City of Durban Standard Engineering Specification Part C - Concrete Work
City of Durban Standard Engineering Specification Part C - Concrete Work
City of Durban Standard Engineering Specification Part C - Concrete Work
CITY OF DURBAN
PART "C"
CONCRETE WORK
CONTENTS OF PART "C" : CONCRETE WORK
(i)
Clause Heading Page No.
(ii)
PART "C" : CONCRETE WORK
C.1 SCOPE
C.2 INTERPRETATION
S.A.B.S. 455 - 1983 : Covered electrodes for the manual arc welding of
carbon and carbon manganese steel.
B.S. 4461 - 1984 : Cold worked steel bars for the reinforcement of
concrete.
B.S. 4482 - 1985 : Hard drawn mild steel wire for the reinforcement of
concrete.
C.3 MATERIALS
C.3.1 Materials
C.3.1.1 Cement
As far as is possible, only one particular brand and type shall be used for all
exposed and visible surfaces.
High Alumina Cement is to be used only when specified in Part "AA" : Project
Specification.
C.3.1.2 Water
Water shall be clean, fresh and free from injurious amounts of acids, alkalis,
organic matter or other substances either in suspension or solution which may
impair the strength or quality of the concrete. Water shall be obtained from the
City water supply where possible and shall be taken from any other source only
on the approval of the Engineer. Where there is reason to suspect the presence
of harmful impurities, the Engineer may require the Contractor to submit the
results of approved tests.
Fine and coarse aggregates shall conform with S.A.B.S. 1083 Table 1 for natural
sand and Table 5 for stone.
The coarse aggregates shall be natural unweathered crushed rock free from
adherent coatings and impurities and shall have an abrasion resistance of not
more than 40%.
C.3.1.4 Admixtures
The use of admixtures in concrete shall be subject to the written approval of the
Engineer. The admixture manufacturer shall provide proof of the experience and
field service using the formulation for which approval is requested. Admixtures
containing chlorides shall not be used.
C.3.1.5 Reinforcement
Unless otherwise specified steel reinforcement shall comply in all respects with
the requirements of the appropriate Standard Specifications.
Curing compounds shall conform with the American Society for Testing and
Materials Standard Specification C.309 'Liquid Membrane - Forming Compounds
for Curing Concrete'. Before using any proprietary curing compounds, the
Contractor shall supply the Engineer with the results of recent S.A.B.S. tests
carried out on the proposed compound.
C.3.1.7 Electrodes
All electrodes used for welding of mild steel structural members shall comply with
S.A.B.S. 455.
Bulk cement shall be stored in weather-proof bins or silos which will provide
protection from dampness and contamination and will minimise air set.
Reinforcement shall be stacked off the ground and, if required by the Engineer,
adequate protection against the weather shall be provided.
C.3.2.4 General
C.4 PLANT
C.4.1 General
All plant used for the work covered by this specification shall be approved by the
Engineer and shall be maintained in good working order. When considered
necessary by the Engineer, stand-by equipment shall be available at short
notice.
The Contractor shall ensure by regular examination, calibration and tests that the
batching system functions efficiently and accurately and that the hoppers and
cement containers are kept dry and clean. The batching plant shall be capable
of batching to an accuracy as specified in clause C.5.8.
In the case of an automatic plant the weighing scales shall be interlocked, so that
a new batch of concrete materials cannot be delivered until the weighing hoppers
have been completely emptied of the previous batch and the scales are in
balance.
The type and capacity of mixing machines shall be such that the rate of output
of concrete is suitable for the rate of concreting. The machine shall be capable
of producing a uniform distribution of the ingredients throughout the batch and
shall generally comply with the specification to which the manufacturer claims it
has been manufactured. When considered necessary by the Engineer, a spare
mixer shall be held in readiness to run on 15 minutes notice in case of
breakdown of the mixer.
C.4.4 Vibrators
C.5 CONSTRUCTION
Reinforcing bars shall be bent in such a manner that, unless otherwise specified,
all hooks and bends shall be in the same plane. Unless hot bending is
specifically authorised, all bars shall be bent cold. Bending shall be done slowly,
using a steady even pressure and avoiding any jerk or impact.
