Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

EDG Test

Download as doc, pdf, or txt
Download as doc, pdf, or txt
You are on page 1of 6

EDG Test Procedure

Page 1 of 7

HK-E-HV701

Document Class

PT. HUTAMA KARYA (Persero)


EPC DIVISION
JOB. No. HV701

For Commissioning

Revised as comment

Revised as comment

For approval

Sep. 08,
2015

Ayhu

Rev.

Description

Date

Prepared Checked Reviewed Approved

Tirda

Tirda

OWNER`S
DWG.NO

PT. PLN (PERSERO)


JASA SERTIFIKASI

Clients Project No.

DWG. NO.

E07007-PR-TM-3007

PLTU KENDARI UNIT 3 1x10 MW

DATE OF ISSUED

REVISION NO.

Sep.08, 2015

Yoga

PLTU Kendari Unit 3 (110 MW) Project


EDG Test Procedure

REV 0

HK-E-HV701

Page 2 of 7

Commissioning Procedure

Table of Contents

1
2
3
4
5
6
7
8
9

COVER
SCOPE
OBJECTIVE
REFERENCE
TEST INSTRUMENT
RISK AND SAFETY PRECAUTION
BUSBAS PROTECTION TEST ITEM
BUSBAS PROTECTION PROCEDURE
ATTACHEMENT

1
2
3
3
3
3
3
3
3

PLTU Kendari Unit 3 (110 MW) Project


EDG Test Procedure

REV 0

HK-E-HV701

Page 3 of 7

Commissioning Procedure

1.

Title
EDG Test Procedure

2.

Scope
EDG body, local panel of EDG, incoming switch 0.4Kv protection.

3.

Objective
This is to assure that the requirements of electrical individual test works c1re
meets the codes requirements and contract specifications. To make sure, the
works are carried out in acceptable workmanship and follow requirements
in the quality manual.

4. Reference
a) HK/SDMIEC Quality manual
b) Applicable manufacture manual/standard
c) Design drawing provided by Design Institute ZT-F201115S-D0201-03
(2/3)

5. Test Instrument

Fluke 17B
Secondary Phase Sequence Tester
DC Resistance Tester
Insulation Resistance Tester
Relay Tester.

6. Risk and Precaution


a.
b.
c.
d.

Everyone must be wear safety


High voltage test area should be circle by rail with warning board.
If happen anything abnormal, testing must be stop
Clean all instrument and tools

PLTU Kendari Unit 3 (110 MW) Project

EDG Test Procedure

REV 0

HK-E-HV701

Page 4 of 7

Commissioning Procedure

7.

EDG Test Item

Visual inspection
Individual Test of EDG.
Local Stop/Start EDG
Local Protection

8.

EDG Test Procedure

8.1.1

Visual Inspection.
Check name plate of each protection and write down.

8.1.2

Individual Test of EDG.

8.1.3

Test of EDG body


1.Measure of EDG DC resistance value between each phase 1%
2.Measured the insulation resistance of EDG winding to ground.
Insulation resistance shall > 5 M.

Test of EDG local control system


1.Checked that inside and outside of EDG control panel are clean.
2.Cable connection of row terminal in EDG control panel is good.
3.Supply power normal work for EDG controller.
4.Simulated normal current, voltage and frequency by protection tester.
5.Checked following fault whether controller action is correct.

Local start/stop of EDG

Put operation, alarm, signal power switch into operation.


Manually start EDG locally.
Regulated voltage of EDG make it run and no load voltage of 400V
Check whether EDG outlet phase sequence is correct.
Checked and record following value after EDG run normally.

PLTU Kendari Unit 3 (110 MW) Project


BUSBAS PROTECTIONTest Procedure

REV 0

HK-E-HV701

Page 5 of 7

Commissioning Procedure

9.

.
Manually stop EDG locally.
Manually start and stop EDG local 3 times. Checked the battery capacity.

ATTACHEMENT
Test form
Calibration date of equipment test
Drawing Equipment

You might also like