Different Type of CB and Its Functions. Erection, Testing & Commissioning of CB
Different Type of CB and Its Functions. Erection, Testing & Commissioning of CB
Different Type of CB and Its Functions. Erection, Testing & Commissioning of CB
ITS FUNCTIONS.
ERECTION, TESTING &
COMMISSIONING OF CB.
CB STANDARDS
Limitations:
On reaction with moisture, easily hydrated to give fluorides
compounds which causes degradation of insulation and
corrosion in the interrupting chamber.
Decomposition of SF6 gas due to reaction of erosion
products with SF6.
Restriction of exposure of SF6 in environment.
Different components of Circuit Breaker
a) Main Interrupter:
b) Pre insertion resistor:
CO-15sec-CO
Storage of Circuit Breaker:
Initial check ups on receipt of CB at site:
a) Check for any physical damage on
insulators.
b) No oil seepage should be from grading
capacitor.
c) Always place Breaker parts on elevated
leveled ground to ensure absence of water
logging.
d) Regularly monitor the positive pressure
inside the DAC and pole column.
Erection of Circuit Breaker
1) Placed breaker supports on the prepared
foundation.
2) Mount the pole column on breaker support and
ensure that gas coupling is positioned in according
to general lay out drawing.
3) Mounting of DAC and coupled the same with tie
insulated rod.
4) Coupled the acctuator assembly with the tie rod of
support column.
5) Make all pipe connection between each phase
operating mechanism to compressor.
6) Make all possible interpole wiring as per drawing.
7) For CGL make CB, apply slow closing procedure
measure the parameters of stroke, over travel and
wipe of mechanism.
Filling of SF6 gas :
Measure the dew point of SF6 gas stored in external cylinder.
Evacuate the Circuit breaker up to required vacuum
Check there is no drop in vacuum.
Fill the Nitrogen gas at positive pressure and ensure that
there is no drop in positive pressure.
Release the Nitrogen gas and fill the SF6 gas in breaker for
required pressure.
Measure the dew point of SF6 gas which should be more
than -35degC at atm pressure or more than -15degC at rated
pressure.
Check any leakage for SF6 gas with the help of SF6 gas
detector or by wrapping polythene on suspected joints.
Pre commissioning operational checks for CB
Low SF6 Pressure alarm.
Operational lock out for gas/Air.
Compressor start/stop switch.
CB auto-reclose lock out.
CB closing lockout.
Mechanical closing Interlock. (For ABB CB)
Air/oil pressure drop in operation.
Number of operation from local when breaker initially
close or open.
Air/oil pressure drop in 24hrs.
Check for pole discrepancy & Anti-hunting feature.
Pre commissioning testing on CB
1)Dew point measurement:
-- Dew point of SF6 gas at rated pressure is the tempreature at
which gas stars condensing.
-- Dew point indicates the change in the value of di-electric
properties of gas which do get changed due to mixing of
impurities like moisture & decomposed products.
-- Dew point of SF6 gas should be more than -35degC at atm
pressure or more than -15degC at rated pressure.
2) IR Measurement and coil resistance measurement:
Measure the IR for the control circuit and breaker. In open & closed condition).
IR shall not be less than Mohm for control circuit & 1Gohm for Breaker.
Measure the coil resistance & series resistor.
Pre Commissioning tests ….cont
3) Capacitance & Tan delta of CB grading capacitor:
--CB grading capacitors have oil filled capacitor elements. The
healthiness of the capacitor elements could be checked by
measurement of Cap & Tan delta.
-- Tan delta is defined as the ratio of resistive component of
current to that of capacitive current flowing in an insulating
material. The more the resistive component of the current, the
more will be the dissipation factor indicating the deterioration
of insulation.
**Test procedure: Earthing of kit – connect LV & HV at apposite
side of grading cap – Select UST mode in test kit – Test shall
be carried out at 2kV/10kV.
Pre Commissioning tests ….cont
4) Circuit Breaker operating timings.
Required for ….
• Close & opening time of main & PIR contacts.
• CO,OC & OCO operation timings.
• Auxiliary switches timing.
• Close & Open coil current.
Limits:
Closing time should be manufacturer specified and in no case shall
exceed 150msec.
Opening time should be manufacturer specified and in no case shall
exceed 25ms for 400kV & 35ms for 220kV.
PIR must get open prior to 5ms before opening of main contacts.
PIR must get close between 8-12ms before closing of main contact.
Pole to Pole discrepancy-3.33ms
Break to Break discrepancy – 2.5ms.
Adjustment in closing timing shall be carried out by adjusting
plunger movement of trip/close coil and adjustment in operating
mechanism.
Pre Commissioning tests ….cont
5) Static contact resistance measurement.
**Measure the contact resistance under static
condition to indicate wear out and
misalignment of the main contacts.
Test Procedure:
Earthing of kit – Breaker in closed position -
connect leads sequentially across each
interrupter – Lead must be connect as close to
CB flange – surface of lead connection should
be cleaned – Inject 100A current through the
kit.
Pre Commissioning tests ….cont
5) Dynamic contact resistance measurement:
i) DCRM is basically to monitor condition of CB mian & arcing
contacts without opening the interrupter.
ii) DCRM test gives information on erosion of arcing & main
contact, contact misalignment, contact wipe, main & arcing
contact resistance, healthiness of damping system, contact
travel & speed, mechanical integrity of various components.
iii) It plots the variation in contact resistance while first, the
arcing and then the main contacts engage and disengage
during CO operation.
iv) By injecting 100Amp(DC) current during CO operation (delay
-300msec & sampling freq-10kHrtz), voltage drop across
arcing & main contacts is measured to compute resistance
values in dynamic condition.
DCRM CONNECTION ARRANGEMENT
Remember…..
Sampling frequency of kit is 10kHz (min)
DCRM to be taken for CO operation.
CO delay time to be atleast 300 ms hence requiring
plot length of about 450ms.
CB flanges where Current and Voltage cables are to
be connected, should be thoroughly cleaned by
CTC
Connection should be done only on Interrupter
flanges and not on PIR or grading Capacitor
flanges.
Current leads to be connected outside whereas
Voltage leads to be connected inside.
Main contact resistance <75micro ohm/break.
Typical DCRM Signature
DCRM of CGL Make CB
Suspected Pole
Thank you for your kind
attention please