Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

Camella Estimate

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 36
At a glance
Powered by AI
The document appears to be a cost proposal for construction works that includes different line items and their costs. It provides unit costs for materials, labor, and total costs.

The document is proposing construction costs for different structural, architectural, and mechanical works. It includes costs for earthworks, masonry, concrete, electrical, plumbing and more.

The proposal includes costs for items like general requirements, earthworks, structural works, architectural works, doors and windows, carpentry works, electrical works, and plumbing works.

COST PROPOSAL

UNIT COST
ITEM DESCRIPTION
I.

QTY.

UNIT

MATERIAL LABOR

GENERAL REQUIREMENTS
a. Mobilization/Demobilization
1.0
b. Temporary Facilities
1.0
c. Safety & Housekeeping
1.0
d. Technical Support & Supervision
1.0
e. Permits & Licenses (including MERALCO and Maynilad/Manila Waters)

50,000
50,000
50,000
75,000
BY OWNER

SUB-TOTAL (Item I)

II.

EARTHWORKS:
a. Site Clearing/Lay-outing/Staking
b. Excavation & Backfilling
c. Soil Poisoning & Gravel Bedding
d. Sub-Grade Preparation & Compaction
e. Disposal of Unsuitable Materials / Debris

144.0
68.0
144.0
144.0
1.0

m
m
lot
m
lot

100
600
300
60
50,000

849.6
1,189.4
509.8

m
m
m

200
200
280

150
150
200

6.2
7.8
8.1
4.7
15.0
8.1
13.2

m
m
m
m
m
m
m

3,500
3,500
3,500
3,500
3,500
3,500
3,500

1,500
1,500
1,500
1,500
1,500
1,500
1,500

38
38
38
38
38
38
38

5
5
5
5
5
5
5

320
320
320
320
320
320
320

120
120
120
120
120
120
120

SUB-TOTAL (Item I)
III.

STRUCTURAL WORKS
A. Masonry Works
1.0 CHB Laying
2.0 Interior Plastering
3.0 Exterior Plastering
B. Concreting Works
1.0 Footing
2.0 Tie Beam / Wall Footing
3.0 R. C. Columns
4.0 Staircase
5.0 Slab on Grade
6.0 Suspended Beams / Girders
7.0 Suspended Slabs
C. Rebar Works
1.0 Footing
2.0 Footing Tie Beam / Wall Footing
3.0 R. C. Columns
4.0 Staircase
5.0 Slab on Grade
6.0 Suspended Beams / Girders
7.0 Suspended Slab

1,034.2
1,854.7
2,887.5
156.1
1,758.2
3,586.7
8,524.8

D. Formworks & Scaffolds


1.0 Footing
2.0 Footing Tie Beam / Wall Footing
3.0 Staircase
4.0 R. C. Columns
5.0 Slab on Grade
6.0 Suspended Beams / Girders
7.0 Suspended Slab

25.0
108.0
16.0
132.5
144.0
132.0
144.0

E. Roof Framing & Roofing

kgs.
kgs.
kgs.
kgs.
kgs.
kgs.
kgs.

m
m
m
m
m
m
m

1.0
2.0
3.0
4.0

Roof framing
Roofing Longspan 0.4mm
Spanish Gutter
Flushing

144.0
144.0
24.0
24.0

mtrs
m
mtrs
mtrs

150
2,500
150
150

###
150
###
151

ARCHITECTURAL WORKS
A. Tileworks
1.0 T & B:
- wall (ht = 2.6m)
- floor
2.0 Bedrooms
3.0 Liv/Din/Fam/Kit

49.0
7.2
144.0
144.0

m
m
m
m

420
480
570
570

240
240
240
240

B. Painting Works
1.0 Interior
2.0 Exterior
3.0 Ceiling

713.7
305.9
227.4

m
m
m

168
168
168

132
144
132

500
170
240

SUB-TOTAL (Item II)


IV.

C. Exterior Moulding
1.0 Round pre-cast
2.0 Horizontal lines
3.0 Tiles (Deco stone look)
D. Steel Works
1.0 Interior
2.0 Exterior
3.0

5.0
42.0
15.0

pcs
mtrs
m

2,000
300
570

135.6
54.2

sq ft
sq ft
sq ft

150
150
150

5.0
15.0
5.0
15.8

units
units
units
sq ft

4,500
3,000
2,000
300

263.4
51.6
12.9

sq ft
sq ft
sq ft

150
150
150

###
###
###

SUB-TOTAL (Item III)


V.

DOORS & WINDOWS


A. Doors
1.0 D1
0.80
2.0 D2
0.70
3.0 D4
0.60
4.0 D6
0.70
B. Windows
1.0 W2
2.0 W3
3.0 W5

X 2.10m panel door


x 2.10m flush door
x 2.10m pvc door
x 2.10m steel door

1.20 x 1.20m steel casement


0.80 x 1.20m steel casement
0.40 x 0.60m steel casement

1,000
1,000
1,000
150

###
###
###

SUB-TOTAL (Item V)
VI.

