BILL OF QUANTITIES

FOR REHABILITATION

&

REMODELLING WORKS

FOR CITY BOYS HOTEL


BILL OF QUANTITIES FOR REHABILITATION & REMODELLING WORKS FOR
CITY BOYS HOTEL

ITEM WORK DESCRIPTION QTY UNIT RATE AMOUNT


(TSH) (TSH)
ELEMENT NO 1
A FININSHINGS
In- situ finishing’s
Cement and sand (1:4) internal plastering
in two coats steel trowelled to a smooth
finish
1930 M2 8000 15,840,000/=
15mm to walls
330 M2 8000 2,640,000/=
15mm to sides and soffits of horizontal
beams
External cement and sand (1:4) rendering
with approved plasticeser in two coats
steel trowelled to a smooth finish
990 M2 8000 7,920,000/=
15mm internal and external fence walls
1320 M2 8000 10,560,000/=
15mm to sides and soffits of horizontal beam
15mm to surface of concrete cill over 100
165 M2 8000 1,320,000/=
but not exceeding 200mm girth
Bed and Backings
86.4 M2 8000 691,200/=
Cement and sand (1:4)
1215 M2 6000 7,290,000/=
28mm bed to receive floor tiles
1080 M2 6000 6,480,000/=
12mm backing to receive wall tiles ceilling
finishings
Sawn soft wood treated with preservatives
50x50mm brendering plain sheet finishings
3375 M 8000 27,000,000/=
12mm gypsum board ceiling lining fixed to
2025 M2 30000 60,750,000/=
timber brendering (measured separately)
60x60mm girth moulded gypsum cornice
2700 M 8000 21,600,000/=
ELEMENT NO. 1 CARRIED TO SUMMARY 162,091,200/=
ELEMENT NO. 2
B CERAMIC TILES
Fixing Spanish BS 6432 or any other
imported laid to regular pattern bedding
and joining in cement mortar (1:4)
grouting joint with coloured Cement
500×500×6mm but jointed straight both
ways to Cement and sand base.

general floor 1215 M2 56000 68,040,000/=


100mm Tile skirting 2700 M 7500 20,250,000/=
Fixing Porcelain tiles, Spanish BS 6432 or
any other equal and approved brand
imported laid to regular pattern and
jointing in Cement mortar (1:4) grounding
joint with coloured Cement.
300×200×6mm but paint straight both
ways to Cement and sand
general wall 1080 M2 32000 34,560,000/=
ELEMENT NO 2 CARRIED TO SUMMARY 122,850,000/=
ELEMENT NO 3
C PAINTING AND DECORATION
Prepare surface and apply one under coat
and two fully coats of vinly matt finish
paint to plastered or rendered surface
internal and External walls
Prepare and apply black bituminous paint 2475 M2 12000 29,700,000/=
two coats to plinth wall externally
Prepare surface and apply one coat red 440 M2 8000 3,520,000/=
oxide primer two under coats oil based gloss
paint
-Security grilles (measured)
Flat overall both sides) 546 M2 12000 6,552,000/=

Prepare surface and apply three coats


woodoc 30 vanish
- general surface over 300mm girth 101 M2 8000 808,000/=
- general surface of glazed door over 202.5 M2 8000 1,620,000/=
300mm girth
- frame or the like not exceeding 18.3 M 5000 915,000/=
100mm girth
- frame or the like over 200mm but not 91.5 M 5000 457,500/=
exceeding 300,, girth
ELEMENT NO.3 CARRIED TO SUMMARY 43,572,500/=
ELEMENT NO 4
D DOORS AND WINDOWS
Prime quality hard wood timber panel doors
45mm thick paneled door divided into two
panels comprising 50x150mmtiles and
middle rail and 50x200mm bottom rail
panels filled in with and including 30mm
thick molded boarding tongued and
grooved all round
Door unit over all size 900x2500mm high 69 NR 400,000 27,600,000/=
3000x2500mm high 60 NR 300,000 18,000,000/=
Frames and finishing 50x150mm frame with
one labour fixed to ground (measured 865.2 NR 15000 12,978,000/=
separately)
Supply and fix the following aluminum
window unit with bronze anodized
aluminum frames million and transoms
and silicone sealant both sides beads for
glass (measured separate) including
assembling as necessary all iron
mongery screwing and bedding frames to
surround in proprietary bedding
compound and pointing externally with
mastic
Window unit over all size 9 NR 350000 3,150,000/=
2500x1500mm 69 NR 300000 20,700,000/=
1500x1500mm 60 NR 150000 9,000,000/=
900x750mm
Supply and fix the following iron mongery
as manufactured by UNION or other equal
and approved fixed to hard wood with
matching screws
Two levers mortice lockset complete with 45 NR 65000 2,925,000/=
furniture 39 NR 85000 3,315,000/=
Three levers mortice lockset complete with
furniture 45 NR 60000 2,700,000/=
Toilet mortice lockset 387 NR 8000 3,096,000/=
100 brass but hinges 90 NR 5000 450,000/=
- stainless steel floor door stopper

