1. The document outlines the planned shutdown procedure for a unit including gradually reducing load through various control modes down to 5-25% load, performing turbine tests, cutting out coal mills, adjusting steam sources, and monitoring systems.
2. It then details procedures for tripping the turbine at 5% load such as closing valves and stopping oil and control systems.
3. Finally, it describes generator side shutdown including reducing MVAR with load, isolating the generator from auxiliary power, reducing the exciter, opening the generator breaker, and purging hydrogen from the system.
1. The document outlines the planned shutdown procedure for a unit including gradually reducing load through various control modes down to 5-25% load, performing turbine tests, cutting out coal mills, adjusting steam sources, and monitoring systems.
2. It then details procedures for tripping the turbine at 5% load such as closing valves and stopping oil and control systems.
3. Finally, it describes generator side shutdown including reducing MVAR with load, isolating the generator from auxiliary power, reducing the exciter, opening the generator breaker, and purging hydrogen from the system.
1. The document outlines the planned shutdown procedure for a unit including gradually reducing load through various control modes down to 5-25% load, performing turbine tests, cutting out coal mills, adjusting steam sources, and monitoring systems.
2. It then details procedures for tripping the turbine at 5% load such as closing valves and stopping oil and control systems.
3. Finally, it describes generator side shutdown including reducing MVAR with load, isolating the generator from auxiliary power, reducing the exciter, opening the generator breaker, and purging hydrogen from the system.
1. The document outlines the planned shutdown procedure for a unit including gradually reducing load through various control modes down to 5-25% load, performing turbine tests, cutting out coal mills, adjusting steam sources, and monitoring systems.
2. It then details procedures for tripping the turbine at 5% load such as closing valves and stopping oil and control systems.
3. Finally, it describes generator side shutdown including reducing MVAR with load, isolating the generator from auxiliary power, reducing the exciter, opening the generator breaker, and purging hydrogen from the system.
Download as DOC, PDF, TXT or read online from Scribd
Download as doc, pdf, or txt
You are on page 1of 3
UNIT PLANNED SHUT DOWN PROCEEDURE
1. LOAD can be reduce by 3 ways:-
a. Fully manual ( up to 5% load) b. Load may be reduced up to 60% under CMC mode, then change over to either Press Control Mode or Manual Mode. c. Load may be reduced up to 40% under Pressure Control Mode, then change over to Manual Mode. d. CMC (up to 60% load then either Press. Control mode or Manual mode)
2. At 60% Load can be carried out Auto Turbine Test (ATT)
to test its availability. 3. Reduce load up to 40% Load . Procedure of Cutting out a coal mills:- Reduce coal feeder position to minimum Stop coal feeder Wait to stop mills, till its Amps drops to minimum e.g. no load condition. Stop mill motor & Close all dampers.
4. Change over Pressure Control Mode to Manual Load Control Mode 5. Cut off HP Heaters 6. Change Over DEA Pegging Steam source from Extraction to CRH. 7. Reduce coal feeding further & reduce Load accordingly up to 20-25%. 8. MONITOR Scanners, If required Cut in Oil support to avoid Flame failure Protection. 9. Cut out LPHs, Change Over UAT to Station Bus and DEA Pegging Steam from CRH to APRDS. 10 FCS to Change Over from Hi range to Low range . 11 Put HPLP Bypass in service . 12 Reduce Fuel & Load. . 13 Trip Turbine at 5% load (Gen Protection can be Tested). . .. i. Ensure turbine ESVs & IVs, CRH NRVs, Extraction NRVs &Block Valve Closed. ii. Trip Oil= Zero, Control oil = 4.8 kg/cm2 iii. Gen Field Breaker OPEN iv. AOP start auto < 2950 rpm or < 4.8 kg/cm 2 oil pressure. v. JOP start auto < 510 rpm vi. Barring Gear valve open < 210 rpm
14 Ensure opening of the following drains:- . 15 HP casing, Seal Steam Hdr, before ESVs & Extraction . NRVs, after CRH NRVs, before / after IV valve NRVs 16 Stop turbine barring if casing / shaft temp < 1200 C . 17 Stop CEP at CASING TEMP OF 1000 C . 18 Shutdown Oil System at 80 0C to 90 0C .
Generator Side Shutdown Operations
1. REDUCE MVAR with load
2. CHANGEOVER to station supply from UAT at 20% Load 3. ISOLATE hydrogen coolers after 15 to 20 minutes of Gen tripping. 4. REDUCE Exciter controller to minimum. 5. Open Generator Breaker at 5% load. 6. STOP stator water pump ( If Stator Cooling System is in service ) 7. OPEN line isolators. 8. PURGE H2 by filling CO2 & purge the CO2 by filling dry compressed Air
Gas-Engines and Producer-Gas Plants
A Practice Treatise Setting Forth the Principles of Gas-Engines and Producer Design, the Selection and Installation of an Engine, Conditions of Perfect Operation, Producer-Gas Engines and Their Possibilities, the Care of Gas-Engines and Producer-Gas Plants, with a Chapter on Volatile Hydrocarbon and Oil Engines