HVDC and Facts
HVDC and Facts
HVDC and Facts
AN INTRODUCTION
Dr.S.VASANTHARATHNA
Long Ago
Past Era
This Era
Mental Torture
-- Power Reliability
ELECTRICITY
The BIG Player
REGIONAL
GRIDS
CHICKEN-NECK
NORTHERN
REGION
NORTHEASTERN
REGION
EASTERN
REGION
WESTER
NREGION
SOUTHERN
REGION
Norther
n
Auraiya
220kV
Malanpur
Malda
Gorakhpu
Singrauli
r/Luckno
w
500M
W
400k
V
Easter
n
500MW
W
220 kV
1000MW
220kV
Ramagundam
400k
V
Rourkela
Jeypor
e
500M
W
Gazuwaka
Southern
NEW is a
major grid
Budhipadar
Vindhyachal Korba
Weste Raipur
rn Chandrapur
Kolhapur
Belgaum
NorthEastern
Bongaigaon
Sasaram
Allahabad
Salakati
Talcher
Balimel
a
2500M
W
220kV
Kolar Upper
Sileru
INDIAN TRANSMISSION
NETWORK 2008
VOLTAGE
UNDER
CENTRAL
UNDER STATE
TOTAL CKM
+500KV HVDC
5668
1504
7172
765 KV
2709
409
3118
400KV
61800
27696
89496
22OKV
10066
112894
122960
TOTAL
80243
142503
222746
Installed Capacity
2,05,340.26 MW
200,000 MW by 2012
9
10
11
INCREASE IN GENERATION
Thermal Power - installed 24,000
MW
Target 66000 MW by 2017
NLC Tamilnadu Power Ltd.
1000 MW coal based plant at
Tuticorin by 2011
SAIL 1000 MW coal fired
plant
Nuclear 2720 MW
Target 20,000 MW by 2020
13
CONGESTION
While load growth has
occurred,
Even
with
increased
generating capacity
still the same prevails
One-way congestion
Two-way congestion
14
POWER QUALITY
a serious issue that touches almost all
industrial,
commercial and
residential
customers in some way.
16
POWER QUALITY
In view of an equipment designer or manufacturer might be that
power quality is a perfect sinusoidal wave, with no variations in the
voltage, and no noise present on the grounding system.
In view of an electrical utility engineer might be that power quality is
simply voltage availability or outage minutes.
In view of an end-user, is that power quality or quality power is
simply the power that works for whatever equipment the end-user is
applying.
18
Mechanical Analogy
Balls Generators
Strings- Interconnection lines
Fill a glass with the water to quarter of its capacity. The dropping of the marble is
akin to a disturbance in the power system. In this situation no water from the glass
will splash out, indicating the system is stable.
Now fill the glass with water close to its brim and drop the same marble into the
glass. In this case, water will splash out, indicating the system is unstable
21
Causes of Blackout
I increases
Heat Increases
Length increases
Sag increases
Flashover on trees
Crosses the safe limit
Transients increase
23
X =XG + XL + XM
EG = EM + jXI
24
Example
A Generator having Xd=0.7 pu delivers
rated load at a pf of 0.8 lag
i) find Pe,Qe,E and
V=1+j0
25
Qe=0.535 pu
26
Qe=1.07 pu
27
51 Hz
28
Low Frequency
N Magnetic Induction Harmonic Effects
Overheat of Machines B Core Loss
Efficiency Fault Current Machine
Saturates Motor Burnsout
High Frequency
N B heat pf
29
Frequency in %
30
32
33
34
35
The implementation of the above objectives requires the development of high power
compensators and controllers.
The technology needed for this is high power electronics with real time operating
control.
The realization of such an overall system optimization control can be considered as
an additional objective of FACTS controllers
Sequence of Events
12:15 p.m. Incorrect telemetry data renders inoperative the state estimator, a power flow monitoring tool operated by the
Indiana-based Midwest Independent Transmission System Operator (MISO). An operator corrects the telemetry problem but forgets to
restart the monitoring tool.
