Concrete Cube is normally tested on 7 and 28 day of concreting until any special
requirement for early test. A set of 6 cube moulds are casted with 3 cube moulds on 7th day
and another 3 cube moulds on 28th day.
The minimum frequency of sampling of concrete of each grade shall be in accordance with
IS:456-2000 with the following :
NOTE – Atleast one sample shall be taken from each shift. Where concrete is produced at
continuous production unit, such as ready-mixed concrete plant, frequency of sampling
may be agreed upon mutually by suppliers and purchasers.
There are different size of concrete cube moulds as , 50,100,150,225 and 300 mm.
= 0.003375 Cum.
= 1 / 0.003375
= 296.296
= 296 Cubes
= 296/6
= 49.33
NOTE – 49 Cube Sets can be casted without considering any wastage factor.
Suraj Shenoy Nagar, Project Coordinator at Aarvee Associates Architects Engineering & Consultants
Answered Mar 12 2017
A concrete cube is of the size 150mm and thus it's volume will be 0.15 x 0.15 x 0.15 =
0.003375 Cubic meter
So theoretically, One Cubic metre of concrete should be able to cast (1/0.003375)= 296.29
cubes considering no concrete is wasted during handling of the same.
As a rule of thumb, if a wastage of 10% is considered, the number of cubes that can be cast
with one cubic metre of concrete will be 296.29/1.10 = 269.35 cubes, say approximately 270
cubes.
Promoted by CodeGym
Try Java programming online courses with CodeGym for free. Easy, fast and quality
learning. Start now!
Freqvency of sampling
For greater than51 m3 concrete - (4+1)sample - i.e. for every 50m3 - 1 sample additional
Abhishek Kaushik, B.Tech Civil Engineering, Guru Gobind Singh Indraprastha University (2018)
Answered Mar 14 2017 · Author has 189 answers and 129.4k answer views
As per IS 456 code,
Freqvency of sampling
Minimum samples of cube per m3 concrete quantity…..
For greater than51 m3 concrete - (4+1)sample - i.e. for every 50m3 - 1 sample additional
And
In 1 sample there are 3 number of cube taken for testing of finding out compressive
strength.
And in extra
Total sample:-
4.5k Views
Promoted by ProductPlan
ProductPlan is the easiest way for teams of all sizes to build and share beautiful
roadmaps.
Ask
Related Questions
How many cubes to be casted for 150 M3?
How many cube specimens are used to find the maximum strength in concrete, and why?
Why are cylinders cast for M80 concrete? Why not cubes?
How many test cubes should cast when having concrete at a site?
When quantity of concrete is 3 M3 then the number of cube is 3, so how many cubes in 7
days and 28 days?
In a concrete cubes set, how many cubes should be passed as per ISO?