CARPENTRY WORKS
Ceiling (CR, gypsum board)
Kitchen Cabinets
Hanging Cabinets

7.2
6.0
9.0

m
m
m

1.0

lot

SUB-TOTAL (Item V)
VII.

ELECTRICAL WORKS
1.0 Rough-ins
2.0 Wires and conduits
3.0 Fixtures and Devices
4.0 Panel Board and devices

1,300
1,300
1,300

1,000
1,000
1,000

1.0

lot

90.0
1.0

m
lot

150
400,000

5.0
10.0
180.0

set
set
m

5,000
3,500
480

5.0 Service Entrance


6.0 Meter Base and pedestal
SUB-TOTAL (Item VI)
VIII.

PLUMBING WORKS
1.0 Septic vault
2.0 Rough-ins
3.0 Fixtures
Water closet
Kitchen Sink w/ faucet
4.0 Water proofing (deck)
SUB-TOTAL (Item VI)

TOTAL BID AMOUNT >>>

###

1,500
800
240

ROPOSAL
TOTAL
UNIT
COST
50,000
50,000
50,000
75,000

TOTAL
AMOUNT
50,000
50,000
50,000
75,000

OWNER
225,000

100
600
300
60
50,000

14,400
40,800
43,200
8,640
50,000

157,040

350
350
480

297,360
416,304
244,685

5,000
5,000
5,000
5,000
5,000
5,000
5,000

31,200
38,880
40,320
23,400
75,000
40,320
66,000

43
43
43
43
43
43
43

44,472
79,752
124,164
6,713
75,604
154,227
366,566

440
440
440
440
440
440
440

11,000
47,520
7,040
58,291
63,360
58,080
63,360

300
2,650
300
301

43,200
381,600
7,200
7,224
2,872,843

660
720
810
810

32,340
5,184
116,640
116,640

300
312
300

214,099
95,427
68,220

2,500
470
810

12,500
19,740
12,150

300
300
300

40,673
16,269
749,882

5,500
4,000
3,000
450

27,500
60,000
15,000
7,118

300
300
300

79,021
15,494
3,874
208,007

2,300
2,300
2,300

16,560
13,800
20,700
51,060

500,000

500,000

500,000

500,000

500,000

300
400,000
6,500
4,300
720

27,000
400,000
32,500
43,000
129,600
632,100

5,395,932

ERDC Konstrukt Co.


Unit-D Lot 11 Block C Delia Apartment, Progressive 3 Village, Molino 1, Bacoor, Cavite
Telephone Nos.: (046)970 8564 / 09063519572

Project

EXTENTION TO TWO (2) STOREY WAREHOUSE WITH DECK

Owner

Mr. Alberto Estacion

Subject

COST ESTIMATE
COST PROPOSAL
UNIT COST
ITEM DESCRIPTION

I.

QTY.

GENERAL REQUIREMENTS
a. Mobilization/Demobilization
b. Temporary Facilities
c. Safety & Housekeeping
d. Technical Support & Supervision
e. Permits & Licenses (including MERALCO and Maynilad/Manila Waters)

UNIT

MATERIAL

LABOR

1.00
1.00
1.00
1.00
BY OWNER

TOTAL
UNIT COST
-

SUB-TOTAL (Item I)

II.

EARTHWORKS:
a. Site Clearing/Lay-outing/Staking
b. Excavation & Backfilling
c. Dewatering Works
d. Soil Poisoning & Gravel Bedding
e. Sub-Grade Preparation & Compaction
f. Disposal of Unsuitable Materials / Debris

m
m
lot
lot
m
lot
SUB-TOTAL (Item I)

III.

STRUCTURAL WORKS
A. Masonry Works
1.0 CHB Laying
2.0 Plastering

491.40
982.80

m
m

200.00
200.00

150.00
150.00

350.00
350.00

B. Concreting Works
1.0 AdditionalColumn/Footing(Retrofitting)
2.0 R. C. Columns
3.0 Staircase
4.0 Suspended Beams / Girders
5.0 Suspended Slabs

1.00
5.76
2.52
13.32
22.96

C. Rebar Works
1.0 AdditionalColumn/Footing(Retrofitting)
2.0 R. C. Columns
3.0 Staircase
4.0 Suspended Beams / Girders
5.0 Suspended Slab

1.00
57.60
55.06
5,940.04
3,114.40

D. Formworks & Scaffolds


1.0 AdditionalColumn/Footing(Retrofitting)
2.0 Staircase
3.0 R. C. Columns
4.0 Suspended Beams / Girders
5.0 Suspended Slab

