Utility Process Training - Basic: Karbala Refinery Project
Utility Process Training - Basic: Karbala Refinery Project
Utility Process Training - Basic: Karbala Refinery Project
Before Start..
Please follow below rules!
1. INTRODUCTION
1) Introduction of Training Course Contents
2) Introduction of Training Schedule
2. PROCESS OVERVIEW
1) Process Principle
2) Basis of Design
3) Process Description
Expected Training
JV/Vendor Unit Unit Description Training Class
Duration
– Purpose
• The system provides drinking water to Buildings for refinery and distribution depot, and
Emergency eyewash and showers located inside refinery and distribution depot.
– Feed
– Product
Process Principle
• Chlorination
Water chlorination is the process of adding hypochlorite to water.
This method is used to kill certain bacteria and other microbes in water as chlorine is highly
toxic. In particular, chlorination is used to prevent the spread of waterborne diseases such
as cholera, dysentery, typhoid, etc.
• UV Radiation
In water, UV generates ozone in situ and thus has many of the advantages of ozone
disinfection.
However, ultraviolet germicidal irradiation alone (as well as chlorination alone) will not
remove toxins from bacteria, pesticides, heavy metals, etc. from water.
2. PROCESS OVERVIEW (Continued) Page : 7 / 32
Basis of Design
– Capacity
• System Capacity : 4000 m3 (Two Storage Tanks, 48 hours hold-up)
* Drinking Water demand : 0.4 m3/day per person
* Expected number of operator : 5000
* Resulting average drinking water make-up : 84 m3/h (2000 m3/day)
NORMAL CASE 35% (29 m3/h) 65% (55 m3/h) 1000 ppm
DESIGN CASE 14% (12 m3/h) 86% (72 m3/h) 2500 ppm
30-AT-5003A 30-AT-5019
2. PROCESS OVERVIEW (Continued) Page : 8 / 32
Basis of Design
From Raw Water Treatment Unit (1) Filtered Water
(UNIT 30)
From Raw Water Treatment Unit (2) Treated Water DRINKING (4) Drinking Water Drinking Water Loop Supply
(UNIT 30) WATER UNIT
Drinking Water
Loop Return
Sodium Hypochl.
Sol’n Static Mixer
1 operating
1 stand by
Discharge P :
Drinking
6.8 kg/cm2g
Water Pumps
2. PROCESS OVERVIEW (Continued) Page : 10 / 32
- 3D model
2. PROCESS OVERVIEW (Continued) Page : 13 / 32
- Process Description
Filtered Water from Ultrafiltration (30-PK-007) is blended with permeate from first Reverse
Osmosis (30-PK-001) to reduce salt concentration and comply with Iraqi standards for “Drinking
Water” (mainly Calcium). A conductivity analyzer (34-AT-0003) is provided on ultra-filtered water
for monitoring and blending ratio adjustment.
2. PROCESS OVERVIEW (Continued) Page : 14 / 32
Blended and chlorinated water is sent to drinking water storage tanks (34-TK-001A/B). Tanks are
under level control acting as master controller on filtered water and treated water flow controls via
ratio controller (34-FFIC-0003).
Each Tank is provided with an eductors (34-J-001 A/B) connected to drinking water loop return line
to facilitate drinking water temperature and composition homogenization. Both tanks are operating
normally.
2. PROCESS OVERVIEW (Continued) Page : 16 / 32
Drinking Water stream is under a residual chlorine analyzer (34-AI-0002) installed in the discharge
line of drinking water pumps.
In this case, shock dosing is required on recycle loop to increase the value.
3. PROCESS FLOW AND CONTROL Page : 17 / 32
- Process Variable
The most important and critical variables for the Drinking water Unit are:
Water level inside the drinking water tank
The correct water level inside the drinking water tank is essential:
to maintain the drinking water circuit filled
to avoid to damage the drinking water pumps
Drinking water tank level (34-LI-0002/0004) working range is 20 % (Low) to 80 % (High)
Chlorine concentration
Free chlorine (34-AI-0002) control range at drinking water supply is 0.2 ~ 0.5 ppmv.
Free chlorine (34-AI-0001) at make-up water could be adjusted appropriately to meet the
control range of 34-AI-0002 with stroke control of 34-PK-003.
3. PROCESS FLOW AND CONTROL (Continued) Page : 18 / 32
- Major Equipment
Drinking Water dosing pumps are automatically operated to allow residual free chlorine at the
Drinking Water distribution between 0.2 ppm and 0.5 ppm max and residual free chlorine on water
make-up to drinking water tanks of 0.5 ppm.
One continuous and one batch sodium hypochlorite solution injections are provided to maintain
the above required residual free chlorine concentration:
Drinking Water Make-Up line to Drinking Water Tanks by static mixer (34-PK-003-MX-001),
Hypochlorite is dosed at 3 ppm maximum.
Shock batch dosage through Sodium Hypochlorite Solution Static Mixer (34-PK-003-MX-002)
which motive fluid is Drinking Water return loop. Hypochlorite is dosed at 1 ppm on whole
drinking water storage volume (4032 m3) in a period of 10 hours once per week.
