Lube Oil Pumps
Lube Oil Pumps
Lube Oil Pumps
(UNIT# 7&8)
TECHNICAL SPECIFICATION
FOR
LUBE OIL PUMPS
2X660MW
SURATGARH STPS,
STAGE-V
PEM-6666-0
2X660
MW RAGHUNATHPUR
VOLUME
SECTION TPP PHASE
REVISION 00
II-26/12/2013
S
DATE
PE-TS-390-567-A001
:13/08/2013
PAGE 1 of 1
INDEX
S.
No.
1.
2.
3.
4.
5.
6.
DESCRIPTION
Preamble
Intent of Specification
Project information
Specific Technical Requirements
a. Scope of Work
b. Electrical Equipment Specification
Technical Specification of Equipment
a. General Technical Specification for Lube
b. General Technical Requirement for LV
c. Electrical Scope Split between BHEL and
d. Quality Plan for Lube Oil Pumps
e. Quality Plan for Basket ( Simplex &
f. Quality Plan for MOTOR
Technical Schedules / Datasheets
a.
b.
c.
d.
e.
f.
Deviation Schedule
Data Sheet for Lube Oil Pumps
Data Sheet for Motor
Electrical Load data format
ANNEXUREIII
:Drawings/Documents required
detail engineering
g. during
Compliance
cum Confirmation
Page 1 of 92
VOLU
ME/
SECT
IIB / A
IIB / B
IIB / C
IIB / D
PAGE
NO.
2
5
8
12
13
21
37
38
48
53
54
59
62
III
73
74
75
76
81
88
89
91
PREAMBLE
392 567-A001
SPEC. NO. PE-TS -390VOLUME :
SECTION :
REV. NO.
00
SHEET
-
OF
DATE
1.1 The Tender document contains three (3) volumes.The bidder shall meet the
requirements of all the three volumes.
1.2 Volume I CONDITIONS OF
CONTRACT This consists of four
parts as below:
Volume - I A
Volume - I B
Volume - I C
Volume - I D
Volume - II B
1.3.1 Volume - II B :
This volume is sub-divided into following sections:
Section - A
Section - B
Section - C
Section - D
Page 2 of 92
PREAMBLE
00
SHEET
-
OF
DATE
The requirements mentioned in Section C/Data Sheets-A of Section-D shall prevail and
govern in case of conflict between the same and the corresponding requirements
mentioned in the descriptive portion in Section -D.
Page 3 of 92
PEM-6666-0
TECHNICAL SPECIFICATION
FOR LUBE OIL TRANSFER
PUMPS
2X660 MW RAGHUNATHPUR
TPP PHASE II- S
VOLUME II B
Page 4 of 92
SECTION
REVISION 00
13/08/2013
DATE: 26/12/2013
PAGE 1 of 1
PEM-6666-0
TECHNICAL SPECIFICATION
FOR LUBE OIL TRANSFER
PUMPS
2X660 MW RAGHUNATHPUR
TPP PHASE II- S
SECTION
REVISION 00
DATE: 26/12/2013
13/08/2013
PAGE 1 of 1
VOLUME II
B SECTION
A
INTENT OF SPECIFICATION
PEM-6666-0
TECHNICAL SPECIFICATION
FOR LUBE OIL TRANSFER
PUMPS
SECTION A
REVISION 00
DATE: 26/12/2013
PAGE 1 of 2
V, UNIT# 7&8
1.0
INTENT OF SPECIFICATION
1.1
1.2
The contractor shall be responsible for providing all material, equipment &
services, which are required to fulfil the intent of ensuring operability,
maintainability, reliability and complete safety of the complete work
covered under this specification, irrespective of whether it has been
specifically listed herein or not.
1.3
It is not the intent to specify herein all the details of design and
manufacture. However, the equipment / system shall conform in all
respects to high standards of design, engineering and workmanship and
shall be capable of performing the required duties in a manner
acceptable to purchaser who will interpret the meaning of drawings
and specifications and shall be entitled to reject any work or material
which in his judgement is not in full accordance herewith.
1.4
1.5
While all efforts have been made to make the specification requirement
complete & unambiguous, it shall be bidders responsibility to ask for
missing information , ensure completeness of specification, to bring out
any contradictory / conflicting requirement in different sections of the
specification and within a section itself to the notice of BHEL and to seek
any clarification on specification requirement in the format enclosed under
VolIII of the specification within 10 days of receipt of tender
documents. In absence of any such clarifications, in case of any
contradictory requirement, the more stringent requirement as per
interpretation of Purchaser/Customer shall prevail and shall be complied by
the bidder without any commercial implication on account of the same.
Further in case of any missing information in the specification not brought
out by the prospective bidders as part of prebid clarification, the same
shall be furnished by Purchaser/ Customer as and when brought to
their notice either by the bidder or by purchaser/ customer themselves.
However, such requirements shall be binding on the successful bidder
without any commercial & delivery implication.
1.6
1.7
PEM-6666-0
TECHNICAL SPECIFICATION
FOR LUBE OIL TRANSFER
PUMPS
SECTION A
REVISION 00
DATE: 26/12/2013
PAGE 2 of 2
V, UNIT# 7&8
1.8
1.9
The bidders offer shall not carry any sections like clarification,
interpretations and /or assumptions.
1.10
In case all above requirements are not complied with, the offer
may be considered as incomplete and would become liable for rejection.
Page 7 of 92
PEM-6666-0
TECHNICAL SPECIFICATION
FOR LUBE OIL TRANSFER
PUMPS
SECTION
REVISION 00
DATE: 26/12/2013
PAGE 1 of 1
V, UNIT# 7&8
VOLUME II
B SECTION
B
PROJECT INFORMATION
SPEC NO.
