GCB Application Guide
GCB Application Guide
GCB Application Guide
discussions, stats, and author profiles for this publication at: https://www.researchgate.net/publication/272685099
CITATIONS READS
0 552
4 authors, including:
Mirko Palazzo
ABB
27 PUBLICATIONS 35 CITATIONS
SEE PROFILE
Generator Circuit-Breakers
Application Guide
Edited by
1 Introduction 6
4 | ABB
Table of contents
8 Case study 1: Impact of the method of connecting a generator to the high-voltage grid on the availability of a power plant 45
8.1 Power plant layout 45
8.1.1 Layout of extra high-voltage substation 47
8.1.2 Layout of high-voltage substation 48
8.1.3 Generator circuit-breaker 48
8.1.4 Station transformer 48
8.2 Data for availability calculations 48
8.3 Simulations 48
8.4 Simulation results 49
8.5 Economic evaluation 50
9 Case study 2: Interrupting capability of generator circuit-breakers in case of delayed current zeros 52
9.1 Generator circuit-breaker model adopted for the simulations 52
9.2 Generator terminal faults 53
9.3 Out-of-phase synchronising 55
9.4 Conclusions 56
References 57
ABB | 5
1 Introduction
A major objective of all power plant operating companies is breaker has several advantages over the unit connection, e.g.:
the achievement of the highest possible plant availability at simplified operational procedures
the lowest possible cost. Obviously, how a generator is con-
improved protection of the generator and the main and unit
nected to the high-voltage grid and how the power supply to
transformers
the unit auxiliaries is secured has a decisive influence on the
increased security and higher power plant availability
availability of a power plant.
Two basically different ways of connecting a generator to the economic benefit
high-voltage transmission network are in use today, namely ABB generator circuit-breakers are suitable for application in
the connection without a circuit-breaker between the genera- all kinds of new power plants such as fossil-fired, nuclear, gas
tor and the low-voltage terminals of the main transformer (i.e. turbine, combined cycle, hydro and pumped storage power
the "unit connection") and the connection with a generator plants as well as for replacement or retrofit in existing power
circuit-breaker (Figure 1). The layout with a generator circuit- stations when they are modernized and/or extended.
a) b)
EHV HV EHV HV
MT MT
UT ST UT ST
G GCB
AUX G AUX
Figure 1: Layout of a thermal power plant without generator circuit-breaker a) and with generator circuit-breaker b)
Legend
MT Main transformer
UT Unit transformer
ST Station transformer
GCB Generator circuit-breaker
EHV Transmission system
HV Sub-transmission system
AUX Unit auxiliaries
6 | ABB
2 History of the development of generator circuit-breakers
During the sixties, when there was a trend towards higher unit segregated units using compressed air as operating and arc-
ratings and, consequently, increased use of phase- extinguishing medium.
segregated generator busducts, ABB developed a circuit- In the 1980s SF6 generator circuit-breakers were successfully
breaker which could meet these new requirements. This was introduced into the market. The design of these circuit-break-
the first circuit-breaker designed to be installed in the run of ers was a three-phase system in single-phase enclosures,
generator busducts (Figure 2). supplied fully assembled on a common frame with operating
Since the delivery of the first specific purpose generator mechanism and control equipment. Mainly the economical
circuit-breaker in 1970, there has been a continuous develop- aspect and reasons of reliability and maintainability convinced
ment of this piece of power plant equipment. At the beginning customers of this modern arc-extinguishing medium.
the circuit-breakers consisted of three metal-enclosed, phase
Figure 2: Air blast generator circuit-breaker type DR mounted in the run of an isolated phase bus
ABB | 7
In the 1990s SF6 generator circuit-breakers were specifically currents up to 210 kA are available. This breaking capacity
developed for open installation, i.e. without enclosure. This corresponds to the highest short-circuit breaking current ever
solution was introduced to allow quick and easy installation achieved with a single SF 6 interrupting unit. The development
even for projects with very small space requirements (Figure 3). was made possible by using the most advanced SF 6 self-
Today SF 6 generator circuit-breakers with rated currents up blast principle. With this achievement modern SF 6 generator
to 24000 A with natural cooling and up to 57000 A with circuit-breakers can now be delivered for generating units with
forced air cooling, respectively, and with short-circuit breaking ratings up to 2000 MVA (Figure 4).
Figure 3: SF6 generator circuit-breaker type HECS-130R for open Figure 4: Generator circuit-breaker type HEC 7 based on SF6
installation technology and self-blast principle
Another development has been the integration of all the and hydro power plants) can also be fitted in the generator
associated items of switchgear into the generator circuit- circuit-breaker housing. This greatly improved functionality
breaker housing. Series disconnectors, earthing switches, allows simpler and more economic power plant layouts.
short-circuiting connection, current transformers, single- Beside a substantial reduction of the first costs this new
bushing voltage transformers, protective capacitors and surge solution - being fully factory assembled and tested - also
arresters can be mounted in the enclosure of the generator makes possible considerable savings in time and expenditures
circuit-breaker (Figure 5). Depending on the type of power for erection and commissioning.
plant additional items like starting switches (for gas turbine
Current transformer
Voltage transformer
Interrupting chamber
Disconnector
Surge arrester
8 | ABB
3 Design of generator circuit-breakers
ABB generator circuit-breaker systems are three-phase sys- All the components are integrated and mounted in the phase
tems with a SF6 circuit-breaker and a disconnector in single- enclosures (Figure 5). The generator circuit-breaker system is
phase enclosures, supplied fully assembled on a common designed for welded connections to the isolated phase bus
frame, with operating mechanisms and control equipment. enclosures. Each enclosure is made of aluminium and capable
In addition to the circuit-breaker and disconnector, the of carrying the induced return current.
generator circuit-breaker systems are available with earthing The phase distance can be selected to suit the busbar
switch, starting switch, short-circuiting connection, current spacing in the power plant.
and voltage transformers, surge capacitor and surge arrester.
The single line diagram of a generator circuit-breaker system
is depicted in Figure 6.
4 5
8 8
7 1 2 7
G
3 3
6 6 9
10
Figure 6: Typical single line diagram of a generator circuit-breaker system
ABB | 9
The interrupting chamber of a generator circuit-breaker is depicted in
Figure 7. On the left side the terminal is visible. The contacts are oper-
ated by a shaft passing through the vertical support insulator.
During the interruption process the current has to commutate from the
nominal contact system to the arcing contact system. This avoids wear
and erosion of the current carrying contacts and ensures trouble-free Figure 7: Interrupting chamber of a
current carrying even after a large number of operations. generator circuit-breaker
7 6 8 3 1
Arc Extinguishing Technology: a
Mode of operation of the interrupting chamber of the type HECS circuit-
breaker systems
a Circuit-breaker CLOSED
d Circuit-breaker OPEN
10 | ABB
3.2 Hydraulic spring operating mechanism
The hydraulic spring operating mechanism combines the interlock prevents movement of the piston to the open posi-
advantages of a hydraulic operating mechanism with those of tion in case of a pressure drop.
a spring energy storage system (Figure 9). For the opening operation, the piston head side is isolated
Energy storage is accomplished with the aid of a disk spring from the high pressure and simultaneously connected to the
assembly, with the advantages of high long-term stability, reli- low pressure oil volume.
ability and non-influence of temperature changes. The charging state of the spring disk assembly is controlled
Tripping of the operating mechanism and energy output are by switching elements, actuating the pump motor to immedi-
based on proven design elements of the hydraulic operating ately maintain the oil pressure.
technique, such as control valves and hydraulic cylinders. A non-return valve between pump and high-pressure oil
The operating mechanism is based on the so-called differen- volume prevents pressure loss in the event of a pump outage.
tial piston principle. The hydraulic system is hermetically sealed against atmo-
For the closing operation the piston head side is isolated from sphere. The mechanically operated position indicator provides
the low pressure and simultaneously connected to the high reliable indication of the circuit-breaker position.
pressure oil volume. The drive operates all three circuit-breaker poles simultane-
As long as the pressure is maintained, the piston remains in ously by mechanical linkages, thus keeping the switching time
the closed position. A pressure controlled mechanical difference between the poles to a minimum.
a) b)
ABB | 11
3.4 Disconnector
The switchgear concept provides a disconnector fitted in lating air distance can be clearly seen through an inspection
series with the circuit-breaker. It is placed on the transformer- window. The moving contact is motor driven. A locking
side of the circuit-breaker and within the same enclosure. The feature prevents motor operation while the disconnector is
disconnector is a tubular telescopic unit and it is equipped being manually operated. A mechanically driven position
with a drive which operates through a mechanical linkage all indicator is provided in a visible position and a crank handle
three poles. This layout provides easy access and simplifies is provided for manual operation. The view of a disconnector
maintenance. In the open position of the disconnector the iso- being in the open position is depicted in Figure 10.
a) b)
Figure 11: Blade type a) and tubular telescopic type b) earthing switches
12 | ABB
3.7 Short-circuiting connection
The short-circuiting connection helps to expedite the test- enclosure has to be removed to allow the fitting of the short-
ing and adjustment of the power plant protection system. It circuiting bar. In the latter case the short-circuiting link is used
can be provided manually mounted for the use between the in conjunction with the earthing switch installed on the
circuit-breaker and the disconnector of the system or motor generator-side of the circuit-breaker (for generator circuit-
operated. In the former case the cover of each phase breaker systems type HECS).
