the total investment
Description Cost ( 103 US$)
Direct costs
Civil 4636 .50
penstock 155.90
Contingencies
15% for electromechanical equipment 174.00
20% for civil and penstock 958.00
Engineering costs
15% for direct costs and contingencies 1063.00
Administration and others
10% for direct costs and contingencies 708.00
Total 8859.00
Interest over 2 years’ period of construction 1373.00
Total Capital costs of project 10232.00
In a feasibility study, the items can be roughly divided as shown in Table 9.1
Annual costs:
Annual costs include the annual capital cost (the financial costs for loan amortization and
interest) and the annual operation and maintenance costs, the latter involving salaries,
material expenses, water fees, overhaul expenses, insurance, interim replacement and
administration, etc. If the capital cost of the transmission line is included in the total
investment, then the annual cost will have two parts: power generation and power supply.
Page 158
The rate of the annual capital cost equals the capital recovery factor; the rate of the annual
operation and maintenance costs.
9.2.2 Benefits
There are two kinds of benefit: direct benefit and indirect benefit
The direct benefit is mainly from the benefits of the energy sale, as in the following
expression
Be E e 1 1 p, (9.7)
Where
Be = benefit from energy sale;
Ee = effective annual energy generation, i.e. the total net energy output given out by the
generator of the hydropower plant during the year after the deduction of energy loss in
outage;
Plant use factor
Grid loss factor
P = energy price
In Equation (9.7) E e 1 1 represents the amount of electric energy on sale. The
project sponsor should decide which energy purchaser will be willing to purchase the
energy output from the hydropower plant and what selling price of the energy can be
obtained in the market.
Besides the benefit from energy sales, there would be a benefit from multipurpose
utilization
Indirect benefit involves tangible and intangible benefits; the former can be calculated in
money terms, e.g. pumping irrigation will increase the yield of the grain harvest, electric
lighting may save kerosene expenses; the latter is uncountable e.g. to raise the standard of
living of the society, also reduces deforestation, increase the opportunity of employment.
Economic analysis should consider the social benefit as far as possible, while financial
analysis deals only with direct cash flow.
Page 159
9.3 METHODS OF ECONOMIC APPRAISAL
The net present value (NPV), benefit–cost ratio (B/C) and internal rate of return (IRR) are
methods generally used in an economic appraisal.
A diagram of equation (9.8) is shown Figure 9.3; when m = the construction period; A =
annual operating and maintenance cost, B = annual benefit, P = annual investment. C in
equation (9.8) involves P and A.
If we set the first year of operation of the hydropower plant as the base year, and the
annual capital input, annual operating and maintenance costs, and annual benefit are
uniform in distribution i.e., p o Pl P2 .... P, An 1 An2 An 3 , B n 1 Bn2 Bn3 B, , then
the NPV can be directly calculated by Equation (9.9)
1 i n 1 p 1 i m1
1
NPV B A 1 (9.9)
i 1 i
n m i
If any residual values R exist at the end of the calculation period they should join the
benefit flow to be discounted.
Example: Given a cash flow as shown in Table 9.2, calculate the NPV when
(a) i = 10%, price escalation = 0;
(b) i = 10%, price escalation = 7%
From the above calculation in Table 9.2 we find that NPV < 0 when the rate of the price escalation
= 0 and NPV > 0 when the rate of the price escalation = 7%; hence the price escalation has a
large influence on the result.
Page 160
If we set the first year of commissioning as the base year, as shown in Figure 9.4, and the capital
cost is uniformly invested over two years, then according to Equation (9.9) we get
1 i
1 i 1
p 1
' 1
NPV B A i 1 n m1
i
n m i
24500 4500
1 0.1 1 150000
1 0.1 1
1
15 21
0.11 0.1 2 0.1
15
20500US dollars .
criterion B / C 1 :
/ 1 i j
n
B
j 0 j
B / C (9.10)
/ 1 i
n j
Cj
j 0
In the above example with an escalation rate of 7 per cent, if we multiply columns (2), (3)
and (4) by column (6) in Table 9.2(b), and add each of the said columns, we then obtain
Page 162
that the present value of the escalating stream of benefit is $256700 and that of the
escalating stream of costs is $194700. The B/C ratio is then 1.32 indicating an
economically feasible project.