TCE.5750A-H-500-001
VOLUME
II
SECTION
RRVUNL, 2 x 660 MW, Super-Critical TPS, StageV, Unit # 7 & 8 at Suratgarh, Rajasthan
SHEET 1 OF 3
1.0
Owner
2.0
Consulting Engineer
3.0
4.0
5.0
186 m (approximate)
6.0
Climatic conditions
Temperatures : Monthly basis
6.1
32.3 deg.C
19.6 deg.C
50 deg.C
6.3
Relative humidity
6.4
312 mm
6.5
7.0
4 km / hr.
Page 9 of 92
ISS
U
E
FORM NO. 329 R5
SPEC NO.
TCE.5750A-H-500-001
VOLUME
II
SECTION
RRVUNL, 2 x 660 MW, Super-Critical TPS, StageV, Unit # 7 & 8 at Suratgarh, Rajasthan
SHEET 2 OF 3
Calculations for wind effect shall be in accordance with IS:875-1987(Part3) taking into account the following:
a) Basic wind speed = 47 m/sec
b) Factor K1 = 1.07
c) Category of terrain = Category 2
d) K3 as per IS 875
Seismic data (As per IS: 1893 latest issue)
8.0
a) Zone
Zone II
b)
c)
d)
e)
DC motor starters, DC
solenoids, DC alarm control
and
AC protection
control & protective devices
f)
g)
Page 10 of 92
SPEC NO.
TCE.5750A-H-500-001
VOLUME
II
SECTION
RRVUNL, 2 x 660 MW, Super-Critical TPS, StageV, Unit # 7 & 8 at Suratgarh, Rajasthan
SHEET 3 OF 3
i)
DC supply
10.0
11.0
Page 11 of 92
ISS
U
E
FORM NO. 329 R5
PEM-6666-0
TITLE
TECHNICAL SPECIFICATION
FOR LUBE OIL PUMPS
VOLUME II - B
SECTION -C
REV
SHEET
SECTION-C
Page 12 of 92
DATE 07/07/07
OF
PEM-6666-0
PE-TS-STD-567-A001
SPECIFICATION NO. PE-TS-392-567-A001
TITLE
TECHNICAL
VOLUME II B
SPECIFICATION
SECTION C
FOR
REV
00
DATE
SHEET
Page 13 of 92
PEM-6666-0
TITLE
TECHNICAL
VOLUME II B
SPECIFICATION
SECTION C
FOR
REV
4.1
00
DATE
SHEET
Surface
preparati
on
Primer Coat
Intermediate coat
Finish
Note:
I.
Any change in painting specification at later date needs to be
complied by bidder without any Commercial implication.
II.
5.1
QUALITY REQUIREMENTS
a)Bidder should maintain excellent quality of works , all supply items shall
meet the relevant quality Standards.
b)
The successful bidder shall furnish Quality Plans/ Inspection Check
Lists for various item for the Package in line with minimum requirement
indicated in specification during detail engineering for Customers approval.
c)For other items for which any specific inspection requirement is not
indicated in the specification but the same included in scope of work ,
vendor specific QPs/ CLs shall be furnished by the Successful bidder for
Customer/Consultants review and approval. All comments made by
customer/ consultant shall be incorporated by the successful bidder without
any commercial and delivery implication.
5.0
SUBVENDOR ITEMS
The makes of subvendor items are subjected
to acceptance by customer
without any additional commercial implication to BHEL .
Page 14 of 92
PE-TS-STD-567-A001
SPECIFICATION NO. PE-TS-392-567-A001
PEM-6666-0
TITLE
TECHNICAL
VOLUME II B
SPECIFICATION
SECTION C
FOR
REV
7.0
00
DATE
SHEET
Page 15 of 92
BHE
L
PE
M
PE-TS-392-567-A001
PE-DC-392-100-N300
DOC. NO.
DATA SHEET A
DATA SHEET FOR LUBE OIL PUMPS
PROJECT TITLE :
RRVUNL - SURATGARH, STPP (2 X 660 MW)
SHEET NO. 01
1.
SERVICE IDENTIFICATION
2.
0
3.
0
4.
0
DRAWING NO.
PE-DG-392-100-N108
PE-DG-392-100-N108
SYSTEM
TYPE
5.
0
NUMBER REQUIRED
ROTARY
POSITIVE
DISPLACEMENT
ONE (01) NO. (COMMON FOR
THE STATION)
ROTARY
POSITIVE
DISPLACEMENT
ONE (01) NO. (COMMON FOR
THE STATION)
6.
0
7.0
6600 LPH
6600 LPH
DISCHARGE PRESSURE
8.
0
SUCTION CONDITION
9.
0
10.
0
LOCATION OF INSTALLATION
INDOOR
INDOOR
LIQUID PUMPED
11.
0
PROPERTIES OF FLUID
12.
0
13.
0
SUCTION / DISCHARGE
PIPING CONNECTION
14.
0
15.
0
RELIEF VALVE
SUCTION STRAINER
16.
0
MATERIALS OF
CONSTRUCTION CASING
GEA
RS
SHA
APPLICABLE CODES /
STATUTORY REGULATIONS
17.
0
OF 01
18.
DRIVE TYPE
INDUCTION MOTOR 415 V, 50
INDUCTION MOTOR 415 V, 50
0
Hz
Hz
NOTE : ALL OTHER GENERAL TECHNICAL REQUIREMENTS / ACCESSORIES & SPARES AS PER
CUSTOMER TENDER SPECIFICATION.
Page 16 of 92
VOLUME II
SPEC NO.
TCE.5749A-H-500-001
LIMITED
TECHNICAL
SPECIFICATION
NO.- PE-TS-392567-A001
SECTION C
18
SHEET 34 OF 92
Sl.No
Description
Uni
t
2.9.11.
2
2.9.11.
3
Set
sSet
s
2.9.11.
4
2.9.11.
5
clutch assembly
All types of bearings in the centrifuge
Set
Set
s
1
2
2.9.11.
6
Set
s
2.9.11.
7
2.9.11.
8
2.9.11.
9
2.9.11.
