Structure (Start To Finish)
Structure (Start To Finish)
29. De-shuttering started after achieving required strength as per IS requirements. (With
temporary supports to beams/slabs).
30. Hacking to be done on concrete surfaces for plastering and slurry coat to be applied to
concrete surface at junction of block workand concrete.
31. Marking course of block work is done and is checked by Quality Engineer.
32. Block work done using templates for doors and windows openings.
33. Meter marking is done on the block work with coloured line dori
36. Ceiling plastering is done. (PVC rings are provided for the electrical junction boxes).
37. Button marking for the wall plaster is done.
38. Electrical chasing, conduiting and box fixing including DB box fixing and packing are
done.
39. Window grills and balcony railings are fixed.
40. Wall plastering is completed including the toilets. Meter marking is again done on the
surface as explained earlier.
41. Plumbing chasing, pipe fixing in toilets/kitchen is completed and tested and packing is
done
56. Texture and first coat paint for balconies and utilities are done.