The placing of bars on fresh layers of concrete as work progresses will not be
permitted. No concrete shall be placed until the Engineer or his representative
has stated that he is satisfied that the reinforcement is correctly positioned as
shown on the drawings.
The minimum clear cover of concrete over all reinforcement shall be as indicated
in the following table unless otherwise specified on the drawings. Correct cover
shall be maintained by concrete spacers whose strength is not less than that of
the concrete specified. Suitable plastic spacers are permitted if approved by the
Engineer.
c) External walls 30
3. Beams
4. Piles
7. Footings
Note: In the above table 'd' refers to the largest reinforcing bar diameter.
All steel reinforcement shall, at the time the concrete is placed, be free from
loose rust, paint, scale, oil, salt or other coatings that may reduce or destroy
bond or accelerate the corrosion, and the surface of the steel shall not be pitted.
Where required by the Engineer or his representative, the reinforcement shall be
washed down immediately prior to concreting.
C.5.1.4 Welding
All welding of mild steel, where permitted, shall be in accordance with B.S.5135.
C.5.2 Formwork
Forms shall conform accurately to the shape, lines, levels and dimensions of
concrete as shown on the drawings.
The design of the formwork and supports shall be the responsibility of the
Contractor and shall be designed and detailed by a registered professional
engineer, if required by the special conditions of contract, and submitted for
approval by the Engineer.
Forms shall be so designed as to support their self mass, the load exerted by the
wet concrete and by the vibration, construction or other loads to which they be
subjected. Where the concrete is to be prestressed, the formwork shall be
constructed in such a manner that the elastic compressive shortening of the
concrete during the tensioning of the tendons is not unduly hindered. The
maximum deflection of any formwork component shall in no case exceed 1/360th
of its span. Form soffits shall be built to a camber corresponding to their
probable deflection under load so that the finished concrete shall conform
accurately with the lines and dimensions shown on the drawings.
Joints in forms shall be sufficiently tight to prevent leakage of mortar, and unless
otherwise specified, all joints shall be either horizontal or vertical.
The inner faces of forms shall be such as will impart the specified finish to the
concrete. Solid steel forms may be used for precast beams and circular
columns. Elsewhere, except where otherwise specified or the written consent
of the Engineer has been obtained, only wrought timber or approved shuttering
boards shall be used for forms in contact with exposed concrete faces.
All timber shall be free from holes, loose knots, cracks, splits, warps or other
defects likely to affect the strength or appearance of the finished structure.
Forms shall be so constructed that they may be readily stripped without jarring
or damaging the fresh concrete. The formwork for beams and slabs shall be
constructed so that the forms on the sides of the beams and on the soffits of
slabs can be removed independently of each other without disturbing the beam
soffits. Chamfer strips shall be provided on all exposed edges.
Wedges and clamps shall be used in preference to nails for securing the form
components and wire ties or tie bolts in reinforced concrete must be capable of
complete removal after use, except as otherwise specified. (See Clause
C.5.17.3).
In the cases where the accommodation of traffic during the construction period
is required, false work shall be designed to span underlying road systems with
a minimum headroom of 5,0 m, unless otherwise specified.
Form surfaces which are to be in contact with concrete shall be coated with non-
staining mould oil or other approved material. Where oil is used it shall be
applied before any reinforcement is placed in position.
All dirt, sawdust, chips and other foreign matter shall be removed from between
the forms before any concrete is deposited.
Forms shall not be removed until the concrete has attained sufficient strength to
supports its own weight and any loads which may be imposed upon it.
This shall be determined by means of cubes cast with the concrete and cured in
accordance with the S.A.B.S. 863. The removal shall be carried out under the
personal supervision of the Foreman only after the permission of the Engineer
has been obtained and in such a manner that the concrete is not jarred, vibrated
or otherwise damaged.
Where test cubes to determine stripping times are not made, the minimum
periods which shall elapse between the time of the placing of the concrete and
the time of removal of the forms shall, unless otherwise agreed with the
Engineer, be in accordance with the table hereunder, where each day covers a
full 24 hour period.
