Drainage Design Manual Section 2
Drainage Design Manual Section 2
Drainage Design Manual Section 2
Section 2
TABLE OF CONTENTS
SECTION 2 : STORM WATER SYSTEM DESIGN................................................................2.1
2.1 Steps in Planning of Storm Water Management Studies...............................................2.1
2.1.1
General............................................................................................................ 2.1
2.1.2
Preparing Concept Plans.................................................................................2.1
2.1.3
System Planning and Design...........................................................................2.3
2.1.4
Review of System Plan and Design.................................................................2.4
2.1.5
Re-Evaluation.................................................................................................. 2.4
2.1.6
Final Design Detailing......................................................................................2.5
2.1.7
Implementation................................................................................................ 2.5
2.1.8
Plan Components............................................................................................2.6
Section 2
SECTION 2
STORM WATER SYSTEM DESIGN
2.1
General
2.1.2
The following tasks should be carried out for the preparation of a storm water
management plan.
Step 1: Establishing Objectives and Standards - Objectives and standards should
be established to guide the planning process. These may be obtained from
the strategy plan for the catchment (if available). The objectives and
standards should provide the basis for and give direction to the planning
process and should be used to determine the expected outputs of the
recommended plan.
Step 2: Data Collection - Data collected for the planning process provides the factual
basis for the plan and allows an appreciation of past and an understanding of
present conditions within the catchment. The extent of data collection would
be the reflection of the objective/s and standard/s set. The data collected for
the development of the strategy plan for the catchment should be used if
available. This data may need to be supplemented with additional data
necessary to further define the characteristics of the area under investigation.
2.1: Base Map - The base map should identify the watershed areas and sub
areas, land use and cover types, soil types, existing drainage patterns,
and other topographic features. This base information is then
supplemented with underground utility locations (and elevations if
available), a preliminary roadway plan and profile, and locations of
existing and proposed structures.
2.2: Hydro meteorological Data - Hydro meteorological data gives
information mainly on the rainfall, and for gauged areas, the runoff.
Step 3: Analysing Existing Conditions - The main purposes of this phase is to use
the data and information collected under the data collection phase to
understand the present state of storm water management related conditions
in the catchment.
2.1
Ministry of Works, Housing & Communications
Section 2
The water quantity and/or quality characteristics for the existing catchment
conditions must be determined.
For existing developments, models are required to:
determine the capacity of existing major and minor conveyance systems;
determine the location and extent of any flooding under major and minor
system;
determine the pollutant loads for existing land uses within the catchment;
and,
determine the performance of any existing water quality control structures.
For proposed developments, models are required to:
determine natural flows within the catchment which may be used as flow
limits for development proposals; and,
determine natural pollutant loadings within the catchment which may be
used as pollutant load limits for development proposals.
Step 4: Formulating Alternatives - Formulation of alternatives is the most important
part of the storm water management planning process because the substance
of the recommended plan originates from this step. Formulation of
alternatives is creative and systematic effort where alternatives are
conceptualised, screened, and if promising, further developed and
consolidated. The essential conceptual, technical, economic, environmental,
financial, legal, administrative, political, and other features of each alternative
should be examined before finalization. In formulating alternative proposals,
the water quantity and quality characteristics must be determined.
Step 5: Comparing Alternatives and Selecting the most Viable One/s - Having
formulated a set of possible alternative solutions for managing storm water,
the alternatives should be compared. The essential features of each
alternative such as size, costs, benefits, and positive and negative attributes
should be compared in summary form for presentation to decision-makers
and the community when required. Alternatives should be compared on the
basis of how well they achieve the established objectives.
As the positive and negative features of each alternative are considered and
compared with features of other alternatives, the possibility of hybrid
alternatives may arise. Hybrid alternatives might achieve a technically
improved solution or might be a means of obtaining support among decisionmakers.
Step 6: Preliminary Concept Development - Layout and design of a storm drainage
system begins with the development of sketches identifying the basic
components of the intended design. This section provides an overview of the
concepts involved in the development of a preliminary concept plan.
Concept plan is usually done on a base map that shows the roadway,
location of bridge points; land use and land cover conditions of the catchment.
Other utility locations and situations should also be identified and shown,
including surface and underground ones and any other storm drain systems.
Storm drain alignment within the road right-of-way is usually influenced, if not
dictated, by the location of other utilities. These other utilities, which may be
2.2
Ministry of Works, Housing & Communications
Section 2
2.1.3
For this chosen mode of study through the aforementioned steps, system planning and
design is the next phase to go into. Planning and design of an integrated urban storm
water management development requires data base on the following area:
locations where flows, flood levels, and water quality are to be assessed; and,
i. Catchment
ii. Flow estimation and check:- Flow estimation could be done by establishing a
hydrologic model by using design rainfall data and the estimation of hydrologic
parameters such as runoff coefficient.
iv. Checking flows in the Major system:- After the initial minor system is
developed, flows in the major design system is checked.
v. Preliminary design:- Using the initial analyses, preliminary design is made for the
major and minor systems. Consideration is also to be given to alternatives which
may result in a more economic design.
In the investigation of an individual scheme, the full range of design alternatives
should be considered to determine the best alternative.
2.3
Ministry of Works, Housing & Communications
Section 2
2.1.4
Evaluating culverts and bridges to assure that applicable criteria are not
violated and the size and characteristics of conveyances are adjusted till the
level of backwater during the major system design runoff event meets target
levels. The backwater computation is also used to define the area affected by
backwater flooding during the major events and to effect the necessary
measures.
2.1.5
Re-Evaluation
Section 2
preliminary design values that will be used subsequently in final design should be
reviewed for accuracy and applicability to final design.
2.1.6
b)
2.1.7
i.
Implementation
Section 2
the credibility of the plan as determined by the quality of the technical work and
the thoroughness of the community involvement carried out during the
planning process; and,
the frequency and severity of storm water-related problems and the level of
concern that past problems will occur again.
The ultimate test of a storm water management plan is the degree to which storm
water problems have been mitigated and the degree to which potential storm
water problems have been prevented from occurring.
2.1.8
Plan Components
Storm water management plans should consist of two major components: a technical
report, and supporting plans.
i.
ii.
2.6
Ministry of Works, Housing & Communications