WBLFF
WBLFF
WBLFF
PILE CAP
A. Excavation
METHOD
QTY
Mobile crane
Concrete skip
LABOUR
Mobile crane
Concrete skip
Concrete mixer
OUTPUT
DURATION
(DAYS)
APPENDIX
8 days
5
2.80hr/m3
3 days
1 (a)
=11 days
Sawn
formwork
as 201m2 Hammer
described to sides of pile
Saw
caps.
D. Reinforcement
E. Concreting
PLANT
2.88hr/m3
9 days
1 (b)
4 days
8
1.25hr/m2
1 (c)
23 days
3
0.16hr/kg
5 days
1 (d)
= 28 days
5
9.00hr/m3
9 days
1 (e)
METHOD
QTY
PLANT
LABOUR
OUTPUT
DURATION
(DAYS)
APPENDIX
1 day
Excavator
2.80hr/m3
1 day
1 (f)
= 2 days
Mobile crane
Concrete skip
2.88hr/m3
1 day
1 (g)
C. Formwork
Hammer
Saw
1.25hr/m3
1 day
1 (h)
D. Reinforcemen
t
E. Concreting
Sawn
formwork
as 7m2
described to sides of pad
footing.
Mobile crane
Bending
machine
1 day
3
0.16hr/kg
1 day
1 (i)
= 2 days
Mobile crane
Concrete skip
Concrete mixer
9.00hr/m3
1 day
1 (j)
B. Reinforcemen
t
C. Concreting
METHOD
QTY
Sawn
formwork
as 264m2
described to sides of
column
stump.
(Provisional)
Mild
Steel
Bar
Reinforcement
1. 6mm diameter as 25kg
links. (Provisional)
Vibrated
reinforced
296kg
122kg
PLANT
Hammer
Saw
LABOUR
OUTPUT
1.25hr/m2
DURATION
(DAYS)
14 days
APPENDIX
1 (k)
1 day
Mobile crane
Bending
machine
1 day
8
0.16hr/kg
1 day
1 (l)
3 days
1028kg
1 day
340kg
1 day
57kg
= 8 days
Mobile crane
9.00hr/m3
5 days
1 (m)
Concrete skip
Concrete mixer
WORK BELOW LOWEST FLOOR FINISHES (CONTD)
concrete Grade 30 as
described. (Provisional)
22m3
ITEM
GROUND
BEAM
A. Formwork
METHOD
Sawn
formwork
as
described to sides and soffit. 865m2
(Provisional).
B. Reinforcement
3. Concreting
QTY
PLANT
Hammer
Saw
LABOUR
OUTPUT
DURATION
(DAYS)
APPENDIX
1.25hr/m2
27 days
1 (n)
Mild
Steel
Bar
Reinforcement
1. 10mm diameter as 1870kg
stirrups.
2. 6mm diameter as 1666kg
stirrups.
High Tensile Steel Bar
Reinforcement
1. 25mm diameter as
main bars.
2. 20mm diameter as
main bars.
3. 16mm diameter as
main bars.
4. 12mm diameter as
main bars.
4 days
3 days
Mobile crane
Bending
machine
3859kg
10
0.16hr/kg
1 (o)
4 days
1772kg
2 days
827kg
5 days
2497kg
8 days
= 26 days
Mobile crane
9.00hr/m3
17 days
1 (p)
Concrete skip
Concrete mixer
WORK BELOW LOWEST FLOOR FINISHES (CONTD)
Grade 30 as described
ITEM
GROUND
FLOOR SLAB
A. Formwork
B. Reinforcement
C. Concreting
METHOD
QTY
Sawn
formwork
as
described to:
1. Soffit.
887m2
2. Edge of slab not 81m
exceeding 100mm high.
3. Edge of slab exceeding 452m
100mm
but
not
exceeding 200mm high.
PLANT
Hammer
Saw
OUTPUT
1.25hr/m2
5
1.00hr/m
1.25hr/m
DURATION
(DAYS)
APPENDIX
28 days
2 days
1 (q)
14 days
= 44 days
Mild
steel
fabric
Mobile crane
reinforcement as described,
Bending
including laps, cutting,
machine
bending
and
notching
around obstructions.
1. A7 (weight 3.02kg/m2)
937m2
2. A8 (weight 3.95kg/m2)
1321m2
1. 150mm thick vibrated 663m2
reinforced
concrete
Grade 30 as described.
2. 125mm thick vibrated 413m2
reinforced
concrete
Grade 30 as described.
