Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

Design of Concrete Gravity Dam Sections

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 23

DESIGN OF CONCRETE GRAVITY DAM

SECTIONS

Fundamentally a gravity dam should satisfy the following criteria:


1. It shall be safe against overturning at any horizontal position within the dam at the
contact with the foundation or within the foundation.
2. It should be safe against sliding at any horizontal plane within the dam, at the
contact with the foundation or along any geological feature within the foundation.
3. The section should be so proportional that the allowable stresses in both the concrete
and the foundation should not exceed.
Safety of the dam structure is to be checked against possible loadings, which may be
classified as primary, secondary or exceptional. The classification is made in terms of
the applicability and/or for the relative importance of the load.
1. Primary loads are identified as universally applicable and of prime importance of the
load.
2. Secondary loads are generally discretionary and of lesser magnitude like sediment
load or thermal stresses due to mass concreting.
3. Exceptional loads are designed on the basis of limited general applicability or having
low probability of occurrence like inertial loads associated with seismic activity.

Technically a concrete gravity dam derives its stability from the force of gravity of the
materials in the section and hence the name. The gravity dam has sufficient weight so
as to withstand the forces and the overturning moment caused by the water impounded
in the reservoir behind it. It transfers the loads to the foundations by cantilever action
and hence good foundations are pre requisite for the gravity dam.
The forces that give stability to the dam include:
1. Weight of the dam
2. Thrust of the tail water
The forces that try to destabilize the dam include:
1. Reservoir water pressure
2. Uplift
3. Forces due to waves in the reservoir
4. Ice pressure
5. Temperature stresses
6. Silt pressure
7. Seismic forces
8. Wind pressure
The forces to be resisted by a gravity dam fall into two categories as given below:
1. Forces, such as weight of the dam and water pressure which are directly
calculated from the unit weight of materials and properties of fluid pressure and
2. Forces such as uplift, earthquake loads ,silt pressure and ice pressure which are
assumed only on the basis of assumptions of varying degree of reliability. In fact to
evaluate this category of forces, special care has to be taken and reliance placed on
available data, experience and judgement.

Figure 23 shows the position and direction of the various forces expected in a concrete
gravity dam. Forces like temperature stresses and wind pressure have not been shown. Ice
pressures being uncommon in Indian context have been omitted.
For consideration of stability of a concrete dam, the following assumptions are made:
1. That the dam is composed of individual transverse vertical elements each of which
carries its load to the foundation without transfer of load from or to adjacent elements.
However for convenience, the stability analysis is commonly carried out for the whole
block.
2. That the vertical stress varies linearly from upstream face to the downstream face
on any horizontal section.
The Bureau of Indian Standards code IS 6512-1984 “Criteria for design of solid gravity
dams” recommends that a gravity dam should be designed for the most adverse load
condition

1.0 LOADINGS FOR CONCRETE GRAVITY DAMS

The significant loadings on a concrete gravity dam include the self-weight or dead load
of the dam, the water pressure from the reservoir, and the uplift pressure from the
foundation. There are other loadings, which either occur intermittently, like earthquake
forces, or are smaller in magnitude, like the pressure exerted by the waves generated in
the reservoir that his the upstream of the dam face. These loadings are explained in the
following section.

Dead load
The dead load comprises of the weight of the concrete structure of the dam body in
addition to pier gates and bridges, if any over the piers. The density of concrete may be
considered as 2400 kg/m³. Since the cross section of a dam usually would not be
simple, the analysis may be carried out by dividing the section into several triangles and
rectangles and the dead load (self weight) of each of these sections (considering unit
width or the block width) computed separately and then added up. For finding out the
moment of the dead load (required for calculating stresses), the moments due to the
separate sub–parts may be calculated individually and then summed up.

Water pressure on dam


The pressure due to water in the reservoir and that of the tailwater acting on vertical
planes on the upstream and downstream side of the dam respectively may be calculated
by the law of hydrostatics. Thus, the pressure at any depth h is given by γh kN/m² acting
normal to the surface. When the dam has a sloping upstream face, the water pressure
can be resolved into its horizontal and vertical componenets, the vertical component being
given by the weight of the water prism on the upstream face and acts vertically downward
through the centre of gravity of the water area supported on the dam face.
In spillway section, when the gates are closed, the water pressure can be worked out in
the same manner as for non–overflow sections except for vertical load of water on the
dam itself. During overflow, the top portion of the pressure triangle gets truncated and a
trapezium of pressure acts (Figure 24).

The pressure due to tailwater is obtained in a similar manner as for the upstream
reservoir water.
In case of low overflow dams, the dynamic effect of the velocity of approach may be
significant and deserve consideration.