The table assumes that the member concerned is not subjected to any heavy
construction loads and that the total force to be supported is not more than half
the design load. Where heavier loads are to be carried, no stripping of soffits
shall be permitted until the concrete has attained its full strength. Any days
during which the average temperature was below 2/C shall be complete
disregarded.
Before re-use, all forms shall be reconditioned and all form surfaces which will
be in contact with concrete shall be thoroughly cleaned.
C.5.3.1 Classification
This is the finish left on a concrete surface after the removal of the forms and the
filling of all holes left by shuttering bolts and the repairs of all defects. The
surface shall be true and even, free from stone pockets, depressions and
projections.
Immediately after removal of the shuttering all defects shall be made good and
the rubbed finish shall be applied within three days as follows:
Before starting this work the concrete shall be kept thoroughly saturated with
water for a minimum period of 3 hours. Sufficient time shall have elapsed before
the wetting down to allow the mortar used in the pointing of the bolt holes and
defects to set properly. Surfaces to be finished shall be rubbed with a medium
coarse carborundum stone, using a small amount of mortar on its face. The
mortar shall consist of cement and fine sand mixed in the proportions used in the
concrete being finished. Rubbing shall be continued until all projections and
irregularities have been removed, all voids filled and a uniform surface has been
obtained. The paste produced by this rubbing shall be left in place for at least
five days. The surface shall be smoothed by being rubbed lightly with a fine
carbonrundum stone.
Off the form finishes require a very high standard in concrete quality, formwork
and technique. The intention is that no after treatment other than treatment of
bolt-holes (which should be placed with regularity and precision) should be
required. Forms shall be unblemished and panels regular. Joints shall be a
feature of the pattern and shall be handled with care. Reinforcement cover
blocks shall be of semi-spherical shape to minimise their appearance on the
finished surface.
(b) Boardmarked finishes shall be obtained from the use of timber planks
which shall be dressed and thicknessed unless otherwise specified. When
unplaned timber is specified, boards with a strong grain shall be mixed with
boards with a less pronounced gain and not grouped together. The
Engineer shall indicate if all boards are not to be horizontal and a
patterned panel effect is required.
(c) Special patterned finishes are required to reflect without blemish the
surface of patterned hardboard, rubber, thermoplastic or other lining as
specified.
The purpose of these finishes is to relive the uniform colour and texture of the
concrete by exposing the aggregate, which shall be the normal size concrete
aggregate except where otherwise specified. Attention is directed to the
necessity for allowing for the material to be removed and ensuring that the
requisite cover to reinforcement is maintained.
(a) Brushed and washed finishes are obtained by stripping and scrubbing the
concrete surface with a stiff wire brush. Unless forms can be stripped at
a very early age (approximately 16 hours at 20/C) this method cannot be
used unless the formwork has been treated with a retarding agent. Care
shall be taken to ensure that concrete is not deposited against the face of
treated forms which should be stripped as early as possible. Where
scrubbing with water is not effective, a solution of hydrochloric acid in the
proportion of 1 part of acid to 4 parts of water shall be thoroughly and
evenly scrubbed into the surface until the desired texture is obtained. The
complete surface shall then be neutralised by washing thoroughly with
water to which a small amount of ammonia has been added. When acid
is used, special precautions shall be taken to protect workmen, underlying
materials and persons passing.
(b) Tooled finishes may be carried out by the use of bush-hammers, light
mechanical chisels or other approved tools, preferably mechanically
operated. No tooling shall be done until the concrete has attained an age
of at least 14 days after casting when normal Portland cement has been
used and 7 days when rapid hardening cement has been used, or longer
as may be necessary to prevent the aggregate particles from being
dislodged.
The final finish shall show a surface of evenly distributed coarse aggregate
particles set in a matrix of mortar, each aggregate particle being in slight
relief. After the tooling has been completed, the surface so treated shall
be scrubbed down with a stiff brush and washed with water.
