Sample Weekly Update Report
Sample Weekly Update Report
SEM CALACA
SCOPE OF WORKS
Item # Activities % Weight Status Start Date Target Completion
1 Fabrication of Bracket and Support ( Cable Tray and Conduit ) 15% 13.0% 07/23/18 10/05/18
2 Fabrication of Junction Box 4% 4% Completed 07/16/18 09/17/18
3 Installation of Cable Tray 15% 12.3% 08/03/18 10/10/18
4 Installation of RSC Conduit 10% 5.4% 08/11/18 10/22/18
5 Installation of Junction Box 3% 2.33% 08/21/18 09/13/18
6 Excavation Works 2% 1.5% 07/23/18 09/19/18
7 Cable Pulling and Harnessing 18% 2.92% 09/07/18 11/29/18
8 Megger and Continuty Testing 4% 4% Completed 10/15/18 11/26/18
9 Termination, Testing & Commisioning 5% 0% 11/26/18 12/25/18
10 Dismantling of Existing Cables 12% 0% 02/01/19 02/15/19
11 Dismantling of Existing Cable Tray Supports 6% 0% 02/16/19 03/02/19
12 Dismantling of Existing Supports and Conduits 6% 0% 03/11/19 02/22/19
TOTAL 100% 45.5% Completed
Installation of JB
SUPPORT
DATE OF JB
JUNCTION BOX TOTAL JB INSTALLED OVERALL %
FABRICATED INSTALLED INSTALLED
SUPPORT
BJB-1 100.00% 100.00% 100.00% 100.00% 100.00% 27-Sep-18
BJB-6B 100.00% 100.00% 100.00% 100.00% 100.00% 29-Sep-18
BJB-13A 100.00% 100.00% 100.00% 100.00% 100.00% 1-Oct-18
BJB-13B 100.00% 100.00% 100.00% 100.00% 100.00% 1-Oct-18
BJB-6A 100.00% 100.00% 100.00% 100.00% 100.00% 1-Oct-18
BJB-12 100.00% 100.00% 100.00% 100.00% 100.00% 2-Oct-18
BJB-15 100.00% 100.00% 100.00% 100.00% 100.00% 2-Oct-18
BJB-5A 100.00% 100.00% 100.00% 100.00% 100.00% 2-Oct-18
BJB-7 100.00% 100.00% 100.00% 100.00% 100.00% 2-Oct-18
BJB-5B 100.00% 100.00% 100.00% 100.00% 100.00% 9-Oct-18
BJB-5C 100.00% 100.00% 100.00% 100.00% 100.00% 9-Oct-18
BJB-5D 100.00% 100.00% 100.00% 100.00% 100.00% 9-Oct-18
BJB-10 100.00% 100.00% 100.00% 100.00% 100.00% 10-Oct-18
BJB-14 100.00% 100.00% 100.00% 100.00% 100.00% 10-Oct-18
BJB-4 100.00% 100.00% 100.00% 100.00% 100.00% 10-Oct-18
BJB-8 100.00% 100.00% 100.00% 100.00% 100.00% 10-Oct-18
BJB-9 100.00% 100.00% 100.00% 100.00% 100.00% 10-Oct-18
BJB-BVA 100.00% 100.00% 100.00% 100.00% 100.00% 10-Oct-18
BJB-2 100.00% 100.00% 100.00% 100.00% 100.00% 11-Oct-18
BJB-3 100.00% 100.00% 100.00% 100.00% 100.00% 11-Oct-18
SJB-A 100.00% 100.00% 100.00% 100.00% 100.00% 1-Nov-18
SJB-R1 100.00% 100.00% 100.00% 100.00% 100.00% 1-Nov-18
SJB-R2 100.00% 100.00% 100.00% 100.00% 100.00% 1-Nov-18
SJB-CD 100.00% 100.00% 100.00% 100.00% 100.00% 2-Nov-18
SJB-L4 100.00% 100.00% 100.00% 100.00% 100.00% 2-Nov-18