Chapter 14
Materials Requirements Planning
• Material Requirements Planning (MRP)
• MRP Logic and Product Structure Trees
• Time Fences
• MRP Example
• MRP II
• Lot Sizing in MRP Programs
Lead Times
Product Structure Tree for Assembly A A 1 day
B 2 days
A C 1 day
D 3 days
E 4 days
F 1 day
B(4) C(2)
Demand
Day 10 50 A
D(2) E(1) D(3) F(2) Day 8
Day 6
20 B (Spares)
15 D (Spares)
Day: 1 2 3 4 5 6 7 8 9 10
A Required 50
Order Placement 50
LT = 1 day
LT = 2
Spares
A 4x50=200
B(4) C(2)
A
Part D: Day 6
B(4) C(2) 40 + 15 spares
Aggregate Plan
(Product Groups)
MPS
(Specific End Items)
Exhibit 14.5
Example of Time Fences
Moderately
Frozen Firm Flexible
Capacity
Forecast and available
capacity
Firm Customer Orders
8 15 26
Weeks
Aggregate Forecasts
Firm orders
product of demand
from known
plan from random
customers
customers
Master
Engineering
production Inventory
design
schedule transactions
changes
(MPS)
• Pegging
– Identify each parent item that created demand.
MRP Example
Item On-Hand Lead Time (Weeks)
X X 50 2
A 75 3
B 25 1
A(2) B(1) C 10 2
D 20 2
C Gross Requirements 45 36 64
LT=2 On-Hand=10 10
Net Requirements 35 36 64
Planned Order Receipt 35 36 64
Planner Order Release 35 36 64
D Gross Requirements 15 135
LT=2 On-Hand=20 15 5
Net Requirements 130
Planned Order Receipt 130
Planner Order Release 130
A(2) B(1)
Day: 1 2 3 4 5 6 7 8 9 10
X Gross Requirements 95
LT=2 On-Hand=50 50
Net Requirements 45
Planned Order Receipt 45
Planner Order Release 45
A Gross Requirements 90 12
LT=3 On-Hand=75 75
Net Requirements 15 12
Planned Order Receipt 15 12
Planner Order Release 15 12
B Gross Requirements 7 45
LT=1 On-Hand=25 7 18
Net Requirements 27
Planned Order Receipt 27
Planner Order Release 27
C Gross Requirements 45 36 54 10
LT=2 On-Hand=10 10
Net Requirements 35 36 54 10
Planned Order Receipt 35 36 54 10
Planner Order Release 35 36 54 10
D Gross Requirements 15 135
LT=2 On-Hand=20 15 5
Net Requirements 130
Planned Order Receipt 130
Planner Order Release 130
No
Realistic? Feedback
Feedback
Yes
Execute:
Capacity Plans
Material Plans