10
2.9.12
All filters
Heater elements
Centrifuge motor
Bearings for Centrifuge motor
Dirty oil pump
Rotating assembly
Set
sSet
No.
Set
4
2
1
1
Set
2.9.12.
2
2.9.12.
3
Bearings
wearing rings (for centrifugal
pump) if applicable
Set
Set
1
1
2.9.12.
4
2.9.12.
No.
2.9.12.
1
Quanti
ty for
both
2
2
Set
9
2.9.13
2.9.13.
1
Set
2.9.13.
2
2.9.13.
3
Bearings
wearing rings (for centrifugal
pump) if applicable
Set
Set
1
1
2.9.13.
4
2.9.13.
5
2.10.0
2.10.1
No.
Set
Nos
Remarks
Consists of
assembly of all
the rotating
parts excluding
bearings
Consists of
assembly of all
the rotating
parts excluding
bearings
IS
S
U
E
R
1
Page 17 of 92
SPEC NO.
VOLUME II
SECTION C 19
TCE.5750A-H-500-001
TECHNICAL
SPECIFICATION
NO.- PE-TS-392567-A001
SHEET 1 OF 12
19.1
ISSU
E
Page 18 of 92
R1
TCE FORM 329 R5
SPEC NO.
SECTION C 19
TCE.5750A-H-500-001
TECHNICAL
SPECIFICATION
NO.- PE-TS-392567-A001
VOLUME II
SHEET 6 OF 12
Package Title
Name of Vendors
VARAT
1
5)
1
6)
1
7)
VENTILATION SYSTEM
1
8)
MISCELLANEOUS
POLCON,
HYDRABAD
AVON
CRANES
PVT. LTD., GURGAON
Page 19 of 92
ISSU
E
R1
TCE FORM 329 R5
SPEC NO.
SECTION C 19
TCE.5750A-H-500-001
TECHNICAL
SPECIFICATION
NO.- PE-TS-392567-A001
VOLUME II
SHEET 12 OF
12
Package Title
Name of Vendors
FLAKT
INDIA
BATLIBOI
THERMAX
ELECTRICAL WORKS
Refer Volume IV
D
Refer Volume V
NOTES
1.
2.
Wherever the make is not specified for any item, the Bidder shall
indicate 2 or 3 reputed makes, out of which Purchaser /
Consultant shall select any one which is acceptable suggest an
acceptable make. This shall have no price implication.
ISSU
E
Page 20 of 92
R1
TCE FORM 329 R5
ELECTRICAL EQUIPMENT
SPECIFICATION FOR
LUBE OIL PUMPS
SPECIFICATION
NO.
VOLUME NO. :
II-B
SECTION
:
C
REV NO. : 00 DATE :
30.10.13
SHEET : 1 OF
1
TECHNICAL
SPECIFICATIO
N FOR
LUBE OIL PUMPS
(ELECTRICAL PORTION)
ELECTRICAL EQUIPMENT
SPECIFICATION FOR
LUBE OIL PUMPS
SPECIFICATION
NO.
VOLUME NO. :
II-B
SECTION
:
C
REV NO. : 00 DATE :
30.10.13
SHEET : 1 OF
1
a) Services and equipment as per Electrical Scope between BHEL and Vendor.
b) Any item/work either supply of equipment or erection material which have
not been specifically mentioned but are necessary to complete the work for
trouble free and efficient operation of the plant shall be deemed to be included
within the scope of this specification. The same shall be provided by the
bidder without any extra charge.
c) Supply of mandatory spares as specified in the specifications of
mechanical equipments.
d) Erection and Commissioning spares.
e) Erection & Maintenance tools & tackles.
f) Electrical load requirement for Lube oil Pumps.
g) All equipment shall be suitable for the power supply fault levels and other
climatic conditions mentioned in the enclosed project information.
h) Bidder to furnish list of makes for each equipment at contract stage, which shall
be subject to customer /BHEL approval without any commercial and delivery
implications to BHEL
i) Various drawings, data sheets as per required format, Quality plans,
calculations, test reports, test certificates, operation and maintenance
manuals etc shall be furnished as specified at contract stage. All documents
shall be subject to customer/BHEL approval without any commercial
implication to BHEL.
2.0
Bidder shall confirm total compliance to the electrical specification without any
deviation from the technical/quality assurance requirements stipulated. In line with
this two signed and stamped copies of the following shall be furnished by the
bidder as technical offer:
a) A copy of this sheet Electrical equipment Specification for Lube Oil Pumps
and sheet Electrical Scope between BHEL and Vendor with bidders
signature and company stamp.
b) List of Erection and Commissioning spares.
c) List of Erection & Maintenance tools & tackles.
d) Electrical load requirement
3.3
List of enclosures :
a) Electrical Scope between BHEL and Vendor
b) Standard Specification for Motors (PE-SS-999-506-E101, VOL-IIB, SEC-D)
c) Motors data sheet-A
d) Motors data sheet-B
e) Quality Plan (motors below 55kW & motors above 55kW)
f) Load data format.
g) Motor & cable customer specification
SPEC.NO.
TCE.5750A-H-500001
PART B
TECHNICAL
PART B
SPECIFICATION
NO.- PE-TS-392567-A001
IV
SECTION:
D13
SHEET 1 OF 7
1.0
AC & DC MOTORS
1.1.
1.2.
All LT motors shall be energy efficient class I in line with IS: 12615. However,
the starting current shall be limited to 600% (inclusive of 20% tolerance) of
full load current.
1.3.
The motor rating shall be arrived at considering 15% margin over the duty
point input or 10% over the maximum demand of the driven equipment,
whichever is higher, considering highest system frequency. Motors shall be
capable of starting and accelerating the load with the applicable method of
starting without exceeding acceptable winding temperatures when supply
voltage is 80% of the rated voltage for HT motors and 85% for LV motors.
