Unit Operating Procedure
Unit Operating Procedure
TABLE OF CONTENTS
TITLE
PAGE NO.
INTRODUCTION ................................................................................................................................. 1
GLOSSARY OF COMMON TERMS .................................................................................................... 1
PRE-OPERATIONAL PROCEDURES ................................................................................................. 2
Cleanup........................................................................................................................................... 2
Chemical Cleaning ......................................................................................................................... 2
Steam Line Blowing ....................................................................................................................... 2
Setting Safety Valves ..................................................................................................................... 2
COLD START-UP ................................................................................................................................ 2
Cold Start Conditions .................................................................................................................... 2
Preparations for Lighting Off ........................................................................................................ 3
Warm Water Filling of the Boiler ................................................................................................... 7
Water Recirculation via Boiler for Clean-up ................................................................................ 7
Start of the Boiler Recirculation Pump (BRP) .............................................................................. 8
Initial Firing Precautions ............................................................................................................... 8
Superheat Steam Temperature Control (Prior to Unit Synchronization) ................................... 9
Air Preheater Protection During Unit Start-Ups On Oil ............................................................... 9
Lighting Off .................................................................................................................................. 10
Rolling and Synchronizing the Turbine ...................................................................................... 16
Introducing Coal .......................................................................................................................... 17
Initial Load Increase to 40% ........................................................................................................ 19
NORMAL OPERATION - UNIT LOAD CHANGES ............................................................................ 22
Decreasing Load .......................................................................................................................... 22
Increasing Load ........................................................................................................................... 23
NORMAL SHUTDOWN TO COLD ....................................................................................................
23
Digitally signed
Signature Not
Verified
by AMIT
GUPTA
WARM START-UP.............................................................................................................................
29
Reason: CAT
IVR
Warm Start Conditions ................................................................................................................
29
Location:
Preparations, Lighting Off, and Load Increase ..........................................................................
29
NTPCEOC
HOT START-UP ................................................................................................................................ 29
Hot Start Conditions .................................................................................................................... 29
Preparations, Lighting Off, and Load Increase .......................................................................... 30
Turbine Rolling and Synchronization ......................................................................................... 31
EMERGENCY PROCEDURES .......................................................................................................... 32
Reheater Protection ..................................................................................................................... 32
TURBINE VALVE CLOSURE (GRID DISCONNECT) ................................................................ 32
TURBINE TRIP .......................................................................................................................... 33
BARHII_00108_ UOP_REV02A.DOC-6/2/11
i
LIST OF FIGURES
TITLE
Figure 1:
Figure 2:
Figure 3:
Figure 4:
Figure 5:
PAGE NO.
Typical Air Flow Curve ....................................................................................................45
Mill Operating Diagram ...................................................................................................46
Startup Curves (Cold, Warm, & Hot Startups)...............................................................47
Boiler Cleanup Diagram..................................................................................................49
Recommended Startup, Shutdown, and Loading Guidelines ...................................... 50
DRAWING NO.
ii
BARHII_00108_ UOP_REV02A.DOC-6/2/11
LIST OF REFERENCES
TITLE
Airflow Control and Distribution ....................................................... Part 6
Boiler Circulating Pump Operating Procedures .............................. Part 2
Recommended Burner Management System .................................. Part 7
Pressure Part Connection and Expansion Movement Diagrams ... Part 2
Process & Instrumentation Diagrams .............................................. Part 2
Pulverized Coal System ..................................................................... Part 6
Pulverizer Operating Procedures ..................................................... Part 6
Soot Blowing Philosophy .................................................................. Part 5
Steam Line Blowing ........................................................................... Part 2
Tilting Tangential Firing System ....................................................... Part 6
Water Treatment................................................................................. Part 2
SSC and Pulverizer Rejects System
BARHII_00108_ UOP_REV02A.DOC-6/2/11
LOCATION
Section 4
Section 3
Section 1
Section 5
Section 7
Section 1
Section 2
Section 4
Section 3
Section 4
Section 3
Tab 9
Tab 1
Tab 2
Tab 8
Tab 3
III
iv
BARHII_00108_ UOP_REV02A.DOC-6/2/11
INTRODUCTION
These procedures are intended to serve as a guide during the initial
stages of operation. They include precautions, which must be observed,
and the proper operating sequences of the steam generator, fuel firing
equipment and auxiliary equipment. Refer to the General Arrangement
Drawings. The sequential procedures do not include all detailed reference to equipment such as the feed pumps, condensate pumps, or the
turbine.
Because the steam generator is only one part of a complex power station and all equipment must operate in unison, all specific procedures
and detailed values cannot be included in this manual. As operating experience is gained and the controls are fine-tuned, the characteristics
and operating requirements of the unit will become apparent.
Refer to the manufacturers instructions in the Maintenance and Vendor
Manual for further operating details for specific equipment, including
pre-operational and operational procedures.
References to other sections included in these operating procedures
are listed in the Table of Contents.
GLOSSARY OF COMMON
TERMS
BRP
SST
MEFCV
HWL-1
HWL-2
WKFCV
HP
High Pressure
LP
Low Pressure
SH
Superheat
RH
Reheat
BFPM
BMCR
SOFA
BARHII_00108_ UOP_REV02A.DOC-6/2/11
SSC
BMS
PRE-OPERATIONAL
PROCEDURES
Cleanup
The furnace should be inspected and cleaned both internally and externally before initial firing and prior to each subsequent cold start-up after
maintenance. Remove all foreign material from the pressure parts.
Clear any grating, pipe lines and electric conduit which may restrict
normal expansion of the steam generator. All personnel should be clear,
and the access doors closed. A complete check list should be prepared
by operating personnel.
