Turbine Startup
Turbine Startup
Turbine Startup
CONTENTS
1.ACW,CW & CCCW Pump
5.PRE CLEAN UP
7.UNIT START UP
a. Cold start up
b. Warm start up
c. Hot start up
A. control stage metal temperature is T<150ºC turbine start cold start up.
C. control stage metal temperature is T>375ºC turbine start Hot start up.
ACW,CW&CCCW PUMP
1.Start ACW Pump.
2.Start CW Pump.
CW PUMP:- Circulating water pumps supply cooling water at the required flow
rate and head to the power plant condenser and the plant auxiliary cooling water
heat exchanger.
CCCW PUMP:- CCCW system supplies the cooling water to the plant
auxiliary equipped cooler. The cooling water is supplied to MDBFP,
TDBFP, Lube oil PHE, Seal oil PHE, EH oil Cooler, SCCW PHE,
Hydrogen Cooling, CEP thrust bearing cooling.
AIR COMPRESSOR&DRYER
4.Start any one instrument, service air compressor & dryer.
3.Check any one oil cooler(PHE) in service from cooling water and lube oil
side and other oil cooler(PHE) is stand by and charge from cooling water
side.
4.Check any one lube oil filter in service and other is stand by.
5.Start TOP and check lub oil header pressure (1.8kg/cm2).
Lub oil supply:-To supply the lubrication oil for each bearing, barring gear
spray, coupling spray and jacking oil pump.
JOP supply:-To supply the jacking oil for bearing no 3 to 6 to jack up the
turbine rotor during Turing gear and low speed operation.
HP oil supply:- To supply the test oil for MOST, auto stop oil and
emergency oil for trip device.
START PRE CLEAN UP
PRE CLEANUP :-
a. Hot well blow.
b. Condenser blow
c. Condenser recirculation
d. LP clean up blow
e. LP clean up recirculation
g. HP clean up blow
h. HP clean up recirculation
9.Start any one DMSW pump and maintain Hot well level through the normal
make up(900mm).
Gland sealing :-The function of the Gland Steam System is to prevent the leakage of
the air into steam turbine.
Preparation for gland sealing:-
a. Start GSC vapor extractor fan and check GSC tank pressure
(-0.066kg/cm2).
b. Charge gland steam header and maintain header pressure 0.25 to
0.32kg/cm2.
17.Start vacuum pump and check vacuum.
LP SHELL VACUUM: 0.0783kg/cm2(a)
HP SHELL VACUUM: 0.1002kg/cm2(a)