HT motors shall also be capable of satisfactory operation at full load at a
supply voltage of 80% of the rated voltage for 5 min. commencing from hot
condition. DC motors shall be suitable for the DC system voltage of 220V.
Motor shall be capable of starting and accelerating the load with the
applicable method of starting, without exceeding acceptable winding
temperatures, when the supply voltage is in the range of 85% to 110% of
rated motor voltage.
1.4.
Motors shall be capable of running for one second if the supply voltage drops
to 70% of the rated voltage. If such operation is envisaged for a period of
one second, the pull out torque of the motor shall be at least 205% of full load
torque.
1.5.
Motors shall withstand for 1 second the voltage and torque stresses
developed due to the vector difference between the motor residual voltage
and the incoming supply voltage equal to 150% of the rated voltage during
fast changeover of buses.
1.6.
Locked rotor current of the HT motors rated 1500 kW and below shall be
limited to 600% (inclusive of 20% tolerance) of the full load current of the
motors and motor rated above 1500 kW shall be limited to 450% (inclusive of
20% tolerance) of full load current of the motor.
1.7.
The locked rotor withstand time under hot condition at 110% rated voltage
shall be more than the starting time at minimum permissible voltage specified
above by at least three seconds or 15% of the accelerating time whichever
is greater. Provision of speed switch shall be avoided to the extent possible.
These motors shall be designed to withstand at least 5% harmonics in the
supply voltage.
1.8.
The degree of protection for the motor enclosure (including terminal box) shall
be IP-55 for outdoor. For single core cable termination, gland plates shall be
of non- magnetic material. All motors located in hazardous area shall have
Page 23 of 92
ISS
U
E
FILE NAME:
F329R5.DOC
SPEC.NO.
TCE.5750A-H-500001
PART B
TECHNICAL
PART B
SPECIFICATION
NO.- PE-TS-392567-A001
VOLUME IV
SECTION:
D13
SHEET 2 OF 7
1.9.
1.10.
1.11.
1.12.
The ring oiling system shall be adequate for starting and continuous operation
of the motor for at least one half hour without pressure oiling system in
operation.
1.13.
For 11kV & 6.6 kV motors, 6-nos. duplex RTD s for winding shall be provided
for remote monitoring, alarm and tripping at DCS. Each bearing shall be
provided with one duplex RTD for temperature remote monitoring, alarm and
tripping at DCS. 6 nos. spare RTDs shall be provided for winding in HT
motors.
1.14.
The maximum double amplitude vibrations for motors shall be as per IS 12075.
1.15.
Maximum noise level measured at a distance of 1.5 meter from the outer
surface of the motor shall not exceed 85 db (A).
1.16.
Cable boxes of all 11kV & 6.6 kV motors shall be Phase segregated & shall
be provided with quick disconnecting type terminal connectors to facilitate
easy disconnection and removal of the motors without requiring unsealing or
otherwise disturbing the external cable connections and leaving the phase
segregated terminal box intact. The terminal boxes shall have fault withstand
capacity equal to at least rated short circuit level of system voltage for 0.25
sec. The terminal boxes shall be reversible to suit cable entry from top or
bottom and suitable for termination of FRLS, XLPE armoured cables.
1.17.
The star connection side terminal box should have sufficient capacity to
accommodate CTs for differential protection for motor above 1000kW.
1.18.
The insulation system for 11000 V AC & 6600 V AC motors shall withstand
the negative or positive 0.3 / 3.0 microsecond wave (2.7 pu rated peak line to
earth operating voltage) switching surges originating from non-effectively
earthed power system. All 11000V AC & 6600 V AC motors shall have BIL
and power frequency withstand voltage as per relevant standards.
1.19.
ISS
U
E
FILE NAME:
F329R5.DOC
SPEC.NO.
TCE.5750A-H-500001 B
PART
TECHNICAL
PART B
SPECIFICATION
NO.- PE-TS-392567-A001
VOLUME IV
SECTION:
D13
SHEET 3 OF 7
1.21.
1.22.
CACW motor shall be provided with water leakage detector with remote
alarms and tripping.
1.23.
1.24.
1.25.
1.26.
All motors for outdoor duty shall have detachable metal canopy.
1.27.
b)
c)
1.28.
1.29.
1.30.
2.0
ACTUATOR
2.1.
2.1.1. Actuator shall be weatherproof type with enclosure conforming to IP-64 degree
of protection. It should be suitable for out-door use without the need for
canopy. If the IP-68 degree of protection is required due to occasional
submergence, the purchaser shall specify the depth and duration of such
submergence.
2.1.2. The actuator shall be suitable for installation in any position without
lubrication leakage or other operational difficulty.
2.1.3. All actuators shall be supplied with non integral starters for open & close.
The main gearbox of the actuator shall be special grease filled.
2.1.4. Each actuator should have a hand wheel for emergency manual
operation. Clockwise operation of hand wheel shall cause clockwise
movement of the
Page 25 of 92
ISS
U
E
FILE NAME:
F329R5.DOC
SPEC.NO.
TCE.5750A-H-500001
PART B
TECHNICAL
PART B
SPECIFICATION
NO.- PE-TS-392567-A001
VOLUME IV
SECTION:
D13
SHEET 4 OF 7
output drive. The hand wheel shall be clearly marked with an arrow and the
word CLOSE.
2.1.5. The hand wheel shall automatically disengage when the power to the motor
is restored i.e. power drive shall have a preference over manual drive.
2.1.6. The manual effort should not exceed 400 N (push / pull). A top bevel gear
set (side mounted hand wheel) shall be employed to reduce the manual effort.
2.1.7. Each actuator shall have a local mechanical position indicator. It should
be suitable to indicate 0 - 100% position of the valve (continuous type).
2.1.8. In order to minimise the amount of spare parts required, parts and subassemblies limit / torque switches, limit switch counter gear assembly,
torque switch drive assembly, mechanical position indicator assembly etc.
individually interchangeable / replaceable throughout the models selected.