Uplift pressures
Uplift forces occur as internal pressure in pores, cracks and seams within the body of
the dam, at the contact between the dam and its foundation and within the foundation.
The recent trends for evaluating uplift forces is based on the phenomenon of seepage
through permeable material. Water under pressure enters the pores and fissures of the
foundation material and joints in the dam. The uplift is supposed to act on the whole
width plane, that is being considered, either at the base or at any position within the
dam. The uplift pressure on the upstream end of the considered horizontal plane is
taken as γhu where hu is the depth of water above the plane. On the downstream the
value is γhd where hd is again the depth of water above the plane.
Silt pressure
The weight and the pressure of the submerged silt are to be considered in addition to
weight and pressure of water. The weight of the silt acts vertically on the slope and
pressure horizontally, in a similar fashion to the corresponding forces due to water. It is
recommended that the submerged density of silt for calculating horizontal pressure may
be taken as 1360 kg/m³.

Earthquake (seismic) forces


Earthquake or seismic activity is associated with complex oscillating patterns of
acceleration and ground motions, which generate transient dynamic loads due to inertia
of the dam and the retained body of water. Horizontal and vertical accelerations are not
equal, the former being of greater intensity.
The earthquake acceleration is usually designated as a fraction of the acceleration due to
gravity and is expressed as α⋅g, where α is the Seismic Coefficient. The seismic
coefficient depends on various factors, like the intensity of the earthquake, the part or
zone of the country in which the structure is located, the elasticity of the material of the
dam and its foundation, etc. For the purpose of determining the value of the seismic
coefficient which has to be adopted in the design of a dam, India has been divided into
five seismic zones, depending upon the severity of the earthquakes which may occur in
different places. A map showing these zones is given in the Bureau of Indian Standards
code IS: 1893-2002 (Part-1).

Wave pressure
The reservoir behind a dam is prone to generation of waves produced by the shearing
action of wind blowing over the surface. Of course, the pressure of the waves against
massive dams of appreciable height is not of much consequence. The height of wave is
generally more important in determination of the free board requirements of dams to
prevent overtopping of the dam crest by wave splash. The force and dimensions of
waves depend mainly on the extent and dimensions of waves depend mainly on the
extent and configuration of the surface area of the reservoir, the depth of the reservoir,
and the velocity of the wind. The procedure to workout the height of waves generated,
and consequently derive the safe free board, may be done according to the method
described in IS: 6512-1984 “Criteria for design of solid gravity dams”. However, since
it is a bit involved, a simpler method is prescribed as that given by the Stevenson formula
(Davis and Sorenson 1969).

(9)
Where
Hw = Height of wave, crest to trough, in m
F = Fetch of the reservoir, that is, the longest straight distance of the reservoir
from the dam up to the farthest point of the reservoir.
When the fetch exceeds 20Km, the above formula can be approximated as

Since the height of the generated waves must be related to the wind velocity, the
original formula has been modified to

Where V = wind speed along the fetch, in km/h


Stevenson’s approximate formula is applicable for wind speeds of about 100km/hour,
which is a reasonable figure for many locations. It is conservative for low wind speeds
but under estimates waves for high wind speeds.
The pressure intensity due to waves (Pw, in KN/m2) is given by the following expression

Where Hw is the height of wave in m. and occurs at 1/8Hw above the still water level
(Figure36).
The total wave pressure Pw per unit length (in KN/m) of the dam is given by the area of
the triangle 1-2-3 as given in Figure 36, and is given as
The centre of application is at a height of 0.375Hw above the still water level.

Free board
Free board is the vertical distance between the top of the dam and the sill water level.
IS:6512-1984 recommends that the free board shall be wind set-up plus 4/3 times wave
height above normal pool elevation or above maximum reservoir level corresponding to
design flood, whichever gives higher crest elevation. Wind set-up is the shear
displacement of water towards one end of a reservoir by wind blowing continuously – or
in repeated regular gusts – from one direction. The Zuider Zee formula (Thomas, 1976)
and recommended by IS: 6512-1984 may be used as a guide for the estimation of set-
up(S):

Where
S = Wind set-up, in
m

V = Velocity of wind over water in m/s F


= Fetch, in km
D = Average depth of reservoir, in m, along maximum fetch
A = Angle of wind to fetch, may be taken as zero degrees for maximum set-up
K = A constant, specified as about 62000
Set-up of the reservoir will depend upon the period of time over which the wind blows,
that is, at least 1hour, for a fetch of 3km or 3hours for a fetch of 20km. On a 80km fetch,
a wind speed of 80 km/hour must last for at least 4hours, whereas for a wind speed of
40km/hour it must last around 8hours for maximum set-up.
The free-board shall not be less than 1.0m above Maximum Water Level (MWL)
corresponding to the design flood. If design flood is not same as Probable Maximum
Flood (PMF), then the top of the dam shall not be lower than MWL corresponding to
PMF.