Sodium Hypochlorite solution concentration is 12% minimum.
Sodium Hypochlorite storage is for 7 days hold-up (1.5 m3 working volume).
Sodium Hypochlorite solution is supplied in drums.
3. PROCESS FLOW AND CONTROL (Continued) Page : 20 / 32
Level Controller (34-LIC-0005) acts as the master controller to control the level of Drinking Water
Storage Tank (34-TK-001AorB) by controlling the flow of Filtered Water by regulating 34-FV-0003
and flow of Treated Water by regulating 34-FV-0002. Ratio Controller 34-FFIC-0003 controls the
ratio of Filtered Water by regulating 34-FV-0003 and Treated Water by regulating 34-FV-0002.
3. PROCESS FLOW AND CONTROL (Continued) Page : 21 / 32
0-90 m3/h
0-50 m3/h
(25)
Input = 1000 ppm
0-80 m3/h
Input = 94 ppm (59)
3. PROCESS FLOW AND CONTROL (Continued) Page : 22 / 32
Analyzer detects conductivity in microS/cm. but it cannot be converted to total dissolved solution..
- 30-SC-5001 for Raw(River) water in ppm TDS (30-AT-5003A/B)
- 30-SC-5033 for RO permeate water in ppm TDS (30-AT-5019)
Generally, 1 microS/cm = 0.640 ppm TDS (for quick reference purpose only).
Residual free chlorine at required concentration at the Drinking Water distribution is maintained by
adjusting the Sodium Hypochlorite Dosing Pumps stroke in Drinking Water Chlorination Package
(34-PK-003).
Chlorine analyzer 34-AE-0001 analyses the residual free chlorine concentration and sends the
signal to 34-AIC-0001A. 34-AIC-0001A will send the signal to multiplication block 34-AY-0001.
34-FIC-0003 on Filtered Water Line and 34-FIC-0002 on Treated Water Line will send the signal to
the Summation Block 34-FY-0004. 34-FY-0004 will also send the summation signal to 34-AY-0001.
3. PROCESS FLOW AND CONTROL (Continued) Page : 23 / 32
The chloride injection rate is proportional to the drinking water make-up flow rate. However, the
make-up flow rate is depending on tank level (34-LIC-0005 cascade with 34-FFIC-0003).
When the make-up water flow rate is changed (increased or decreased), the injection rate shall be
changed according to the change of the water flow rates.
This flow rate change is expressed as the delta (D) between process value (PV) and set point (SP)
of 34-FFIC-0003. As of the results, the injection rate is also adjusted according to the delta (D) as
shown below;
Feed forward controller (34-AIC-0001B) using the delta is adjusting chemical injection rate ahead to
avoid dilution and/or enrichment by the first part of make-up water.
Pump selector (34-HS-0001) is provided for selection of injection pump (34-PK-003-P-001A/B).
3. PROCESS FLOW AND CONTROL (Continued) Page : 25 / 32
PDF Document
4. START-UP AND SHUTDOWN Page : 26 / 32
In case of initial start-up, it needs to be filled the underground drinking water header.
During the underground recirculation loop is filling, the tank level shall be maintained at 20% to
allow gravity flow. Service all eye wash stations to eliminate the air pocket in the drinking water
line.
1) Make sure level of tank 34-TK-001A/B is higher than 20% with auto mode.
2) Open 1-1/2” bypass valves between the pump suction and discharge lines.
Due to gravity, the water will fill the pump suction line, discharge header, Ultraviolet Sterilizer
and underground drinking water header.
3) Start 34-P-001A/B and adjust the discharge valve to appropriate pressure (34-PG-0001A)
4) Check chloride concentration of 34-AI-0002.
- Make sure Chlorine content is 0.2 ~ 0.5 mg/L by (34-AI-0002).
- Take water sample from 34-SC-0001 (34-P-001A/B Drinking Water Pumps Discharge Line)
- If required, shock dosing shall be performed
5) Start Ultraviolet sterilization
6) At the end of water filling, water make-up valves will be almost closed
7) Maintain the pump operation and open discharge valve fully
8) Put stand-by pump at remote mode for auto start by 34-PALL-0002
4. START-UP AND SHUTDOWN (Continued) Page : 30 / 32
Each ultraviolet sterilization train is designed for 100% capacity. During normal operation, both
trains can be operated (if required), (each 50%).
Caution:
Do not operate UV system until the UV chamber is completely filled with water. Do not allow
flow through UV chamber during start-up (until warming-up)
- Shutdown Procedure
1) Stop the drinking water pump
a. Put 34-LIC-0005 to manual mode and set output as 0.0%.
b. Put 34-FIC-0002 and 34-FIC-0003 to manual mode and Close valves.
c. Stop pump 34-P-001A and the local/remote selector position in LOCAL for both pumps.
2) Procedure
• Change the line up chlorine injection line from 34-PK-003-MX-001 to 34-PK-003-MX-002
• Adjust stroke of the pump to meet 2.0 l/h (30% stroke). Expected duration is 10 hours.
• If chlorine content at 34-AI-0002 is higher than 0.5 ppm, stop dosing.
• After shock dosing, line up change to 34-PK-003-MX-001 for normal operation.