Pre-Engineered Construction Analysis and Design of Portal Frame
Pre-Engineered Construction Analysis and Design of Portal Frame
Pre-Engineered Construction Analysis and Design of Portal Frame
ISSN: 2278-0181
Vol. 4 Issue 05, May-2015
without use of any brick work has inspired us to analyse ii. If the shed is open from all sides i.e. no brick wall
construction of portal frames made with pre-engineered enclosure is required then complete steel columns as
construction components. well roof is viable solution.
STATEMENT OF PROBLEM iii. Pre-engineered concept of structure is nothing but
Portal Frame with high roof hall is designed with following steel building in which excess steel is avoided by
specifications: tapering the section as per bending moment
1. Portal beam span=15m Fig. (2) requirement.
2. Portal column height=6m above plinth level iv. If the structure is to be planned away from city areas,
3. Central height= 9 m above plinth where wind pressure can be predominant and the
4. Bay spacing=5 m c/c structure need to be enclosed with brick wall then
structure is designed with column with R.C.C and
GABLED ROOF G.C.I.Sheets Roofing
beams and roof with steel.
3m
5m c/c Therefore our study is extended to above 4 type of
pre-engineered portal frames construction.
The design problem of portal frame stated above has been
analyzed with respect to following considerations:
PORTAL FRAME FOR HALL 15M X 30M
As 30m
a first step of analysis the portal frame for above problem
Portal Column 6m is designed by conventional design procedure for following
construction materials and technology:
1 Steel section for Columns & Beams or R.C.C. Columns &
Beams to support G.C.I. sheets Roof
15m
15m
3m
5m c/c
CONCLUSION -
Cost Comparison of Portal design – The literature survey shows that construction of high roof
* Roofing materials its section members are same for all type buildings like Cinema hall, studios, a mol etc. Portal Frames is
of portal designs consider for the hall best solution to construct large span buildings. The top floor
* Footing also in all case be same. It is designed as in case of may be sheet roofing and there may be intermediate floors
R.C.C. Portal and adopted same for all types of construction with R.C.C. slab and partition brick walls. The finding of this
i.e. steel and pre-engineered type. research study clearly reveals that in such buildings R.C.C.
Hence cost comparison is meaning full w.r.t.to portals column portals with tapered section will be economical and easy in
and beam section size and their materials. construction because the tapering can be achieved by wooden
* Rate analysis for different construction materials is given in form work. Many researchers have worked on design of
Appendix – I: (A) Steel Sections, (B) Reinforced Cement portals with steel sections and specially recommend tapered
Concrete Portals section for economical reasons. But the availability of
* Construction cost analysis for R.C.C. portal is given in required tapered steel section is difficult and costly affairs.
Appendix. The cost is found Rs. 19925 per m3 Hence for pre-engineered construction works R.C.C. portals
* Cost of steel section in case of conventional type steel will be an ideal solution of high roof buildings.
section is Rs. 120 per Kg.
* Cost of steel sections in case of Pre-engineered components REFERENCES -
is Rs. 200 per Kg [1] Subramanian. N, “Pre- Engineered buildings selection of framing system,
The result is tabulated from table 1 to 6. The bar chart roofing and wall materials” The Master builder, July, 2008, pp 48-62.
representation clearly shows that portal with tapered R.C.C. [2] Meera C.M, “Pre-Engineered Building Design of an Industrial
Warehouse”, International journal of Engineering Sciences and Emerging
section is most economical. It costs only 35000 to build one Technologies, Volume 5, Issue 2, June – 2013, pp: 75- 82.
[3] Syed Firoz et al, “Design concept of Pre Engineered Building”,
International Journal of Engineering Research and Applications (IJERA),
Vol. 2, Issue 2, April 2012, pp.267-272.
[4]. B.N. Dutta”Estimating & costing”.
[5] Video on” house construction with plastic bottles by Samarpan
Foundation”.
No Sec
. Particulars modulus Kg./m Amount
1m
1 ISMB Section 250 length 37.5 80 material
1m
2 ISMB Section 200 length 25.2 80 cost
1m
3 ISMB Section 150 length 14.5 80
4 Labour Cost
i) Conventional section 30% 24
Total 104
ii) Pre-engineered stepped section 50% 40
Total 120