2.0 STABILITY ANALYSIS OF GRAVITY DAMS

The stability analysis of gravity dams may be carried out by various methods, of which
the gravity method is described here. In this method, the dam is considered to be made
up of a number of vertical cantilevers which act independently for each other. The
resultant of all horizontal and vertical forces including uplift should be balanced by an
equal and opposite reaction at the foundation consisting of the total vertical reaction and
the total horizontal shear and friction at the base and the resisting shear and friction of
the passive wedge, if any. For the dam to be in static equilibrium, the location of this
force is such that the summation of moments is equal to zero. The distribution of the
vertical reaction is assumed as trapezoidal for convenience only. Otherwise, the problem
of determining the actual stress distribution at the base of a dam is complicated by the
horizontal reaction, internal stress relations, and other theoretical considerations.
Moreover, variation of foundation materials with depth, cracks and fissures which affect
the resistance of the foundation also make the problem more complex. The internal
stresses and foundation pressures should be computed both with and without uplift to
determine the worst condition.
The stability analysis of a dam section is carried out to check the safety with regard to
 Rotation and overturning
 Translation and sliding
 Overstress and material failure

Stability against overturning


Before a gravity dam can overturn physically, there may be other types of failures, such
as cracking of the upstream material due to tension, increase in uplift, crushing of the
toe material and sliding. However, the check against overturning is made to be sure that
the total stabilizing moments weigh out the de-stabilizing moments. The factor of safety
against overturning may be taken as 1.5. As such, a gravity dam is considered safe also
from the point of view of overturning if there is no tension on the upstream face.

Stability against sliding


Many of the loads on the dam act horizontally, like water pressure, horizontal
earthquake forces, etc. These forces have to be resisted by frictional or shearing forces
along horizontal or nearly-horizontal seams in foundation. The stability of a dam against
sliding is evaluated by comparing the minimum total available resistance along the
critical path of sliding (that is, along that plane or combination of plans which mobilizes
the least resistance to sliding) to the total magnitude of the forces tending to induce
sliding.

Failure against overstressing


A dam may fail if any of its part is overstressed and hence the stresses in any part of
the dam must not exceed the allowable working stress of concrete. In order to ensure
the safety of a concrete gravity dam against this sort of failure, the strength of concrete
shall be such that it is more than the stresses anticipated in the structure by a safe
margin. The maximum compressive stresses occur at heel (mostly during reservoir
empty condition) or at toe (at reservoir full condition) and on planes normal to the face
of the dam. The strength of concrete and masonary varies with age, the kind of cement
and other ingredients and their proportions in the work can be determined only by
experiment.
The calculation of the stresses in the body of a gravity dam follows from the basics of
elastic theory, which is applied in a two-dimensional vertical plane, and assuming the
block of the dam to be a cantilever in the vertical plane attached to the foundation.
CONSTRUCTION SEQUENCE OF CONCRETE GRAVITY DAM

1.0 RIVER DIVERSION


Regardless of the type of dam, whether concrete or embankment types, it is necessary to
de-water the site for final geological inspection, for foundation improvement and for
the construction of the first stage of the dam. In order to carry out the above works the
river has to be diverted temporarily. The magnitude, method and cost of river diversion
will depend upon the cross- section of the valley, the bed material in the river, the type
of dam, the expected hydrological conditions during the time required to complete the
dam construction works, and finally upon the consequences of failure of any part of the
temporary works.
For concrete dams, it may be necessary to divert the river during the first phase of the
construction of the dam. Once this is complete, the river may be allowed to overtop the
dam and flow without causing serious damages to the structure or its foundation. For
concrete dams, sluice openings are left open in the first stage of concreting and the
higher stages constructed. If the second stage outlets are too small for the flood to
pass, they would be submerged after the whole works
The Bureau of Indian standards code IS 10084 (part 2) -1994 “Design of diversion
works – criteria” describes the design criteria for diversion channel and open cut or
conduit in the body of the dam.

At sites where diversion of flow through tunnels or close conduits is not possible (due to
topographical considerations) or proves to be uneconomical, diversion through
excavated channels called diversion channels is effected. Diversion channels are often
classified according to the type of diversion namely, single stage or multiple stage
diversion scheme. In the former which is more suitable for narrow valleys, the same set
of diversion channel and coffer dams is utilised throughout the period of construction. In
the latter, which is generally suitable for wide valleys, the channels and coffer dams are
shifted from place to place in accordance with phasing of the work. A more useful
classification, however, is based on the type of the dam to be constructed namely
diversion channel for masonry or concrete dams and that for the earth or rockfill dams.
The following paragraphs taken from Bureau of Indian Standards code IS: 10084 (Part
2) – 1994 “Design of diversion works – criteria” provides criteria for diversion channels
for dam construction.
2.0 PREPARATION OF FOUNDATION FOR DAM CONSTRUCTION

A concrete gravity dam intended to be constructed across a river valley would usually
be laid on the hard rock foundation below the normal river overburden which consists of
sand, loose rocks and boulders. however at any foundation level the hard rock
foundation, again, may not always be completely satisfactory all along the proposed
foundation and abutment area, since locally there may be cracks and joints, some of
these (called seams) being filed with poor quality crushed rock. Hence before the
concreting takes place the entire foundation area is checked and in most cases
strengthened artificially such that it is able to sustain the loads that would be imposed
by the dam and the reservoir water, and the effect of water seeping into the foundations
under pressure from the reservoir.
Generally the quality of foundations for a gravity dam will improve with depth of
excavation. Frequently the course of the river has been determined by geological faults
or weaknesses. In a foundation of igneous rock, any fault or seam should be cleaned
out and backfilled with concrete. A plug of concrete of depth twice the width of the seam
would usually be adequate for structural support of the dam, so that depth of excavation
will, on most occasions depend upon the nature of infilling material, the shape of the
excavated zone and the depth of cutoff necessary to ensure a acceptable hydraulic
gradient after the reservoir is filled.

