Kihbt 1 Project Road Visits
Kihbt 1 Project Road Visits
Kihbt 1 Project Road Visits
PROJECT
Kiambu, Muranga, Nyandarua, Kirinyaga, Nyeri,
Laikipia Counties
Plumb bob
Sledge Hammer
Ranging Rods
Claw Hammer
Nails
Mason
Hammer
Pegs
Profiles
Definition
• Setting out is the transfer of geometric measurements of the structure from the
drawings onto the ground.
• This is done by marking pegs on the ground at the site to indicate, initially
horizontal dimensions and, gradually, vertical levels of each of the components
of the structure.
General:
• Before the setting out is done, a site visit shall have been done by the engineer
to evaluate the site conditions and all other necessary information leading to a
specific choice of a particular type of structure to be constructed or maintained.
• In this evaluation a sketch map of the site with all its measurements should be
noted.
• The road cross sections and standards, which are necessary for the
establishment of vertical and horizontal alignments of the road components,
should be sketched.
• These sketches help the Engineer to carry out approximate estimates of
materials, stores, work and cost of the road.
• They are the details from these drawings which are set out on the ground during
setting out process.
• Setting out of dimensions of any construction is important because:
- It enables easy translation of drawing details into simple instructions,
which can easily be remembered by artisans.
- It enables sufficient information to be provided in the form of ‘pegs’,
nails, paint marks or crayon inks etc to permit as much accurate
construction as per design drawings.
After the horizontal alignment has been determined, the centreline is marked
at 20 m intervals by guiding a person with a ranging rod so that the rod is in line
with the two ranging rods at the intersection points.
Mark the start and the end of curves.
Do not set out straight lines in curves.
Cross-section
A cross section of a road set out in the field with ranging rods and pegs shows:
•The location of the centre line of the road.
•The location of the shoulders, side slopes, side drains and back slopes.
•The location of drifts, splashes and mitre drains
•The level of the camber, shoulders, side drains, drifts, splashes and mitre
drains.
•The amount of dig and fill
CURVE SETTING OUT METHODS
METHOD APPLICATION
SUITABLE ONLY FOR USE FOR CURVES WITH A RADIUS OF LESS THAN 30
STRING METHOD METRES.
THE AREA MUST BE FLAT AND FREE OF OBSTRUCTION.
MOST SUITABLE FOR JUNCTION CURVES AND HAIRPIN BENDS.
A (STANDARD) 13 6.5
C (REDUCED) 10 5.0
E (SUPERELEVATION) 13 6.5
F (RAR) 10 5.0
STRIPPING AND GRUBBING
•This activity includes the removal of all grass, upper grass roots and other
vegetation remaining after bush clearing (except trees) over the width that
earthworks will take place (Figure below).
•All topsoil should also be removed from the grubbed width as this would weaken
the road if included in its construction.
• The vegetation and topsoil should be discarded outside of the grubbed width.
Jembe (Hoe), Rake and Shovel are required for this activity.
TREE AND STUMP REMOVAL
• This activity includes the felling of trees within the area previously bush cleared
(See Figure below).
• The stumps must also be up-rooted and all material disposed of outside of the
cleared width.
• Burning may be necessary with the precautions described under "Bush Clearing".
• Great care must be taken in felling trees to avoid injuries; sufficient ropes should
be fixed to the tree to achieve a controlled felling.
• Most trees can be felled complete with roots using ropes if the soil is excavated
from around the main roots and these are then severed with axe or saw.
•Tree shading of the road surface retards sun and wind drying after rain.
•If trees have to be felled efforts should be made to replace them with saplings planted
in a location causing no obstruction to the road or to landowners.
•The saplings may be obtained from the Kenya Forest Services nursery.
Boulder Removals
• Boulders and rock are encountered in limited sections of some roads (Figure
below).
• Careful consideration should be given to minimising the work involved in crossing
these areas.