Figure 12: Ring core current transformer Figure 13: Single-phase voltage transformers
ABB | 13
R S T R S T
DE 6
open delta connection of the tertiary
Earth Fault windings
Protection Relay
DE 6
Earth Fault
Protection Relay
Figure 14: Insertion of a ferroresonance damping device (DE6) in the Figure 15: Insertion of a ferroresonance damping device (DE6) in the
open delta of the residual voltage windings (tertiary windings) of a open delta of the residual voltage windings (tertiary windings) of a
set of voltage transformers (voltage transformer with one secondary set of voltage transformers (voltage transformer with two secondary
winding) windings)
14 | ABB
3.13 Connecting zone
The connecting zone is designed to provide a detachable ABB recommended type and arrangement of flexible copper
(bolted) connection between the generator circuit-breaker straps responds to these requirements as follows:
life parts and the conductors of the adjacent isolated phase
bus (IPB) or busduct. The main components of the connect- 1), 2) & 5) Fully type tested together with the generator circuit-
ing zone are depicted in Figure 18 and Figure 19. The flexible breaker to prove that the stringent requirements imposed by
connections shall be designed for: the relevant IEC and IEEE standards with regard to dielectric
strength, hottest spot temperature and mechanical stress are
1) carrying the rated continuous current and the rated short- fully met. The special shape easily adapts to different distances
time withstand current without exceeding the maximum between terminals ensuring that dielectric strength require-
permissible temperatures ments are always met.
2) ensuring that the dielectric strength requirements are met 3), 4) & 5) Flexible type employing laminates with pressure-
welded contact ends designed and tested for high mechanical
3) compensating expansion and contraction of the conductor stress.
due to temperature changes
6) Silver plated contact ends with high requirements on
4) compensating vibrations and withstanding the stress contact surface evenness and material properties.
caused during switching operations
ABB | 15
3.14 Phase enclosure
The magnetic field in the neighborhood of the connection be- capable of carrying the induced return current thus minimising
tween generator and transformer may have adverse effects on the impact of the magnetic field. In order to avoid pollution
equipment and building steel if the current exceeds a certain due to ingress of dust and moisture, the generator switchgear
value. The values of magnetic fields outside of the generator enclosure is designed to allow air tightness and to withstand a
circuit-breaker housing could induce voltages and currents slight internal overpressure.
which in turn might produce undesired heating effects. Inspection windows are provided in the phase enclosures near
For this reason, and to avoid electromagnetic forces between to the disconnector, earthing switch and starting switch, to
the current-carrying busbars the generator circuit-breaker allow visually checking of the position of each of them.
system is designed for welded connections to the isolated Occasionally, the busbars in power plants are not enclosed
phase bus enclosures. and in general, effects of magnetic fields for small generator
Each single phase enclosure is made of aluminium and continuous current is usually of no concern.
16 | ABB
4 Standard for generator circuit-breakers
ABB | 17
5 Selection of generator circuit-breakers
18 | ABB
5.3.1 Rated maximum voltage 5.3.2 Power frequency
The rated maximum voltage is the generator circuit-breakers The rated frequency for generator circuit-breakers is 50 Hz or
upper limit for operation and it is selected so that it is higher 60 Hz, depending on the system power frequency in which
than or equal to the maximum operating voltage of the the generator circuit-breaker is installed.
generator.
Sn
I max =
3 Vmin
I max is the maximum r.m.s. value of the current which the Sn is the rated power of the generator
generator circuit-breaker shall be able to carry V min is the minimum operating voltage of the generator
continuously
20000
19000
18000
indoor outdoor (RAL 9010)
17000
Current (Arms)
16000
15000
14000
13000
12000
11000
-25.0 -20.0 -15.0 -10.0 -5.0 0.0 5.0 10.0 15.0 20.0 25.0 30.0 35.0 40.0 45.0 50.0
Ambient Temperature (C)
Figure 20: Current carrying capability curves for generator circuit-breaker type HECS-100L operating at a power frequency of 50 Hz and
isolated phase bus temperatures of 90 C / 70 C (conductor / enclosure respectively)
ABB | 19
5.3.4 Rated dielectric strength 5.3.5 Rated short-circuit duty cycle
The rated dielectric strength of a generator circuit-breaker The rated short-circuit duty cycle of a generator circuit-
is selected in accordance with the Table II depending on its breaker is two unit operations with a 30 min interval between
rated maximum voltage. operations (CO30 minCO) [1].
Vmax
I ac =
3 X eq
I ac is the a.c. component of the fault current Vmax is the maximum r.m.s. value of the applied voltage
X eq is the equivalent reactance of the circuit referred to prior to fault (it can generally be considered equal to
the LV-side of the step-up transformer the maximum service voltage of the HV-system re-
ferred to the LV-side of the step-up transformer)
20 | ABB
The required asymmetrical system-source interrupting capa- equal to the sum of 1/2 cycle (protection system tripping
bility of a generator circuit-breaker is composed of the r.m.s. delay) plus the minimum opening time of the particular
symmetrical current and the percentage d.c. component. The generator circuit-breaker.
values of the d.c. component are expressed in percent of the The standard value for the time constant of the decay of the
peak value of the symmetrical short-circuit current and are d.c. component is 133 ms. For time constants different than
measured at the primary arcing contact parting time. The pri- 133 ms, the following formula can be used:
mary arcing contact parting time can be generally considered
t cp
Idc = 2 Iac e
I dc is the d.c. component of the fault current tcp is the primary arcing contact parting time
Iac is the a.c. component of the fault current is the time constant of the decay of the d.c.
component and it can be calculated by using the fol
lowing formula:
X eq
=
Req
Xeq is the equivalent reactance of the circuit referred to Req is the is the equivalent resistance of the circuit
the LV-side of the step-up transformer referred to the LV-side of the step-up transformer
is equal to 2 f with f being the power frequency
I dc
a=
2 I ac
The typical course of the system-source short-circuit current nent of the fault current is usually constant. Its value depends
and of its degree of asymmetry are shown in Figure 21 and on the opening time of the circuit-breaker and on the relay
Figure 22, respectively. It is understood that the degree of time of the protection system and it assumes a typical value
asymmetry of the system-source short-circuit current is gen- of 75% at the primary arcing contact parting time.