1.00
12.80
57.60
169.84
229.60

ARCHITECTURAL WORKS
A. Tileworks
1.0 T & B:
- wall (ht = 1.20m)
- floor
2.0 0.60m x 0.60m unglazed ceramic tiles
B. Painting Works
1.0 Interior
2.0 Exterior

lot
m
m
m
m

20,000.00
3,500.00
3,500.00
3,500.00
3,500.00

150.00
150.00
150.00
150.00

20,000.00
3,650.00
3,650.00
3,650.00
3,650.00

2,500.00
38.00
38.00
38.00
38.00

5.00
5.00
5.00
5.00

2,500.00
43.00
43.00
43.00
43.00

lot
m
m
m
m

26,000.00
320.00
320.00
320.00
320.00

120.00
120.00
120.00
120.00

26,000.00
440.00
440.00
440.00
440.00

14.40
8.00
229.60

m
m
m

420.00
480.00
570.00

240.00
240.00
240.00

660.00
720.00
810.00

721.00
491.40

m
m

168.00
168.00

132.00
144.00

300.00
312.00

sq ft

150.00

150.00

300.00

lot
kgs.
kgs.
kgs.
kgs.

SUB-TOTAL (Item II)


IV.

C. SteelWorks
1.0 Stair railing

38.74
SUB-TOTAL (Item III)

A. Windows
1.0 W2
2.0 W3

1.20 x 1.20m steel casement


Louvers

61.98
16.00

sq ft
l.m.

150.00
450.00

150.00
150.00

300.00
600.00

8.00

550.00

350.00

900.00

1.00

lot

36.00
1.00

m
lot

150.00
200,000.00

150.00

300.00
200,000.00

2.00
85.00

set
m

5,000.00
480.00

1,500.00
240.00

6,500.00
720.00

SUB-TOTAL (Item V)
VI.

CARPENTRY WORKS
Ceiling (CR, gypsum board)
SUB-TOTAL (Item V)

VII.

ELECTRICAL WORKS
1.0 Rough-ins
2.0 Wires and conduits
3.0 Fixtures and Devices
4.0 Panel Board and devices
5.0 Service Entrance
6.0 Meter Base and pedestal

450,000.00

SUB-TOTAL (Item VI)


VIII.

PLUMBING WORKS
1.0 Septic vault
2.0 Rough-ins
3.0 Fixtures
Water closet
4.0 Water proofing (deck)
SUB-TOTAL (Item VI)

TOTAL BID AMOUNT >>>

2,680,899.61

TOTAL
AMOUNT
-

171,990.00
343,980.00

20,000.00
21,024.00
9,198.00
48,618.00
83,804.00

2,500.00
2,476.80
2,367.41
255,421.72
133,919.20

26,000.00
5,632.00
25,344.00
74,729.60
101,024.00
P

1,328,028.73

9,504.00
5,760.00
185,976.00

216,300.00
153,316.80

11,620.80
P

582,477.60

18,593.28
9,600.00
P

28,193.28

7,200.00
P

7,200.00

450,000.00

450,000.00

10,800.00
200,000.00
13,000.00
61,200.00
P

285,000.00

2,680,899.61

ERDC Konstrukt Co.


Unit-D Lot 11 Block C Delia Apartment, Progressive 3 Village, Molino 1, Bacoor, Cavite
Telephone Nos.: (046)970 8564 / 09063519572
Project

TWO (2) STOREY APARTMENT WITH DECK

FA

591.00

Ground Flr
Second Flr
RoofDeck
Access Stair

196.00
175.00
180.00
40.00

Owner

Mr. Alberto Estacion

Subject

COST ESTIMATE
COST PROPOSAL
UNIT COST
ITEM DESCRIPTION

I.

QTY.

GENERAL REQUIREMENTS
a. Mobilization/Demobilization
b. Temporary Facilities
c. Safety & Housekeeping
d. Technical Support & Supervision
e. Permits & Licenses (including MERALCO and Maynilad/Manila Waters)

UNIT

1.00
1.00
1.00
1.00
BY OWNER

MATERIAL

LABOR

TOTAL
UNIT COST

50,000.00
50,000.00
50,000.00
75,000.00

50,000.00
50,000.00
50,000.00
75,000.00

100.00
150.00
25,000.00
120.00
60.00
50,000.00

100.00
150.00
25,000.00
120.00
60.00
50,000.00

SUB-TOTAL (Item I)

II.

EARTHWORKS:
a. Site Clearing/Lay-outing/Staking
b. Excavation & Backfilling
c. Demolition of existing wall
d. Soil Poisoning & Gravel Bedding
e. Sub-Grade Preparation & Compaction
f. Disposal of Unsuitable Materials / Debris

330.00
190.00
1.00
196.00
330.00
1.00
SUB-TOTAL (Item I)

m
m
lot
lot
m
lot

III.