The B/C ratio can also be attained by converting the capital cost and its interest during the
construction period to an annuity value, then
B
B/C (9.11)
i 1 i n
P I A
1 i n 1
Where
B = annual benefit i 1 i
n
Like the NPV, IRR incorporates all the pertinent economic data, but the criterion does not
reflect any information on project scale and, consequently it cannot be used as the sole
ranking criterion. The IRR expression is:
NPV
n Bj Cj
0,
j 0 1 IRR
j
(9.12)
Where IRR – i on the condition that NPV = 0
Page 163
If the investment, annual operating maintenance cost, and annual benefit are uniform, we
can find the IRR by equation (9.9) through iterative calculation.
Page 164
Table 9.3: A financial cash – flow calculation (103 $US)
Year Capital O&M(10% Total Benefit Net Present Net Sum of Sum of
Cost escalation Cost (10% benefit value present Net benefit Net
) (2)+(3) escalation (3)-(4) factor value (6) present
) (12.5%) (6)x(7) value (8)
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10)
0 375000 375000 -375000 1.0000 -375000 -375000 -375000
1 16 500 16500 67375 50785 0.8889 45223 -324125 -329777
2 18 150 18150 74112 55962 0.7901 44216 -268163 -285561
3 19 965 19965 81524 61559 0.7023 43235 -206604 -202326
4 21 961 21961 89676 67715 0.6243 42270 -138089 -200048
5 24 158 24158 98644 74486 0.5549 41334 -64403 -158714
6 26 573 26573 108508 81935 0.4933 40416 17532 -118298
7 29 231 29231 119359 90128 0.4385 39517 107660 -73731
8 32 154 32154 131295 99141 0.3897 38639 206801 -40142
9 35 369 35369 144424 109055 0.3464 37781 315856 -2361
10 38 906 38906 158867 119961 0.3079 36942 435817 34581
11 42 797 42797 174753 131956 0.2737 36120 567773 70701
12 47 076 47076 192229 145153 0.2433 35318 712926 109019
13 51 784 51784 211452 159668 0.2163 34533 872594 140556
14 56 962 56962 232597 175635 0.1923 33766 1048229 174318
15 62 659 62659 255856 193197 0.1709 33 015 1241426 207333
The sources of income include the finance from the loan, bonds and credit, energy and
power values.
Expenditure involves project investment, interest during construction, debt service,
operating and maintenance costs, fund drawing, tax and insurance etc.
Page 165
In the calculation of the payback period, the debt should be liquidated by annual profits
and revenues. The government would provide policies to accelerate the liquidation e.g.
income tax is not payable during the pack back period, to pay back the loan through the
partial amortization fund, etc.
Table 9.4 shows an example of a finical balance of a project.
From that balance we have found that the negative cash flows occur in 1981, 1982, 1984,
and 1985, which must be covered from other financial resources. However, there is a
positive cash flow during the first complete year of operation
Page 166
1. Engineering, administration,
Financial and legal
2. Construction and contingencies
3. Interest during construction
4. Debt service on loan and bonds 249 249 249 249 249 249 248
5. O&M escalated at 10% 32 35 39 43 47 52 52
Total expenditure 281 284 288 292 296 301 292
Income
1. Loan and bond sale
2. Interest returned on bond money
3. Capacity credit 15 15 15 15 15 15 15
4. Power generation revenue 606 667 732 807 887 976 976
escalated at 10%
Total income Balance 621 682 748 822 902 991 991
Balance 340 398 460 530 606 690 699
If the sponsor obtains a short-term loan from the bank with an interest rate of 13 per cent to fill the
deficit in 1981 and 1982 and will pay back the loan in 1983, then we list the payback-period
calculation as shown in Table 9.5 (assume that the amortization fund is paid for the debt, and taxes
are exempt, so that only O&M expenses are deducted from the generation benefit).
From the calculation in Table 9.5, we can see that the project sponsor will liquidate the debt
during the six years after putting the project into operation (in table 9.4 the planner gave the debt
service until 1995, which is safe).