Chemical Cleaning
Specific pre-operational chemical cleaning procedures are included
elsewhere in this manual. The fuel firing and boiler circulating pump operating procedures, outlined under COLD START_UP, Lighting Off,
should be used as a guide when operating the fuel firing equipment.
Steam Line Blowing
Prior to starting up a new steam generator, or following a major pressure part repair, the main steam and reheat steam lines should be
blown out to remove scale and other foreign matter. Steam line blowing,
which prevents damage to the turbine, should be done prior to chemical
cleaning. Refer to Steam Line Blowing Procedures for recommended
operating procedures and precautions.
Setting Safety Valves
The safety valves may be set following Unit load increase to near full
load for the first time. Refer to the safety valve manufacturer's instructions for setting procedures. Popping pressures and blowdowns should
be adjusted to conform with design values.
COLD START-UP
Cold Start Conditions
1.
2.
BARHII_00108_ UOP_REV02A.DOC-6/2/11
The unit has been chemically cleaned, and the steam lines have
been blown and safety valves have been set (before initial turbine
operation).
2.
All control systems have been checked and are available for service.
All safety interlock systems should be checked prior to start-up to
ensure proper functioning. Exercise the systems by creating the
actual interlock actuating conditions. Simulate the activating condition if the actual condition cannot be created.
3.
4.
The auxiliary fuel firing equipment has been checked out to ensure it is properly functioning. Recheck the following items to
make sure that:
a.
b.
c.
d.
5.
BARHII_00108_ UOP_REV02A.DOC-6/2/11
The pulverizers and feeders have been checked out and are
available for service. Recheck the following items to ensure that:
a.
b.
All hot air gates are closed and all hot air control dampers are
closed.
c.
All cold air gates are closed and the cold air control dampers
are open no more than 5%. If the PA fans have been off for
more than 5 minutes, the Cold Air Dampers are driven to a
100% airflow position.
d.
All bunker outlet valves are open and coal is available to the
feeders.
e.
6.
7.
The feedwater system and at least one feedwater pump, including the instrumentation and equipment, has been checked out
and is available for operation. During a start-up, the feedwater
flow should be controlled in automatic mode for best results.
8.
The deaerator auxiliary steam supply is operational and deaerated feedwater at 220F (104C) is available. To avoid oxygen
corrosion in the boiler, the use of deaerated feedwater with a
temperature of greater than 215F (102C) is recommended. Refer to Water Treatment instructions.
9.
The boiler recirculating pump (BRP) has been checked out, the
suction and discharge isolation valves are open, and all pump instrumentation is available for service. The pump differential pressure monitoring must be in service. Ensure that the proper trip
settings have been made.
Water treatment
instructions may please
be furnished.
10. The steam generator start-up system valves are ready for operation (MEFCV, HWL-1, HWL-2, WKFCV), with isolation valves
open. The SST level control using HWL-1 and HWL-2 valves has
been checked and is available for service.
11. The Startup system drain transfer system is ready for operation.
This system includes the flash tank, condensate receiving tank,
and drain transfer pumps.
12. Auxiliary steam is available from another operating boiler or
common system for supplying the deaerator, and feedwater tank.
13. Cooling water system is in operation.
CAUTION: The ID fans may be capable of developing
drafts that exceed furnace design pressure. Before starting an ID fan and before adjusting the ID flow control
device, an airflow path through the unit must be established and maintained by placing other dampers in the
system in the start-up positions indicated below.
The ID fan flow control device must be kept closed or at
the minimum open position until after the fan is started.
This minimizes the possibility of developing excessive
negative pressure in the unit during the starting procedure.
Furnace draft must be maintained within safe limits at all
times. Extreme care should be taken when draft and airflow controls are in the manual mode. Be alert for possible malfunctions of automatic control equipment resulting in abnormal excursions, negative or positive, in furnace pressure.
BARHII_00108_ UOP_REV02A.DOC-6/2/11
14. All air and gas handling equipment has been checked out and is
available for service. Air and gas duct dampers should be in the
start-up position as follows:
a.
For the first draft group to be started (ID and FD fans), the fan
outlet shutoff dampers are closed and the flow control device is
at minimum.
b.
For the second draft group (opposite ID and FD fans), the outlet shutoff dampers are open to provide a flow path through the
unit.
c.
The PA fan outlet shutoff dampers and flow control device are
closed or at the minimum position.
d.
The steam coil airheater inlet and outlet dampers are open and
the bypass dampers are closed. Alternately, if steam airpreheating is not desired, then the steam coil airheater inlet
and outlet dampers are closed and the bypass dampers are
open. Steam coil airheater usage should be based on maintaining average cold end temperature of the airheaters above
the recommended level for oil firing and coal firing. Refer to the
airheater operating manual for recommended setpoints.
e.
The air heater gas inlet isolation gates, gas outlet proportioning
dampers, and gas outlet isolation dampers are open for the
secondary APH, and closed for primary APH.
f.
g.
h.
i.
j.
One pulverizer seal air fan inlet shutoff damper is open with the
associated fan ready.
k.
15. The air heaters have been prepared for service and an adequate
means of extinguishing an air heater fire is available and ready
for use. Refer to the air heater instructions for details.
16. The soot blowing equipment has been checked for proper operation and the system is in the start-up mode with all blowers re-
BARHII_00108_ UOP_REV02A.DOC-6/2/11
BARHII_00108_ UOP_REV02A.DOC-6/2/11
The economizer outlet vent valve and waterwall outlet vent valve
is open.
2.
3.
4.
5.
6.