erally monotonically decreasing with time as the a.c. compo-
100.0
2
90.0
1.5 80.0
2 Iac 70.0
Degree of asymmetry (%)
1
60.0
Current (pu)
0.5 50.0
Idc
40.0
0
t cp 30.0
20.0
-0.5
10.0
-1 0.0
0 10 20 30 40 50 60 70 80 90 100 0 10 20 30 40 50 60 70 80 90 100
Time (ms) Time (ms)
Figure 21: Prospective system-source short-circuit current Figure 22: Degree of asymmetry of the system-source short-circuit
current
ABB | 21
The system-source short-circuit current is generally fed by the
HV-system and by the motors connected to the LV-side of the HV-System
Generator
Unit Auxiliary Circuit-Breaker
Transformer
Figure 23: (right side) Typical power plant layout with a step-up
Motors M G Generator
transformer and a unit auxiliary transformer
Vmax 1 1
I ac = +
3 (X sys + X GSUT ) I rM VrM2 V AUXT _ HV
2
+ X AUXT
I LR SrM V AUXT _ LV
Vmax is the maximum r.m.s. value of the applied voltage SrM is the rated apparent power of the motors connected
prior to fault (it can be considered equal to the to the LV-side of the unit auxiliary transformer
maximum service voltage of the HV-system referred I LR / IrM is the ratio of the locked-rotor current to the rated
to the LV-side of the step-up transformer) current of the motor
X sys is the equivalent reactance of the HV-system referred XAUXT is the short-circuit reactance of the unit auxiliary
to the LV-side of the step-up transformer transformer referred to the HV-side of the unit
X GSUT is the short-circuit reactance of the step-up auxiliary transformer
transformer referred to the LV-side of the step-up VAUXT_HV
transformer is the transformation ratio of the unit auxiliary
VAUXT_LV
VrM is the rated voltage of the motors connected to the transformer
LV-side of the unit auxiliary transformer
The d.c. component of the system-source short-circuit current for the power plant layout depicted in Figure 23 can be
calculated by using the following formula:
t cp t cp
( )
I dc tcp = 2
Vmax
1 sys + GSUT
e +
1 M + AUXT
e
3 (X sys + X GSUT ) I rM VrM 2 VAUXT _ HV
2
+ X AUXT
I LR SrM VAUXT _ LV
2
I rM VrM 2 V AUXT _ HV
+ X AUXT
sys + GSUT =
(X sys + X GSUT ) M + AUXT =
I LR SrM V AUXT _ LV
(R sys + RGSUT)
2
R M I rM VrM 2 V AUXT _ HV
+ RAUXT
X M I LR SrM V AUXT _ LV
Rsys the equivalent resistance of the HV-system referred RAUXT the resistive component of the short-circuit
to the LV-side of the step-up transformer impedance of the unit auxiliary transformer referred
R GSUT the resistive component of the short-circuit to the HV-side of the unit auxiliary transformer
impedance of the step-up transformer referred to the is equal to 2 f with f being the power frequency
LV-side of the step-up transformer
XM / RM the X/R ratio of the motors connected to the LV-side
of the unit auxiliary transformer
22 | ABB
The degree of asymmetry of the fault current measured at the
contact parting time is:
( )
a tcp =
( )
Idc tcp
2 Iac
VmG SrG 1 1 1 1 1
I gen sym = 2
et ''d + et 'd +
3 VrG x''d x'd x'd x d xd
Igen sym is the a.c. component of the generator-source short- x'd is the pu value of the direct-axis transient reactance
circuit current x" d is the pu value of the direct-axis subtransient
V mG is the maximum generator line-to-line voltage reactance
S rG is the rated power of the generator ' d is the direct-axis transient short-circuit time constant
V rG is the rated voltage of the generator " d is the direct-axis subtransient short-circuit time
xd is the pu value of the direct-axis synchronous constant
reactance
If the fault initiation takes place when the voltage in one phase constants of the generator; the d.c. component decays with
passes through zero the resulting fault current in that phase the armature time constant a. The armature time constant
exhibits the maximum degree of asymmetry. The a.c. compo- can be calculated with the following formula:
nent decays with the subtransient and transient time
X2
a =
2 f R a
ABB | 23
The value of X2 can be approximated by:
X ''d + X ''q
X2 =
2
X"d is the direct-axis subtransient reactance of the Xq is the quadrature-axis subtransient reactance of the
generator generator
The generator-source asymmetrical short-circuit current for the phase with the highest asymmetry, the generator being in the
no-load mode, can be calculated by the following simplified formula:
is equal to 2 f with f being the power frequency xq is the quadrature-axis subtransient reactance in pu
Since x" d is approximately equal to x"q for turbo generators, the equation can be written as follows:
If the a.c. component of the fault current decays faster than asymmetry of the fault current is higher than 100% thus lead-
the d.c. component, it can happen that for a certain period of ing to delayed current zeros. The typical course of the degree
time following the initiation of the fault the magnitude of the of asymmetry of the generator-source short-circuit current is
d.c. component of the fault current is bigger than the peak shown in Figure 25.
value of its a.c. component. In such a case the degree of
150
Degree of Asymmetrie [%]
100
50
0
0 0.02 0.04 0.06 0.08 0.10 0.12 0.14
time [s]
24 | ABB
In addition the a.c. component of the generator-source short- circuit current and typically shows a degree of asymmetry
circuit current and its degree of asymmetry can vary if the measured at the primary arcing contact parting times are in
generator is unloaded or delivering power with lagging power the order of 130% (see Figure 25). Special attention should
factor (i.e. working in the over-excited mode) or leading power be paid if the generator is loaded with leading power factor
factor (i.e. working in the under-excited mode) prior to fault. before fault initiation. In such a case the degree of asymmetry
Typical fault current wave-shapes are depicted in of the fault current can reach very high values and exceed
Figures 26, 27 and 28. 130%.
The magnitude of the a.c. component of the fault current In order to accurately simulate the behaviour of the genera-
which is fed by the generator is typically about 80% of the tor in case it is loaded prior to fault computer simulations are
magnitude of the a.c. component of the system-source short- necessary.
250.0 250.0
[kA ] [kA ]
187.5 187.5
125.0 125.0
62.5 62.5
0.0 0.0
-62.5 -62.5
-125.0 -125.0
-187.5 -187.5
-250.0 -250.0
0.00 0.05 0.10 0.15 0.20 0.25 [s] 0.30 0.00 0.05 0.10 0.15 0.20 0.25 [s] 0.30
Figure 26: Prospective generator-source short-circuit current Figure 27: Prospective generator-source short-circuit current
(generator unloaded prior to fault initiation) - fault initiation at UA = 0 (generator delivering power with lagging power factor prior to fault
initiation) - fault initiation at UA = 0
250.0
[kA ]
187.5
125.0
62.5
0.0
-62.5
-125.0
-187.5
-250.0
0.00 0.05 0.10 0.15 0.20 0.25 [s] 0.30
Additional resistance in series with the armature resistance In case of a short-circuit current with delayed current zeros
forces the d.c. component of the short-circuit current to the capability of a circuit-breaker to interrupt a given short-
decay faster. Such additional resistance may be the connec- circuit current can be considered as being demonstrated if
tion from the generator to the fault location, but especially the generator circuit-breaker is capable of forcing the current
the circuit-breaker arc resistance after contact separation. If to zero within the time interval in which it is able to interrupt a
there is an arc at the fault location, this arc resistance further current (i.e. within the maximum permissible arcing time).
reduces the time constant of the d.c. component from the According to IEEE Std C37.013-1997 (R2008) demonstrating
initiation of the fault. The values of these additional series the capability of a generator circuit-breaker to interrupt short-
resistances are normally high enough to force a fast decay of circuit currents with delayed current zeros may be difficult and
the d.c. component of the short-circuit current so that current limited in high power testing stations. Since various designs
zeros are produced.
ABB | 25
of generators behave differently, it may not be possible to The arc-voltage of a circuit-breaker depends on the instanta-
simulate the required current shape in the testing station. neous value of the current and on the type of the extinguish-
Therefore the capability of a circuit-breaker to interrupt a ing medium, its pressure, the intensity of its flow and the
short-circuit current with delayed current zeros can be ascer- length of the arc. The uarc-i characteristic of one break of the
tained by calculations that take into account the effect of the circuit-breaker has to be derived from short-circuit current
arc-voltage of the circuit-breaker on the prospective short- interrupting tests. To be able to investigate the behaviour
circuit current. The arc-voltage model used for this purpose has of the circuit-breaker during the interruption of short-circuit
to be derived from tests (IEEE Std C37.013-1997 (R2008), currents with delayed current zeros the arc-voltage versus
Clause 6.2.7). The technical data of the actual generator shall current characteristic has to be transferred into a mathematical
be used for these computations. model. From the arc-voltage u arc(i,t) and the current i(t) the
arc resistance Rarc(i,t) can be obtained. In order to model the
According to IEEE Std C37.013-1997 (R2008), Clause behaviour of the SF6 circuit-breaker a non-linear time-varying
7.3.5.3.5.3 the following two cases shall be investigated: resistance of the value R arc(i,t) has to be inserted into the
simulation at the time of the separation of the contacts of the
1) Generator at no-load with the generator circuit-breaker circuit-breaker.
closing into a three-phase fault. In the computation the arc-
voltage of the generator circuit-breaker starting at contact Figures 29 to 32 show examples of the corresponding cal-
separation shall be taken into account. culation results. Figures 29 and 30 represent the case of the
generator being under no-load condition with the generator
2) Generator in service with leading power factor. An arcing circuit-breaker closing into a three-phase fault. In the compu-
fault is assumed in at least two phases. In the computation tation the arc-voltage of the generator circuit-breaker starting
the arc-voltage at the fault location starting at the initiation of at contact separation is taken into account. Figure 29 repre-
the fault and the arc-voltage of the generator circuit-breaker sents the case with fault initiation at voltage zero and Figure
starting at contact separation shall be taken into account. 30 represents the case with fault initiation at voltage maxi-
mum in one phase. Figures 31 and 32 represent the case of
Further the following two situations shall be considered for a the generator being in service with a leading power factor. In
particular generator-source short-circuit current in case of a the computation the arc-voltage at the fault location starting
three-phase fault (IEEE Std C37.013-1997 (R2008), Clause at the initiation of the fault and the arc-voltage of the genera-
6.2.7.2): tor circuit-breaker starting at contact separation is taken into
account. Figure 31 represents the case with fault initiation
1) Fault initiation at voltage zero in one phase which implies at voltage zero and Figure 32 represents the case with fault
that the current in the corresponding phase exhibits the initiation at voltage maximum in one phase.
maximum degree of asymmetry. As the maximum calculated arcing time (i.e. 20.9 ms, see
Figure 29) is shorter than the maximum arcing time of the
2) Fault initiation at voltage maximum in one phase which generator circuit-breaker of concern it can be concluded that
implies that the current in the corresponding phase is the circuit-breaker is capable of interrupting these fault
symmetrical. currents showing delayed current zeros.