Improvement of the foundation for a dam may be effected by the following major ways:
1. Excavation of seams of decayed or weak rock by tunneling and backfilling with
concrete.
2. Excavation of weak rock zones by mining methods from shafts sunk to the zone and
backfilling the entire excavated region with concrete.
3. Excavation for and making a subterranean concrete cutoff walls across leakage
channels in the dam foundation where the where the water channels are too large or too
wet for mining or grouting
4. Grouting the foundation to increase its strength and to render it impervious.

Grouting of the foundation of the dam to consolidate the entire foundation rock and
consequently increasing its bearing strength is done by a method that is referred to as
consolidation grouting. This is a low pressure grouting for which shallow holes are
drilled through the foundation rock in a grid pattern. These holes are drilled to a depth
ranging from 3 to 6 m. Prior to the commencement of the grouting operation, the holes
are thoroughly washed with alternate use of water and compressed air to remove all
loose material and drill cuttings. The grout hole are then tested with water under pressure
to obtain an idea of the tightness of the hole which is necessary to decide the consistency
of the grout to be used and to locate the seams or other openings in the rock which are
to be plugged . The grout is then injected with these holes at relatively low pressure
which is usually less than about 390 KN/m². Since this is a low pressure grouting it is
accomplished before any concrete for the dam is laid. This grouting results in the
consolidation of the foundation into more or less monolithic rock by bonding together
the jointed or shattered rocks. Some of the recommendations for grouting under
pressure in rock foundations have been taken from Bureau of Indian Standards code IS:
6066 – 1994 “Pressure grouting of rock foundations in river valley projects –
recommendations” have been presented in the following paragraphs.

Methods of rock grouting


Rock grouting consists essentially of drilling a series of grout holes in rock and injecting
grout under pressure, which eventually sets in the openings and voids in the rock. The
drilling and grouting operations can be carried out either to the full depth in one operation
or in successive depths either by stage grouting or packet grouting. Grouting in the
valley should proceed from river bed to the abutments. There are two broad methods
for grouting: Full depth grouting and stage grouting.
In the full depth method each hole is drilled to the full desired depth, washed, pressure
tested and grouted in one operation. This method is usually limited to short holes 5m or
less in depth or holes up to 10 m that have only small cracks and joints with no risk of
surface leakage. In deep bore holes high grouting pressures have to be used for proper
penetration of grout at an economical spacing of holes. As full depth grouting involves
the risk of disturbance in the upper elevation it is not generally considered for grouting
deep holes. For grouting in heterogeneous strata, where the nature of rock
discontinuities is subject to large variations in relation to the depth, full depth grouting is
not recommended and stage grouting is preferred to packer grouting in such cases.
Stage grouting is done by drilling the holes to a predetermined depth and grouting this
initial depth at an appropriate pressure to its final set (within 2 to 4 hours) deepened for
the next stage. Alternatively the grout is allowed to harden and re drilling is carried out
through the hardened grout and the hole extension to the next stage. In another procedure
called the one stage re drilled method, which is sometimes used grout is washed out
within a small depth of the top of the stage being grouted and only one stage is re
drilled for proceeding to the next stage. In each of procedures the cycle of grouting-
drilling-washing-re drilling is repeated until the required depth of the hole is reached.
General criteria for size and depth of grout holes
The pattern and depth of holes is governed primarily by the design requirements and
the nature of the rock. When the purpose is consolidation, the holes are arranged in a
regular pattern over the entire surface area required to be strengthened and the depth is
determined by the extent of broken rock as well as the structural requirements regarding
the deformability and strength of the foundation. When the purpose is
impermeablisation the grout holes are arranged in a series of lines to form a curtain
approximately perpendicular to the direction of the seepage. The depth of holes is
dependent on design consideration as also on the depth of pervious rock and
configuration of zones of relatively impervious strata.
The size of grout holes is generally less important than the cost of drilling holes and the
control of the inclination. For grouting with cement, 38 mm holes are used. The advantage
gained by drilling large holes does not often justify the increase in drilling costs. In
long holes the diameter at the top of the hole may have to be larger than the final
diameter at the bottom of the hole to facilitate telescoping or allow for the wear of the
bit.

Patterns of holes for curtain grouting


Single lines grout curtains are effective only in rocks having a fairly regular network of
discontinuities with reasonably uniform size of openings. In such cases a curtain of
adequate width can be achieved by grouting a single line of holes. In massive rocks,
with fine fissures uplift control is primarily obtained by drainage and the grout curtain is
only used as a supplementary measure to avoid concentration of seepage which may
exceed the capacity of the drainage system. Single line curtain may serve this limited
objective in comparatively tight rock formations.