2.1.9. The actuator shall be painted with corrosion resistant epoxy resin paint.
Paint shade shall be Grey (Shade 631) as per IS-5.
2.1.10. In order to prevent condensation, a space heater shall be provided in the
switch compartment, suitable for continuous operation. Actuator mounting
dimensions shall be according to ISO-5210. For rising stem applications,
the design must allow the removal of actuator from the output drive without
disturbing the function of valve.
LIMIT AND TORQUE SWITCHES
2.2.1. Independent torque and limit switches shall be provided in the actuator.
A minimum of two position limit switches and two torque switches, one
each for each direction of travel, having 4 NO + 4 NC potential free
contacts, shall be supplied. If called for in the data sheet, two additional
limit switches shall be provided for intermediate positions.
2.2.2. Torque switch dial shall be graduated directly in kg-m for easy setting to
desired value within the range specified. Separate dials shall be provided for
CLOSE and OPEN torque switches.
2.2.3. Two additional limit switches with 2NO + 2NC contacts, each adjustable at
any intermediate position, shall be provided in the actuator.
2.2.4. The rating of both torque and limit switches shall be 240 V AC, 5 Amps.
The switches shall individually be enclosed to a minimum of IP-64 protection
class.
2.2.5. Torque and limit switches shall have only stainless steel flaps for better
protection against environmental condition.
2.2.6. Limit switches shall be operated by gear driven cams, which are
mechanically linked to the driving devices. The counter gear used for
counting and tripping the limit switches shall be of metallic construction like
brass etc. No plastic gearing shall be allowed.
ISS
U
Page 26 of 92 E
FILE NAME:
F329R5.DOC
SPEC.NO.
TCE.5750A-H-500001
PART B
TECHNICAL
PART B
SPECIFICATION
NO.- PE-TS-392567-A001
VOLUME IV
SECTION:
D13
SHEET 5 OF 7
2.2.7. To guarantee proper function under high ambient temperatures, torque and
limit switch sensing shall be of mechanical type.
2.3.
2.3.1. All motors shall be specifically designed for valve actuator operation, which
is characterised by high starting torque, low stall torque & low inertia. All
motors shall be high starting torque type to facilitate unseating of valve.
2.3.2. Motor shall be suitable for power supply of 415 V, 3 ph, 50 Hz, AC.
2.3.3. Motor shall be squirrel cage induction type and shall generally conform to IS-325.
2.3.4. Motor shall have minimum class 'F' insulation with temperature rise restricted
to class 'B' under the design ambient temperature.
2.3.5. Motor shall be of totally enclosed surface cooled (TESC) type with IP-67
protection class after mounting on actuator.
2.3.6. Motor shall have three thermostats connected in series, one in each phase
of stator winding, for protection against overheating.
2.3.7. Motor shall be suitable for operation under voltage variation of + 10%,
frequency variation of + 5% and combined voltage & frequency variation of
10% absolute.
2.3.8. Motor shall be suitable for direct on-line (DOL) starting and starter shall be
non integral to the motor.
2.3.9. It should be possible to separate the motor from the lubricant filled gearing of
the actuator allowing easy replacement of motor without loosing any lubricant
regardless of mounting position.
2.3.10. Finsh shall be provided on the motor body to ensure better heat dissipation.
2.3.11. It shall be possible to change the output rpm of the actuator, if required, at
the site at a later date, without hampering the mounting arrangement and loss
of any lubricant.
2.4.
Page 27 of 92
ISS
U
E
FILE NAME:
F329R5.DOC
SPEC.NO.
TCE.5750A-H-500001
PART B
TECHNICAL
PART B
SPECIFICATION
NO.- PE-TS-392567-A001
VOLUME IV
SECTION:
D13
SHEET 6 OF 7
2.5.1. Common potential free contact shall be available to annunciate the fault
condition to the remote control station or DCS.
2.5.2. The following individual relay / potential free contacts shall be provided for
the remote indication:-
Actuator OPEN.
Actuator CLOSE
Thermal overload relay shall be provided to trip the actuator in case of overload
2.6. The DC and AC actuator shall be provided with accessories viz., Torque limit
switch, end of travel switch, adjustable limit switch, hand wheel motor,
thermostat, etc. Complete actuator shall be tested at factory as per IS 9334.
All actuators should have minimum 2 limit switches for each position, and
should have position transmitters wherever required.
3.0
TESTS
3.1. All routine & acceptance tests as per relevant IS shall be conducted on motors.
For all AC and DC motors of rating below 100kW, type test certificates shall
be furnished. If the test reports are not found in order by Purchaser then these
tests shall be conducted by the Vendor without any cost implication.
ISS
U
Page 28 of 92
E
FILE NAME:
F329R5.DOC
SPEC.NO.
TCE.5750A-H-500001
PART B
TECHNICAL
PART B
SPECIFICATION
NO.- PE-TS-392567-A001
VOLUME IV
SECTION:
D13
SHEET 7 OF 7
3.2.
Type test shall be carried out on one no. of each type and rating of motor
of rating 100kW and above, which shall be witnessed by Purchaser.
3.3.
Efficiency and loss measurements shall be done for all LT motors as per
relevant standard (Being energy efficient motors.) as routine test.
3.4.
For 11000V AC & 6600V AC motors, in addition to all the tests specified
above, polarisation index test shall be carried out as a routine test on each
motor (the minimum value of polarisation index for all motors shall be 2
when determined according to IS: 7816).
3.5.
Noise level measurement test shall be conducted on one motor of each type.
3.6.
Vibration measurement shall be taken for each motor of 45kW & above.
3.7.
4.0
Page 29 of 92
ISS
U
E
FILE NAME:
F329R5.DOC
EC.
EI
A A
CE.5750A-H-500001
EC I
PART B
TECHNICAL
A
B
SPECIFICATION
NO.- PE-TS-392567-A001
r
t st & t
ts
t
t
IE
: D16
HEE 1
F9
ABLES
1.1
H T POWER CABLES
11
( E)
6.6
( E)
&
,
,
,
C
,
.