When the level in the SST reaches the high water level setpoint,
the HWL-1 valve will begin to open. Increase boiler feedwater
flow to 30% BMCR and ensure that the HWL-1 valve reaches
>30% open for more than 2 minutes. The water system is considered full when:
a.
The SST water level remains stable for 2 minutes with feedwater flow at 30% BMCR
and
The HWL-1 valve has been actively limiting SST level during
the above 2 minutes.
7.
After filling the water system, the feedwater flow to the boiler can
be reduced to 0% (local recirculation).During boiler filling, the water level in the deaerator must be maintained and water temperature at 220 F (104C).
1.
When the feedwater quality at the outlet of the HP feedwater heaters and the separator is not within the required limits (based on
sample analysis), a feedwater clean-up recirculation via the boiler
is necessary.
2.
Establish flow through the economizer, evaporator, and separator, and discharge from the boiler through HWL-1 to the flash
BARHII_00108_ UOP_REV02A.DOC-6/2/11
4.
5.
1.
a.
b.
c.
d.
e.
2.
3.
4.
With the BRP in operation, flow through the economizer and waterwall tubes increases substantially. It is recommended that the
water quality at the separator be re-checked. If necessary, continue to circulate water via the clean-up loop, including the polishing plant, until control limits are met at the separator outlet prior to
initial firing (reference figure 4 phase III).
1.
2.
High excess air through the air heaters. This minimizes the dilution of combustion air by inert gases carried over by the air heater
rotors.
BARHII_00108_ UOP_REV02A.DOC-6/2/11
Superheat Steam
Temperature Control
(Prior to Unit
Synchronization)
The boiler will normally be started-up de-coupled from the turbine using
the HP and LP bypass systems, which provide a steam flow path
through the superheater, to the reheater, and to the condenser. This
provides additional flexibility for adjusting steam temperatures to match
turbine requirements at start-up. The primary methods for controlling
steam temperature will be firing rate and airflow adjustment.
Air Preheater Protection
During Unit Start-Ups On
Oil
It is ALSTOMs strong recommendation to have the airheater soot blowing system continuously in service when firing oil to start up a boiler.
This measure is intended to help avoid airheater fires due to accumulation of oil vapor on heating surfaces or ash particles in the airheater
baskets. A retractable soot blower is normally installed at the cold end
of the airheater on the gas side, arranged close to the changeover of air
to gas side when looking in direction of rotation, opposite the hot spot
detection device. This soot blower is primarily designed to reduce
and/or control ash build-up in the airheater surface. It is not a cleaning
device such as the stationary wash down nozzles.
Steam is the preferred soot blowing media. However, on some units
auxiliary steam sources are not available when starting a unit, and normal sootblowing steam requirements are not reached until a later stage
in the start-up process. In those cases, compressed air is an acceptable alternate blowing media, though less effective than steam. If neither
steam nor compressed air is available, then extra attention must be given to any possible fuel oil carryover which could deposit in the airheater.
A device to identify such carryover would be a water-cooled lance, temporarily located in the gas path leading from the economizer outlet to
the airheater gas inlet (102 mm / 4 oxygen test ports could be used).
This lance, maintained at 93oC (200oF) or below, will cause any oil vapor in the flue gas to condense on it. If the lance is periodically withdrawn by a plant observer, it will indicate if corrective action to the oil firing system has to be taken.
For those units where neither auxiliary steam nor compressed air is
available for cold starts on oil, the hot spot detection system must be in
service. This system will identify any possible start of a fire in the airheater. Also, the top oil elevations should not be utilized since they are
more prone to cause oil carryover. Special attention must be given to
the readings of gas and air temperatures leaving the airheater. An unusual increase in any of these temperatures must be investigated immediately. Any indication of an airheater fire must be reacted to immediately because once a fire is well under way it cant be stopped before
the airheater is severely damaged.
BARHII_00108_ UOP_REV02A.DOC-6/2/11
Lighting Off
1.
10
Start the secondary and primary air heaters. Refer to the air heater instructions for operating details.
BARHII_00108_ UOP_REV02A.DOC-6/2/11
Start the first draft group: Start one ID fan, then the corresponding FD fan. Open the outlet shut-off dampers. Adjust the ID fan
for proper furnace draft, and set furnace pressure control to automatic. Adjust unit airflow to minimum 30%, and set unit airflow
control to automatic.
3.
Start the second draft group: After closing the outlet shut-off
dampers, start the other ID fan, then the corresponding FD fan.
Open the shut-off dampers and adjust the flow control device to
balance the draft groups, and place the second group into automatic.
4.
5.
BARHII_00108_ UOP_REV02A.DOC-6/2/11
11
When the fans are started, the secondary air damper control
should modulate the auxiliary air dampers to maintain a programmed set point differential pressure between the windbox and
furnace.
7.
8.
9.
10. Upon completion of the purge cycle, check that all firing prerequisites are satisfied, including the following control settings:
a.
b.
c.
d.
e.
f.
g.
12
Place the LP bypass valve in operation per manufacturers instructions. Typical procedure is:
BARHII_00108_ UOP_REV02A.DOC-6/2/11
Elevation
AB warmup
CD warmup
B coal
C coal
D coal
E coal
F coal
G coal
H coal
J coal
Notes
13
BARHII_00108_ UOP_REV02A.DOC-6/2/11
BARHII_00108_ UOP_REV02A.DOC-6/2/11
15
16
1.
2.
3.
SH and RH steam temperatures are maintained by adjusting firing rate and airflow.
4.
5.
6.
7.
8.
9.