LABOUR
Mobile crane
Concrete skip
Concrete mixer
2 days
10
0.2hr/m2
1 (r)
3 days
= 5 days
14 days
9.00hr/m3
7 days
= 21 dyas
1 (s)
FRAME
ITEM
METHOD
LABOUR
OUTPUT
DURATION
(DAYS)
APPENDIX
1.08hr/m2
13 days
3 (a)
46hr/tonne
1 day
20hr/tonne
1 day
20hr/tonne
1 day
5373kg
32hr/tonne
4 day
379kg
22hr/tonne
1 day
513kg
46hr/tonne
1 day
QTY
COLUMN
A. Formwork
Sawn
formwork
described to sides
columns.
B. Reinforcement
C. Concreting
as 777m2
of
Mild
Steel
Bar
Reinforcement
1. 6mm diameter as 511kg
links.
High Tensile Steel Bar
Reinforcement
1. 25mm diameter as
main bars.
2. 20mm diameter as
main bars.
3. 16mm diameter as
main bars.
4. 12mm diameter as
main bars.
5. 10mm diameter as
links.
PLANT
Hammer
Saw
Mobile crane
Bending machine
142kg
5
342kg
3 (b)
= 9 days
Mobile crane
4.40hr/m3
4 days
3 (c)
Concrete skip
Concrete mixer
Grade 30 as described.
FRAME (CONTD)
ITEM
BEAM
A. Formwork
METHOD
Sawn
formwork
described to sides
soffits of beams.
B. Reinforcement
LABOUR
OUTPUT
DURATION
(DAYS)
APPENDIX
0.94hr/m2
18 days
3 (d)
24hr/tonne
1 day
24hr/tonne
1 day
12hr/tonne
2 days
1205kg
12hr/tonne
1 day
2112kg
16hr/tonne
1 day
2315kg
22hr/tonne
1 day
QTY
PLANT
as
Hammer
and 1198m2 Saw
Mild
Steel
Bar
Mobile crane
Reinforcement
Bending machine
1. 6mm diameter as 1088kg
stirrups.
2. 10mm diameter as 1969kg
stirrups.
High Tensile Steel Bar
Reinforcement
1. 25mm diameter as
main bars.
2. 20mm diameter as
main bars.
3. 16mm diameter as
main bars.
4. 12mm diameter as
main bars.
8005kg
= 7 days
3 (e)
C. Concreting
Mobile crane
Concrete skip
Concrete mixer
4.40hr/m3
6 days
3 (f)
LABOUR
OUTPUT
DURATION
(DAYS)
APPENDIX
0.94hr/m2
11 days
3 (g)
FRAME (CONTD)
ITEM
ROOF BEAM
A. Formwork
METHOD
Sawn
formwork
described to sides
soffits of beams.
B. Reinforcement
QTY
as
and 747m2
PLANT
Hammer
Saw
Mild
Steel
Bar
Mobile crane
Reinforcement
Bending machine
1. 6mm diameter as 1109kg
stirrups.
2. 10mm diameter as 267kg
stirrups.
High Tensile Steel Bar
Reinforcement
1. 25mm diameter as
main bars.
2. 20mm diameter as
main bars.
3. 16mm diameter as
main bars.
4. 12mm diameter as
main bars.
3 (h)
24hr/tonne
1 day
24hr/tonne
1 day
1674kg
12hr/tonne
1 day
559kg
12hr/tonne
1 day
559kg
16hr/tonne
1 day
1501kg
22hr/tonne
1 day
= 6 days
C. Concreting
Mobile crane
Concrete skip
Concrete mixer
4.40hr/m3
7 days
3 (i)
LABOUR
OUTPUT
DURATION
(DAYS)
APPENDIX
0.94hr/m2
2 days
0.94hr/m2
8 days
1.00hr/m
12 days
FRAME (CONTD)
ITEM
METHOD
QTY
UPPER FLOOR
SLABS
A. Formwork
1. Wrot
formwork
as 132m2
described to soffit of
floor slabs.
2. Sawn
formwork
as 564m2
described to soffit of
floor slabs.
3. Sawn
formwork
as 797m
described to edge of
slab, not exceeding
100mm high.
B. Reinforcement 1. Mild
steel
fabric 724m2
reinforcement
A7
(weight 3.02kg/m2) as
described,
including
laps, cutting, bending
and notching around
obstructions.
PLANT
Hammer
Saw
8
3 (j)
= 22 days
Mobile crane
Bending machine
10
0.2hr/m2
4 days
6 days
3 (k)
2. Mild
steel
fabric 1168m2
reinforcement
A8
(weight 3.95kg/m2) as
described,
including
laps, cutting, bending
and notching around
obstructions.
C. Concreting
= 10 days
Mobile crane
Concrete skip
Concrete mixer
11 days
8
1.35hr/m3
7 days
= 18 days
3 (l)