250.0 250.0
[kA ] [kA ]
187.5 187.5
125.0 125.0
62.5 62.5
0.0 0.0
-62.5 -62.5
-125.0 -125.0
-187.5 -187.5
t cp t cp
-250.0 -250.0
0.00 0.05 0.10 0.15 0.20 0.25 [s] 0.30 0.00 0.05 0.10 0.15 0.20 0.25 [s] 0.30
Figure 29: Interruption of generator-source short-circuit current with a Figure 30: Interruption of generator-source short-circuit current with a
SF 6 generator circuit-breaker SF6 generator circuit-breaker
generator unloaded prior to fault initiation generator unloaded prior to fault initiation
fault initiation at UA = 0 fault initiation at UA = max
contact parting time tcp = 39 ms contact parting time tcp = 39 ms
arcing time = 20.9 ms arcing time = 20.7 ms
26 | ABB
250.0 250.0
[kA ] [kA ]
187.5 187.5
125.0 125.0
62.5 62.5
0.0 0.0
-62.5 -62.5
-125.0 -125.0
-187.5 -187.5
t cp t cp
-250.0 -250.0
0.00 0.05 0.10 0.15 0.20 0.25 [s] 0.30 0.00 0.05 0.10 0.15 0.20 0.25 [s] 0.30
Figure 31: Interruption of generator-source short-circuit current with a Figure 32: Interruption of generator-source short-circuit current with a
SF 6 generator circuit-breaker SF6 generator circuit-breaker
generator delivering power with leading power factor prior to fault generator delivering power with leading power factor prior to fault
initiation initiation
fault initiation at UA = 0 fault initiation at UA = max
contact parting time tcp = 39 ms contact parting time tcp = 39 ms
arcing time = 18.2 ms arcing time = 18.6 ms
In some cases the arc-voltage of the generator circuit-breaker is not recommendable because the longer fault arcing time
is not high enough to force current zeros within the maximum might lead to severe damages to power plant equipment with
permissible arcing time of the circuit-breaker (this can hap- consequent long downtime for repair. A better approach con-
pen for example if a vacuum interrupter is employed as a sists in choosing a generator circuit-breaker which is proven
generator circuit-breaker). In such a case a solution which to be able to interrupt the fault current without the aid of any
is sometimes adopted is to delay the tripping signal to the intentional tripping delay.
generator circuit-breaker. It has to be noted that this solution
ABB | 27
A three-phase fault is the most severe case and gives the The TRV shall be calculated after the interruption of a sym-
maximum short-circuit current and the maximum TRV rate. metrical current as any asymmetry in the current wave-shape
The neutral of the generator is not solidly grounded, thus the would lead to a less severe TRV. At the interruption of the
phase-to-ground fault current is not significant. short-circuit current with maximum asymmetry, the transient
The typical power plant layout is shown in Figure 23, where oscillation of the recovery voltage will be very small or even
the generator and the step-up transformer have essentially non-existent since at the moment of short-circuit current
the same rating. For TRV calculations the contribution of interruption, the normal frequency voltage value may be very
auxiliary transformer to the fault current can be neglected as it small or zero.
is a minor source of short-circuit current.
3 Z0
k pp =
2 Z 0 + Z1
In practical applications the step-up transformer is Ynd The zero-sequence impedance of such a system is much
connected and the star point of the stator winding of the higher than Z1 thus leading to
generator is usually grounded via a high resistance.
3Z0 3Z0
k pp = = 1.5
2 Z 0 + Z1 2 Z0
28 | ABB
5.3.9.4 Rated inherent transient recovery voltage
The rated inherent transient recovery voltage is the reference voltage that a) one line starts at the origin of time axis and is
constitutes the limit of the inherent transient recovery voltage of circuits tangent to the TRV curve with a slope equal to the
that the generator circuit-breaker shall be capable of withstanding under TRV rate-of-rise
fault conditions and shall be defined by an oscillatory wave-shape having
a TRV rate-of-rise, time delay (td) and peak voltage (E2) [1]. b) one line is horizontal and is tangent to the TRV
The waveform of transient recovery voltages approximates to a damped curve at the time of TRV peak T2.
oscillation.
c) one line starts on the time axis at the rated time
The TRV curve is bounded by three lines: delay (t d) and runs parallel to the first reference line
td t3 T2
Figure 33: Inherent TRV curve for first-pole-to-clear for required symmetrical
interrupting capability for three-phase faults
2
E2 = V k af k pp = 1.84 V
3
The rated TRV is the inherent value assuming an ideal generator circuit- it decreases the oscillation frequency and the
breaker. These values may be modified by the generator circuit-breaker RRRV of the TRV
characteristics or by the asymmetry of the current. it increases the time delay of the TRV
A system with a TRV that exceeds the rated values of the generator
it increases the peak value of the TRV
circuit-breaker must be modified in such a way as to lower the TRV. This
is generally achieved by connecting capacitors phase-to-ground on both If the circuit-breaker requires that the inherent TRV
sides of the generator circuit-breaker. be modified by the addition of capacitors, then the
The additional capacitance has three effects: amount of equivalent capacitance required has to
be given in the test report and on the nameplate [1].
ABB | 29
5.3.9.5 System-source faults
For system-source faults the maximum value of short-circuit current is r.m.s. value of the symmetrical short-circuit current
obtained for a given transformer when Xsys is minimum or assumed to until the second and third poles open. The voltage
be zero. It is assumed that the contribution of the auxiliary system to drop in the transformer is equal to the total power
the fault current is negligible. The natural frequency of the transformer is frequency recovery voltage for
much higher than the natural frequency of the HV-system. The TRV first X sys = 0. Therefore, the TRV rate is maximum when
oscillates at the prospective value of 1.5 2 XGSUT Iac, where Iac is the the short-circuit current is maximum [1].
R eq L eq GCB
Veq Ceq
3 Z0
Veq = Vmax 1.5 Vmax
2 Z 0 + Z1
Vmax is the maximum r.m.s. value of the applied in case of system-source short-circuit currents and
voltage prior to fault (it can generally be considered generator-source short-circuit currents, respectively)
equal to the maximum phase-to-ground service Z0 is the equivalent zero-sequence impedance of the
voltage of the HV-system referred to the LV-side three-phase circuit
of the step-up transformer and to the maximum Z1 is the equivalent positive-sequence impedance of the
phase-to-ground operating voltage of the generator three-phase circuit
30 | ABB
Leq can be considered equal to 1.5 L1 where L1 is the equiva- is the positive-sequence resistance of the three-phase circuit.
lent positive-sequence inductance of the three-phase circuit.
Following the same procedure Req is equal to 1.5 R1 where R1 Ceq can be calculated by using the following expression:
C0 + 2 C1
Ceq = If C0 = C1 then Ceq = C1 = C0
3
C0 is the zero-sequence capacitance of the three-phase C1 is the positive-sequence capacitance of the three-
circuit phase circuit
1 Req2
>
L eq Ceq 4 L eq2
thus leading to an underdamped wave-shape of the TRV. frequency and one oscillating at the frequency imposed by the
The TRV will appear as the superposition of sinusoidal curves circuit parameters:
oscillating at different frequencies, i.e. one oscillating at power
R eq
t
u TRV (t) = 2 Veq cos ( t ) e
2 L eq
cos t )
)
1 Req2 1 1 Req2
= assuming >>
L eq Ceq 4 L eq2 L eq Ceq L eq Ceq 4 L eq2
Assuming that cos( t) ~ 1 at the time of TRV peak represented by the following expression:
(being >> ) the transient recovery voltage can be finally
R eq
t
u TRV (t) = 2 Veq 1 e
2 L eq
cos t )
)
The TRV peak value occurs at time T2 = L eq Ceq
R eq R eq Ceq
T2
2 L eq 2 Leq
E2 = 2 Veq 1 e cos T2 ) =
) 2 Veq 1 + e
ABB | 31
5.3.10 Rated load current switching capability
During normal service of the generator, the load current is in the motor mode in pumped storage power plants. The gen-
reduced to zero before an opening operation of the genera- erator circuit-breaker shall be capable of interrupting those
tor circuit-breaker is initiated. However, the interruption of currents and withstanding the TRV appearing across the open
full load current may be required occasionally for emergency contacts immediately after the interruption of the current.
