Boq of MEP For Factory
Boq of MEP For Factory
Boq of MEP For Factory
The tender price for the Fire Fighting works as described or referred to in the drawings and specifications in
accordance with the General Conditions and Preliminaries is made up of the complete Supply, Installation, Testing
and putting into Commissioning, Handing over in approved working order and maintenance thereafter for a period of
12 months.
The Tender Prices be a firm price and shall include all custom duties, sales tax and any other taxes, insurance,
labour, transportation of and hoisting of equipment, hacking and making good of damage surface.
Quantities and work descriptions provided are indicative only. Contractor shall verified and satisfied
themselves by doing site inspection and measurement. Any additional works where not specified in anywhere
and deemed necessary to complete the whole works shall be included in this tender prices else it is deemed
to be included.
Date Date
SOP-1
SCHEDULE OF PRICE
1.2 Clearing and cleaning off site rubbish and temporary Lump Sum
works in stages and cleaning upon completion.
1.5 Contractor Site Office, Workshop, store and Consultant Lump Sum
site office
1.11 Local Authorities and Fees - Payment of fees for Lump Sum
application to local authorities for permits and any
liaison
1.13 Scaffolding and all necessary temporary support for Lump Sum
construction - approved by JKKP
SOP-2
SCHEDULE OF PRICE
1.16 Temporary toilet and sewerage treatment tank subject Lump Sum
to Engineer's approval.
1.17 Security services by employing guard person until the Lump Sum
completion of project
1.18 Site Mobilization including ingress and egress of all Lump Sum
construction vehicle and equipment in order to complete
the construction
SOP-3
SCHEDULE OF PRICE
1.22 Liaison with relevant Authorities for inspections and to Lump Sum
obtain all approval and certificates including payment of
all necessary inspection fees, notices, documentations,
drawings, etc.
Notes:
b) Liaison with authorities as stipulated above implies the
following:
i) For electrical work, arranging for TNB to install cables from the TNB
sub-station to the site , to submit form for application of permanent
supply, and assist client to make relevant payment to TNB for meter
deposit if required and other work as necessary and application to
Suruhanjaya Tenaga
b) For Telephone work, informing Telekom before starting work,
arranging for inspection after completion, prepare & submit of As-built
drawings to Telekom, obtaining of Letter of Acceptance other work as
necessary
SOP-4
SCHEDULE OF PRICE
b) Hose Reel Diesel Pump with capacity: 120 l/min @ 50m, 1 Set
2900 rpm c/w check valves, gate valves, flexible joints, y-
strainers, pressure switches, pressure gauges, isolators,
tees, bends, battery, Diesel and accessories.
c) Hose Reel Pump Control Panel c/w all necessary wiring in 1 Lot
Pump Room.
d) Stainless Steel Electrode Sensor c/w all necessary wiring Lump Sum
e) Swing type Hose Reel Drum c/w 25mmx30m. rubber hose, 40 Nos
jet/spray nozzle including 25mm gate valve and supports
h) 50mm G.I. 'B' hose reel pipe c/w fitting, isolating gate valve, Lump Sum