1:31 p.m. The Eastlake, Ohio generating plant shuts down. The plant is owned by FirstEnergy, an Akron, Ohio-based
company that had experienced extensive recent maintenance problems
2:02 p.m. The first of several 345 kV overhead transmission lines in northeast Ohio fails due to contact with a tree in Walton
Hills, Ohio.
2:14 p.m. An
3:05 p.m. A 345 kV transmission line known as the Chamberlain-Harding line fails in Parma, south of Cleveland, due to a tree.
3:17 p.m.
3:32 p.m. Power shifted by the first failure onto another 345 kV power line, the Hanna-Juniper interconnection, causes it to sag into a
tree, bringing it offline as well. While MISO and FirstEnergy controllers concentrate on understanding the failures, they fail to inform
system controllers in nearby states.
3:41 p.m. A circuit breaker connecting FirstEnergy's grid with that of American Electric Power is tripped as a 345 kV power line (Star-
Voltage dips temporarily on the Ohio portion of the grid. Controllers take no action.
3:46 p.m. A fifth 345 kV line, the Tidd-Canton Central line, trips offline.
37
345 kV line trips due to undervoltage and overcurrent interpreted as a short circuit.
4:064:08 p.m. A sustained power surge north toward Cleveland overloads three 138 kV lines.
4:05:57 p.m. The Sammis-Star
4:09:02 p.m. Voltage sags deeply as Ohio draws 2 GW of power from Michigan, creating simultaneous undervoltage and overcurrent conditions as power
attempts to flow in such a way as to rebalance the system's voltage.
4:10:34 p.m. Many transmission lines trip out, first in Michigan and then in Ohio, blocking the eastward flow of power around the south shore of Lake Erie.
Suddenly bereft of demand, generating stations go offline, creating a huge power deficit. In seconds, power surges in from the east, overloading east-coast
power plants whose
4:10:37 p.m. The eastern and western Michigan power grids disconnect from each other. Two 345 kV lines in Michigan trip. A line that runs from Grand
Ledge to Ann Arbor known as the Oneida-Majestic interconnection trips. A short time later, a line running from Bay City south to Flint in Consumers Energy's
system known as the Hampton-Thetford line also trips.
4:10:38 p.m. Cleveland separates from the Pennsylvania grid.
4:10:39 p.m. 3.7 GW power flows from the east along the north shore of Lake Erie, through Ontario to southern Michigan and northern Ohio, a flow more
than ten times greater than the condition 30 seconds earlier, causing a voltage drop across the system.
4:10:40 p.m. Flow flips to 2 GW eastward from Michigan through Ontario (a net reversal of 5.7 GW of power), then reverses back westward again within a
half second.
4:10:43 p.m. International connections between the United States and Canada begin failing.
4:10:45 p.m. Northwestern Ontario separates from the east when the Wawa-Marathon 230 kV line north of Lake Superior disconnects. The first Ontario
power plants go offline in response to the unstable voltage and current demand on the system.
4:10:46 p.m. New York separates from the New England grid. 4:10:50 p.m. Ontario separates from the western New York grid.
4:11:57 p.m. The Keith-Waterman, Bunce Creek-Scott 230 kV lines and the St. Clair-Lambton #1 230 kV line and #2 345 kV line between Michigan and
Ontario fail. 4:12:03 p.m. Windsor, Ontario and surrounding areas drop off the grid.
4:12:58 p.m. Northern New Jersey separates its power-grids from New York and the Philadelphia area, causing a cascade of failing secondary generator
plants along the Jersey coast and throughout the inland west.
4:13 p.m. End of cascading failure. 256 power plants are off-line, 85% of which went offline after the grid
separations occurred, most due to the action of automatic protective controls.
38
In India
On 2nd January 2010, Northern Region experienced a partial grid disturbance on the
night of 2nd January, 2010 at 03:01 hrs. in which power supply in Punjab, North Haryana,
Himachal Pradesh, Jammu & Kashmir and UT Chandigarh sub-system were affected.
with 14 x 400 kV lines and 79 x 220 kV lines out.
Load affected in this area was about 7,500 MW and there was about 4,000 MW loss of
generation.
Dense fog mixed with pollution reduces the breakdown strength of insulators and increases the
conductivity along the surface of insulators causing the flash over across insulators and tripping
of lines on earth fault.