circumstances or when the synchronous machine is working
32 | ABB
400 400
[kA ] [kA ]
300 300
200 200
100 100
0 0
-100 -100
-200 -200
-300 -300
-400 -400
0.00 0.05 0.10 0.15 0.20 0.25 0.30 0.35 [s] 0.40 0.00 0.05 0.10 0.15 0.20 0.25 0.30 0.35 [s] 0.40
Figure 35: Prospective out-of-phase fault current out-of-phase Figure 36: Prospective out-of-phase fault current out-of-phase
angle 0 = 30 angle 0 = 60
400 400
[kA ] [kA ]
300 300
200 200
100 100
0 0
-100 -100
-200 -200
-300 -300
-400 -400
0.00 0.05 0.10 0.15 0.20 0.25 0.30 0.35 [s] 0.40 0.00 0.05 0.10 0.15 0.20 0.25 0.30 0.35 [s] 0.40
Figure 37: Prospective out-of-phase fault current out-of-phase Figure 38: Prospective out-of-phase fault current out-of-phase angle
angle 0 = 90 0 = 120
400 400
[kA ] [kA ]
300 300
200 200
100 100
0 0
-100 -100
-200 -200
-300 -300
-400 -400
0.00 0.05 0.10 0.15 0.20 0.25 0.30 0.35 [s] 0.40 0.00 0.05 0.10 0.15 0.20 0.25 0.30 0.35 [s] 0.40
Figure 39: Prospective out-of-phase fault current out-of-phase angle Figure 40: Prospective out-of-phase fault current out-of-phase angle
0 = 150 0 = 180
ABB | 33
5.3.13 Excitation current switching capability
IEEE Std C37.013-1997 (R2008) defines the excitation cur- buses or cables). This might results in voltage oscillations of
rent switching capability as the highest magnetizing current high amplitudes. Modern transformers have a low no-load
that a generator circuit-breaker shall be required to switch at current value compared to older designs, and their magnetic
any voltage up to rated maximum voltage at power frequency characteristics are such that a relatively low amount of energy
without causing an overvoltage exceeding the levels agreed is released when current chopping occurs during switching,
upon between the user and the manufacturer. leading to moderate chopping overvoltages [1]. Chopping
During normal operation, a generator step-up transformer is overvoltages are produced only on the transformer side of the
rarely switched in an unloaded condition. Anyway, consider- generator circuit-breaker. No overvoltages occur on the
ation should be given to switching of transformer excitation generator side because the inductance of the generator is
current. Excitation current switching is not so much a matter much lower than the magnetizing impedance of the trans-
of the generator circuit-breaker capability, but a question of former, and the energy content is low and not of sufficient
whether overvoltages are produced due to current chopping. magnitude to produce overvoltages [1].
Due to instabilities of the arc between the circuit-breaker The overvoltage generated by current chopping can be esti-
contacts premature current zeros at high frequencies occur mated with the following formula where it has been assumed
frequently when switching small inductive currents, leading to that the energy stored in the magnetizing inductance of the
current chopping. The chopped current flowing in the no- step-up transformer is transferred to the equivalent capaci-
load inductance charges the capacitances of the transformer tance without losses. In addition the magnetizing character-
windings and the capacitances of the connection between the istics and the hysteresis loop of the step-up transformer have
step-up transformer and the generator circuit-breaker (e.g. been neglected.
1 1 L mag
L mag i 2 = Ceq v 2 v=i
2 2 Ceq
v is the voltage generated by current chopping Ceq is the equivalent capacitance to ground of the step-
i is the chopped current up transformer windings and the connection of the
L mag is the magnetizing inductance of the step-up step-up transformer to the generator circuit-breaker
transformer terminals
The value of chopped current, and consequently the overvol- addition the generator circuit-breaker systems are generally
tages produced, are mainly dependent on the type of gen- equipped with capacitors which help to mitigate the transient
erator circuit-breaker. Experience indicates that the current recovery voltage appearing after current interruptions. Those
chopping level of SF 6 self-blast generator circuit-breakers is capacitors are also very effective in reducing the overvoltages
low and no overvoltages of concern are expected. Further- produced by current chopping. It has to be mentioned that
more, the transformer LV-side is usually protected by surge the capacitors installed at the generator circuit-breaker termi-
arresters which reduce these overvoltages. The energy to nals increase the chopping current level but on the other hand
be absorbed by the arresters is usually extremely small. In they help reducing the generated overvoltage.
34 | ABB
6 Application of generator circuit-breakers
The major demands on the electrical layout of power plants The criteria which are used to evaluate and assess the
can be summarised as follows: generator circuit-breakers application exert considerable
transfer the generated electric energy from the generator to influence on the electrical layout of the power plant.
the HV-transmission system considering operation require-
ments as well as availability, reliability, and economical
aspects
supply of electric power for auxiliary and station service
systems to ensure a safe and reliable power plant operation
ABB | 35
Protection: The differential protection is used as the main Operation and maintenance: Preventive and especially
protection for a step-up transformer. The block differential corrective maintenance of a three-winding transformer might
protection is applied as a back-up protection. Due to a higher be an issue as this occurrence would lead to the outage of
number of windings involved, the protection of a three- two units. A solution which can be adopted to reduce the
winding transformer is relatively more complicated compared downtime is to buy a spare transformer. In order to reduce the
to the case when two-winding transformers are employed. cost of the spare equipment sometimes three single-phase
Except for the number of windings, no additional noticeable three-winding transformers are employed and only one spare
differences can be found between protection functions of two- single-phase machine is considered.
and three-winding transformers. In addition to the above mentioned items, availability and
commercial feasibility have to be considered too in order to
make a more thorough comparison between two- and three-
winding transformers.
36 | ABB
Generator circuit-breakers are widely used in pumped storage Because of their ability to interrupt fault current also at
power plants because the use of such circuit-breakers allows frequencies below 50/60 Hz ABB generator circuit-breakers
the electrical scheme (Figure 41f) to be greatly simplified. ensure an adequate protection of power plant equipment.
MT MT MT
UT ST UT
GCB GCB GCB
SS UT
SFC
G AUX G AUX G
AUX
a) b) c)
MT MT
MT MT MT
PRD PRD
UT UT SS SS
GCB GCB GCB GCB GCB GCB
BS BS BS BS BS SS SS BS
G G AUX G G AUX G G
SFC
UT
d) e) f) AUX
Figure 41: Different power plant layouts which employ generator circuit-breakers
Legend
MT Main transformer AUX Unit auxiliaries
UT Unit transformer SS Starting switch
ST Station transformer BS Braking switch
GCB Generator circuit-breaker SFC Static frequency converter
EHV Transmission system PRD Phase-reversal disconnector
HV Sub-transmission system
ABB | 37
6.2 Advantages of generator circuit-breakers
The use of generator circuit-breakers for the switching of gen- As a disadvantage of this solution in comparison with the unit
erators at their terminal voltage offers many advantages when connection especially in the case of large generating units
compared to the unit connection, e.g.: the high costs of the generator circuit-breaker are sometimes
simplified operational procedures mentioned. This argument however refers to air-blast genera-
tor circuit-breakers and with the appearance of modern SF6
improved protection of the generator and the main and unit
generator circuit-breakers for units with ratings of up to 2000
transformers
MVA is no longer valid.
increased security and higher power plant availability
economic benefit
38 | ABB
Such incidents have a detrimental effect on the availability of Compared to high-voltage circuit-breakers modern SF6 gen-
a power plant. It should be noted that the generator rapid de- erator circuit-breakers exhibit higher maintenance intervals as
excitation equipment is in most cases too slow to avoid this they are especially designed for a high mechanical and electri-
kind of damage. cal endurance. Depending on the application the down-time
In many cases equipment damage can be reduced or even of a unit due to circuit-breaker maintenance can therefore be
prevented by using a generator circuit-breaker in conjunction significantly reduced when a generator circuit-breaker is used.
with an adequate generator protection.
Figure 42: Description of operation procedures for layouts with and without generator circuit-breaker
ABB | 39
steep because the fault current is only fed by the generator. Investigations have shown that a generator circuit-breaker
Anyway the pressure can quickly reach the tank withstand can prevent tank rupture in about 80% of all cases of main
pressure thus leading to the explosion of the transformer. The transformer internal failures [11]. The use of a generator
dotted lines represent the course of the pressure rise if no circuit-breaker can greatly reduce the probability of a trans-
generator circuit-breaker is available. former tank rupture during internal fault. This will reduce the
When the generator-fed component of the fault current is related downtime of the power plant thus leading to a higher
interrupted by the generator circuit-breaker the pressure rise availability.
is generally stopped quickly enough to prevent the transformer In Figure 45 the sequence of events which have led to a
tank explosion. Anyway depending on the fault arc energy transformer explosion is shown. It is interesting to see how
and on the transformer tank withstand pressure the pressure fast a ground fault developed into a three-phase fault and
rise inside the transformer tank can be so steep that the tank consequently into an explosion after approx 150 ms. In such
withstand pressure of the transformer is reached even before a case the presence of a generator circuit-breaker would have
the high-voltage circuit-breaker can be operated for contri- allowed the interruption of the generator-fed fault current in
buting to transformer protection. less than 4 cycles thus preventing such a damage.
a) Case without generator circuit-breaker (unit connection) b) Case with generator circuit-breaker
Ig Is Ig Is
G Grid
G Grid
Fault Fault
Interruption of HV
Interruption of HV
Circuit-Breaker
Circuit-Breaker
Current Current
Interruption of Generator
Circuit-Breaker
I s +I g I s +I g
Ig Ig
Figure 43: Interruption of generator-fed fault currents with and without generator circuit-breaker
Pressure
Time
Figure 44: Pressure rise inside transformer tank for different fault locations
40 | ABB
Sequence of events
HV circuit-breaker: 1 phase does not close Transformer LV terminals: two phase fault
HV circuit-breaker: 1 phase does not open Transformer HV windings: various types of faults
Transformer HV bushings: single phase earth fault HV circuit-breaker: two phase flashover
Figure 46: Examples of failures which can lead to unbalanced load conditions
ABB | 41
The thermal stresses result from the negative sequence com-
ponent of the fault current that interacts with the generator
damper windings. Unbalanced load conditions can give rise,
within a very short time, to dangerously high temperatures
in the damper windings. These temperatures are particularly
critical for turbo generators and in the worst case may cause
the rotor to jam in the stator. If a generator circuit-breaker is
present it will separate the generator from the fault within 4
cycles and thus effectively prevent damage to the generator.