supports and painting of in factory
i) 25mm G.I. 'B' hose reel pipe c/w fitting, isolating gate valve, Lump Sum
supports and painting in factory
SOP-5
SCHEDULE OF PRICE
SOP-6
SCHEDULE OF PRICE
c) Nozzles 2 Nos
d) Heat Detectors 1 No
e) Smoke Detectors 1 No
g) Warning Light 1 No
h) Alarm Bell 1 No
2.3.3 TX Room
a) 45 kg CO2 cylinders, pilot cylinders c/w gas, solenoid 6 Nos
valves, installation of CO2, supports and accessories
SOP-7
SCHEDULE OF PRICE
c) Nozzles 2 Nos
d) Heat Detectors 1 No
e) Smoke Detectors 1 No
g) Warning Light 1 No
h) Alarm Bell 1 No
c) Nozzles 2 Nos
d) Heat Detectors 1 No
e) Smoke Detectors 1 No
g) Warning Light 1 No
h) Alarm Bell 1 No
SOP-8
SCHEDULE OF PRICE
c) Nozzles 36 Nos
d) Heat Detectors 5 No
e) Smoke Detectors 3 No
g) Warning Light 1 No
h) Alarm Bell 1 No
SOP-9
SCHEDULE OF PRICE
c) Nozzles 26 Nos
d) Heat Detectors 3 No
e) Smoke Detectors 2 No
g) Warning Light 1 No
h) Alarm Bell 1 No
SOP-10
SCHEDULE OF PRICE
b) Diesel Sprinkler Pump OH3 @30m c/w orifice plate, check 1 Set
valves, gate valves, flexible joints, y-strainers, pressure
switches, pressure gauges, reducer, anti-vibration spring
isolators, inertial block, battery, Diesel Tank, tees, bends
and accessories
g) Stainless Steel Electrode Sensor c/w all necessary wiring Lump Sum
SOP-11
SCHEDULE OF PRICE
k) 200 mm ND black steel class 'C' pipe c/w bituminous Lump Sum
wrapping conforming to BS 1387 from installation alarm
valve to factory and warehouse c/w valves, supports, long
bends, tees, fittings and accessories
Zone 2
i) 150mm ND pipe Lump Sum
ii) 100mm ND pipe Lump Sum
iii) 80mm ND pipe Lump Sum
iv) 65mm ND pipe Lump Sum
v) 50mm ND pipe Lump Sum
vi) 40mm ND pipe Lump Sum
vii) 32mm ND pipe Lump Sum
viii) 25mm ND pipe Lump Sum
SOP-12
SCHEDULE OF PRICE
Zone 3
i) 150mm ND pipe Lump Sum
ii) 100mm ND pipe Lump Sum
iii) 80mm ND pipe Lump Sum
iv) 65mm ND pipe Lump Sum
v) 50mm ND pipe Lump Sum
vi) 40mm ND pipe Lump Sum
vii) 32mm ND pipe Lump Sum
viii) 25mm ND pipe Lump Sum
Zone 4
i) 150mm ND pipe Lump Sum
ii) 100mm ND pipe Lump Sum
iii) 80mm ND pipe Lump Sum
iv) 65mm ND pipe Lump Sum
v) 50mm ND pipe Lump Sum
vi) 40mm ND pipe Lump Sum
vii) 32mm ND pipe Lump Sum
viii) 25mm ND pipe Lump Sum
Zone 5
i) 150mm ND pipe Lump Sum
ii) 100mm ND pipe Lump Sum
iii) 80mm ND pipe Lump Sum
iv) 65mm ND pipe Lump Sum
v) 50mm ND pipe Lump Sum
vi) 40mm ND pipe Lump Sum
vii) 32mm ND pipe Lump Sum
viii) 25mm ND pipe Lump Sum
Zone 6
i) 150mm ND pipe Lump Sum
ii) 100mm ND pipe Lump Sum
iii) 80mm ND pipe Lump Sum
iv) 65mm ND pipe Lump Sum
v) 50mm ND pipe Lump Sum
vi) 40mm ND pipe Lump Sum
vii) 32mm ND pipe Lump Sum
viii) 25mm ND pipe Lump Sum
SOP-13
SCHEDULE OF PRICE
Zone 7
i) 150mm ND pipe Lump Sum
ii) 100mm ND pipe Lump Sum
iii) 80mm ND pipe Lump Sum
iv) 65mm ND pipe Lump Sum
v) 50mm ND pipe Lump Sum
vi) 40mm ND pipe Lump Sum
vii) 32mm ND pipe Lump Sum
viii) 25mm ND pipe Lump Sum
Zone 8
i) 150mm ND pipe Lump Sum
ii) 100mm ND pipe Lump Sum
iii) 80mm ND pipe Lump Sum
iv) 65mm ND pipe Lump Sum
v) 50mm ND pipe Lump Sum
vi) 40mm ND pipe Lump Sum
vii) 32mm ND pipe Lump Sum
viii) 25mm ND pipe Lump Sum
i) Factory No.