BARHII_00108_ UOP_REV02A.DOC-6/2/11
Coal firing can commence when steam flow reaches approx. 1520% BMCR, and PA temperature is approximately 350 deg F
(177C) (sufficient for mill operation).
2.
Start at least one PA fan. After fan(s) are started, open the PA
fan outlet dampers and primary APH isolation gates. Bring the
primary hot air duct pressure up to set point by manually adjusting the PA fan flow control device. Then, transfer to automatic
control.
3.
Place the SSC drag chain in service per manufacturers instructions. Place the economizer hopper ash removal system in service according to manufactures instructions.
4.
Pulverizer B or alternately pulverizer A, serving the lower elevations of coal nozzles, should be prepared for operation at this
time so it can be readily started. Refer to pulverizers and pulverized coal system and the Control System instructions for start-up
sequences and controls.
The condition may exist when an upper elevation of coal will be
placed in service for start-up, with ignition provided by the associated elevation of warm-up fuel. Start-up by this procedure is al-
BARHII_00108_ UOP_REV02A.DOC-6/2/11
17
Confirm that the pulverizer reject hopper is ready for service (discharge valve closed, loop seal full, and inlet valve open). Place
the pulverizer reject sluicing system in service (refer to SSC and
Pulverizer Reject System ..)
6.
7.
Start the pulverizer. Open the hot air shutoff gate. Place the pulverizer airflow and temperature control on automatic.and bring
the pulverizer up to the required operating temperature without
coal. When ready to fire coal, manually start the feeder at minimum rating. Ignition of the pulverized coal should take place immediately. When the pulverizer is proven in service, the fuel-air
dampers should open automatically. Maintain the fuel feed at a
minimum rate consistent with stable ignition. Visually observe the
ignition point of the flame. If ignition does not take place within 5
seconds after coal appears at the coal nozzles, stop the feeder.
Determine the cause of ignition failure before attempting to restart
the feeder
Pulverizer start-up will cause a sudden and sharp increase in
steam pressure. The pressure will level out rapidly as the HP bypass station responds.
Check the pulverizer oil temperature. The oil temperature should
never exceed 158F (70C).
8.
18
BARHII_00108_ UOP_REV02A.DOC-6/2/11
10. When the feeder rating of the first pulverizer has reached approximately 80%, place the second pulverizer, which supplies the adjacent elevation of coal nozzles, in service in a similar manner.
When the second adjacent pulverizer is proven in service, equalize the feeder rating of both. The warm-up fuel must remain in
service until both feeders achieve 50% rating.
If the adjacent pulverizer is not available for service, place the pulverizer serving the next closest elevation of coal nozzles in service.
Do not remove the warm-up fuel from service until the two adjacent
coal elevations are in service with feeder ratings greater than 50%.
11. When the unit load reaches 30% of full load, the Burner Management System and secondary air damper controls should close
the auxiliary air dampers which serve the compartments adjacent
to the coal nozzles out of service. The Windbox to Furnace Differential Controller, provided in the Closed Loop Control System
should gradually increase the windbox-to-furnace differential
pressure to approximately 4 in. w.g.(102 mm H2O) as load is increased per the prescribed curve.
12. The airflow to the furnace must be sufficient for the firing rate. Automatic control equipment is normally arranged to maintain such
a balanced condition. The operation of the O2 measuring devices,
often tied in with the airflow control, should be checked periodically for proper operation.
Initial Load Increase to
40%
1.
2.
3.
Place the superheat steam temperature controls (spray) in automatic at 20% load. The spray block valves are interlocked to remain closed below 20% load.
4.
After reaching 30% BMCR load and firing is stable with at least 2
adjacent coal elevations at 50% rating , auxiliary fuel can be removed from service. Elevation AB is issued an elevation stop
command.
5.
BARHII_00108_ UOP_REV02A.DOC-6/2/11
19
7.
At app. 40% BMCR, the firing rate matches the economizer inlet
flow. The steam temperature at the separator outlet will reach a
stable superheated condition, causing the level in the SST to decrease, and the boiler will enter the once-through (dry) mode. The
boiler is proven in once-through (dry) mode when all the following
conditions exist:
a.
b.
c.
d.
When the controls swithch from wet to dry mode, FW flow control
will be released from SST level control to FW-Firing Rate coordination to control separator outlet steam temperature, and the BRP will
be auto-stopped (note that BRP operation can continue with the
unit is dry mode if desired).
8.
When the BRP stops, the warm-keeping system for the start-up
system should be put into operation. The warm-keeping system
maintains the start-up system in a warm condition so that it can
be immediately put into service. This system uses water from the
economizer outlet link as the source of heat. A wet-leg fluid level
is maintained in the startup system by automatically draining fluid
to the superheat desuperheaters via the WKFCV valve.
9.
BARHII_00108_ UOP_REV02A.DOC-6/2/11
21
2.
Select the feeder to manual and Gradually reduce the feeder rating of the selected pulverizer to minimum.
3.
When the feeder rating is at minimum, close the hot air damper
and shutoff gate and adjust the cold air damper to maintain 100%
pulverizer airflow.
4.
5.
6.
The associated warm-up fuel may be shut down when the furnace
conditions have stabilized.
BARHII_00108_ UOP_REV02A.DOC-6/2/11
2.
3.
Open the hot air shutoff gate and place the Pulverizer Airflow and
Temperature Control into automatic and bring the pulverizer up to
operating temperature (Refer to the Pulverizer and Pulverized
Coal System sections of this manual).
4.
5.
When the pulverizer is grinding and coal ignition has been established, gradually increase the feeder rating until it equals that of
the other feeders in service. Then, place the feeder on automatic
control.
6.