If no generator circuit-breaker is fitted, the generator will con-
tinue to supply a negative sequence current until de-excitation
is completed. The de-excitation may take several seconds,
during which time the generator may suffer severe damage.
Unbalanced load cases might lead to severe damage as
depicted in Figure 47. In this case the rotors touching of the
Figure 47: Damage resulting from unbalanced load conditions
stator destroyed the generator completely. (source: Allianz Insurance Company)
Overhead Line
GS
3~
Coupling
Figure 48: Layout of a power plant in which a case of generator motoring occurred
42 | ABB
6.2.4 Economic benefit
Several economic advantages are brought about by the Should the high-voltage substation be erected at some
employment of a power plant layout with generator circuit- distance from the power plant the generator circuit-breaker
breaker compared to the unit connection: can be used to protect the overhead line linking the power
The possible integration of all the associated items of plant to the substation. No separate high-voltage circuit-
switchgear into the enclosure of the generator circuit-breaker breaker at the power plant is required for this purpose.
allows simpler and more economic power plant layouts. The through-fault capability required of the unit transformers
This solution hence allows savings in time and expenditures is substantially reduced.
for erection and commissioning. The higher availability of the power plant leads to an in-
When a layout with a generator circuit-breaker is used it is creased number of the operating hours and therefore to a
possible to omit the station transformer and the associated higher profit for the operator of the power plant. Substantial
high-voltage and medium-voltage switchgear. If the station surplus of receipts can be achieved in this way and the pay-
transformer cannot be dispensed with, the use of a trans- back time for the expenditures of a generator circuit-breaker
former with reduced rating (rated as a shut-down trans- is generally very low.
former) is usually sufficient.
ABB | 43
7 Maintenance of generator circuit-breakers
Overhaul of generator circuit-breakers is scheduled based on interruption of currents far above the rated continuous current
the criteria of service time, number of mechanical CO opera- longer arcing times are expected. Therefore, the ablation of
tions and number of current interruptions whichever occurs contact material increases disproportionately. In addition, high
first. electro-dynamical forces arise which reduce the mechanical
Specifically the electrical endurance of the generator circuit- lifetime of the circuit-breaker.
breaker depends on the magnitude of the current which is
switched. To each opening operation, an ablation coefficient For typical applications generator circuit-breakers do not have
k is assigned. The ablation coefficient depends on the r.m.s. to switch load currents and therefore overhaul is generally
value of the switched current. Within a range up to 150% of scheduled based on service time. Depending on the type of
the rated continuous current the ablation coefficient is generator circuit-breaker typical overhaul intervals are 15 to
proportional to the ablation of the arcing contacts. With the 20 years.
44 | ABB
8 Case study 1: Impact of the method of connecting a generator
to the high-voltage grid on the availability of a power plant
In order to quantify the impact of how a generator is con- network were considered, namely:
nected to the high-voltage grid on the availability of a power a layout without a circuit-breaker between the generator
plant, the contribution of the connection of the generator to and the low-voltage terminals of the main transformer (unit
the high-voltage transmission network and of the supply to connection), refer to Figure 49)
the unit auxiliaries to the unavailability of one generating unit
a layout with a generator circuit-breaker and a station trans-
has been determined with the help of computer program
former (rated as shut-down transformer), refer to Figure 50)
based on the Monte Carlo method [13]. Three different ways
a layout with a generator circuit-breaker, refer to Figure 51)
of connecting the generator to the high-voltage transmission
345 kV
138 kV
GSUT GSUT
UT UT UT UT ST ST
G G
GEN 22 kV GEN 22 kV
Figure 49: Layout of a 2 x 360 MW thermal power plant with two station transformers and no generator circuit-breaker
ABB | 45
345 kV
138 kV
GSUT GSUT
UT UT UT UT ST
G G
GEN 22 kV GEN 22 kV
Figure 50: Layout of a 2 x 360 MW thermal power plant with one station transformer and generator circuit-breakers
345 kV
GSUT GSUT
UT UT UT UT
G G
GEN 22 kV GEN 22 kV
Figure 51: Layout of a 2 x 360 MW thermal power plant with generator circuit-breakers and no station transformer
46 | ABB
8.1.1 Layout of extra high-voltage substation
The secure operation of extra high-voltage substations is A feature of the double busbar with double circuit-breaker
greatly influenced by their layout. In order to assure the conti- arrangement (Figure 52c) is that each outgoing feeder is con-
nuity of the supply, the links between incoming and outgoing nected to the rest of the installation by two parallel circuit-
feeders of a substation have to remain intact, even in spite of breakers, i.e. this scheme uses circuit-breaker redundancy to
a number of connecting elements not being available. Obvi- secure operation under disturbed conditions.
ously every effort is made to attain this goal with a minimum Since each line has two circuit-breakers, one circuit-breaker
capital outlay. can be taken out of service at any time without interrupting
The following substation schemes have been investigated: the operation.
double busbar with single circuit-breaker (Figure 52a) A more economic kind of redundancy is achieved with the
ring arrangement (Figure 52d) which is considered as an
one and a half circuit-breaker (Figure 52b)
appropriate solution for substations with only a few feed-
double busbar with double circuit-breaker (Figure 52c)
ers. Each feeder requires only one circuit-breaker and each
ring (Figure 52d) circuit-breaker can be isolated without interrupting the supply.
crossed-ring (Figure 52e) Starting from this scheme, new concepts were developed to
increase structural redundancy.
For large installations the double busbar with single circuit- In the normal state of the crossed-ring substation arrange-
breaker arrangement (Figure 52a) is preferred. The presence ment (Figure 52e) the circuit-breakers of the basic ring (BR)
of two busbars makes maintenance possible without inter- are closed while those of the cross-links (CL) are open. If
rupting the supply. On the other hand a circuit-breaker failure one circuit-breaker in the basic ring fails, another ring can
leads to the loss of all feeders connected to that busbar and be formed so that the original availability is maintained. It
the busbar protection may cause the loss of the substation if can be seen that even in the case of non-availability of two
all feeders are connected to the same busbar. adjacent circuit-breakers, the respective node can be fed via
A scheme representing a mixture of equipment and structural the remaining circuit-breaker. With any of the other topologies
redundancy is the one and a half circuit-breaker arrange- introduced above, this situation would automatically lead to
ment (Figure 52b). It is often used for very important substa- the loss of the node. The impact of the use of gas insulated
tions because of its high availability and good operational switchgear (GIS) instead of air insulated switchgear (AIS) has
flexibility. In this case three circuit-breakers are employed for also been investigated. The GIS solution leads to a lower
two outgoing feeders. All circuit-breakers are normally closed. failure rate and to a higher MTTR and, even though it is more
Uninterrupted supply is thus maintained even if one busbar expensive, it is to be preferred when problems of space or
fails. pollution are present.
a) b) c)
d) e)
BR BR BR CL
BR CL CL BR
BR BR BR CL
ABB | 47
8.1.2 Layout of high-voltage substation
The layout of the high-voltage substation used for the investi-
gation is a double busbar with single circuit-breaker arrange-
ment (Figure 52a) and uses air insulated switchgear.
8.3 Simulations
The simulations have been carried out with the help of a During a simulation run, when a failure occurs it is treated by
computer program based on the Monte Carlo method [20]. tripping the circuit-breakers forming the protection group of
This is a very powerful technique to quantitatively estimate the the failed component immediately after the occurrence of the
reliability of complex systems like power plants; furthermore it failure. After the time necessary to isolate the failed compo-
allows to quantify the impact of the connection scheme of a nent (i. e. the switching time) the circuit-breakers are closed
generator to the extra high-voltage network on the availability again. When the repair of the component is completed (or
of the plant. a spare part has become available), the above procedure is
Monte Carlo methods estimate the reliability of a system by repeated. Also the transfer of the auxiliaries between different
simulating the process and its random behaviour. The simula- sources during the starting-up and the shutting-down of the
tion consists in a repeated process of generating deterministic unit (or when a failure occurs) is modelled. The operational
solutions to a given problem with each solution correspond- state of a unit further depends on the state of its auxiliaries,
ing to a set of deterministic values of the underlying random as the number of auxiliaries available influences the level of
variables. The main element of Monte Carlo simulation is possible power production.
therefore the generation of random numbers from probability One of the results obtained from the simulations is the power
distributions describing the random variables of interest, e.g. throughput of the power plant.
the failure and repair rates of different items of power plant
equipment.