STRUCTURAL WORKS
A. Masonry Works
1.0 CHB Laying
2.0 Interior Plastering
3.0 Exterior Plastering

1,656.00
1,112.00
817.00

m
m
m

200.00
200.00
280.00

150.00
150.00
200.00

350.00
350.00
480.00

B. Concreting Works
1.0 Footing
2.0 Footing Tie Beam / Wall Footing
3.0 R. C. Columns
4.0 Staircase
5.0 Slab on Grade
6.0 Suspended Beams / Girders
7.0 Suspended Slabs

33.99
28.62
32.26
6.72
33.00
55.20
82.50

m
m
m
m
m
m
m

3,500.00
3,500.00
3,500.00
3,500.00
3,500.00
3,500.00
3,500.00

150.00
150.00
150.00
150.00
150.00
150.00
150.00

3,650.00
3,650.00
3,650.00
3,650.00
3,650.00
3,650.00
3,650.00

C. Rebar Works
1.0 Footing
2.0 Footing Tie Beam / Wall Footing
3.0 R. C. Columns
4.0 Staircase
5.0 Slab on Grade
6.0 Suspended Beams / Girders
7.0 Suspended Slab

1,723.73
3,091.17
4,812.55
260.18
2,930.40
5,977.79
14,208.00

38.00
38.00
38.00
38.00
38.00
38.00
38.00

5.00
5.00
5.00
5.00
5.00
5.00
5.00

43.00
43.00
43.00
43.00
43.00
43.00
43.00

D. Formworks & Scaffolds


1.0 Footing
2.0 Footing Tie Beam / Wall Footing
3.0 Staircase
4.0 R. C. Columns
5.0 Slab on Grade
6.0 Suspended Beams / Girders
7.0 Suspended Slab

99.60
219.40
58.00
367.80
363.00
404.80
660.00

320.00
320.00
320.00
320.00
320.00
320.00
320.00

120.00
120.00
120.00
120.00
120.00
120.00
120.00

440.00
440.00
440.00
440.00
440.00
440.00
440.00

150.00
2,500.00
150.00

150.00
150.00
150.00

300.00
2,650.00
300.00

E. Roof Framing & Roofing


1.0 Roof framing
2.0 Roofing Longspan ga. 24
3.0 Gutter and flushing

80.00
40.00
80.00
SUB-TOTAL (Item II)

kgs.
kgs.
kgs.
kgs.
kgs.
kgs.
kgs.

m
m
m
m
m
m
m

mtrs
m
mtrs

IV.

ARCHITECTURAL WORKS
A. Tileworks
1.0 T & B:
- wall (ht = 1.20m)
- floor
2.0 Bedrooms
3.0 Liv/Din/Fam/Kit
B. Painting Works
1.0 Interior
2.0 Exterior
3.0 Ceiling

72.00
60.00
324.00
322.00

m
m
m
m

420.00
480.00
570.00
570.00

240.00
240.00
240.00
240.00

660.00
720.00
810.00
810.00

1,112.00
817.00
379.00

m
m
m

168.00
168.00
168.00

132.00
144.00
132.00

300.00
312.00
300.00

C. Exterior Moulding
1.0 Round pre-cast
2.0 Horizontal lines
3.0 Tiles (Deco stone look)

5.00
42.00
15.00

pcs
mtrs
m

2,000.00
300.00
570.00

500.00
170.00
240.00

2,500.00
470.00
810.00

D. Steel Works
1.0 Interior
2.0 Exterior
3.0 Entrance gate per unit

225.96
90.38
258.24

sq ft
sq ft
sq ft

150.00
150.00
150.00

150.00
150.00
150.00

300.00
300.00
300.00

5.00
15.00
5.00
15.82

units
units
units
sq ft

4,500.00
3,000.00
2,000.00
300.00

1,000.00
1,000.00
1,000.00
150.00

5,500.00
4,000.00
3,000.00
450.00

263.40
51.65
12.91

sq ft
sq ft
sq ft

150.00
150.00
150.00

150.00
150.00
150.00

300.00
300.00
300.00

SUB-TOTAL (Item III)


V.

DOORS & WINDOWS


A. Doors
1.0 D1
0.80
2.0 D2
0.70
3.0 D4
0.60
4.0 D6
0.70
B. Windows
1.0 W2
2.0 W3
3.0 W5

X 2.10m panel door


x 2.10m flush door
x 2.10m pvc door
x 2.10m steel door

1.20 x 1.20m steel casement


0.80 x 1.20m steel casement
0.40 x 0.60m steel casement

SUB-TOTAL (Item V)
VI.

CARPENTRY WORKS
Ceiling (CR, gypsum board)
Kitchen Cabinets
Hanging Cabinets

25.00
10.00
15.00

m
m
m

550.00
550.00
550.00

350.00
350.00
350.00

900.00
900.00
900.00

1.00

lot

90.00
1.00

m
lot

150.00
400,000.00

150.00

300.00
400,000.00

5.00
10.00
180.00

set
set
m

5,000.00
3,500.00
480.00

1,500.00
800.00
240.00

6,500.00
4,300.00
720.00

SUB-TOTAL (Item V)
VII.