The associated warm up fuel elevation may be taken out of service when the furnace conditions have stabilized and at least two
pulverizers are in service, each with a feeder rating of at least
50%.
7.
BARHII_00108_ UOP_REV02A.DOC-6/2/11
23
24
1.
2.
Reduce the unit load to 60% Tmcr following the prescribed sliding
pressure vs. load curve (for a shutdown to hot, a higher pressure
may be desirable to preserve energy in the unit).
3.
4.
5.
When the turbine is shutdown and CVs are closed, reduce boiler
load at a controlled rate <3% per minute following the sliding
pressure curve to 110 kg/cm2. Hold pressure constant and continue to shutdown the boiler as prescribed below.
6.
7.
9.
10. Overfire air will be reduced automatically as the unit load is reduced per the prescribed control curves. Below approximately
30% load, overfire will be closed to a minimum position. Keep the
overfire air dampers at minimum open position to prevent the
nozzle tips from overheating.
11. Operate all soot blowers as load is reduced. Refer to the Soot
Blowing/Water Cannon Philosophy section and to the soot blower
manufacturers instructions.
12. Normally the unit controls will be on automatic during the shutdown, which will automatically maintain the design fuel-air balance. If it is necessary to use manual control, reduce the airflow
by reducing FD fan flow in line with the fuel reduction until 30%
airflow is reached. Do not reduce the airflow below this rating until
all fires are out, a furnace post firing purge has been completed
and the unit is off the line (Refer to Figure 1, typical air flow curve
in the back of this section, and the Percent Excess Air Versus
Load curve, as found in the Design and Operation manual, To
avoid firing instability during this period of high airflow, the auxiliary air dampers at all elevation should open and the windbox-tofurnace differential pressure reduced to its lower setting per the
prescribed control curve.
13. Check the boiler expansion movements as the load is reduced.
14. Remove the pollution control equipment from service according to
the manufactures instructions.
15. At app. 40% steam flow, feedwater flow will be higher than the firing rate. The steam temperature at the separator outlet will fall
below the superheated region, and a water level will develop in
BARHII_00108_ UOP_REV02A.DOC-6/2/11
25
b.
c.
d.
Difference between economizer inlet temperature and feedwater inlet temperature >10F (6C).
26
BARHII_00108_ UOP_REV02A.DOC-6/2/11
b.
If not already done, reduce the airflow through the unit to 30%
minimum airflow. Keep the fans and air heaters in service until
the unit has cooled to the desired temperature. Air heaters and
fans should not be taken out of service until the air heater gas
inlet temperatures have dropped below 400F (205C).
c.
26. If the cooling process must be accelerated to permit entry into the
steam generator for maintenance, proceed as in step 25, except:
a.
Continue running the fans at the desired rate to cool the unit.
The air heaters may be shut down when the gas entering temperature has dropped below 400F (205C). Refer to the air
heater instructions.
With the air heaters stopped and the fans running, deposits of
fly ash may accumulate in the air heater and cause a rotor unbalance.
b.
27. Do not shut down the scanner/ignitor air fan until the furnace
temperature has dropped to below 300F (149C).
28. If the boiler is to be laid up wet, refer to Lay-up Procedures.
29. If the boiler will be emptied, the boiler water temperature should
be reduced to at least 200F (93C) before draining.
NORMAL SHUTDOWN TO
HOT STANDBY
CAUTION: Exercise care to prevent water from entering
the turbine through the main steam line(s), the hot reheat line(s), or the cold reheat line(s) during and after
the shutdown process. This prevents water damage to
the turbine during a subsequent restart. Possible water
sources are:
a. Overflow from the separator into the superheater
when a high water level exists.
b. Water entering the superheater or reheater through
the desuperheaters due to open desuperheater control valves or valve leakage with the feed pumps
running.
BARHII_00108_ UOP_REV02A.DOC-6/2/11
27
2.
It is not necessary to close the feeder inlet gates and run the
spouts and feeders empty. As each pulverizer is taken out of service, close the hot air shutoff gate. Stop the feeder when the
coal/air temperature drops to 130F (54 deg C). Run the pulverizer for a 3 minute period until it is empty, and then stop the pulverizer.
3.
28
4.
After the fires are extinguished, keep the ID, FD and PA fans and
air heaters running until the air heater gas inlet temperatures
have dropped to below 400F (205C). Close all gas duct and
secondary air duct dampers after the air heaters and fans are
shut down. Keep the scanner air fan running.
5.
Shut down the BRP after the unit has been bottled up. However,
if an immediate hot restart is anticipated, keep the BRP in service
for more effective warm-up circulation.
BARHII_00108_ UOP_REV02A.DOC-6/2/11
WARM START-UP
Assuming that the unit has been down for a short period of time (less
than approximately 36 hours), the unit can be re-started in a similar sequence to Cold Start-up procedure as outlined below:
2.
1.
Preparations, Lighting
Off, and Load Increase
HOT START-UP
Assuming the unit has been down for a comparatively short period of
time (<8 hours) following a normal unit shutdown and considerable
steam pressure has been maintained, use the following procedures to
restart the unit:
Hot Start Conditions
1.
BARHII_00108_ UOP_REV02A.DOC-6/2/11
29
3.
1.
2.
3.
If the air heaters and fans were shut down at reduced temperature (see NORMAL SHUTDOWN TO HOT STANDBY,), start the
air heaters and fans as outlined under COLD START-UP, Lighting Off. If the unit was bottled up hot with the air heaters still running, start the fans in the normal sequence.