For brief estimation in a feasibility study, the method of annual equivalent cost can be applied to
calculate the payback period. Let us take the same example as shown in Table 9.3. If we assume
8.5 years for the payback period, i = 12.5% percent, the total capital cost $375000. Then the
capital recovery factors equals 0.1976, and the annual capital cost is $74124. From the calculation
in Table 9.6, we find that the debt can be paid back at the ninth year (from column (7))
Page 167
Table 9.5: The payback period calculation (103$ US)
Items 1981 1982 1983 1984 1985 1986
1. Cumulative borrowed capital at
the beginning of the year 0 77.7 187.9 2024.3 2166.4 2184.0
2. Borrowed capital of this year 73.0 94.0 1812.0 -121.0 -67.0 -15.0
3. Interest of this year 4.7 16.2 142.2 263.1 281.6 283.9
4. Sum of capital and interest 77.7 187.9 2024.3 2166.4 2381.0 2452.9
5. Revenue from generation with 0 0 0 0 207 455
10% escalation
6. O&M expenses with 10% 0 0 0 0 10 24
escalation
7. Sinking fund 0 0 0 0 197 431
8. Debt at the end of the year 77.7 187.9 2024.3 2166.4 2184.0 2021.9
Items 1987 1988 1989 1990 1991
1. Cumulative borrowed capital at
the beginning of the year 2021.9 1795.7 1492.1 1097.1 592.7
2. Borrowed capital of this year -15.0 -15.0 -15.0 -15.0 -15.0
3. Interest of this year 262.8 233.4 194.0 142.6 77.1
4. Sum of capital and interest 2269.9 2014.1 1671.1 1224.1 654.7
5. Revenue from generation with
10% escalation 501.0 551.0 606.0 667.0 732.0
6. O&M expenses with 10% 27.0 29.0 32.0 35.0 39.0
escalation
7. Sinking fund 474.0 522.0 574.0 632.0 693.0
8. Debt at the end of the year 1795.7 1492.1 1097.1 592.7 -38.3
Note: (1) the figure –121 is interest returned on the bond money; -67 is that plus capacity
Credit; -15 is capacity credit.
(2) Half interest is considered for the borrowed capital of the present year.
(3) All the data are transcribed from Table 9.4
Page 168
9.5.3 Generation cost and profit analysis
Generation costs are the sum of the annual operating and maintenance costs plus the
amortization cost. The amortization cost depends on the amortization rate, which equals
the inverse of the amortization period. However, the amortization period can be shortened
in order to accelerate amortization.
Unit generation cost in an important index on which the energy price is mainly based. Unit
generation cost is the generation cost divided by the annual energy output. Here the annual
energy output is the net energy given out to the grid or user after deducting the plant use
and outage losses (see Equation (9.7) of Sub section 9.3.2)
Table 9.6: Annual equivalent cost used for the payback period calculation $US
Year Debt service O&M (10% Total cost Benefit Net cash Sum of net
escalation (10% flow (50-(4) cash flow
escalation)
(1) (2) (3) (4) (5) (6) (7)
1 74124 16500 90624 76375 -14249 -14249
2 74124 18150 92274 74112 -18162 -32411
3 74124 19965 94089 18524 -12565 -44976
4 74124 21961 96085 89676 -6409 -51385
5 74124 24158 98284 98644 360 -51025
6 74124 26573 100697 108508 7811 -43214
7 74124 29231 103355 119359 16004 -27210
8 74124 32154 106278 131259 25017 -2193
9 74124 35369 109493 144244 34931 +32 738
The electrical energy must be sent to consumers for sale. The cost of energy sales equals the
generation cost plus the energy supply cost. The unit cost of energy sales equals the cost of energy
sales divided by the annual energy for sale. Here the annual energy for sale is the net energy sold
to consumers after deducting the transmission losses (see equation (9.7) of Sub section 9.3.2).
The profit obtained from power generation is the net benefit from the energy sales, which equals
the total benefit of energy sales from which the cost of energy sales and taxes (or other terms of
expenses) is deducted. The profit is first used to repay debts, then for private or group benefit.
Page 169
9.4.3 Uncertainty Analysis
For hydropower projects there would be a lacking of certainty about capital cost estimates,
future annual costs and the future value of energy. Uncertainty analysis aims to analyze the
capability to ensure an outcome unfavorable to the project sponsor. This risk should be
analyzed and minimized as much as is feasible.
Uncertainty analysis includes sensitivity analysis and risk analysis.
Page 170
Self-Check Summery Exercises
1. Why basic and specific investigation of resources is carried out in the planning phase of
Hydropower project?
2. Some methods are developed for estimation of flow to ungagged sites. Why? Mention at least
three of the methods?
3. What are the principal objectives of instrumentation in Hydropower development?
4. What are the positive and negative impacts of hydropower projects in relation to social and
environmental?
5. What are main stages in dam site appraisal and project development activities?
6. Enumerate the phases of power system planning process in transmission and distribution of
electric power?