ii) Office No.
ii)
SOP-14
SCHEDULE OF PRICE
ii)
SOP-15
SCHEDULE OF PRICE
SOP-16
SCHEDULE OF PRICE
SOP-17
SCHEDULE OF PRICE
a)
b)
SOP-18
SCHEDULE OF PRICE
e) Supply and install equipment frame and neutral earthing Lump Sum
including earth bar, earth chamber, concrete cover, earth
rod, extension joint, copper tape and accessories to achieve
an earth resistance of less than 1 ohm and comply with
specifications for 11kV System to complete.
ii)
SOP-19
SCHEDULE OF PRICE
4.1.2 Transformer
a) Supply, deliver, install, test, commission and maintain of Oil 1 Lot
immersed type cast resin Dyn11 11/0.433 kV, 50Hz,
2.5MVA, ONAN Distribution Transformer including off load
tap changer, IP30 enclosure, analog temperature sensors
and protection monitoring, alarm panels, mounting
equipment, supports, earthing system and all other
necessary accessories to complete.
ii)
SOP-20
SCHEDULE OF PRICE
4.2.2 Supply and install the metalclad floor mounted 50kA Main 1 No
Switchboard MSB-1 complete with circuit breakers,
ammeter, voltmeter, current transformers, IDMT earth fault
relay, power factor correction system, capacitor bank,
reactor, full size busbars, sensing and control wiring, phase
indicating lights, ventilation fan, supports and all other
accessories.
4.2.4 Supply and install metalclad 35kA TPN wall mounted Sub-
Switchboard c/w circuit breakers, IDMT Earth Fault/Earth
Leakage Relay, ammeter, voltmeter, current transformers,
full size busbars, time switch, contactors, control wiring,
earthing system, support and accessories for the following:
a) SSB-F1 1 Lot
b) SSB-F2 1 Lot
c) SSB-U 1 Lot
d) SSB-O 1 Lot
f) DB-FGF 1 Lot
SOP-21
SCHEDULE OF PRICE
4.2.6 Supply and install Cable c/w supports and accessories from
Sub-Switchboard SSB-F2 to the following:
a) DB-FGC by using 4x1C-10mm 2 PVC Cu. Cable in MS m
trunking
b) DB-FGD by using 4x1C-10mm 2 PVC Cu. Cable in MS m
trunking
c) DB-FGG by using 4x1C-25mm2 PVC Cu. Cable in MS m
trunking
d) DB-FGH by using 4x1C-10mm 2 PVC Cu. Cable in MS m
trunking
4.2.7 Supply and install Cable c/w supports and accessories from
Sub-Switchboard SSB-O to the following:
a) DB-OGA by using 4x1C-10mm2 PVC Cu. Cable in MS m
trunking
b) DB-OGB by using 4x1C-10mm2 PVC Cu. Cable in MS m
trunking
c) DB-OGC by using 4x1C-25mm2 PVC Cu. Cable in MS m
trunking
d) DB-O1A by using 4x1C-10mm2 PVC Cu. Cable in MS m
trunking
e) DB-O1B by using 4x1C-10mm2 PVC Cu. Cable in MS m
trunking
f) DB-O1C by using 4x1C-25mm2 PVC Cu. Cable in MS m
trunking
g) SSB-O2 by using 4x1C-50mm2 PVC Cu. Cable in MS m
trunking
h) DB-GH by using 1x4C-6mm2 PVC/SWA/PVC Cu. Cable m
underground
SOP-22
SCHEDULE OF PRICE
4.2.8 Supply and install Cable c/w supports and accessories from
Sub-Switchboard SSB-U to the following:
