Check List For Chilled Water Secondary Pump: Sl. No Description Remarks
Check List For Chilled Water Secondary Pump: Sl. No Description Remarks
13 Ensure easy operation of suction valve opening and closing,if so apply lubriction.
Check for any cable colour change in motor cable terminations and Tightness of the
14
termination and if so rectify.
Check for any cable colour change in VFD starter panel and ensure the tightness of all
15
the electrical connection.
17 Remove the Motor fan guard and clean the fan with a clean brush.
18 Clean the pump and insulated pipe lines externally with cotton cloth.
Switch OFF the power supply and ensure pump shaft rotates freely by hand and Switch
19
ON the Power Supply
20 Clean pump suction strainer.
Check the Over load relay setting.(It should be setted as ).Test and Ensure the O/L
21
operation by pressing the "Test" Button in O/L Relay.
22 Check and Record the Motor load current and Winding resistance Value