48 | ABB
8.4 Simulation results
The simulations have been carried out assuming that the breaker is used. This improvement is in the order of 0.4%.
power plant supplies base load. The availability of the unit The ring scheme seems to be very interesting: in this case the
(turbine and generator) has been set to 86.67%. This value availability improvement is in the order of 0.44%. The results
takes into account forced and scheduled outages of the unit. clearly indicate that, from a point of view of power plant
The results of the simulations are summarized in Table III and availability, a layout with a generator circuit-breaker offers a
Table IV. distinct advantage over the unit connection.
The difference in the throughput power directly reflects the With respect to the design of the extra high-voltage substa-
contribution of the different schemes used to connect the tion, it can be seen that in case of a layout with generator
generators to the extra high-voltage transmission network circuit-breaker, the number of station transformers has a
on the availability of the power plant. The results show that negligible influence on the power plant availability.
the use of a layout with a generator circuit-breaker positively On the other side, the difference in the throughput power be-
affects the availability. Figure 53 depicts the possible avail- tween a gas insulated substation and an air insulated substa-
ability improvements when a layout with a generator circuit- tion is generally very small (see Table IV).
0.44%
0.42%
0.42% 0.42%
0.40%
a) b) c) d) e)
Figure 53: Relative availability improvement for a layout with generator circuit-breaker (related to the basic scheme without a generator circuit-
breaker)
ABB | 49
EHV substation HV substation Generator Station Power
(refer to Figure 52) (refer to Figure 52) circuit-breaker transformer throughput
i
1
Cpv = Ci
1+ r
Ci is the expense payable in i years in zero-year r is the effective discount rate (interest rate - inflation
currency value rate)
C pv is the present value of cost C i i is the number of years at the end of which the
expense Ci is paid.
i
N 1
PV _ FM = (Ii OCi MCi ) AC CWC IC
i=1 1+ r
PV_FM is the present value of the figure of merit MCi are the maintenance costs of selectable equipment in
N is the number of years of service (service life) year i
r is the effective discount rate AC are the acquisition costs of selectable equipment
li is the income in year i CWC are the civil works costs of selectable equipment
OC i are the operation costs in year i IC are the installation costs of selectable equipment
50 | ABB
The differences in the figure of merit of different power plant outs with a generator circuit-breaker generally have a higher
layouts are depicted in Figure 54. It can be noticed that lay- figure of merit than layouts without a generator circuit-breaker.
Additional calculations have shown that layouts with a Moreover, the use of a generator circuit-breaker makes the
generator circuit-breaker and without a station transformer ring scheme (Figure 52d) without station transformer one of
may even have somewhat higher figures of merit, especially in the best options; such a conclusion is due to the fact that
cases with low downtimes (e. g. power stations which supply this scheme is very cheap (low number of components) and
base load) where the losses during the time when the unit is shows a similar reliability as the other schemes when a
shut down do not matter very much. generator circuit-breaker is installed.
100.50%
100.40%
100.30%
With no GCB
100.20% With GCB and one
station transformer
100.10%
100.00%
99.90%
99.80%
99.90%
a) b) c) d) e)
Layout of EHV substations (refer to Figure 52)
ABB | 51
9 Case study 2: Interrupting capability of generator circuit-
breakers in case of delayed current zeros
The requirements imposed on generator circuit-breakers The capability of the generator circuit-breaker to interrupt fault
greatly differ from the requirements imposed on general currents which show delayed current zeros can be ascer-
purpose transmission and distribution circuit-breakers. Due tained by calculations that take into account the effect of the
to the location of installation between the generator and the arc-voltage of the circuit-breaker on the prospective fault
associated step-up transformer a generator circuit-breaker current. In order to carry out a thorough investigation on the
must meet high technical requirements with respect to the interrupting capability of generator circuit-breakers, a com-
interruption of fault currents. In addition to their generally high parison between SF6 and vacuum extinguishing technologies
magnitude, these currents can be characterized by delayed is provided.
current zeros.
52 | ABB
9.2 Generator terminal faults
The current to be interrupted by the generator circuit-breaker tion of the fault, the magnitude of the d.c. component of the
in case of faults between the terminals of the generator fault current is bigger than the peak value of its symmetrical
circuit-breaker and the LV-windings of the step-up trans- component. In such a case the degree of asymmetry of the
former is called generator-source short-circuit current. If the fault current is higher than 100%, thus leading to delayed cur-
fault initiation takes place when the voltage in one phase rent zeros. The degree of asymmetry of the generator-fed fault
passes through zero the resulting fault current in that phase current is typically about 130%.
exhibits the maximum degree of asymmetry. The symmetrical The course of the generator-source short-circuit current is
component decays with the subtransient and transient time depicted in Figure 55. Fault initiation takes place at 100 ms
constants of the generator; the d.c. component decays with and a bolted fault has been assumed (i.e. that there is no
the armature time constant. If the symmetrical component of arc-voltage at the fault location). The fault initiation occurs at
the fault current decays faster than the d.c. component, it can voltage zero in phase A.
happen that, for a certain period of time following the initia-
150
[kA ]
100
50
-50
-100
-150
0.00 0.05 0.10 0.15 0.20 0.25 [s] 0.30
Figure 56 and Figure 57 show the corresponding calcula- taken into account. Figure 56 represents the case with fault
tion results with the generator circuit-breaker closing into a initiation at voltage zero and Figure 57 shows the case with
three-phase fault. In the computation the arc-voltage of a fault initiation at voltage maximum in one phase.
SF6 generator circuit-breaker starting at contact separation is
150 150
[kA] [kA]
100 100
50 50
0 0
-50 -50
-100 -100
t cp t cp
-150 -150
0.08 0.10 0.12 0.14 0.16 0.18 [s] 0.20 0.08 0.10 0.12 0.14 0.16 0.18 [s] 0.20
Figure 56: Interruption of generator-source short-circuit current with Figure 57: Interruption of generator-source short-circuit current with
a SF6 generator circuit-breaker (generator unloaded prior to fault a SF6 generator circuit-breaker (generator unloaded prior to fault
initiation, fault initiation at U A = 0, arcing time = 17.6 ms) initiation, fault initiation at UA = max, arcing time = 20.2 ms)
ABB | 53
For comparison purposes the interrupting capability of a gen- corresponding calculation results. Figure 58 represents the
erator circuit-breaker employing vacuum extinguishing tech- case with fault initiation at voltage zero and Figure 59 shows
nology is also analysed. Figure 58 and Figure 59 show the the case with fault initiation at voltage maximum in one phase.
150 150
[kA] [kA]
100 100
50 50
0 0
-50 -50
-100 -100
t cp t cp
-150 -150
0.08 0.10 0.12 0.14 0.16 0.18 0.20 0.22 [s] 0.24 0.08 0.10 0.12 0.14 0.16 0.18 0.20 0.22 [s] 0.24
Figure 58: Interruption of generator-source short-circuit current with Figure 59: Interruption of generator-source short-circuit current with
a vacuum generator circuit-breaker (generator unloaded prior to fault a vacuum generator circuit-breaker (generator unloaded prior to fault
initiation, fault initiation at U A = 0, arcing time = 39.0 ms) initiation, fault initiation at UA = max, arcing time = 80.9 ms)
A method sometimes adopted to reduce the arcing time of the step-up transformer explode in case of internal failures.
the circuit-breaker is to introduce an intentional tripping delay. For this reason many power station operators consider the
A value in the range of 100 ms 200 ms is usually sufficient solution of intentionally delaying the tripping as not recom-
to limit the degree of asymmetry of the fault current at contact mendable. Therefore the preferred method to handle the
separation to values the generator circuit-breaker can cope delayed current zeros phenomena is to choose a generator
with. It has to be noted that this solution would lead to longer circuit-breaker having an arc-voltage magnitude sufficiently
fault duration and consequently to severe damages to power high to force current to zero without the aid of any intentional
station equipment with consequent long downtime for repair. tripping delay [22].