a) DB-UGA by using 4x1C-25mm2 PVC Cu. Cable in MS m
trunking
b) DB-UGB by using 4x1C-25mm2 PVC Cu. Cable in MS m
trunking
c) DB-U1A by using 4x1C-10mm2 PVC Cu. Cable in MS m
trunking
d) DB-U1B by using 4x1C-10mm2 PVC Cu. Cable in MS m
trunking
d) SSB-U2 by using 4x1C-50mm2 PVC Cu. Cable in MS m
trunking
4.2.9 Supply and install metalclad 10kA TPN wall mounted Sub-
Switchboard c/w circuit breakers, IDMT Earth Fault/Earth
Leakage Relay, ammeter, voltmeter, current transformers,
full size busbars, time switch, contactors, control wiring,
earthing system, support and accessories for the following:
a) SSB-O2 1 Lot
b) SSB-U2 1 Lot
4.2.8 Supply and install Cable c/w supports and accessories from
Sub-Switchboard SSB-O2 to the following:
a) DB-RA by using 2x1C-6mm2 PVC Cu. Cable in MS trunking m
(Rest Room 1)
b) DB-R by using 2x1C-6mm2 PVC Cu. Cable in MS trunking m
(Rest Room 2)
c) DB-R by using 2x1C-6mm2 PVC Cu. Cable in MS trunking m
(Rest Room 3)
d) DB-R by using 2x1C-6mm2 PVC Cu. Cable in MS trunking m
(Rest Room 4)
d) DB-R by using 2x1C-6mm2 PVC Cu. Cable in MS trunking m
(Rest Room 5)
e) DB-R by using 2x1C-6mm2 PVC Cu. Cable in MS trunking m
(Rest Room 6)
f) DB-R by using 2x1C-6mm2 PVC Cu. Cable in MS trunking m
(Rest Room 7)
g) DB-O2C by using 2x1C-6mm2 PVC Cu. Cable in MS m
trunking (Common)
SOP-23
SCHEDULE OF PRICE
4.2.9 Supply and install Cable c/w supports and accessories from
Sub-Switchboard SSB-U2 to the following:
a) DB-RB by using 2x1C-6mm2 PVC Cu. Cable in MS trunking m
(Rest Room 1)
b) DB-RB by using 2x1C-6mm2 PVC Cu. Cable in MS trunking m
(Rest Room 2)
c) DB-RB by using 2x1C-6mm2 PVC Cu. Cable in MS trunking m
(Rest Room 3)
d) DB-RB by using 2x1C-6mm2 PVC Cu. Cable in MS trunking m
(Rest Room 4)
e) DB-RB by using 2x1C-6mm2 PVC Cu. Cable in MS trunking m
(Rest Room 5)
f) DB-RB by using 2x1C-6mm2 PVC Cu. Cable in MS trunking m
(Rest Room 6)
g) DB-RB by using 2x1C-6mm2 PVC Cu. Cable in MS trunking m
(Rest Room 7)
h) DB-RB by using 2x1C-6mm2 PVC Cu. Cable in MS trunking m
(Rest Room 8)
i) DB-RB by using 2x1C-6mm2 PVC Cu. Cable in MS trunking m
(Rest Room 9)
j) DB-RB by using 2x1C-6mm2 PVC Cu. Cable in MS trunking m
(Rest Room 10)
k) DB-RB by using 2x1C-6mm2 PVC Cu. Cable in MS trunking m
(Rest Room 11)
l) DB-RB by using 2x1C-6mm2 PVC Cu. Cable in MS trunking m
(Rest Room 12)
m) DB-RB by using 2x1C-6mm2 PVC Cu. Cable in MS trunking m
(Rest Room 13)
n) DB-RB by using 2x1C-6mm2 PVC Cu. Cable in MS trunking m
(Rest Room 14)
o) DB-RB by using 2x1C-6mm2 PVC Cu. Cable in MS trunking m
(Rest Room 15)
p) DB-RB by using 2x1C-6mm2 PVC Cu. Cable in MS trunking m
(Rest Room 16)
q) DB-RB by using 2x1C-6mm2 PVC Cu. Cable in MS trunking m
(Rest Room 17)
r) DB-RB by using 2x1C-6mm2 PVC Cu. Cable in MS trunking m
(Rest Room 18)