It has been observed that whenever temperature is low i.e. below 9 degree and humidity is high,
more than 90 degree, formation of sufficient smog takes place causing flash over across
insulators strings.
Evening peak hours of 1st Jan 2010 were normal, however low ambient temperature (below
100 C) and high relative humidity (above 90 %) were observed in the region. Such atmospheric
condition was witnessed for the first time during this winter season. Situation was under alert
condition as it has been experienced in the past that such atmospheric conditions are favorable
for fog / smog formation and tripping of transmission lines may occur.
This was followed by another partial disturbance almost on the same pattern, during the late
evening hours on the same day i.e. 2nd January, 2010 at 21:54 hrs.
39
40
Power Factor
Problems due to Power Factor
Watts
2
2
kVA
kVA==(KW)
(KW)2++(KVAR)
(KVAR)2
42
42
The power factor impact can be quite largefor example, for a metropolitan
area of 5million people,
the shift from winter peak to summer peak demand
can
shift peak load
from 9,200 MW in winter to 10,000 MW in summer
that change to summer electric loads
can
shift the load power factor
from 0.92 in winter down to 0.88 in summer
and this will increase
the MVAr load demand from 3,950 in winter up to 5,400 in summer
43
44
44
Load Compensation
Management of Reactive Power to improve
Power Quality
Installing Shunt Compensating devices
Line Compensation
Ferranti effect is minimised
Underexcited operation of synchronous
generators is not required
The power transfer capability of the line is
enhanced.
Compensating Devices
Capacitors
Capacitors and Inductors
Active Voltage Source (Synchronous
generator)
Controlling the sending and receiving end
voltages
Controlling the angle between sending and
receiving end voltages
Controlling the series reactance
Series Capacitor
-Controls impedance
Switched Shunt-Capacitor and Reactor
-Controls voltage
Transformer LTC
-Controls voltage
Phase Shifting Transformer
-Controls angle
Synchronous Condenser
-Controls voltage
Special Stability Controls
-Typically focuses on voltage control but can often include direct control
of power
Others (When Thermal Limits are Involved)
-Can included reconductoring, raising conductors, dynamic line
monitoring, adding new
lines, etc.
49
IPC
IPFC
SSSC
TCSC
TCSR
TCVL
TCVR
TSC
TSR
TCBR
TCPAR
TCPST
TSSR
TCR
UPFC
52
53
54
Series Controller
V
FC
Storage
SSSC, IPFC,
TCSC, TSSC,
TCSR, and TSSR.
Variable
Impedancecapacitor/ Reactor/ Power
Electronics based variable
source of main frequency,
subsynchronous
and
harmonic frequencies (or a
combination) to serve the
desired load
It injects voltage in series with
the line
If the voltage is in phase
quadrature with the line
current, the series controller
only supplies or consumes
variable reactive power
Any other phase relationship
will involve handling of real
power as well.
Shunt Controller
I
F
C
Unified
Series - Series
Controller
F
C
Dc link
ac lines
FC
Coordinated
Series and Shunt
Controller
V
FC
I
FC
Lin
e
Coordinat
ed Control
59
60
THYRISTOR-CONTROLLED REACTOR
Often the main TCR reactor is split into two halves, with the thyristor valve
connected between the two halves. This protects the vulnerable thyristor valve
from damage due to flashovers, lightning strikes etc.
By
Thyristor-controlled reactors can also be used for limiting voltage rises when
circuits are open.
Continuous control
No transients
Elimination of harmonics by tuning the capacitors
Compact design
TSC is a
shunt-connected
thyristor-switched capacitor
whose effective reactance is varied
in a stepwise manner
by full- or zero-conduction operation of the
thyristor valve
65
SVC
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
The signal washout is the high pass filter that prevents steady changes in
the speed from modifying the IPFC input parameter.
The value of the washout time constant w T should be high enough to allow
signals associated with oscillations in rotor speed to pass unchanged.
From the viewpoint of the washout function, the value of w T is not critical
and may be in the range of 1s to 20s.