(c) Sand blasted finishes shall be obtained by sand blasting the thoroughly
cured concrete surface of the same ages as given under (b) Tooled
Finishes with hard sharp sand to produce an even, fine, clean surface in
which the mortar has been cut away, leaving the coarse aggregate
exposed.
It is essential that all surfaces on which applied finishes are to be used shall be
sound, clean and free of mould oil.
(a) Rendered finishes require a good key. Unless otherwise specified this
may be provided by flicking on to the previously soaked and still moist
surface of 1 part cement to 2 parts of sharp sand. This shall be left
untouched apart from curing.
(b) Painted finishes of the type specified shall be applied strictly in accordance
with the paint manufacturer's instructions. Very smooth surfaces shall be
acid washed, lightly sand blasted or rubbed with abrasive stones before
being painted. Painting shall be delayed as long as possible and two coats
applied unless otherwise specified.
C.5.4.1 Classification
Immediately after placing, the concrete shall be screeded with a true edged
wooden board working between forms or other guides set accurately to line and
level. No mortar shall be added and noticeable surface irregularities caused by
the displacement of coarse aggregate shall be made good by re-screeding after
removing or tamping down the interfering aggregate.
C.5.5.1 Supervision
During the whole or any time that the placing of concrete is being carried out, the
concreting operation shall be under the supervision of a suitably experienced
person.
C.5.5.2 Records
The Contractor shall keep a complete record of all concrete work which shall
cover the quantity and quality of concrete, the placing of reinforcing steel and the
results of all tests. A daily record shall also be kept of the progress of the work,
of the protection given to the concrete while curing, and the position of all
construction joints not shown on the drawings.
These records shall be available at all times during the progress of the work for
inspection by the Engineer or his representative.
C.5.6.1 Properties
The grades of concrete used in the various parts of the structure shall be as
indicated on the plans and specifications. The required properties of the various
grades are set out in the table hereunder and in other sections of this clause.
The main criterion for each grade shall be the 28 day compressive strength value
in the structural design and determined by means of cube tests made as
described in clause C.7.2.
* First figure indicates the minimum 28 day cube strength in MPa. Second
figure indicates the nominal maximum size of aggregate in mm.
Note: The maximum cement content for all grades of concrete shall not
exceed 450 kg per m without the express permission of the
Engineer which shall be given in writing.
The concrete shall be of such consistency and composition that it can be worked
readily into the corners and angles of forms and around the reinforcement
without permitting the materials to segregate.
The Contractor shall select the slumps he proposes to use within the permitted
maximum slumps set out in the table hereunder. The tolerance must, however,
comply with the requirements of clause C.7.3. With the approval of the
Engineer, the Contractor may adjust the proportions of cement and aggregate
as may be necessary to produce a mixture which will be easily placeable at all
times, due consideration being given to the methods of placing and compacting
used.
The Contractor shall be the party responsible for design of the mixes to achieve
the required properties with the materials which he proposes to use.
At the earliest possible stage in the contract the Contractor shall submit samples
of the aggregates which he proposes to use on the works. He shall also submit
for approval the proposed slumps and the proportions in which he proposes to
use the materials for each grade of concrete in each type of construction. In
addition he shall state the minimum cement/water ratio in terms of total water in
the mix for each grade of concrete, and the use of any admixtures.
No structural concrete shall be placed on the job until the Contractor has
satisfied the Engineer as to the suitability of the mixes concerned.
If the concrete produced fails to comply with the specification the Contractor shall
make adjustments in order to meet the specified requirements.
If during the progress of the work, the Contractor desires to use materials or
proportions other than those originally approved, or if in the opinion of the
Engineer or his representative, the materials from the sources originally
approved change in characteristics, he shall provide evidence satisfactory to the
Engineer that the new materials and/or new combination of materials will
produce concrete meeting the requirements of the specification and will not bring
about unacceptable changes in the appearance or other characteristics of the
structure.
When any changes are made in terms of this subclause, they shall be made at
the Contractor's expense, and no extra payment will be allowed by reason of
such change.