ELECTRICAL WORKS
1.0 Rough-ins
2.0 Wires and conduits
3.0 Fixtures and Devices
4.0 Panel Board and devices
5.0 Service Entrance
6.0 Meter Base and pedestal

500,000.00

SUB-TOTAL (Item VI)


VIII.

PLUMBING WORKS
1.0 Septic vault
2.0 Rough-ins
3.0 Fixtures
Water closet
Kitchen Sink w/ faucet
4.0 Water proofing (deck)
SUB-TOTAL (Item VI)

TOTAL BID AMOUNT >>>

8,206,803.57

TOTAL
AMOUNT
50,000.00
50,000.00
50,000.00
75,000.00

225,000.00

33,000.00
28,500.00
25,000.00
23,520.00
19,800.00
50,000.00
P

179,820.00

579,600.00
389,200.00
392,160.00

124,063.50
104,463.00
117,749.00
24,528.00
120,450.00
201,480.00
301,125.00

74,120.56
132,920.22
206,939.74
11,187.91
126,007.20
257,045.06
610,944.00

43,824.00
96,536.00
25,520.00
161,832.00
159,720.00
178,112.00
290,400.00

24,000.00
106,000.00
24,000.00
P

4,883,927.19

47,520.00
43,200.00
262,440.00
260,820.00

333,600.00
254,904.00
113,700.00

12,500.00
19,740.00
12,150.00

67,788.00
27,115.20
77,472.00
P

1,532,949.20

27,500.00
60,000.00
15,000.00
7,117.74

79,021.44
15,494.40
3,873.60

208,007.18

22,500.00
9,000.00
13,500.00
P

45,000.00

500,000.00

500,000.00

27,000.00
400,000.00
32,500.00
43,000.00
129,600.00
P

632,100.00

8,206,803.57

ERDC Konstrukt Co.


Unit-D Lot 11 Block C Delia Apartment, Progressive 3 Village, Molino 1, Bacoor, Cavite
Telephone Nos.: (046)970 8564 / 09063519572
Project

TWO (2) STOREY APARTMENT WITH DECK

FA

591.00

Ground Flr
Second Flr
RoofDeck
Access Stair

196.00
175.00
180.00
40.00

Owner

Mr. Alberto Estacion

Subject

COST ESTIMATE
COST PROPOSAL
UNIT COST
ITEM DESCRIPTION

I.

QTY.

GENERAL REQUIREMENTS
a. Mobilization/Demobilization
b. Temporary Facilities
c. Safety & Housekeeping
d. Technical Support & Supervision
e. Permits & Licenses (including MERALCO and Maynilad/Manila Waters)

UNIT

1.00
1.00
1.00
1.00
BY OWNER

MATERIAL

LABOR

TOTAL
UNIT COST

50,000.00
50,000.00
50,000.00
75,000.00

50,000.00
50,000.00
50,000.00
75,000.00

100.00
150.00
25,000.00
120.00
60.00
50,000.00

100.00
150.00
25,000.00
120.00
60.00
50,000.00

SUB-TOTAL (Item I)

II.

EARTHWORKS:
a. Site Clearing/Lay-outing/Staking
b. Excavation & Backfilling
c. Demolition of existing wall
d. Soil Poisoning & Gravel Bedding
e. Sub-Grade Preparation & Compaction
f. Disposal of Unsuitable Materials / Debris

330.00
190.00
1.00
196.00
330.00
1.00
SUB-TOTAL (Item I)

m
m
lot
lot
m
lot

III.

STRUCTURAL WORKS
A. Masonry Works
1.0 CHB Laying
2.0 Interior Plastering
3.0 Exterior Plastering

1,656.00
1,112.00
817.00

m
m
m

200.00
200.00
280.00

150.00
150.00
200.00

350.00
350.00
480.00

B. Concreting Works
1.0 Footing
2.0 Footing Tie Beam / Wall Footing
3.0 R. C. Columns
4.0 Staircase
5.0 Slab on Grade
6.0 Suspended Beams / Girders
7.0 Suspended Slabs

33.99
28.62
32.26
6.72
33.00
55.20
82.50

m
m
m
m
m
m
m

3,500.00
3,500.00
3,500.00
3,500.00
3,500.00
3,500.00
3,500.00

150.00
150.00
150.00
150.00
150.00
150.00
150.00

3,650.00
3,650.00
3,650.00
3,650.00
3,650.00
3,650.00
3,650.00

C. Rebar Works
1.0 Footing
2.0 Footing Tie Beam / Wall Footing
3.0 R. C. Columns
4.0 Staircase
5.0 Slab on Grade
6.0 Suspended Beams / Girders
7.0 Suspended Slab