Preparations, Lighting
Off, and Load Increase
CAUTION: Prevent possible water damage to the turbine by using extreme care to eliminate all water from
the main steam line(s), cold and hot reheat lines, and
superheater and reheater elements and headers before
the turbine is rolled. Refer to the turbine manufacturer's
instructions and to the Valve Operating Diagram for the
proper drain valve settings.
4.
5.
Set the HP and LP bypass control set-point to the existing pressure in auto mode per manufactures instructions.
6.
For hot start-ups, the fuel startup sequence should follow this table (A elevation is the bottom elevation):
Sequence Step
1
2
3
4
5
6
7
8
9
10
30
Elevation
CD warmup
EF warmup
C coal
D coal
E coal
B coal
A coal
F coal
G coal
H coal
Notes
BARHII_00108_ UOP_REV02A.DOC-6/2/11
8.
Set warm-up flow control to auto and increase fuel flow set point
to 5% of BMCR firing rate.
9.
2.
3.
SH and RH steam temperatures are maintained by adjusting firing rate and airflow.
BARHII_00108_ UOP_REV02A.DOC-6/2/11
31
Synchronize the generator and put on initial load according to turbine/generator startup instructions.
5.
6.
7.
8.
9.
32
BARHII_00108_ UOP_REV02A.DOC-6/2/11
2.
3.
After stabilization, if desired the SG load and pressure can be reduced at a controlled rate of <3% per minute within SG temperature gradient limitations and within the bypass capacity limitation.
If the HP bypass is not proven open within a short time delay, all fuel
should be tripped automatically and instantaneously.
The superheater and reheater safety valves will protect against overpressure. The reheater drains to the condenser should be opened to
evacuate the steam in the reheater in the event of a unit trip.
POST-TRIP PROCEDURES
The furnace must be purged immediately following a master fuel trip.
Empty any pulverizer containing coal as soon as possible. Refer to Master Fuel Trip.
BARHII_00108_ UOP_REV02A.DOC-6/2/11
33
34
BARHII_00108_ UOP_REV02A.DOC-6/2/11
Maintain the unit airflow at the pre-trip value for at least 1 minute
and then gradually reduce the airflow to the purge rate (30% airflow) and complete a unit post trip purge.
2.
Procedure after Master Fuel Trip when all ID and FD Fans are off:
The ID and FD fans discharge dampers shall be opened to allow
natural ventilation of the unit. Opening of fan(s) dampers shall be
timed or controlled to avoid excessive furnace pressure excursions
during fan(s) coast-down. The fans discharge dampers shall remain open for a period of at least 15 minutes.
During this 15-minute period, the ID and FD fans shall not be
started.
At the end of the 15-minute period, the ID/FD fans may be started
in accordance with ID/FD fan(s) start-up procedures.
If the unit will not be re-started for an extended time, a flow of air
through the unit shall be maintained.
3.
4.
If all auxiliaries are lost during a fuel trip, refer to the Boiler Circulating Pump Operating Procedures for handling the low pressure
cooling water. The cooling flow must be maintained.
5.
If all auxiliary power sources were lost during a trip, after completing the 15 minute natural draft purge described above, start the
fans and air heaters when power is restored, increase the unit airflow to the purge rate and complete a 5 minute purge. Observe
the hot restart precautions in the air heater instructions. The BRP,
if available, should be placed in service during the purge, and the
boiler should be refilled. (See Boiler Circulating Pump Operating
Procedures for restarting procedures).
6.
If pulverizers are in service when the fuel trip occurs, all operating
pulverizers will be automatically inerted. Refer to section on Pulverizer Inerting and Fire Fighting for details. The pulverizers must
remain under inerting until they can be cleared of coal or cooled
to ambient.
7.
After a boiler trip at a high pressure, a controlled pressure reduction is carried out to the highest pressure with which a restart is
possible (to approximately 160 bar) to obtain reliable SST level
indication.
8.
The BRP should be placed back in service and recirculation established to maintain uniform temperatures throughout the boiler
circulation system and to enable a restart of the boiler. The boiler
must be refilled to re-establish normal SST level for BRP restart
and the minimum recirculation flow must be re-established as a
pre-requisite for re-firing. This process will naturally cause pressure to decay, concurrent.with the controlled pressure reduction.
BARHII_00108_ UOP_REV02A.DOC-6/2/11
35
Check that the startup system is ready for operation (HWL-1 isolation valve open, HWL-2 is interlocked to prevent opening at high
pressure to protect the flash tank) and the drain transfer system
is ready for operation. Place the BFPM in service, stabilize deaerator conditions, and establish feedwater flow of 10% BMCR to
the boiler to refill to normal SST level. Follow the same procedure
for boiler filling as outlined previously. When SST level is stable
with HWL-1 at stable opening and all BRP start permissives are
satisfied, start the BRP (Refer to Boiler Circulating Pump Operating Procedures). Zero the feedwater flow as SST level recovers
and attains the operational setpoint. If restart of the BRP is delayed, excessive HWL action will result in draining of water at
pressure, oscillatory dump-feed action, with further reduction in
boiler pressure and extension of startup time
10. The pre-firing furnace purge can be initiated once all purge permissives are met.
11. If the boiler can be immediately restarted, then raise load to
>20% on auxiliary fuel utilizing the HP/LP bypass and successively clear the pulverizers serving at least the 2 lower coal elevations
using the steam transport system prior to re-synchronizing the
turbine. The remaining pulverizers can be cleared using steam
transport before or after the turbine is synchronized. Refer to the
pulverizer clearing procedure located in the steam inerting section
of the Design and Operations manual for additional details:
36
a.
Close the pulverizer discharge gates on all other idle pulverizers containing coal during each steam transport procedure.