1.2
E
C
,
/G
7098 (
,
II), IEC-502
L T POWER CABLES
C
1100
,
,
,
F
(
C
I
E).
7098
.
DC
6-
1.3
CONTROL CABLES
C
1100
1.5 .
7
,
I 1554
,
,
F
C
C ,
C
-I. I
.
1.4
INSTRUMENTATION CABLES
A
, 0.5
(I1
(
I2
(
,
C.
)
I3),
,G
.
1.5
( E)
,
, C
6.6
1100 -(E)
&
, E
, E
.
C
1.6
( E)
I
1.6.
1
/
,
IEC-60331
CEA
I
Page 30 of 92
FI E
A E: F329 5.D C
CE F
. 329
EC.
EI
A A
CE.5750A-H-500-001
PART B
TECHNICAL
SPECIFICATION
NO.A
B
t
t
ts
CAB E & CAB E CA
EC I
st &
PE-TS-392-567-A001
( )
DC
( )
DC
DC
( )
HEE 2
: D16
F9
IE
DC
( )
()
( )
( )
:G
:
B
G
400
G
G
1.6.2
F
( )
( )
( )
&
( )
&
.
1.6.3
F
( )
( )
( )
( )
()
( )
( )
()
-C
-
-H F
&
/
H F
I
FI E
C
A E: F329 5.D
Page 31 of 92
CE F
. 329
EC.
EI
A A
CE.5750A-H-500001
EC
I
PART B
TECHNICAL
A
B
SPECIFICATION
NO.- PE-TS-392567-A001
r
st &
t
t
s
I
E
: D16
HE
E
F9
C
.
ABLE PROPERTIES
2.
1
,
/
.
2.
2
2.
3
F
( )
C
29
27+ 2 C
A
0
250 C
-D-2863.
-D-286377
21
( )
20%
IEC-60754-1
(1994). H
F
2%.
F
()
I -10810-53.
( )
C
62. C
( )
I
-108
C
()
-61 &
A.
( )
IEC-331.
( )
60%
F
A
2
0
( )
-D-2843-77 (1977).
.
DI
53387.
()
I
10810.
2.4
IEC-322-1 (1993)
C
F3
IEEE-383. I
2.5
I
G
-424-1475
(1977).
,
,
G
.
2.6
.
I
Page 32 of 92
FI E
A E: F329 5.D C
CE F
. 329
EC.
EI
A A
CE.5750A-H-500001
EC
I
x
st &
PART B
TECHNICAL
A
B
SPECIFICATION
NO.- PE-TS-392567-A001
2.7
t
s
I
E
HE
E
F9
3.0
3.1
: D16
ABLE SIZING
POWER CABLES
3.1.
1
:( )
50
. C.
( )
(
(
E).
( )
50
( )
D -
. C.
I /IEC
3.1.
2
.F
6
1
415
0.5
3.1.
3
.6
. F
.
415
,
-
.
3.1.
4
( )
( )
F
)
F
3.1.
5
DBF
DBF
15%
20%
15%
.
3%
.
5%
3.1.
6
,
, 3
2.5
.
.
C
3.1.
7
3.1.
8
DC
C
.
C
1.
2
I
Page 33 of 92
FI E
A E: F329 5.D C
CE F
. 329
EC.
EI
A A
CE.5750A-H-500001
EC I
r
t st & t
ts
t
t
IE
PART B
TECHNICAL
A
B
SPECIFICATION
NO.- PE-TS-392567-A001
3.1.8.1
1100
: D16
HEE 5
F9
,
DCDB,
DC
F
E/
C
C
3.1.8.2
DCDB
DCDB
DC
DB
3%.
3.1.8.3
C
.
3.2
3.2.1
ABLES
C
- A
.
C
I
4.0-
2.5
.
3.2.2
1%
. F
0.2%. I
,
.
3.3
INSTRUMENTATION CABLE
3.3.1
IEC-60189-2
3.3.2
3.3.3
3.3.4
3.3.5
:
D
0.04
-
0.0
A '
C
A'
' '
2.5
.
:
'
'
' ',
200
.
120
3.3.6
C
I
Page 34 of 92
FI E
A E: F329 5.D C
CE F
. 329
EC.
EI
A A
CE.5750A-H-500001
E
C
x
st &
PART B
TECHNICAL
A
B
SPECIFICATION
NO.- PE-TS-392567-A001
r
t
1,
3.3.
7
C
0.04
/
ts
2
,
: D16
I
E
3,. 1, 2, 3..,
1, .
2
,
H
E
E
1
,
2,
3, .
.,
F9
/
0.008
15%.A
0.5
.
3.3.
8
3.3.
9
C
500
3.3.1
0
3.3.1
1
.
.
C
1
2
C
500
F
/
.
40
0
:
IEC-60189 .G
-1 :
IEC-60189 -
-2:
4.0
4.1
C
(-
-C
ABLE TERMINATIONS
C
.
4.2
A 1100
D
C
H
5.0
CABLE JOINTS
C
.I
,
,
3.1.2
.A
6.0
,
,
,
.
POWER RECEPTACLES
I
Page 35 of 92
FI E
A E: F329 5.D C
CE F
. 329
PART B
&
TECHNICAL
RT
SPECIFICATION NO.PE-TS-392-567-A001
o
.