Before any ready-mixed concrete is used on the job, the Contractor shall furnish
the Engineer with a copy of his letter to the suppliers in which he specified -
When required the Contractor shall satisfy the Engineer that acceptable
alternative means of supplying concrete have been arranged to be brought into
operation in the event of disruption in the supply of concrete. In this connection,
the Engineer may require that the alternative means of supply shall commence
if the disruption in the supply of ready-mixed concrete has lasted for an elapsed
period in time of 1 hours.
The use of ready-mixed concretes shall in no way relieve the Contractor of any
of his responsibilities for providing concrete complying with the specifications.
C.5.8 Batching
C.5.8.1 Cement
C.5.8.2 Water
Dependable equipment shall be provided for measuring the mixing water either
by mass or by volume to an accuracy within 3 per cent.
The total quantity of water allowed for shall include the free water present in the
aggregates. The moisture content of the fine aggregate shall be determined at
the beginning and half way through each concreting shift, after showers of rain
or at such other intervals as may be required by the Engineer.
C.5.8.3 Aggregates
All measuring devices shall be maintained in good order and condition, and no
build-up of material on any part of the equipment shall be permitted.
C.5.9 Mixing
Mixing shall continue until there is a uniform distribution of the materials and the
mixture is uniform in colour. The minimum period of mixing shall be not less than
that recommended by the manufacturers at the recommended speed and not
more than 30 minutes. The entire contents of the mixer shall be removed from
the drum before the materials for the succeeding batch are loaded. Upon
cessation of mixing for any period exceeding 30 minutes, the mixer shall be
entirely cleaned out.
The first batch at the start of a concreting operation shall have approximately
25% of the coarse aggregate omitted. The cost of this batch shall be included
in the normal rates for concrete.
C.5.10 Transporting
Concrete shall be transported from the mixer to its final position on the work in
such a manner that segregation or loss of any of the ingredients or
contamination by foreign materials is prevented.
During transportation the concrete shall be protected from wind and sun; shall
be prevented from drying out or losing moisture and shall not be subjected to
excessive jarring or jolting. Drying out may be prevented by the provision of
covers and/or other protective devices.
Distribution of concrete by pumping shall be agreed with the Engineer and the
services of a concrete technologist shall be employed to design concrete mixes
for pumping. The design of the concrete shall be such as to minimise shrinkage
and creep.
C.5.11 Placing
The Contractor shall give the Engineer adequate notice of his intention to place
concrete. The concrete shall be placed within one hour from the time of
discharge from the mixer. Re-tempering by the addition of water or other
material will not be permitted. The forms to be filled shall be clean internally. All
excavations and other contract surfaces of an absorbent nature shall be left
damp, but no free water shall be permitted to remain on these surfaces.
Wherever possible the concrete shall be deposited vertically into its final position
to avoid segregation or displacement of reinforcement and other embedded
items.
When concreting closed circuits, work shall proceed from one or more points on
the periphery in opposite directions at the same time such that at completion of
the circuit the junction is formed with freshly-placed concrete. Each load shall
be placed against the face of the previously deposited concrete and not away
from it.
No concrete shall be placed if the air temperature in the shade is falling and is
below 8/C or is rising and is below 5/C. Concreting shall not commence if the
air temperature in the shade is above 35/C. The temperature of the concrete at
the point of placing shall not exceed 30/C unless otherwise specified.
C.5.12 Compaction
C.5.13 Curing
C.5.13.1 General
(c) covering with sand or other moisture retaining materials in contact with the
concrete surface and kept CONTINUOUSLY wet;
(d) sprayed with water and covered with waterproof paper, polyethylene
sheets or other impervious material free from rents and tears and lapping
by not less than 150 mm, the surface being resprayed whenever any sign
of drying out is evident;
Curing of concrete made from various types of cement shall continue for the
following minimum times from the date of casting:
C.5.14 Joints
Expansion and construction joints shall be located only where indicated on the
drawings. Any additional construction joints required by the Contractor shall be
approved by the Engineer. Where "off the form" finishes are specified, joints
shall be arranged to coincide with the edges of boards or panels wherever
possible.