1,723.73
3,091.17
4,812.55
260.18
2,930.40
5,977.79
14,208.00

38.00
38.00
38.00
38.00
38.00
38.00
38.00

5.00
5.00
5.00
5.00
5.00
5.00
5.00

43.00
43.00
43.00
43.00
43.00
43.00
43.00

D. Formworks & Scaffolds


1.0 Footing
2.0 Footing Tie Beam / Wall Footing
3.0 Staircase
4.0 R. C. Columns
5.0 Slab on Grade
6.0 Suspended Beams / Girders
7.0 Suspended Slab

99.60
219.40
58.00
367.80
363.00
404.80
660.00

320.00
320.00
320.00
320.00
320.00
320.00
320.00

120.00
120.00
120.00
120.00
120.00
120.00
120.00

440.00
440.00
440.00
440.00
440.00
440.00
440.00

150.00
2,500.00
150.00

150.00
150.00
150.00

300.00
2,650.00
300.00

E. Roof Framing & Roofing


1.0 Roof framing
2.0 Roofing Longspan ga. 24
3.0 Gutter and flushing

80.00
40.00
80.00
SUB-TOTAL (Item II)

kgs.
kgs.
kgs.
kgs.
kgs.
kgs.
kgs.

m
m
m
m
m
m
m

mtrs
m
mtrs

IV.

ARCHITECTURAL WORKS
A. Tileworks
1.0 T & B:
- wall (ht = 1.20m)
- floor
2.0 Bedrooms
3.0 Liv/Din/Fam/Kit
B. Painting Works
1.0 Interior
2.0 Exterior
3.0 Ceiling

72.00
60.00
324.00
322.00

m
m
m
m

420.00
480.00
570.00
570.00

240.00
240.00
240.00
240.00

660.00
720.00
810.00
810.00

1,112.00
817.00
379.00

m
m
m

168.00
168.00
168.00

132.00
144.00
132.00

300.00
312.00
300.00

C. Exterior Moulding
1.0 Round pre-cast
2.0 Horizontal lines
3.0 Tiles (Deco stone look)

5.00
42.00
15.00

pcs
mtrs
m

2,000.00
300.00
570.00

500.00
170.00
240.00

2,500.00
470.00
810.00

D. Steel Works
1.0 Interior
2.0 Exterior
3.0 Entrance gate per unit

225.96
90.38
258.24

sq ft
sq ft
sq ft

150.00
150.00
150.00

150.00
150.00
150.00

300.00
300.00
300.00

5.00
15.00
5.00
15.82

units
units
units
sq ft

4,500.00
3,000.00
2,000.00
300.00

1,000.00
1,000.00
1,000.00
150.00

5,500.00
4,000.00
3,000.00
450.00

263.40
51.65
12.91

sq ft
sq ft
sq ft

150.00
150.00
150.00

150.00
150.00
150.00

300.00
300.00
300.00

SUB-TOTAL (Item III)


V.

DOORS & WINDOWS


A. Doors
1.0 D1
0.80
2.0 D2
0.70
3.0 D4
0.60
4.0 D6
0.70
B. Windows
1.0 W2
2.0 W3
3.0 W5

X 2.10m panel door


x 2.10m flush door
x 2.10m pvc door
x 2.10m steel door

1.20 x 1.20m steel casement


0.80 x 1.20m steel casement
0.40 x 0.60m steel casement

SUB-TOTAL (Item V)
VI.

CARPENTRY WORKS
Ceiling (CR, gypsum board)
Kitchen Cabinets
Hanging Cabinets

25.00
10.00
15.00

m
m
m

550.00
550.00
550.00

350.00
350.00
350.00

900.00
900.00
900.00

1.00

lot

90.00
1.00

m
lot

150.00
400,000.00

150.00

300.00
400,000.00

5.00
10.00
180.00

set
set
m

5,000.00
3,500.00
480.00

1,500.00
800.00
240.00

6,500.00
4,300.00
720.00

SUB-TOTAL (Item V)
VII.

ELECTRICAL WORKS
1.0 Rough-ins
2.0 Wires and conduits
3.0 Fixtures and Devices
4.0 Panel Board and devices
5.0 Service Entrance
6.0 Meter Base and pedestal

500,000.00

SUB-TOTAL (Item VI)


VIII.