In single line curtains (Figure 43), it is customary to drill a widely spaced system of
primary holes, subsequentially followed by secondary and tertiary holes at a
progressively small spacing. The usual practice is to split the spacing from primary to
the secondary to the tertiary phase. One of the criteria for deciding on the primary
spacing is the length of expected intercommunication of grout between holes. The initial
spacing usually varies from 6m to 12 m but the choice of spacing should be based on
geological conditions and on experience. At every phase of the grouting operation, the
results of percolation tests and ground absorption data should be compared with the
previous set of holes in order to decide whether a further splitting of the spacing of holes
in worthwhile. When no significant improvement is noticed either in terms of decrease of
the grout absorption or water percolation, careful review should be made of rock features,
the nature of the rock and its relation to the pattern of holes. Sometimes it may be more
advantageous to drill another line of holes at a different angle and orientation than to
split the spacing further. Spacing below 1 meter are rarely necessary and the
requirement of a spacing closer than 1 meter often indicates an unsuitable orientation
and inclination of holes. Possibly multiple line curtains may be necessary. If the area is
too limited, the setting time of the grout becomes important since it is not desirable to
drill close to a freshly grouted hole. Before pressure grouting is started, drilling of all the
holes should be completed within a distance of 20 m of the hole to be grouted.

Depending upon initial investigation and strata conditions, the spacing of primary hole
treatment should be decided. If the primary holes were spaced more than 6 m apart
secondary holes should be drilled and grouted. On completion of primary holes spaced
closer than 6m or secondary holes (when the primary holes are spaced more than 6 m),
should the percolation tests carried out in a few test holes indicate that further grouting
of the area is necessary, secondary, or tertiary treatment as the case may be, should be
carried out systematically thereafter in the whole area or in the particular section where
the rock conditions are bad. Similarly tertiary holes should be taken over the whole area
or the full length of the section which requires the treatment.
In addition to the systematic grouting of primary Secondary or tertiary and subsequent
holes it may be necessary to drill and grout additional holes for treatment of peculiar
geological feature such as faults, sheared zones and weathered rock seams.

Pattern of holes for consolidation grouting


The choice of pattern of holes, for consolidation grouting depends on whether it is
necessary to wash and jet the hole systematically. When washing has to be carried out a
hexagonal pattern (Figure 44) would be preferred as this admits for flow reversal. When
systematic washing and jetting is carried out to remove all soft material in seams it is
generally not necessary to use a primary and secondary system of holes.

When it is desirable to test the efficacy of consolidation grouting by comparing the grout
absorption in primary and secondary holes a rectangular or square pattern (Figure 44) of
holes would be preferred. This is generally the case when the joints are irregular and
relatively free from in-filling or it is not necessary to remove the material filling the
joints.

Grouting mixture
Rock grouting is normally performed with a mixture of cement and water with or without
additives. The cement should be ordinary Portland, Portland Pozzolana, Portland slag,
Supersulphated or Sulphate-resisting Portland. The solid materials which may be used
as additive to the grout mixture could be Paxxolanas (such as fly ash and calcined
shade), fine sand or other fine non-cementeitious materials like clay and silt. While
using additives constant field checks and review should be undertaken to achieve the
desired results in respect to permeability and strength. Admixtures when added in small
quantities to the grout mixture impact certain desirable characteristics like delaying or
hastening setting time and increasing the workability.

Drilling equipment
The entire grouting operation is carried out by first drilling and then injecting the grout
under pressure. The various types of drilling equipments can be grouped as under

A. Precursive Drilling equipment


a) Standard drifter or wagon drill
b) Dom the hole drilling equipment, and
c) Overburden drilling equipment

B. Rotary drilling equipment with suitable drive, that is hydraulic, electric, diesel or
compressed air

Precussive drilling methods are generally more economical in all kind of rocks. For deep
rocks it may be advantageous to use overburden drilling equipment. By virtue of the
greater rigidity of the casing tube combined with the drill rods, better control on
inclination of holes can generally be achieved in the overburden drilling equipment.
Down the hole hammer is also capable of maintaining a better control on the inclination.
However, the hammer may get clogged when the drill cuttings form slush in form
saturated strata and cannot be removed by air flushing.
During precussive drilling in stratified rocks where the resistance of the rock is prone to
variation the holes may get curved and control on inclination may be lost. In such cases
guide tubes may be used for ensuring verticality of the holes or alternatively rotary
drilling may be used. Irrespective of whether air or water is used for flushing the hole
during drilling, thorough cleaning by water flushing is essential before starting grouting
operations.

Grouting equipment
The major equipment required for carrying out grouting are Grout Mixer and Grout
Pump. These are explained below.