Fault durations exceeding 100 ms are usually sufficient to let
54 | ABB
9.3 Out-of-phase synchronising
Out-of-phase synchronising occasionally occurs in power the inertia constants of turbine, rotor and excitation equip-
plants [4]. The main reasons for out-of-phase synchronising ment of the generator are of special importance. Because the
are wiring errors made during commissioning or during main- fault current to be interrupted by the generator circuit-breaker
tenance when connecting voltage transformers and synchro- is characterized by delayed current zeros it is extremely im-
nising equipment. The current resulting from out-of-phase portant to prove that the circuit-breaker by means of its arc-
synchronising may show delayed current zeros; their causes voltage is capable of forcing current to zero within its maxi-
are totally different compared to generator terminal faults. The mum permissible arcing time. Even though it is recognized
rapid movement of the rotor from initial out-of-phase angle 0 that synchronising with out-of-phase angle up to 180 might
to = 0 results in a very small symmetrical component of the occur, [1], [2] cover only requirements for a maximum of 90.
fault current and a dominant d.c. component when the condi- Therefore for the present study simulations referring to such a
tion of = 0 is reached. As the instant when the = 0 con- fault conditions have been performed. The wave-shape of the
dition is reached is determined by the movement of the rotor, out-of-phase current in case of 0 = 90 is depicted in Figure 60.
150
[kA ]
100
50
-50
-100
-150
0.00 0.05 0.10 0.15 0.20 0.25 [s] 0.30
The simulation results are depicted in Figures 61, 62, 63 and sent the case of synchronisation occurring when the voltage
64. Figures 61 and 62 show the course of the fault current across the open contacts of pole A (UA) of the generator
in case a SF6 generator circuit-breaker is employed. Figures circuit-breaker is zero, while Figures 62 and 64 show the case
63 and 64 show the corresponding results in case of use of a when UA is at its maximum value.
vacuum generator circuit-breaker. Figures 61 and 63 repre-
150 150
[kA] [kA]
100 100
50 50
0 0
-50 -50
-100 -100
t cp t cp
-150 -150
0.08 0.10 0.12 0.14 0.16 0.18 [s] 0.20 0.08 0.10 0.12 0.14 0.16 0.18 [s] 0.20
Figure 61: Interruption of out-of-phase current with a SF 6 generator Figure 62: Interruption of out-of-phase current with a SF6 generator
circuit-breaker (out-of-phase angle 0 = 90, fault initiation at U A = 0, circuit-breaker (out-of-phase angle 0 = 90, fault initiation at UA =
arcing time = 16.5 ms) max, arcing time = 18.9 ms)
ABB | 55
150 150
[kA] [kA ]
100 100
50 50
0 0
-50 -50
-100 -100
t cp t cp
-150 -150
0.08 0.10 0.12 0.14 0.16 0.18 [s] 0.20 0.05 0.10 0.15 0.20 0.25 0.30 0.35 [s] 0.40
Figure 63: Interruption of out-of-phase current with a vacuum Figure 64: Interruption of out-of-phase current with a vacuum
generator circuit-breaker (out-of-phase angle 0 = 90, fault initiation generator circuit-breaker (out-of-phase angle 0 = 90, fault initiation
at UA = 0, arcing time = 18.2 ms) at UA = max, arcing time = 206.8 ms)
The results show that the fault current resulting from out-of- value and the arc-voltage of the circuit-breaker is not high
phase synchronising can impose extremely severe interrupt- enough to force current to zero before the condition of = 0
ing conditions if the generator circuit-breaker closes when is reached.
the voltage across its contacts in one pole is at its maximum
9.4 Conclusions
The possible occurrence of fault currents in power stations one phase leads to a longer arcing time compared to the case
which show delayed current zeros has been investigated. In of a fault occurring at voltage zero.
addition to the delayed current zeros phenomena associated The generator circuit-breaker employing SF6 as extinguishing
with generator terminal faults the case of synchronisation medium is suitable for the application as the calculated arcing
under out-of-phase conditions has also been analysed. The time lies well below the maximum permissible value.
capability of the generator circuit-breaker to interrupt fault The cases of generator terminal faults and 90 out-of-phase
currents which show delayed current zeros has been investi- synchronisation occurring at voltage maximum in one phase
gated by calculations that take into account the effect of the lead to severe stress for the vacuum circuit-breaker. The
arc-voltage of the generator circuit-breaker on the prospective vacuum circuit-breaker is not suitable for the application be-
fault current. In order to carry out a more thorough investiga- cause it is not capable of forcing the current to zero within the
tion on the interrupting capability of generator circuit-breakers permissible arcing time.
a comparison between SF6 and vacuum extinguishing tech- Therefore the preferred method to cope with currents exhibit-
nologies has been made. ing delayed current zeros is to choose a generator circuit-
In all the cases analyzed the application of a vacuum circuit- breaker having an arc-voltage magnitude sufficiently high
breaker results in longer arcing times compared to the SF6 to force the current to zero within the maximum permissible
device. Furthermore the fault occurring at voltage maximum in arcing time.
56 | ABB
References
[1] IEEE Std C37.013-1997 (R2008) IEEE Standard for [12] I. M. Canay; L. Werren: Unbalanced Load Stresses
AC High-Voltage Generator Circuit Breakers Rated on a Sym- in Generators due to Switching Failures, Faults in Power
metrical Current Basis. Transformers, Instrument Transformers and Lightning Arrest-
ers, ABB Technical Report ASB 88/200, 1988.
[2] IEEE Std C37.013a-2007 IEEE Standard for AC High
Voltage Generator Circuit Breakers Rated on a Symmetrical [13] A. Dubi, Monte Carlo Applications in Systems Engi-
Current Basis - Amendment 1: Supplement for Use with Gen- neering, John Wiley & Sons Ltd, 2000.
erators Rated 10100 MVA.
[14] D. Braun, F. Granata, M. Delfanti, M. Palazzo and M.
[3] IEC 62271-100 High-voltage switchgear and con- Caletti , Reliability and Economic Analysis of Different Power
trolgear Part 100: Alternating-current circuit-breakers. Station Layouts, Conference Proceedings of IEEE Power
Tech, Bologna, 2003.
[4] D. Braun and G. S. Kppl, Transient Recovery Volt-
ages During the Switching Under Out-of-Phase Conditions, [15] IEEE Power Engineering Society, Survey of Genera-
International Conference on Power Systems Transients, New tor Step-Up (GSU) Transformer Failures, Special Publication
Orleans, 2003. of the IEEE Power Engineering Society Transformers Commit-
tee, 1998.
[5] I. M. Canay, D. Braun and G. S. Kppl, Delayed cur-
rent zeros due to out-of-phase synchronizing, IEEE Transac- [16] CIGRE Working Group 13.06, Final Report of the
tions on Energy Conversion, Vol. 13, No. 2, June 1998. Second International Enquiry on High Voltage Circuit-Breaker
Failures and Defects in Service, CIGRE Publication No. 83,
[6] Terens, L.; Neudrfler, W.: Application Aspects of 1994.
the Static Frequency Converter System in Pumped Storage
Power Plants, Waterpower 95, Proceedings of the Interna- [17] M. H. J. Bollen, Literature Search for Reliability Data
tional Conference on Hydropower, San Francisco, July 25-28, of Components in Electric Distribution Networks, Eindhoven
1995. University of Technology, 1993.
[7] Trnka, R.: Die elektrische Bremsung grosser Maschi- [18] CIGRE Working Group 12.05, An International
nenstze, Elin-Zeitschrift, 1979, pp 29. Survey on Failures in Large Power Transformers in Service,
Electra, No. 88, 1983, pp 21-42.
[8] Electric Power Research Institute: Power Transformer
Tank Rupture: Risk Assessment and Mitigation, EPRI Report [19] CIGRE Working Group 23.02, Report on the Second
TR-104994, 1995. International Survey on High Voltage Gas Insulated Substa-
tions (GIS) Service Experience, Cigre Publication No. 150,
[9] D. Braun, L. Widenhorn and J. Ischi, Impact of the 2000.
electrical layout on the availability of a power plant, Proceed-
ings of the 11th CEPSI, Kuala Lumpur, 1996, pp. 330-336. [20] CLOCKWORK GROUP, A Users Guide to Power
Plant Workbench Version 1.1, Austin , 1999-2000.
[10] L. Widenhorn; K. Froehlich; B. Culver: Minimised
Outage Time of Power Plant Units after Step-up Transformer [21] I. M. Canay, Comparison of Generator Circuit-Breaker
Failure, Conference Proceedings of POWER GEN Asia 94, Stresses in Test Laboratory and Real Service Condition, IEEE
Hong Kong, 1994, pp.145-150. Transactions on Power Delivery, Vol. 16, No. 3, July 2001.
[11] B. Culver, K. Froelich and L. Widenhorn, Prevention [22] M. Palazzo, D. Braun and M. Delfanti, Investigation
of Tank Rupture of Faulted Power Transformers by Generator on the Occurrence of Delayed Current Zeros Phenomena in
Circuit Breakers, ETEP, Vol 6, January/February 1996, Power Stations and Related Stress Imposed on Generator
pp 39-45. Circuit-Breakers, International Conference on Power Systems
Transients, Delft, 2011.
ABB | 57
Notes
58 | ABB
Contact us