PSTI-PPT On Hydro
PSTI-PPT On Hydro
PSTI-PPT On Hydro
DEVELOPMENT,INFRASTRUCTURE FACILITIES
COST STRUCTURE,MAINTENANCE & OPERATION.
• Introduction
• Present & Future Developments
• Steps involved in hydro power development
Identification of site
Hydrology 1
Assessment of power potential
Field investigations
Hydrological investigations
Topographical survey
Geological investigations
Construction material survey
Material testing
Relevant information of electrical system.
2
Design of electrical equipments
Hydraulic consideration
Electrical Considerations
Switching Safety and Electrical control Equipment:
3
• Infrastructure facilities required for a Hydroelectric Power
Project.
Dam
Water reservoir
Intake or control gates
The Head pond
The penstock
Water turbines
Generators
Transformer and Switch Yard
Tailrace
Power Houses and Facilities
Other infrastructure facilities
4
Layout of powerhouses
Classification based on characteristics
Isolated plant
Interconnected plant
Base load Stations
Peak load stations
Classification on the capacity of plants
Midget Plants
Low capacity plants
Medium capacity plants
High head plants
5
Classification on Hydraulic characteristics
Run-off-the-River type
Storage plants
Tidal plants
Types of Power house
Indoor
Semi outdoor
Outdoor
Underground
Advantages
Disadvantages
Choice between outdoor, semi outdoor
& indoor
6
Classification based on loads
Low head plants
Medium head plants
High head plants
Comparison of these types
Location of high head plants
Structure required for high head plants
7
Types of Turbines
Propeller or Axial flow types
Reaction types
Impulse types
Powerhouses, equipments & facilities
Types of powerhouses
Super structure
Sub structure
Conventional
Outdoor & Semi outdoor
Horizontal shaft
Underground
8
Terms relating to hydro power generation
Water power potential
Various water levels
Various heads
Firm & Secondary power
Various capacities
Load curves
Load, plant, capacity factor
Utilization, diversity, demand factor
Cold, operating & spinning reserves
9
• Equipments provided in the layout of the
powerhouse
Hydraulic equipments
Turbines
Gates and valves
Relief valves for penstocks
Governors
Flow measuring devices
Electrical equipments
Generators
Exciters
Transformers
Switching equipments
Low-tension buses
Switchboard panels
Switchboard equipments and instruments
Oil switches
Reactors
10
High Tension system
Buses
Circuit breakers, Current &Potential transformers
Lightning arrestors, Isolators
Outgoing connections
Auxiliaries
Control and Relay protection
Power and Control Cables
Earthing System
Storage batteries
Station lighting
11
Auxiliary systems
De-watering, filling, drainage system
Cooling and service water system
Fire and alarm system
Lubricating system & insulating oil system
Compressed air system
Heating, ventilation and air conditioning systems
Flow, pressure & level measuring system
Machine shop equipment and Crane
Emergency power system
Office rooms and Store
12
• Power and Energy in a Hydroelectric Project
HWL
Flow
Q
TWL
Turbine-Generator
m3/sec
m
P = 9.81 Q H tg kW
13
• Power and Energy in a Hydroelectric Project
m3/sec
m
P = 9.81 Q H tg kW
kWh
E = P t / 106 Mu
Head Water & Tail-water Rating curves
Rewriting,
TG manufacturers
E = 9.81 (Qt) H (htg)
Flow-Duration Curve
14
• Flow Duration Curve and Installed Capacity
Left Bank Canal
Reservoir
Dam Anicut
Distributary Gauging Station
(Typical)
(10 km Approximate)
Right Bank Canal
(60 km Approximate)
15
• Flow Duration Data
16
Flow (m3/sec)
1000
2000
3000
4000
5000
0
Jun-99
Jul-99
Aug-99
Sep-99
Oct-99
Nov-99
Dec-99
Jan-00
• Dam releases during a typical year
Feb-00
Mar-00
Apr-00
May-00
17
Flow (m3/sec)
100
20
40
60
80
0
Jun-99
Jul-99
Aug-99
Sep-99
Oct-99
Nov-99
Dec-99
Enlarged View
Jan-00
Feb-00
• Dam releases during a typical year -
Mar-00
Apr-00
May-00
18
• Computed flows over the anicut (weir)
v/s dam releases
100
90
80
70 Com puted Flows over weir
Flow (m3/sec)
60
Released flows from dam
50
40
30
20
10
0
Nov-99 Dec-99 Feb-00 Mar-00 May-00 Jul-00 Aug-00 Oct-00
19
• Flow Duration Curves
100
80
Ddam releases (1990-91 to 1999-2000)
Flow (m3/sec)
60
Dam releases (1999-2000)
40
Computed flows (1999-2000)
20
0
0 10 20 30 40 50 60 70 80 90 100
% Exceedance in a year
20
• Installed Capacity and Annual Energy
Case Installed Annual
Capacity Energy
(MW) (Mu)
(1) Dam Releases - 10 years 3 6.6
Not Viable
21
CONCLUSIONS
• Head is by and large determined by topography
• Flow is to be established prudently and with caution
• Hence, Hydrology is the backbone of a hydel project, on
which depends the
- Installed Capacity i.e., the scale of the project
- Annual Energy
- Capital Cost
- Project Viability and Project Funding
22
CONCLUSIONS (Continued)
• Developers should invest more of their time and
resources for Hydrological investigations, even
though such an investment apparently does not
yield immediate returns
• In this case, a GD measuring station should have
been established at the project site
• A simple and straightforward flow measurement is
much more reliable than any sophisticated
theoretical computations
23
Schematic Layout of a Hydroelectric Project
Diversion Structure
Powerhouse
Penstocks Tailpond
Tailrace
24
25
26
Components of a Hydro Electric Power Project
27
Cross section of a Hydro Electric Power Plant
28
Basic components of a conventional hydropower
plant
29
Major parts of Turbine- Generator
30
Cross Section of Kaplan Turbine
31
Cross Section of Pelton
32
Cross Section of Francis Turbine
33
Cross Section of Pump Turbine
of the pumped storage power plant
34
Assembly of a Pelton Turbine
35
Runner of a Francis Turbine
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
The largest hydro- electric power station
in the world
63
The upper reservoir and dam
64
Pipes supplying water
65
Hydroelectric Reservoir
66
67
68
69
70
71