SOP-24
SCHEDULE OF PRICE
a) 1 way 150mm HDPE corrugated pipe for 11kV cable from Lump Sum
HVB1 to HVB2
b) 2 way 150mm HDPE corrugated pipe incoming to 11kV Lump Sum
Switch Gear room
c) 4 way 150mm HDPE corrugated pipe outgoing from MSB Lump Sum
room
d) 2 way 150mm HDPE corrugated pipe incoming to Utility Lump Sum
Building
d) 2 way 150mm HDPE corrugated pipe outgoing from factory Lump Sum
SOP-25
SCHEDULE OF PRICE
4.2.12 To supply and install fire man switch c/w all necessary Lump Sum
wiring and accessories to Bomba requirement to MSB1
4.2.13 Perform site tests, protection relays calibrations and settings Lump Sum
by an independent test engineer as per specifications for
Low Voltage Switchboard
4.2.14 Supply and install equipment frame and neutral earthing Lump Sum
including earth bar, earth chamber, concrete cover, earth
rod, extension joint, copper tape and accessories to achieve
an earth resistance of less than 1 ohm and comply with
specifications for LV switchboards, distribution boards,
cable ladder, cable tray, trunking, etc. to complete.
b)
c)
SOP-26
SCHEDULE OF PRICE
SOP-27
SCHEDULE OF PRICE
o) DB-UGB 14 No.
p) DB-U1A 8 No.
q) DB-U1B 8 No.
r) DB-U2C 10 No.
4.3.5 Supply and install high bay light point by using 2x1C-
4.0mm2+E PVC Cu. Cable in concealed high impact UPVC
conduit/M.S. trunking c/w supports, 10A light switch and
other accessories to complete from the following distribution
board
a) DB-FGA 55 No.
b) DB-FGB 56 No.
c) DB-FGC 48 No.
d) DB-FGD 33 No.
4.3.6 Supply and install LED compound light point by using 1x2C- m
16mm2 PVC/SWA/PVC Cu. Cables underground including
excavation, backfilling with sand & compaction c/w supports
and other accessories to complete from DB-GH
SOP-28
SCHEDULE OF PRICE
4.3.7 Supply and install LED compound light point by using 2x1C-
4.0mm2 +E PVC Cu. Cables in concealed high impact
UPVC conduit/M.S. trunking c/w supports and other
accessories to complete from the following distribution
boards.
a) DB-FGA 9 No.
b) DB-FGC 9 No.
4.3.8 Supply and install 13A small power points by using 2x1C-
2.5mm2 +E PVC Cu. Cables in concealed high impact
UPVC conduit/M.S. trunking c/w 13A switch socket outlet
and other accessories to complete from the following
distribution boards.
a) DB-FGG 38 No.
b) DB-FGH 26 No.
c) DB-OGB 56 No.
d) DB-O1B 84 No.
e) DB-O2C 10 No.
f) DB-R 48 No.
g) DB-RA 8 No.
h) DB-UGA 16 No.
i) DB-UGB 15 No.
j) DB-U1A 8 No.
k) DB-U1B 12 No.
l) DB-RB 108 No.
m) DB-GH 4 No.
4.3.9 Supply and install 13A small power points by using 2x1C-
2.5mm2 +E PVC Cu. Cables in concealed high impact
UPVC conduit/M.S. trunking c/w 13A metal clad switch
socket outlet and other accessories to complete from the
following distribution boards.
a) DB-FGE 24 No.
b) DB-FGF 24 No.