This prevents hot furnace gases from being carried back into
the pulverizers in the event of a furnace pressure rise when a
pulverizer is started.
b.
Start the lower elevation of warm-up fuel and establish the ignition energy required to start a pulverizer. Refer to, COLD
START-UP, and to the Control System suppliers instructions
for ignition energy requirements and permissives.
c.
d.
Clear pulverizer A by following the pulverizer transport procedure located in the steam inerting section of the Design and
Operations manual
e.
f.
g.
Continue with normal unit start up sequence until both pulverizers are in service and the turbine is synchronized.
h.
When boiler load is approximately 20%, the remaining pulverizers may be cleared one at a time using the steam transport
BARHII_00108_ UOP_REV02A.DOC-6/2/11
j.
12. If, due to load conditions and/or requirements to the Burner Management System, it is impossible to establish ignition permissives
to allow steam transport, inerting steam shall be maintained until
each pulverizer can be cleared of coal using steam transport or
cooled to ambient
13. If the boiler cannot be re-started and the aurxiliary steam source
cannot be continued indefinitely, then the pulverizers (those still
containing coal) must be switched to an alternate steam inerting
source or to an alternate inerting medium until they can be cooled
to ambient and manually emptied. Refer to the clearing procedure
located in the Pulverizer Inerting and Fire Fighting section of the
Design and Operations manual for additional details.
BARHII_00108_ UOP_REV02A.DOC-6/2/11
37
2.
Shut off all steam being discharged from the unit (trip turbine,
steam driven auxiliaries, and such).
3.
4.
5.
6.
7.
8.
9.
Hydrostatically test the boiler before putting the unit back in service.
38
BARHII_00108_ UOP_REV02A.DOC-6/2/11
BARHII_00108_ UOP_REV02A.DOC-6/2/11
39
40
BARHII_00108_ UOP_REV02A.DOC-6/2/11
2.
3.
When all fires are extinguished continue the airflow through the
unit at a reduced rate to purge all combustible gases, vapors, etc.
Shut down the fans when the unit is cooled sufficiently.
4.
Feed water to the boiler by manual control. To speed cooling, boiler pressure can be reduced by opening the superheater outlet
drains.
5.
If there is a serious water loss and the water flow/level cannot be maintained with the feedwater supply available. Use the following method:
1.
2.
3.
4.
Leave the fans and air heaters in service until pressure is off the
unit.
5.
Once the unit is cool enough to enter, inspect the pressure parts for
damage caused by the loss of water level. After the necessary repairs have been made, apply a hydrostatic test and obtain the approval of the proper authorities before putting the unit back in service.
ECONOMIZER TUBES
An economizer tube leak can be detected by sound and/or increased
makeup water requirements. Check the leak as soon as possible. Water
leaks in the economizer can cause considerable erosion damage to adjacent tubes. Water carried over from an economizer tube leak may
cause plugging of hoppers and air heaters. Any decision to continue
BARHII_00108_ UOP_REV02A.DOC-6/2/11
41
OPERATION WITHOUT
BRP
General Remarks
Starting the boiler without the BRP is an unusual activity, and should
therefore be carried out in exceptional cases only.
The minimum economizer flow must be supplied by the BFPM, and in
lieu of recirculation, water is drained through the start-up system HWL
valves to the flash tank, receiving tank, transfer pumps, and returned to
the condenser.
Because there is no water recirculation, heat and water losses will be
much higher. So to compensate, additional make-up water should be
available and additional heat input (both quantity and length of time) will
be required. Adequate preparations should be made before attempting
this type of startup.
Cold Start Without BRP
42
1.
2.
Close the BRP suction and discharge isolation valves, and the
BRP bypass valve.
3.
4.
5.
6.
Light-off the boiler in the usual manner. When the first ignitor is
proven in service, the feedwater flow setpoint will automatically be
controlled to 40%. Warm-up the boiler in the usual manner. Drain
flow will increase above 40% as the boiler water swells.
BARHII_00108_ UOP_REV02A.DOC-6/2/11
8.
9.
10. At approximately 40% load the boiler will enter the once-through
mode. When once-through mode is proven, the warm-keeping
system should be put into operation.
11. Follow normal operation for unit load changes.
Shutdown Without BRP
1.
2.
At approximately 40% load, the boiler will transfer to the recirculation mode. With the BRP off, the feedwater flow setpoint will automatically control the BFP loading to maintain the minimum economizer flow setpoint.
3.
The HWL-1 will open in auto mode when the level in the SST
reaches the high setpoint. If additional drain capacity is needed,
HWL-2 will open when HWL-1 reaches full open and level continues to rise.
4.
Note that the start up system valves (HWL-1, HWL-2) are interlocked to prevent opening above 2100 psig (148 kg/cm2) to protect the flash tank, so pressure must be reduced to less than this
value before the transfer to recirculation mode is made.
5.
Continue to reduce load and shutdown the unit following the normal procedure.
6.
Keep the BFP in service with the feedwater flow at minimum setpoint of 40% until the boiler water temperature is reduced to the
desire point. Keep the water level near normal in the SST, draining water via HWL valves as required.
43
2.
Close the BRP suction and discharge isolation valves, and the
BRP bypass valve.
3.
Set the feedwater flow setpoint to 40%. The HWL-1 and HWL-2
will open in auto mode when the level in the SST reaches the
high setpoint, and will drain the full capacity of 40%.
4.
Note that the start up system valves (HWL-1, HWL-2) are interlocked to prevent opening above 2100 psig (148 kg/cm2) to protect the flash tank, so pressure must be less than this value before initiating the startup.
5.
