Material Requirement Planning: Amitabh Patnaik
Material Requirement Planning: Amitabh Patnaik
Material Requirement Planning: Amitabh Patnaik
AMITABH PATNAIK
Material Requirements
Planning
• Materials requirements planning (MRP) is the
logic for determining the number of parts,
components, and materials needed to produce
a product.
• MRP provides time scheduling information
specifying when each of the materials, parts,
and components should be ordered or
produced.
• Dependent demand drives MRP.
• MRP is a software system.
Material Requirements
Planning System
• Based on a master production schedule,
a material requirements planning
system:
– Creates schedules identifying the
specific parts and materials required
to produce end items.
– Determines exact unit numbers
needed.
– Determines the dates when orders for
those materials should be released,
based on lead times.
4
Master
Engineering
production Inventory
design
schedule transactions
changes
(MPS)
Reports
MRP OUTPUTS
MRP INPUTS MRP PROCESSING
Changes
Master
schedule Order release
Planned order
schedule
MRP computer
BOM program Exception Report
Planning reports
Performance Control
report
Inventory
Records Inventory transaction
Example of MRP Logic and
Product Structure Tree
Given the product structure tree for “A” and the lead time and demand
information below, provide a materials requirements plan that defines
the number of units of each component and when they will be needed.
Lead Times
Product Structure Tree for Assembly A A 1 day
B 2 days
A C 1 day
D 3 days
E 4 days
F 1 day
B(4) C(2)
Demand
Day 10 50 A
D(2) E(1) D(3) F(2) Day 8
Day 6
20 B (Spares)
15 D (Spares)
First, the number of units of “A” are scheduled backwards to
allow for their lead time. So, in the materials requirement plan
below, we have to place an order for 50 units of “A” in the 9th
week to receive them in the 10th week.
Day: 1 2 3 4 5 6 7 8 9 10
A Required 50
Order Placement 50
LT = 1 day
Next, we need to start scheduling the components that make up “A”. In
the case of component “B” we need 4 B’s for each A. Since we need 50
A’s, that means 200 B’s. And again, we back the schedule up for the
necessary 2 days of lead time.
Day: 1 2 3 4 5 6 7 8 9 10
A Required 50
Order Placement 50
B Required 20 200
Order Placement 20 200
LT = 2
Spares
A 4x50=200
B(4) C(2)
Day: 1 2 3 4 5 6 7 8 9 10
A Required 50
LT=1 Order Placement 50
B Required 20 200
LT=2 Order Placement 20 200
C Required 100
LT=1 Order Placement 100
D Required 55 400 300
LT=3 Order Placement 55 400 300
E Required 20 200
LT=4 Order Placement 20 200
F Required 200
LT=1 Order Placement 200
A
Part D: Day 6
40 + 15 spares
B(4) C(2)
G D
Primary MRP Reports