The basic concept of voltage regulation is the addition of an appropriate inphase or a quadrature component to the prevailing terminal voltage in order to
change (increase or decrease) its magnitude to a desired value.
In thyristor based approach of voltage regulation, the insertion of voltage is
obtained by selection of appropriate tap of a regulating transformer (insertion
transformer), in series with the line.
104
Impulsive transient-medium
2.5
capacitor switching
1.5
2
1
1.5
amplitude in pu
0.5
0.5
-0.5
-1
-0.5
-1.5
-2
0.01
0.02
0.03
0.04
0.05
time in ms
0.06
0.07
0.08
0.09
0.1
-1
50
100
150
200
250
time in ms
300
350
400
450
Capacitor Switching
Impulsive Transients
Sag-short duration
1
0.8
0.6
0.4
amplitude in pu
amplitude in pu
0.2
0
-0.2
-0.4
-0.6
-0.8
-1
Momentary Interruptions
0.02
0.04
0.06
0.08
0.1
time in min
0.12
Voltage Sag
0.14
0.16
0.18
105
0.2
1
0.8
0.6
a m p lit u d e in p u
0.4
0.2
0
-0.2
-0.4
-0.6
-0.8
-1
0.02
0.04
0.06
0.08
0.1
time in m
0.12
0.14
0.16
0.18
500
VC
0.2
500
0.02
0.04
bus voltage
0.06
0.08
0.1
ti
Harmonics
Voltage Imbalance
106
107
108
109
110
111
112
113
114
Phase 1
Initial Feasibility Studies to Determine System
Constraints and Reinforcement Needs
Phase 1 type studies are typically performed by
the transmission owner or its consultant. The
main study tools and FACTS model requirements
for Phase 1 type studies are:
Phase 2
Studies to Determine Type of Equipment,
Location, and Ratings
Phase 2 type studies are typically
performed by the transmission owner or its
consultant.
118
Phase 3
Pre- Specification Studies for Defining
Equipment Requirements
To be Able to Write a Technical
Specification and RFP to
Submit to
Potential Bidders
Phase 3 type studies are typically
performed by the transmission owner or its
consultant.
123
125
Phase 4
Pre-Manufacturing and Equipment Design
and Verification Studies
Phase 4 type studies are typically
performed by the vendor after an award of
a contract for the FACTS installation.
126
Phase 5
Studies for post-commissioning system
operation
Studies are typically performed by the
transmission owner.
128
FACTS controllers
Control attribute
STATCOM
SVC, TCR,
TSC, TSR
TCBR
SSSC, TCSC,
TSSC, TCSR,
TSSR
TCPST
UPFC, GUPFC
TCVL
TCVR, IPFC
Operating problem
Corrective action
FACTS controllers
Voltage limits:
Low voltage at heavy load
STATCOM, SVC
STATCOM, SVC
Thermal limits:
Transmission circuit overload
Reduce overload
Loop flows:
Parallel line load sharing
Issue
17 Close-in fault Causes Voltage Dip
Trips DR
18 Switchgear Ratings
19 Self Excited Induction Generator
20 Long Feeder Steady State
Stability
21 Stability During Faults
22 Loss of Exciters Causes Low
Voltage
23 Inrush of Induction Machines Can
Cause Voltage Dips
24 Voltage Cancelled by Forced
Commutated Inverters
25 Capacitor Switching Causes
Inverter Trip
26 Flicker from Windmill Blades
27 Upstream Single Phase Fault
Causes Fuse Blowing
28 Under frequency Relaying
29 Distribution Automation Studies
132
44
33
22
11
THE ROLE OF
CUSTOMERS
THE ROLE OF
MANUFACTURERS
REFERENCE
1.E.Acha, V.G.Agelidis, O.Anaya-Lara, T.J.E.Miller, Power Electronic Control in
Electrical Systems, Elsevier, 2002
2. D.P.Kothari, I.J.Nagrath, Modern Power System Analysis, McGrawHill, 2011
3. K.R.Padiyar, FACTS controllers in Power Transmission and Distribution, New
Age International Publishers, 2007.
4. www.abb.com
5. www.areva.com
6. www.epri.com
134
135