PLUMBING WORKS
1.0 Septic vault
2.0 Rough-ins
3.0 Fixtures
Water closet
Kitchen Sink w/ faucet
4.0 Water proofing (deck)
SUB-TOTAL (Item VI)

TOTAL BID AMOUNT >>>

8,206,803.57

TOTAL
AMOUNT
50,000.00
50,000.00
50,000.00
75,000.00

225,000.00

33,000.00
28,500.00
25,000.00
23,520.00
19,800.00
50,000.00
P

179,820.00

579,600.00
389,200.00
392,160.00

124,063.50
104,463.00
117,749.00
24,528.00
120,450.00
201,480.00
301,125.00

74,120.56
132,920.22
206,939.74
11,187.91
126,007.20
257,045.06
610,944.00

43,824.00
96,536.00
25,520.00
161,832.00
159,720.00
178,112.00
290,400.00

24,000.00
106,000.00
24,000.00
P

4,883,927.19

47,520.00
43,200.00
262,440.00
260,820.00

333,600.00
254,904.00
113,700.00

12,500.00
19,740.00
12,150.00

67,788.00
27,115.20
77,472.00
P

1,532,949.20

27,500.00
60,000.00
15,000.00
7,117.74

79,021.44
15,494.40
3,873.60

208,007.18

22,500.00
9,000.00
13,500.00
P

45,000.00

500,000.00

500,000.00

27,000.00
400,000.00
32,500.00
43,000.00
129,600.00
P

632,100.00

8,206,803.57

ERDC Konstrukt Co.


Unit-D Lot 11 Block C Delia Apartment, Progressive 3 Village, Molino 1, Bacoor, Cavite
Telephone Nos.: (046)970 8564 / 09063519572
Project

TWO (2) STOREY APARTMENT WITH DECK

FA

591.00

Ground Flr
Second Flr
RoofDeck
Access Stair

196.00
175.00
180.00
40.00

Owner

Mr. Alberto Estacion

Subject

COST ESTIMATE
COST PROPOSAL
UNIT COST
ITEM DESCRIPTION

I.

QTY.

GENERAL REQUIREMENTS
a. Mobilization/Demobilization
b. Temporary Facilities
c. Safety & Housekeeping
d. Technical Support & Supervision
e. Permits & Licenses (including MERALCO and Maynilad/Manila Waters)

UNIT

1.00
1.00
1.00
1.00
BY OWNER

MATERIAL

LABOR

TOTAL
UNIT COST

15,000.00
15,000.00
15,000.00
15,000.00

15,000.00
15,000.00
15,000.00
15,000.00

50.00
80.00
6,000.00
70.00
20.00
10,000.00

50.00
80.00
6,000.00
70.00
20.00
10,000.00

SUB-TOTAL (Item I)

II.

EARTHWORKS:
a. Site Clearing/Lay-outing/Staking
b. Excavation & Backfilling
c. Demolition of existing wall
d. Soil Poisoning & Gravel Bedding
e. Sub-Grade Preparation & Compaction
f. Disposal of Unsuitable Materials / Debris

225.00
100.00
1.00
100.00
125.00
1.00
SUB-TOTAL (Item I)

m
m
lot
lot
m
lot

III.

STRUCTURAL WORKS
A. Masonry Works
1.0 CHB Laying
2.0 Interior Plastering
3.0 Exterior Plastering

1,000.00
800.00
500.00

m
m
m

70.00
70.00
80.00

70.00
70.00
80.00

140.00
140.00
160.00

B. Concreting Works
1.0 Footing
2.0 Footing Tie Beam / Wall Footing
3.0 R. C. Columns
4.0 Staircase
5.0 Slab on Grade
6.0 Suspended Beams / Girders
7.0 Suspended Slabs

33.99
28.62
32.26
6.72
33.00
55.20
82.50

m
m
m
m
m
m
m

1,500.00
1,500.00
1,500.00
1,500.00
1,500.00
1,500.00
1,500.00

60.00
60.00
60.00
60.00
60.00
60.00
60.00

1,560.00
1,560.00
1,560.00
1,560.00
1,560.00
1,560.00
1,560.00

C. Rebar Works
1.0 Footing
2.0 Footing Tie Beam / Wall Footing
3.0 R. C. Columns
4.0 Staircase
5.0 Slab on Grade
6.0 Suspended Beams / Girders
7.0 Suspended Slab

1,723.73
3,091.17
4,812.55
260.18
2,930.40
5,977.79
14,208.00

kgs.
kgs.
kgs.
kgs.
kgs.
kgs.
kgs.

18.00
18.00
18.00
18.00
18.00
18.00
18.00

2.00
2.00
2.00
2.00
2.00
2.00
2.00

20.00
20.00
20.00
20.00
20.00
20.00
20.00

D. Formworks & Scaffolds


1.0 Footing
2.0 Footing Tie Beam / Wall Footing
3.0 Staircase
4.0 R. C. Columns
5.0 Slab on Grade
6.0 Suspended Beams / Girders
7.0 Suspended Slab

99.60
219.40
58.00
367.80
363.00
404.80
660.00

m
m
m
m
m
m
m

80.00
80.00
80.00
80.00
80.00
80.00
80.00

45.00
45.00
45.00
45.00
45.00
45.00
45.00

125.00
125.00
125.00
125.00
125.00
125.00
125.00

60.00
900.00
60.00

60.00
60.00
60.00

120.00
960.00
120.00

E. Roof Framing & Roofing


1.0 Roof framing
2.0 Roofing Longspan ga. 24
3.0 Gutter and flushing

80.00
40.00
80.00
SUB-TOTAL (Item II)

mtrs
m
mtrs

IV.