Only those construction joints shown on the drawings shall be measured and
paid for. The Contractor shall allow in his pricing for any additional construction
joints that he may require.
The method of preparing the construction joints shall be one of the following:
Before a new batch of concrete is poured against the joint, all loose matter
on the surface shall be removed. The old concrete at the joint shall be in
a saturated, but surface-dry condition, with no puddles of free water laying
on the surface.
The procedure given in (a) above shall be followed, except that the old
surface shall be prepared and kept continuously wet for a minimum of 24
hours before the placing of the new concrete.
The procedure for preparing and cleaning given in (a) above shall be
followed before the steel reinforcement of the floor to be cast on the
columns is placed in position.
C.5.14.3 Waterstops
The cutting of any holes or chases in the concrete other than those shown on the
drawings or otherwise approved by the Engineer shall not be permitted.
Except with the written approval of the Engineer no pipes other than those shown
on the drawings shall be embedded in the concrete and the position of all
services to be embedded shall be checked by the Engineer or his representative
before concreting commences. The clear space between pipes of any kind
embedded in reinforced concrete and the clear space between such pipes and
reinforcement shall not at any point be less than 40 mm, or 5 mm plus the
maximum size of coarse aggregate, whichever is the greater.
C.5.16.1 General
Unless otherwise specified, no-fines concrete shall only be used for non-
structural work.
Aggregates for no-fines concrete shall be graded so that not more than 10 per
cent (10%) by mass of aggregate is retained on a sieve having 19 mm square
openings and not more than 5 per cent (5%) by mass passes a sieve having
9,5 mm square openings.
No-fines concrete shall be mixed with one part of cement to 9 parts of aggregate.
C.5.17.1 General
C.5.17.3 Patching
Where defects do not warrant the removal of defective concrete, one or more of
the following procedures shall be required by the Engineer:
(a) Where the structural strength might be affected and must be restored,
repairs may be effected by the application of either pneumatically-placed
mortar or of a mortar made of silica sand and an approved epoxy
formulation mixed and applied in accordance with the manufacturer's
recommendations.
(b) Where there are no fears as to structural strength, all defective material
shall be chipped away until a dense uniform surface of concrete exposing
solid coarse aggregate is obtained. Feathered edges shall be cut away to
form surfaces perpendicular to the concrete face. Seized shutter bolts
shall be cut back to at least 35 mm into the concrete. All loose material
shall be hosed away and the surface of the cavity shall be saturated with
water for at least 3 hours, after which a thin layer of neat cement mortar
shall be applied to the surface. The cavity then shall be filled with stiff
mortar mixed in the same proportions of cement to sand as that used in
the original concrete. The mortar shall be throughly tamped into place in
layers. The use of up to 30% white cement in place of the normal cement
may be required to reduce the darker appearance of a patch. An interval
of thirty minutes shall then elapse before a final surface tamping is given
to the patch, after which the surface shall be treated to resemble the
surrounding concrete as closely as possible. Board marks may be
reproduced by striking a suitable piece of timber held against the plastic
concrete. The patch shall be neat and workmanlike in appearance and
after completion it shall be kept wet over a period of at least three days.
C.6 TOLERANCES
(a) degree III accuracy for use where a high degree of accuracy is
unnecessary, e.g. mass foundations;
C.6.2 Reinforcement
Permissible Deviation in mm
Description Degree
III and II I
Spacing between two adjacent bars +/- 20 +/- 15
C.6.3 Formwork
Permissible Deviation in mm
Description Degree
III II I
Permissible Deviation in mm
Description Degree
III II I
Tolerances for bow or camber, twist, squareness and for silos and slip form
concrete, prestressed concrete and precast concrete will be stated in Part "AA" :
Project Specification wherever applicable.
C.7 TESTING
C.7.1 General
During the progress of construction the Engineer shall have the right to have the
undermentioned tests carried out on the concrete.
The Contractor shall co-operate in making such tests to the extent of allowing
free access to the work for the selection of samples, of the supply of the samples
themselves, of providing storage for specimens and of affording protection to the
specimens against injury or loss.