• There are a number of methods for dealing with these problems (Also see Figure
13):
• Modify alignment
• Remove boulders from road
• Bury boulders
• Split boulders using fire and water
• Split boulders using hand tools
• Split boulders using explosives
• Modify Alignment
• The horizontal alignment can sometimes be modified to avoid short sections with
rock and boulder problems. The vertical alignment may also be raised using fill
material. Often stones are available in the areas of boulders and rock. These can
be used to construct a hand packed stone pavement over the boulders or rock
thus overcoming the problem and avoiding the need to gravel that section of road.
Remove Boulders from Road
This is applicable for boulders of volume less than about 0.5 cubic metre. The
boulder is moved using crowbars as levers once a path has been excavated to
allow this. Lengths of track rail can be useful for rolling the boulders along.
Bury Boulders
If the boulder is larger than 0.5 cubic metre or lying deep in soil, it is often most
effective to dig a hole next to the stone and bury it. Care must be taken when
excavating alongside the boulder that labourers are working in safety. If the
boulder is lying on the centreline, it may be left if the camber formation works will
cover it.
Boulder Removals
• Split Boulders Using Fire and Water
• An individual boulder or a rock surface may be cracked by building a substantial fire
around/over it. The vegetation arising from previous activities may be used for this
purpose. The fire will usually need to be fuelled for a long period (more than 6
hours) to heat up and expand the rock sufficiently. The boulder/surface should then
be dowsed with cold water to encourage rapid shrinkage, and struck with
sledgehammers. Cracks should develop along weak planes allowing the rock to be
broken into pieces.
• Split Boulders using Hand Tools
• If the boulders or rock are weathered or cracked it is often possible to break it into
smaller pieces using pickaxes, sledgehammers and chisels/wedges, or plugs and
feathers. Holes can even be drilled in rock using hand quarry drills and
sledgehammers. These are then used for the splitting tools,
• Split Boulders using Explosives
• If there is a large number of boulders or a solid rock face to be removed then the
use of explosives may be justified. Care must be taken in drilling the holes (using
hand tools or compressed air driven tools) in the correct location and orientation. A
licensed blaster must carry out handling of explosives and blasting. This can be
arranged through the Engineer or a contractor.
• SAFETY
• It is essential that safety of labourers is given high priority in any work with trees,
rock or boulders.
KEY NOTES
BOULDER REMOVAL
DEALING WITH BOULDERS AND ROCK
Earthworks
Two methods
1. Excavation to level
2. Reshaping
Excavation to level
This type of formation method only applies to new alignments
Procedure
Vertical alignment ( ETL slots)
Excavation to level and compaction
Ditch excavation (middle third compaction)
Inslope and backslope excavation
Spreading and camber formation
Final compaction
Reshaping
This type of formation is for existing alignments with camber
Procedure
Vertical alignment(reshaping slots)
Side drain excavations
Spreading and compaction
DRAINAGE AND STRUCTURES
• Setting out of culverts
Consider a a minor road with 5.4m carriageway cross section
Procedure for setting out a culvert
Step 1
Establish 2 pegs (A & B) at both road edges and make sure the pegs are
the same level(use line & level or abney level)
Step 2
Measure the distance between step A and peg B (usually 5,4m for minor
roads)
Step 3
Calculate the depth to be excavated at the inlet to ensure adequate
cover(ext dia +overfill)
Step 4
•Calculate the difference in level between peg A & B with the chosen
culvert gradient ( assume 4% of the carriageway).
Step 5
•Calculate the depth to be excavated at the outlet (B) ( step 3+ step 4) =
step 5
Step 6
Raise level peg A by the same measurement that you have calculated
under step 4 by establishing a second peg (difference in level)
Step 7
Find the end of the outlet drain by using bonning rods and a stick or rod
of length 1.39 as in step 5 .Walk S and rod away from B until the tops of
A ,B and S are in line.
GRAVELLING WORKS
Site organization
•Traffic control
•Positioning of materials on site
•Labour arrangements
Daily production target with three teams: On a 5.4m cross-section, the three team are spaced out 300 m apart, all
working in the same lane and in the same direction. Over a six day week
Width 2.7m -> 300m a total of 900 m full width can be produced.