ARCHITECTURAL WORKS
A. Tileworks
1.0 T & B:
- wall (ht = 1.20m)
- floor
2.0 Bedrooms
3.0 Liv/Din/Fam/Kit

72.00
60.00
324.00
322.00

m
m
m
m

90.00
90.00
170.00
170.00

70.00
70.00
70.00
70.00

160.00
160.00
240.00
240.00

B. Painting Works
1.0 Interior
2.0 Exterior
3.0 Ceiling

800.00
500.00
379.00

m
m
m

80.00
80.00
80.00

70.00
65.00
70.00

150.00
145.00
150.00

C. Exterior Moulding
1.0 Round pre-cast
2.0 Horizontal lines
3.0 Tiles (Deco stone look)

5.00
42.00
15.00

pcs
mtrs
m

500.00
80.00
150.00

200.00
80.00
100.00

700.00
160.00
250.00

D. Steel Works
1.0 Interior
2.0 Exterior
3.0 Entrance gate per unit

225.96
90.38
258.24

sq ft
sq ft
sq ft

60.00
60.00
60.00

60.00
60.00
60.00

120.00
120.00
120.00

5.00
15.00
5.00
15.82

units
units
units
sq ft

800.00
500.00
500.00
80.00

250.00
250.00
250.00
70.00

1,050.00
750.00
750.00
150.00

263.40
51.65
12.91

sq ft
sq ft
sq ft

50.00
50.00
50.00

60.00
60.00
60.00

110.00
110.00
110.00

SUB-TOTAL (Item III)


V.

DOORS & WINDOWS


A. Doors
1.0 D1
0.80
2.0 D2
0.70
3.0 D4
0.60
4.0 D6
0.70
B. Windows
1.0 W2
2.0 W3
3.0 W5

X 2.10m panel door


x 2.10m flush door
x 2.10m pvc door
x 2.10m steel door

1.20 x 1.20m steel casement


0.80 x 1.20m steel casement
0.40 x 0.60m steel casement

SUB-TOTAL (Item V)
VI.

CARPENTRY WORKS
Ceiling (CR, gypsum board)
Kitchen Cabinets
Hanging Cabinets

25.00
10.00
15.00

m
m
m

150.00
150.00
150.00

100.00
100.00
100.00

250.00
250.00
250.00

1.00

lot

90.00
1.00

m
lot

75.00
175,000.00

80.00

155.00
175,000.00

5.00
10.00
180.00

set
set
m

2,000.00
1,300.00
180.00

5,000.00
320.00
70.00

7,000.00
1,620.00
250.00

SUB-TOTAL (Item V)
VII.

ELECTRICAL WORKS
1.0 Rough-ins
2.0 Wires and conduits
3.0 Fixtures and Devices
4.0 Panel Board and devices
5.0 Service Entrance
6.0 Meter Base and pedestal

175,000.00

SUB-TOTAL (Item VI)


VIII.

PLUMBING WORKS
1.0 Septic vault
2.0 Rough-ins
3.0 Fixtures
Water closet
Kitchen Sink w/ faucet
4.0 Water proofing (deck)
SUB-TOTAL (Item VI)

TOTAL BID AMOUNT >>>

2,890,552.79

TOTAL
AMOUNT
15,000.00
15,000.00
15,000.00
15,000.00

60,000.00

11,250.00
8,000.00
6,000.00
7,000.00
2,500.00
10,000.00
P

44,750.00

140,000.00
112,000.00
80,000.00

53,024.40
44,647.20
50,325.60
10,483.20
51,480.00
86,112.00
128,700.00

34,474.68
61,823.36
96,251.04
5,203.68
58,608.00
119,555.84
284,160.00

12,450.00
27,425.00
7,250.00
45,975.00
45,375.00
50,600.00
82,500.00

9,600.00
38,400.00
9,600.00
P

1,746,024.00

11,520.00
9,600.00
77,760.00
77,280.00

120,000.00
72,500.00
56,850.00

3,500.00
6,720.00
3,750.00

27,115.20
10,846.08
30,988.80
P

508,430.08

5,250.00
11,250.00
3,750.00
2,372.58

28,974.53
5,681.28
1,420.32

58,698.71

6,250.00
2,500.00
3,750.00
P

12,500.00

175,000.00

175,000.00

13,950.00
175,000.00
35,000.00
16,200.00
45,000.00
P

285,150.00

2,890,552.79

You might also like