ELEMENT NO 4 CARRIED TO SUMMARY 103,914,000/=


ELEMENT NO 5
E PLUMBING AND ENGINEERING
INSTALLATION
Sanitary installation appliances
supply and fix the following sanitary
appliances (Armitage shanks references)
including all connections and fixing to
floor or wall where necessary:-
Asian squatting white vitrous china low level
WC suite with horizontal outlet flush valve
cistern 6 litre bottom supply and internal over
floor with free flow plastic siphon fitting
domex screws and p-trap 10 NR 175000 1,750,000/=
- European type WC 35 NR 350,000 12,250,000/=
- Hand wash basin 45 NR 145,000 6,525,000/=
- Shower rose 45 NR 30000 1,350,000/=
- Toilet roll holder with shelf screwed to tiled 45 NR 30000 1,350,000/=
wall
- soap dispenser with hand push buttom 45 NR 35000 1,575,000/=
screwed to tiled wall 45 NR 30000 1,350,000/=
- Towel rail
- 600x760x6mm mirror 45 NR 75000 3,375,000/=
Special quality plate glass with silver
resistant coating one side, fixing with
domex screws to background requiring
plugging
- Allow sum for construction or repair of 1 ITEM 2,500,000/=
all main holes
- Allow sum for pipe work for clean 1 ITEM 2,000,000/=
water
- Repair of sewage system connection 1 ITEM 3,500,000/=
to main sewage
ELEMENT NO 5 CARRIED TO SUMMARY 37,525,000/=
ELEMENT NO 6
F ELECTRICAL INSTALLATION
Allow for installation of Electricity and its 1 ITEM 75,000,000/=
accessories including Air conditional, TVs
and stand by Generator

ELEMENT NO 6CARRIED TO SUMMARY 75,000,000/=


ELEMENT NO 7
G ROADS PARKING AND PAVINGS
General excavation from existing ground
level
Excavate to reduce levels average 200mm 200 M³ 5000 1,000,000/=
deep
Surface treatment
Grade surface of excavation or filling graded 200 M³ 15000 3,000,000/=
gravel
Pre cast concrete units finished fair on all
exposed faces including hoisting into
position and bedding joining pointing as
necessary in cement mortar(1:7)
600x600x100mm paving 1000 M2 10000 10,000,000/=
Slabs steel trowel finished bedded on and
including 50mm sand bed to breaking joint
pattern
ELEMENT NO 7CARRIED TO SUMMARY 14,000,000/=
ELEMENT NO 8
H EXTERNAL WORKS
Allow construction of generator
House including boundary walling and Gates 1 ITEM 15,000,000/=

ELEMENT NO 8 CARRIED TO SUMMARY 15,000,000/=


ELEMENT NO 9 25,000,000/=
I PROVISIONALSUMS 1 ITEM

ELEMENT NO 9 CARRIED TO SUMMARY 25,000,000/=


SUMMARY OF BILL OF QUANTITY

A ELEMENT NO 1 FINISHINGS 162,091,200/=

B ELEMENT NO 2 CERAMIC TILES 122,850,000/=

C ELEMENT NO 3 PAINTING AND DECORATION 43,572,500/=

D ELEMENT NO 4 DOORS AND WINDOWS 103,914,000/=

E ELEMENT NO 5 PLUMBING AND ENGINEERING INSTALLATION 37,525.000/=

F ELEMENT NO 6 ELECTRICAL INSTALLATION 75,000,000/=

G ELEMENT NO 7 ROADS PARKING AND PAVINGS 14,000,000/=

H ELEMENT NO 8 EXTERNAL WORKS 15,000,000/=

I ELEMENT NO 9 PROVISIONAL SUMS 25,000,000/=

TOTAL 598,952,700/=

ADD 18% VAT 107,811,486/=

GRAND TOTAL 706,764,186/=