PROGRESS REPORT UPTO 03-OCT-2018

WELD SHOP STEEL STRUCTURE

S.NO DESCRIPTION TOTAL WEIGHT KG WEIGHT % WEIGHT ERECTED KG BALANCE WEIGHT KG BALANCE % REMARKS
1 TA RR FLR 11314.51 5.9795389969 11314.51 100 Area not Hand over
2 TA MAIN BUCK 26894.01 14.2130575323 26894.01 100 Area not Hand over
3 TA CTR FLR 8414.72 4.4470459957 8414.72 100 Area not Hand over
4 TA SIDE LINE 27396.44 14.4785838147 27396.44 100 Area not Hand over

5 QL RR FLR 15026.47 7.9412509558 15026.47 100 Marking completed, level


checking inprogress

Structure framing completed.


6 QL MAIN BUCK 27077.35 14.309949813 15652.95 11424.4 42.2 29 sep client decided the floor
levels for erection structure.

7 QL CTR FLR 11374.72 6.0113590265 11374.72 100 Marking completed, level


checking inprogress

Chemical anchoring in progress.


8 QL SIDE LINE 29835.61 15.7676464551 29835.61 100 Assembling of structure frame in
progress.

Structure framing completed.


9 BB LINE 22383.55 11.829350994 12413.44 9970.11 44.5 23 sep to 30 sep levels was
maintain by the (Client/BM)

10 BC LINE 9503.06 5.0222164159 9503.06 100 Drilling for bolts chemical


anchoring in progress

TOTAL BOQ WEIGHT 189220.44 100 28066.39 161154.05