Light-off the boiler following the normal procedure. When the first
ignitor is proven in service, the feedwater flow setpoint will automatically be controlled to 40%. Warm-up the boiler following the
normal procedure.
6.
7.
8.
9.
44
BARHII_00108_ UOP_REV02A.DOC-6/2/11
APPENDIX A FEEDWATER
SPECIFICATIONS FOR
ONCE THRU BOILERS
BARHII_00108_ UOP_REV02A.DOC-6/2/11
45
100
90
80
70
60
50
40
30
20
PURGE
AIRFLOW
10
0
0
10
20
30
40
50
60
70
80
90
100 110
LIGHTING
OFF
ON THE
LINE
WARMING
UP
46
BARHII_00108_ UOP_REV02A.DOC-6/2/11
130
120
Seven Mills
Six Mills
110
100
Five Mills
90
80
Four Mills
70
60
Three Mills
50
40
Two Mills
30
20
One Mill
10
0
0
10
20
30
40
50
60
70
80
90
100
110
120
Mill Capacity - %
Curve S-xxxx
NTPC BARH II
PREDICTED PERFORMANCE
Mill Operating Diagram with Worst Coal
150
NOMAL OPERATING RANGE
40% TO 85% MILL CAPACITY
140
130
120
Eight Mills
Boiler Load - %
110
Seven Mills
100
90
Six Mills
80
Five Mills
70
Four Mills
60
50
Three Mills
40
30
Two Mills
20
One Mill
10
0
0
10
20
30
40
50
60
70
80
90
100
110
120
Mill Capacity - %
Curve S-xxxx
BARHII_00108_ UOP_REV02A.DOC-6/2/11
47
48
BARHII_00108_ UOP_REV02A.DOC-6/2/11
BARHII_00108_ UOP_REV02A.DOC-6/2/11
49
2
5
MEFCV
8
16
ECONOMIZER
WATERWALLS
CONDENSER
CONDENSATE PUMPS
CONDENSATE DEMINERALIZER
LP HEATERS
FEED PUMPS
10 HP HEATERS
11 RECIRCULATION LINE FOR
PRE-BOILER CLEAN-UP
12 FLASH TANK
M
HWL1
13 RECEIVING TANK
14 MIXING PIECE / FILTER
14
HWL2
16 CIRCULATING PUMP
12
10
HWL-1
HWL-2
MEFCV
13
M
17
PHASE II
PHASE III
50
BARHII_00108_ UOP_REV02A.DOC-6/2/11
decreasing
increasing
decreasing
600F(333C )//hr
Load Range
Cold
Hot
0.50%
0-10%
0.50%
10-40%
1%
1%
40-100%
1-2%
3-4%
Load Range
40-50%
3% MCR/min
50-100%
5% MCR/min
<40%MCR
>40%MCR
>20%MCR
BARHII_00108_ UOP_REV02A.DOC-6/2/11
(avoid turbine holds, etc near 40% load during transition from recirculation to once-through mode)
51
52
BARHII_00108_ UOP_REV02A.DOC-6/2/11
Description/Location
Valve Open
Valve Closed
SH link to SH Platen
Note 1: Valves may be used during warmup to obtain the required outlet steam temperatures (approx 100 deg F superheat) for turbine rolling. Steam is diverted by sequencing valves open
and closed. Valves should be either fully open or fully closed. Valves must be closed immediately upon synchronization (before appreciable load is picked up) to prevent possible overheating
of superheater elements. If additional backpass system valves are supplied by the customer, they may be used in place of these valves for superheat control.
Note 2: Reheater drains and vents that are not connected to the condenser must be closed prior to establishing vacuum.
BARHII_00108_ UOP_REV02A.DOC-6/2/11
Description/Location
Valve Open
Valve Closed
SH link to SH Platen
Note 1: Valves may be used during warmup to obtain the required outlet steam temperatures (approx 100 deg F superheat) for turbine rolling. Steam is diverted by sequencing valves open
and closed. Valves should be either fully open or fully closed. Valves must be closed immediately upon synchronization (before appreciable load is picked up) to prevent possible overheating
of superheater elements. If additional backpass system valves are supplied by the customer, they may be used in place of these valves for superheat control.
Note 2: Reheater drains and vents that are not connected to the condenser must be closed prior to establishing vacuum.
BARHII_00108_ UOP_REV02A.DOC-6/2/11
Descritpion/Location
Valve Operation
Open for SST high level control, closed at all other times
Open before starting BRP, close when transfer to once-through mode is complete
Open when filling or draining BRP, locked closed at all other times
Open when startup system is out of service above 30% load, closed at all other times
Open when startup system is out of service above 30% load, closed at all other times
Open when filling and draining unit, closed at all other times
Open when filling and draining unit, closed at all other times.
Open for SST high level control, closed at all other times
BARHII_00108_ UOP_REV02A.DOC-6/2/11
Open when filling the SH for hydrostatic test. See operating recommendations for cold or hot start.
Open when draining the unit. See operating recommendations for cold or hot start
Open when filling the SH for hydrostatic test, closed at all other times.
Open when filling the SH for hydrostatic test. See operating recommendations for cold or hot start.
SH link to SH Platen
Open when filling the SH for hydrostatic test. Operate in conjunction with SH link from Desuperheater vents
Open when filling the SH for hydrostatic test. See operating recommendations for cold or hot start
Open when filling the reheater for hydrostatic test, closed at all other times
Open when filling the reheater for hydrostatic test, closed at all other times. See operating recommendations for cold or hot
start.
See operating recommendations for cold or hot start
BARHII_00108_ UOP_REV02A.DOC-6/2/11