Grout mixer: The mixer should have two tank namely mixing tank and agitating tank.
Mixers are generally cylindrical in shape, with axis either horizontal or vertical or
equipped with a system of power driven paddles for mixing. Grout should be mixed in a
mixer operating at 1500 r.p.m. or more. The high speed of mixing serves the purpose of
violently separating each cement grain from its neighbour thus permitting thorough
wetting of every grain. This proves to be advantageous by chemically activating each
grain to through hydration before reaching its final resting state. Further individual grains
penetrate finer cracks more readily than flocs. Vertical barrel type mixers have proved
satisfactory when small mixers are required for use in confined or limiting working
spaces. This type of mixer consists essentially of a vertical barrel having a shaft with
blades for mixing, driven by a motor mounted on top of the mixer above the barrel.
Centrifugal pump mixers mix the grout by re circulating it through a high speed
centrifugal pump. They are sometimes referred to as colloidal type mixers, but they
don’t achieve a true colloidal grout mix. However they possess considerable merit and
produce grout of excellent texture. When mixing sand-cement grouts their action tends
to guard against segregation.

Grout pump: A pump suitable for grouting should permit close control of pressures,
allow a flexible rate of injection, and be designed to minimize clotting of valves and
ports. Grout pimps are of three types namely, piston, screw, and centrifugal.

Washing and testing of holes and surface preparation


Any grouting operation requires major washing of the holes, testing of the holes with
water under pressure and surface preparation. The purpose of washing the holes is two
fold. First to clean the hole to remove the material deposited on the surface during the
drilling operation and second to provoke deliberate inter-connections between adjoining
grout holes to remove known seams and layers of erodable material. It should be borne
in mind that inter-connections between holes are effective only if he washing operations
are carried out systematically to remove all the soft material. Isolated inter-connections
don’t serve much useful purpose as soft material may still remain in position in a known
and irregular pattern. A distinction is therefore made between washing of holes at the
end of the drilling operation and systematically washing of group of holes in order to
remove the erodable material in the intervening area for which the term jetting is used.

Washing of holes
On completion of a drilling of a stage and before injection, the holes should be washed
by allowing drilling water to run until the return from the hoe is reasonably clean. The
quantity of water flowing into the hole during the period should be adequate and generally
not less than 15 l/min.
When no return of drilling or washing water occurs, the holes should be washed for a
reasonable period based on site experience. This is generally for 20 minutes. If an
abrupt loss of drill water occurs during drilling and similarly when a strong flow of
artesian water is encountered, the drilling should be stopped and the hole grouted even if
it has not reached its final depth.

Percolation tests
For routine grouting operations, and simple water test conducted before and after
grouting, the test pressure should be limited so as to avoid hydraulic fracture. The value
of limiting pressure for various strata and depths should be established by preliminary
investigations where cyclic tests should be conducted to evaluate pressure at which
fracturing occurs. Additional tests may be carried out in trial grouting plots or in selected
primary grouting holes to verify the pressure limits established during preliminary
investigations.
Water percolation tests may be used to measure the effectiveness of the grouting
treatment. The tests may be simple or cyclic. Cyclic testing is recommended for
evaluation stage while before and during grouting operations simple tests should be
carried out.
Water tests should be carried out in primary stages before injection to amplify
information available from the site investigation. Tests should be carried out in
secondary stages before injection to indicate the results of primary injections. Test may
be carried out in individual test holes at any time to indicate the results of all treatment
carried out before that time. Test holes drilled for this purpose should be sited midway
between completed injection holes.

Jetting
Jetting operation are carried out in order to deliberately provoke connection between
bore holes and to remove known deposits of erodable material. Jetting should be
carried out in group of holes arranged in a square, triangular or hexagonal pattern
known as cells.

Surface treatment
For effective treatment of the surface zones, sufficient pressure should be developed to
achieve the spread required witH a convenient spacing of holes. Adequate cover should
be maintained during grouting to ensure that adequate pressure is applied without
causing upheaval or excessive surface leakage.

Injection of grout
As for the method of injection, grout holes should be injected by direct connection to the
pump. Each pump should be provided with a packer at the surface or with a short strand
pipe threaded at its outer end to accept stand or control fittings, which should be
provided with a pressure gauge, bleeder valve and a valve enabling delivery from pump
to be cut-off from the hole. Either single line or circulation system may be used, usually
circulating system is preferred, however when adequate controls are possible to regulate
the pump discharge and pressure by using pumps of suitable design, single line grouting
system can be used.
Once the grouting of stage or group of holes has been commenced it should be
continued without interruption up to completion. In general a stage may be considered
complete when the absorption of grout at the desired limiting pressure is less than 2
l/min averaged over a period of 10 minutes.
As far as practical a continuous flow of grout should be maintained at the desired
pressure and the grouting equipment should be operated to ensure continuous and
efficient performance throughout the grouting operation. After grouting is completed, the
grout holes should be closed by the means of a valve to maintain to grout pressure for a
sufficient period to prevent escape of the grout due to back pressure and flow reversal,
due to causes like artesian conditions. For this purpose a period of one or two hours is
generally sufficient, however this should be verified by trial.