ST
V SW T
SU
RS SU
S T
TR
T RS
S
TV
W
TR
S
W RS
W
R
S
S
V SW T
S T
R V
TR
T RS
T
S
S
R V
T R
R T
TS
R Y
T
T
U
TR
TU T RS
R T R
R
R
U
T
US
Y T
V
TS
T
TS
TT
ISSUE
R1
R
Page 36 of 92
PEM-6666-0
SPECIFICATION NO.PE-TS-392-567-A001
PE-TS-STD-567-A001
TITLE
TECHNICAL SPECIFICATION
FOR LUBE OIL PUMPS
VOLUME II - B
SECTION -D
REV
SHEET
SECTION-D
Page 37 of 92
07/07/07
DATE 26/12/2013
OF
PEM-6666-0
TITLE
TECHNICAL
SPECIFICATION
SECTION D
(GENERAL) FOR
REV
01
SHEET
1.0
VOLUME II B
DATE
OF
07/07/07
GENERAL
This specification covers the design material constructional features manufacture
assembly inspection
& testing at manufacturer's or his subcontractor's works, suitable painting &
packing requirements of Lube Oil transfer pumps and drives along with all
accessories as specified hereinafter.
2.1
PEM-6666-0
TITLE
TECHNICAL
SPECIFICATION
SECTION D
(GENERAL) FOR
REV
01
SHEET
3.1
VOLUME II B
DATE
OF
07/07/07
Casting
The pump shall be horizontal, positive displacement type, designed for oil
service and suitable for occasional dry running. The casing shall also have end
plates/pump cover which close the ends of the body to form the pumping
chamber. The casing shall house rotating assembly. Gear type with a drive shaft.
3.2
Rotor
The rotor shall constitute of a shaft on which either Gear are mounted. The
rotating assembly shall be encased in the casing and shall be properly sealed.
Mechanical Seal could be offered for sealing purpose. The seal material shall
have low coefficient of friction and shall be suitable for the fluid handled.
3.3
3.4
Coupling
The pumps shall be directly coupled to their drives through a flexible
coupling. Suitable coupling guards also shall be provided along with the
coupling. The pump and its drive motor shall be mounted on machined base
frame.
3.5
Base Frame
Common/individual base frame shall be provided for pump and motor. The
base frame shall be fabricated/casted construction providing rigidity and
stability and shall be capable of supporting the weight and reactions of the
pump & motor. The base plate will have a drip pan with suitable draining
arrangement and shall be suitably drilled for the anchor bolts. The material of
construction shall be of tested quality structural steel as per IS2062 or
equivalent.
Anchor bolts, nuts, lock nuts, seating steel work as required shall be supplied with
the equipment. Only hexagonal nuts shall be used for holding down the
equipment.
3.6
Lifting Arrangement
Each pump shall incorporate suitable lifting attachments e.g. lifting lugs or eye
bolts etc. to facilitate erection & maintenance.
3.7
PEM-6666-0
TITLE
TECHNICAL
SPECIFICATION
SECTION D
(GENERAL) FOR
REV
01
SHEET
4.0
VOLUME II B
DATE
OF
07/07/07
4.1
The data sheets for Pump and motors placed under volIII of specification forms
part of specification. The * marked details are to be filled up by the bidder
without altering the data already filled up.
4.2
The material of construction of Strainer body will be either ASTM A 106 Gr.B
pipe or ASTM A216 WCB or fabricated from IS 2062 plates. However, the exact
MOC is subject to acceptance by customer and there will be no additional
commercial implication on account of above.
4.3
The driving motor power shall be selected based on highest viscosity of oil.
The selection of pump motor rating shall be based on criterion given in the
electrical portion of the specification.
4.4
VOID.
4.5
The pump shall be designed for the normal operating temperature specified
in the data sheet. However, the pump should be able to perform without any
malfunctioning at the maximum temperature also as indicated in the data
sheet.
4.6
VOID.
4.7
VOID.
4.9
Pumps shall be designed for smooth pulsation and noise free operation. Pump
shall be designed to have maximum efficiency at the normal duty point.
VOID.
PEM-6666-0
TITLE
TECHNICAL
SPECIFICATION
SECTION D
(GENERAL) FOR
REV
01
SHEET
4.15
4.16
VOLUME II B
DATE
OF
07/07/07
b)
Weight of moving parts, its frequency and its height from floor shall be
furnished.
c)
d)
Civil loads per bolt / pocket (static and dynamic) in tabular form considering
worst case.
The successful bidder will have to depute competent designer (s) at BHELs
office during detailed engineering stage to discuss drawings and other technical
documents as and when required by BHEL. However, the vendor will be informed
in advance by minimum 7 days.
4.17 All the drawings required to be furnished to customer during detailed engineering
stage shall include technical parameters, details of paints and lubrication,
hardness and BOQ / BOM in tabular form indicating all major components
including bought out items and their quantity, material of construction indicating
its applicable code / standard, weight, make etc.
4.18
All the drawings and documents including general arrangement drawing, data
sheet, calculation etc. shall be furnished to the customer during detailed
engineering stage and include / indicate the following details for clarity w.r.t.
Inspection, construction, erection and maintenance and information etc.:
a)
All drawings and documents shall bear BHELs title block and drawing /
document number. However, BHELs drawing / documentnumbering
scheme shall be furnished to the successful bidder after the placement of
L.O.I.
b)
All drawings and documents shall indicate the list of all reference
drawings including general arrangement.
c)
All drawings shall include / show plan, elevation, side view, cross section,
skin section, blow up view of all major self manufactured and bought out
items shall be labelled and included in BOQ / BOM in tabular form.
d)
e)
PEM-6666-0
TITLE
TECHNICAL
VOLUME II B
SPECIFICATION
SECTION D
(GENERAL) FOR
REV
01
SHEET
DATE
OF
07/07/07
Details of cable entry for pump shall be shown in all the 3 views (plan,
elevation and side view) indicating dimensions from a reference point.
4.19
All calculations which are required to be submitted shall be done manually and
necessarily in SI units and the same shall be furnished along with the copy of
authentic supporting literature e.g. Code, Hand book, National / international
Standards etc.
5.1
5.2
VOID
5.3
5.4
Steel forging used in pumps shall be tested for both physical properties and
chemical composition.
5.5
The castings shall be sound, clean and free from porosity blowholes, hard
duration and other harmful defect.