7. Differentiate between economic life, design period and payback period?
8. In what way or to what extent a hydropower project can bring tangible benefits
9. What sort of information / documents is required for conducting the economic and financial
Appraisal of a hydropower project?
10. Two sites in the Abay river basin are under study for the construction of hydropower Project.
The contour map of the basin and description of the sites are shown below.
Site A
The shape of the valley V-shape or nearly u-shape
There is small overburden at the river bed level and the geology of the abutment is sound rock.
The shape of the watershed is narrow.
Site B
The shape of the valley is nearly trapezoidal
There is deep overburden at the river bed and the geology of the abutment is good
The shape of the watershed is wide
Inflow to site B is from the two tributaries
Page 171
Tribut
ary-1
Main River
Year Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
1997 186.9 116.0 77.4 63.2 73.5 410.6 2113.6 4397.5 3775.4 2083.3 764.5 394.5
1998 268.2 161.2 92.2 115.4 163.1 410.6 1824.2 4077.7 3833.4 2127.8 767.1 399.0
1999 221.7 133.4 92.8 117.3 107.0 missing 1739.8 3655.5 3007.1 3432.5 1084.2 473.1
2000 264.9 165.0 267.5 324.9 171.5 448.0 1376.2 4173.1 missing 905.0 431.9 243.7
2001 143.7 107.0 62.5 80.6 92.8 469.9 1892.5 4619.8 3464.1 2351.5 856.0 412.5
Months Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Rainfall (mm) 11.7 23.7 36.5 65.1 50.3 158.3 316.8 305.3 128.3 95.1 37.8 10.9
Evaporation(mm) 191.7 217.7 222.6 217.2 207.3 135.7 110 112.5 136.2 169.3 173.2 182.4
Page 172
Site-A Site-B
Expected data after study Catchment area= 5,650km2
3m3/s should be released from the storage so as to maintain for environment and aquatic life
Elevation(m) 1442 1445 1450 1455 14460 1465 1470 1475 1480
Capacity (Mm3) 0 4.96 11.4 20.33 32.17 48.92 74.92 115.75 175
Elevation(m) 1485 1490 1495 1500 1505 1510 1515 1520 1525
Capacity (Mm3) 250.6 342.23 451.1 575.92 716.5 874.67 1049.7 1241.2 1448.4
Plant type: ICS with a load factor of 0.48 , Grid loss factor = 0.35
Plant use factor of o.67 Energy price = 0.75Birr/kwh
Mean annual energy generation = 9708Wh/yr.
Conveyance: Length of head race tunnel = 1685m
Length of tail race tunnel = 1140m
Tail race level = 1320m a.s.l
Generator efficiency (16poles, 50HZ) = 92%, Turbine efficiency = 90%, Normal operating
speed=150rpm
a) Propose the appropriate type of dams for each site in relation to valley shape, flooding
nature of the catchment and geology of the site? With regard to valley shape and selected
dam type, recommend the possible type of spillway to be constructed for each site?
b) Determine the height of the dam required to store the water, the gross head, and net head
available for this particular project? Assume Francis type turbine is used.
c) Develop FDC and determine the firm power and the installed capacity of the plant?
d) Design the components of the hydropower scheme?
Page 173
11. The costs and benefits of the hydropower project is given below
Page 174
portion of the river drainage basin. The outflows from the reservoir are given in table C.
Scale of the isohytal map is 1:400,000.Using the information above: Determine
a) The river flow at its mouth that would be useful for the hydropower study and also what is
the firm flow from the Flow duration curve you develop?
b) If the characteristics of the turbine is proposed the following :
Normal operating speed=150rpm, Net head available=16m, turbine efficiency=94%
i) The maximum power output from the installation?
ii) Estimate the specific speed and specify the type of turbine
Avg. value of precipitation b/n isohytal lines (mm) Planimetered Area (mm2)
762 11.94
889 26.13
1016 14.45
Month Jan Feb Mar Apr May June July Aug Sep oct Nov Dec
No of
days 31 28 31 30 31 30 31 31 30 31 30 31
Discharge
(m3/s) 7.11 7.14 9.88 33.13 80.02 64.31 22.57 11.84 9.4 9.4 9.51 8.44
Page 175
References:
1. Water Power by E. Mosonyi, Vol. I &II
2. Hydraulic Structures by P. Novak
3. Water Power Engineering by Barrows
4. Water Power Engineering by Dandaekar & Sharma
Page 176