Pressure
The grouting pressure should be adequate to achieve the desired grout and the pressure
should be limited so as to avoid disturbances and upheaval of the ground and should take
into account reservoir pressure.
For structures on rock foundations, it is a basic requirement that no disturbance should
be caused to the surface zones of the foundation by the grouting operation. When
grouting is undertaken below an existing structure no upheaval of the foundation can be
allowed as it would have very harmful consequences on the structure and/or the
equipment. In general the disturbance caused by the grouting is dependent more on the
manner in which the pressure is developed and the nature of the rock than on the
absolute magnitude of pressure. Relative higher pressures can be sustained without
damage to the foundations, when pressure is built up gradually, as resistance to flow is
developed by deposition of grout On the other hand when pressures are raised hastily
damage can occur even at relatively low pressure. In general, horizontal stratified or low
dripping rocks are more vulnerable to disturbance by grouting pressure than fractured
igneous or metamorphic rocks or steeply dipped sedimentary rocks. Rocks previously
subjected to folding or fracturing or rocks in the process of adjustment after removal of
overburden load are also more vulnerable to disturbances.
The most common difficulty experienced in consolidation grouting is surface leakage. It
is therefore customary to pipe through the entire height of concrete or masonary and
carry out the grouting after the rock has been completely covered. This not only eliminates
surface leakage but permits use of higher pressure so that even the smaller seams can be
grouted effectively.

3.0 TEMPERATURE CONTROL OF MASS CONCRETE FOR DAMS

When a concrete gravity dam is constructed of mass concrete, it undergoes volumetric


changes with time due to the release of heat of hydration by the concrete. A rapid rise in
the temperature of mass concrete takes place during the phase when the concrete
mass is in plastic stage and undergoes hardening. After hardening, the concrete gradually
cools due to effect of atmospheric temperature, which tends to subject the concrete to
high tensile stresses. Cracking occurs in the concrete when these tensile stresses exceed
the tensile strength of the concrete. This cracking is undesirable as it affects the water
tightness, durability and appearance of hydraulic structures. Hence, methods to control
the temperature rise during dam construction is absolutely essential. The methods to
control temperature in dams is prescribed in the Bureau of Indian Standard code IS:
14591-1999 “Temperature control of mass concrete for dams – guidelines”, some of
which are given below.
Most commonly used methods are precooking, post cooling and reducing heat of
hydration by proper mix design. The ideal condition would be simply to place the
concrete at stable temperature of dam and heat of hydration removed, as it is generated,
so that temperature of concrete is not allowed to rise above stable temperature. However
this is not possible to achieve practically. Therefore, the most practical method is to
pre cool concrete so as to restrain the net temperature rise to acceptable levels.

Pre-cooling
One of the most effective and positive temperature control measure is precooling which
reduces the placement temperature of concrete. The method, or combination of methods,
used to reduce concrete placement temperatures will vary with the degree of cooling
required and the equipment available with the project authority or the contractor. In this
method usually the fine and coarse aggregates and the water are separately cooled to
the requisite temperatures.
Mixing water may be cooled to varying degrees, usually from 00 C to 40 C. Adding
crushed ice or ice flakes to the mix is an effective method of cooling because it takes
advantage of the latent heat of fusion of ice. The addition of large amount of ice flakes,
however, may not be possible in cases where both coarse aggregate and sand contain
appreciable amount of free water, in which case the amount of water to be added to the
mix may be so small that substitution of part of the water to be added with ice may not
be feasible. From practical considerations, not more than 70 percent of water should be
replaced by crushed ice. Although most rock minerals have comparatively low heat
capacity, since aggregates comprise the greatest proportion of concrete mix, the
temperature of the aggregate has the greatest influence on the temperature of the
concrete. Cooling of coarse aggregate to about 1.7°C may be accomplished in several
ways. One method is to chill the aggregates in large tanks of refrigerated water for a
given period of time or by spraying cold water. Effective cooling of coarse aggregate is
also attained by forcing refrigerated air through the aggregate while the aggregate is
draining in stock piles, or while it is in a conveyer belt or while it is passing through the
bins of the batching plant.

Post-cooling
Post cooling is a means of crack control. Control of concrete temperature may be
effectively accomplished by circulating cold water through thin walled pipes embedded
in concrete. This will reduce the temperature of newly placed concrete by several
degrees, but the primary purpose of the system is to accelerate the subsequent heat
removal and accompanying volume decrease, during early ages when the elastic modulus
is relatively low. Post cooling is also used where longitudinal contraction joints are
provided in order to reduce the temperature of concrete to the desired value prior to
grouting of transverse contraction joint. Post cooling will create a flatter temperature
gradient between the warm concrete and the cooler exterior atmosphere which, in turn,
helps in avoiding temperature cracks. Other methods such as evaporative cooling with a
fine water spray, cold water curing and shading may prove beneficial, but the results are
variable and do not significantly affect the temperature in the interior of massive
placement. The embedded cooling system consist of aluminum or synthetic plastic pipe
or tubing generally of 25 mm diameter and 1.50 mm wall thickness placed in grid like
coils over the top of each concrete lift. When the expected active cooling period exceeds
3 months, steel tubing should be used. The number of coils in a block depends upon the
size of the block and the horizontal spacing of the pipes. For practical reasons, pipe coils
are placed and tied to the top of a hardened concrete surface and thus vertical spacing
of the pipe corresponds to lift thickness. A horizontal spacing same as the vertical spacing
will result in the most uniform cooling pattern but variations may be allowed. Supply and
return headers, with manifolds to permit individual connections to each coil are
normally placed on the downstream face of the dam. In some case, cooling shafts,
galleries and embedded header system may be used to advantage.
4.0 CONCRETING PROCEDURES FOR GRAVITY DAMS