Within any period of the time during which one grade of concrete is being
continuously placed the Contractor shall at his own expense -
(a) provide the following number of sets of three standard metric 150 mm
metal cube moulds;
25 - 50 2
50 - 100 3
100 - 200 4
200 + 5 or as required
by the Engineer
(b) provide sufficient extra cube moulds for 3 day, 7 day, etc., crushing tests
to be made as he so requires for his own purposes i.e. for shutter
stripping, post-stressing cables, etc;
(c) make and cure all cubes on site under the supervision of the Engineer, in
accordance with the S.A.B.S. Method 863;
(d) transport all cubes to the required place of testing i.e. Durban Corporation
Materials Testing Soils Laboratory or S.A.B.S. Laboratory as directed by
the Engineer, not sooner than the last working day prior to the date of test;
The test results from any single source shall satisfy the appropriate criteria given
below -
(a) no test result shall fall below the specified strength by more than 3 MPa;
(b) the average of any group of 3 consecutive test results shall exceed the
specified strength by not less than 2 MPa.
Each class and source of concrete, as well as each major portion of a structure
or type of structure as directed, shall be dealt with separately when assessing
compliance with clause C.7.2.
Materials
Slump as per Table C.5.6.2 and carried out as specified in S.A.B.S. 878.
(a) when the specified slump does not exceed 75 mm, the average of the two
tests is within 12 mm of the specified slump.
(b) when the specified slump exceeds 75 mm the average of the two tests is
within 25 mm of the specified slump.
Cover Tests
Where the Engineer or his representative has reason to doubt whether the
concrete cover over the reinforcement is not in accordance with the requirements
of clause C.5.1.3, the cover shall be tested with a cover meter. If necessary, the
Engineer or his representative shall then indicate to the Contractor where he
must expose the reinfrocement to prove the depth of cover.
Should the strength of test specimens made and tested in accordance with
clause C.7.2 fail to meet the requirements of this specification, the Engineer may
order -
(a) that the materials or proportions of the remainder of the grade of concrete
concerned shall be varied so that the strength is not less than the required
strength;
(b) that test cores shall be drilled from the concrete and tested in accordance
with the S.A.B.S. Method 865 to determine the estimated actual strength
and the estimated potential strength of the concrete.
If the results of the core tests show that the concrete meets the test
requirements, the structure shall be accepted.
If the core tests show that the concrete does not meet the strength requirements,
an appropriate full scale load test, as determined by the Engineer, may be
applied on the structure containing the defective concrete.
If load tests are, in the opinion of the Engineer, impracticable, or where the
portions of the structure subjected to such test fail to pass the test specified, he
shall have the right to require strengthening or replacement of the portions of the
structure concerned.
The costs of all tests required by the Engineer or his representative shall be
borne by the Council except that costs of tests as set out hereunder shall be
borne by the Contractor -
(b) all tests as may be made necessary by reason of the provisions of clause
C.5.6.5;
(c) such tests, including concrete coring and load tests, as may in the opinion
of the Engineer be made necessary by failure on the part of the Contractor
to meet the requirements of this specification.
C.8.1 Concrete
The quantities for concrete in the schedule of quantities represent the net
amount of concrete cast into the forms and the prices shall include for all
necessary materials, labour and use of plant and for compacting and bringing to
the required finish, for any protective works against rain and hot weather, curing
and for hacking, cleaning and bonding.
Unless specifically indicated to the contrary, all horizontal concrete surfaces are
to be finished with a wooden float.
The measurement and payment for each ton (1 000 kg) of reinforcement is to
include for all supply, cutting, bending, hooked ends and binding at laps and
intersections with and including annealed wire of suitable gauge and hoisting and
maintaining in position in an approved manner whilst concreting. The weights
given are net and do not include for rolling margins or binding wire for which
allowance must be made in pricing.
The quantities for shuttering and formwork are measured by the square metre
of surface area of concrete work in contact with the forms and prices are to
include for all necessary falsework materials, labour and plant used for the
erection thereof and shall include keyed joints and chamfers.