Areas, which in the opinion of the purchaser will create doubts about soundness
to the castings, shall be subjected to dyepenetration test as per ASTM
Specification A16595.
No welding or repairs shall be carried out without prior permission of the
purchaser. The entire surface of the castings shall be subjected to Dye
penetrant test as per ASTM A16595. Evaluation of indication shall be as per
relevant standard.
5.6
PEM-6666-0
TITLE
TECHNICAL
VOLUME II B
SPECIFICATION
SECTION D
(GENERAL) FOR
REV
01
SHEET
DATE
OF
07/07/07
Before weld repair after defect has been rouged out and grounded to
ensure removal of defect.
5.7
5.8
All the impellers shall be statically and dynamically balanced at the operating
speed as per the requirement of ISO 1940 G 6.3.
5.9
Performance Tests
Performance tests shall be conducted for each of the pump with unit motor at
the manufacturer's works in the presence of the purchaser or his authorized
agent in accordance with relevant Indian/ equivalent standards. At least 5
points, approximately equally spaced on the characteristic curve including
relief valve set pressure, rated flow & pressure shall be tested and acceptance
will be determined as per the relevant standard. These tests shall be conducted
with actual drive motor being furnished. In general, performance tests shall
include the following tests.
a) Establish flow and pressure characteristic
b) Establish flow and power characteristic
c) Establish flow and efficiency characteristic
Purchaser or their authorized representative shall have access to all the tests.
Prior intimation shall be given allowing adequate time for preparation of the
witness of the test. After the performance testing, the observations noted and
the computation of results for rated performance shall be submitted to
purchaser for approval. On approval the pump shall be undertaken for strip
testing and its components shall be examined for visual and other tests
before being taken for dispatch in the presence of purchaser or their
authorized inspection agencies.
PEM-6666-0
TITLE
TECHNICAL
VOLUME II B
SPECIFICATION
SECTION D
(GENERAL) FOR
REV
01
SHEET
DATE
OF
07/07/07
Test on each pump for vibration level in the transverse, horizontal and
vertical directions shall be carried out. Noise level shall be measured at the
rated speed. Measurement of oil leakage at seal/stuffing box shall be recorded if
any.
5.10
Test at Site
The pumps will be tested at site to verify its mechanical performance and
checking the vibration and noise level. If the pumps fail to operate smoothly
then such deficiencies shall be rectified by the supplier by making suitable
alterations in the pump set and additional tests required to show the effect of
such alterations shall be performed by him. The change made in the pump shall
be certified with technical back up information to the satisfaction of the
purchaser.
5.11
Performance Guarantee
The vendor shall guarantee the material and workmanship of all equipment as
well as the operation of the pump as per requirement of this specification.
The vendor shall also guarantee for each pump the discharge pressure at the
specified rated capacity and also corresponding efficiency, brake horsepower
and relief valve set pressure .
6.0
PEM-6666-0
TITLE
TECHNICAL
VOLUME II B
SPECIFICATION
SECTION D
(GENERAL) FOR
REV
01
SHEET
DATE
OF
07/07/07
For export jobs, seaworthy packing shall be used. Details of Seaworthy packing
will be either project specific. In case there is no specification for seaworthy
packing, the same shall be furnished by the bidder for BHELs approval.
However, there will not be any additional cost implication on account of the
same.
7.1
8.1
ii)
iii)
ix) Quality plans duly corrected in line with customers comments, if any.
9.0
PEM-6666-0
TITLE
TECHNICAL
VOLUME II B
SPECIFICATION
SECTION D
(GENERAL) FOR
REV
01
SHEET
DATE
OF
07/07/07
Each pump shall have a permanently attached brass metal tag on the body
indicating the following information both in Hindi and English:
a)
b)
c)
Design Pressure.
d)
Page 46 of 92
PEM-6666-0
TITLE
TECHNICAL
VOLUME II B
SPECIFICATION
SECTION D
(GENERAL) FOR
REV
01
SHEET
Page 47 of 92
DATE
OF
07/07/07
TITLE :
GENERAL TECHNICAL
REQUIREMENTs FOR
LV MOTORS
SPECIFICATION
NO. PE-SS-999-506E101
VOLUME
NO. :
II-B
REV
00
SHEETNO.: 1: OF
FOR
LV MOTORS
Page 48 of 92
1 DATE
TITLE :
GENERAL TECHNICAL
REQUIREMENTs FOR
LV MOTORS
1.0
SPECIFICATION
NO. PE-SS-999506-E101
VOLUME
NO. :
II-B
SECTION
:
D
REV NO. : 00 DATE :
29/08/2005
SHEET : 1 OF 4
INTENT OF SPECIFIATION
The specification covers the design, materials, constructional features, manufacture, inspection
and testing at manufacturers work, and packing of Low voltage (LV) squirrel cage induction
motors along with all accessories for driving auxiliaries in thermal power station.
Motors having a voltage rating of below 1000V are referred to as low voltage (LV) motors.
2.0
DESIGN REQUIREMENTS
3.2
Motors and accessories shall be designed to operate satisfactorily under conditions specified in
data sheet-A and Project Information, including voltage & frequency variation of supply system as
defined in Data sheet-A
3.3
Motors shall be continuously rated at the design ambient temperature specified in Data Sheet-A
and other site conditions specified under Project Information
Motor ratings shall have at least a 15% margin over the continuous maximum demand of the
driven equipment, under entire operating range including voltage & frequency variation specified
above.
3.4
Starting Requirements
3.4.1
Motor characteristics such as speed, starting torque, break away torque and starting time shall
be properly co-ordinated with the requirements of driven equipment. The accelerating torque at
any speed with the minimum starting voltage shall be at least 10% higher than that of the
driven equipment.
3.4.2
Motors shall be capable of starting and accelerating the load with direct on line starting
without exceeding acceptable winding temperature.
Page 49 of 92