A concrete gravity dam is normally executed as a mass concrete work, except for some
reinforced concreting works as in:
- Piers and bridges over the spillway
- Around galleries and other openings
- Divide wall between adjacent spillways
- Energy dissipators
- Intake to sluices

The Bureau of Indian Standards code IS 457-1957 “Code of practice for general
construction of plain and reinforced concrete for dams and other massive structures”
provides guidelines for practices to be followed in plane and reinforced concreting for
mass concrete dams. The main points that have to be taken care are mentioned in the
following paragraphs

Aggregate production
Huge quantities of aggregate would be required for the construction of a massive
structure like a concrete gravity dam The acceptability of the natural aggregate is to be
judged upon the physical and the chemical properties of the material and the
accessibility, proximity to site and economic workability of the deposit. A suitable quarry
has to be identified in the neighbourhood that can supply continuous source of
aggregates.

Structural steel
These may be according to the latest recommendations of the relevant bureau of Indian
Standard Codes.

Concrete production and handling


Standard practice is for materials to be batched by weight. The time of mixing is often
specified as 2 minutes. The procedure to be adopted for moving concrete from the
mixers on to the dam will be governed by site conditions. Having produced a good
plaeable concrete, the problem is to transport it to the dam site with the least possible
segregation or change in consistency, so that it may be compacted uniformly into the
dam without reasonable effort. Nowadays a cableway laid across the dam valley is often
used with buckets of capacity 1.5 to 2 m³. At many construction sites concrete is placed
using chutes or even a belt conveyor. It is recommended that concrete shall have to be
placed in position within 30 minutes of its removal from the mixer.
Concrete placing, consolidation and curing
For laying concrete over the rock foundations, it has to be ensured that the surface is
clean and free from mud, dirt, oil, organic deposits, or other foreign material which may
prevent a tight bond between rock and concrete. In case of earth or shale foundations all
soft or loose mud and surface debris shall have to be scrapped and removed. Then the
surface has to be moistened to a depth of about 15 cm to prevent the subgrade from
absorbing water from the fresh concrete. A layer of concrete that is laid is generally kept
as 1.5 m, in a view to ease construction and limit excessive temperature rise. These
layers of concreting are called lifts and between two successive lifts a horizontal joint
would invariably arise. The concrete of subsequent lifts has to be placed after allowing
sufficient time for the previously laid concrete to cool and attain its initial set and
become hard. Prior to placement of concrete of the next lift, the surface of the
previously placed concrete has to be thoroughly cleaned by the use of high velocity jet
of water and air as well as by wet-sand blasting. Further immediately before the concrete
placing of the next lift begins, a 12.5 mm thick layer of mortar should be applied to
permit proper bond between the concrete of the lower lift. Since the area of the concrete
block near the foundation would be quite large, joints in the vertical plane, but parallel
to the dam axis have to be introduced to ease the concrete placement and to allow safe
dissipation of the heat of hydration of concrete. These joints called the longitudinal
joints are normally spaced at intervals of 15m to 30 m. Thus during construction a
continuous concrete pour is seen to be confined between the transverse joints (defining
a block) and the longitudinal joints. Once a lift is cast it is thoroughly compacted with
needle vibrators. The longitudinal joints subdivide each block formed by the transverse
joints into several smaller sub blocks, but since each block must be a monolithic, these
joints are invariantly provided with horizontal keys (or undulations)over the entire
surface, which helps to make a good bond with the adjacent lift . It has however,
been recognized that the provision of longitudinal joints is basically unsound unless a
high degree of perfection is maintained while placing the adjacent pore of concrete
and then grouting the gap properly. Hence the present practice is to avoid the longitudinal
joints altogether, even in the case of high dams and a better alternative is to attain
necessary temperature control by the methods described earlier. Curing of concrete is
important but a difficult task for the construction engineer. Primarily it is necessary
to maintain satisfactory moisture content in the hardening concrete. This may be achieved
either by the application of water (usually from sprinklers or perforated hoses, or
occasionally by panding on the top of the lift) or by prevention of loss of water (by
application of some membrane to the surface). A second requirement for good curing
is favourable temperature. This can be achieved by any of the water methods but not by
the membrane methods.

You might also like