4.3.10 Supply and install 13A small power points by using 1x3C-
2.5mm2 +E PVC/SWA/PVC Cu. Cables in underground c/w
13A metal clad switch socket outlet and other accessories
to complete from the following distribution boards.
a) DB-FGE 1 No.
b) DB-GH 1 No.
SOP-29
SCHEDULE OF PRICE
4.3.14 Supply and install fire alarm panel power points by using
2x1C- 2.5mm2 +E PVC Cu. Cables in concealed high
impact UPVC conduit/M.S. trunking c/w accessories to
complete from the following distribution board
a) DB-GH 1 No.
b) DB-FGE 1 No.
c) DB-FGF 2 No.
4.3.15 Supply and install autogate point by using 1x7C- 2.5mm2 1 No.
PVC/SWA/PVC Cu. Cables underground including
excavation, backfilling with sand & compaction c/w supports
and other accessories to complete from DB-GH
SOP-30
SCHEDULE OF PRICE
4.3.20 Supply and install the following light fittings and other
equipment complete with supports, mounting accessories
etc.
a) 1x18W bare channel LED light fitting c/w low driver and 378 No.
accessories
b) 2x18W recessed LED light fitting c/w mirror optic reflector, 127 No.
louvre, driver and accessories
c) 1x10W recessed LED down light fitting c/w driver, mirror 53 No.
optic reflector, and accessories
d) LED Emergency light c/w 3 hours back up battery and 93 No.
accessories.
e) LED Keluar sign c/w 3 hours back up battery and 48 No.
accessories
f) Twin Spot LED Emergency Light c/w 3 hours back up 55 No.
battery and accessories
f) 230W LED high bay light fitting c/w driver and accessories 192 No.
106W LED compound light fitting c/w 1.5 meter arm 18 No.
bracket, control gear and accessories
g) 106W HPSV compound light fitting c/w single arm 1.5m 1 No.
mounted on 9m Height G.I. Pole, control gear and
accessories
h) 2x106W HPSV compound light fitting c/w double arm 1.5m 3 No.
mounted on 9m Height G.I. Pole, control gear and
accessories
i) 5' ceiling fan c/w fan hook and regulator 91 No.
b)
SOP-31
SCHEDULE OF PRICE
4.4.3 To supply and install 500mm air terminal rods c/w supports,
base ridge saddle and accessories for the following building
4.4.5 To construct earthing point c/w earth rod, chamber, heavy Lump Sum
duty chamber cover, clamp, and accessories etc. to
requirement for the proper functioning of the system for the
following building
a) Factory, Lump Sum
b) Utility Lump Sum
a)
b)
SOP-32
SCHEDULE OF PRICE
e) Supply and install 3x25 mm copper tape c/w support, Lump Sum
clamps, joint and accessories as per drawings to TNB
requirement
f) Supply and install 6 way earth terminal c/w support, clamps Lump Sum
and accessories as per drawings to TNB requirement
SOP-33
SCHEDULE OF PRICE
5.1.5 To supply and install 50x100 M.S. trunking c/w chase Lump Sum
work, pull wires and fixing accessories
SOP-34
SCHEDULE OF PRICE
5.1.10 Supply and install telephone earthing system for MDF Lump Sum
equipment, TDP, M.S. cable trunking, etc. to
complete.
b)
SOP-35
SCHEDULE OF PRICE
5.2.4 Data point using 4 pair Cat6e Unshielded Twisted Pair 44 Lot
(UTP) cable in MS trunking complete with RJ45 outlet,
terminations, supports, brackets, earthing and all
other necessary accessories from patch panel
5.2.5 Data point using 4 pair Cat6e Unshielded Twisted Pair 1 Lot
(UTP) underground cable in GI conduit complete with
RJ45 outlet, terminations, supports, brackets, earthing
and all other necessary accessories from patch panel
to Guard House
SOP-36
SCHEDULE OF PRICE
SOP-37