Chapter 7: Stormwater Management: Regulatory Framework
Chapter 7: Stormwater Management: Regulatory Framework
Chapter 7: Stormwater Management: Regulatory Framework
REGULATORY FRAMEWORK
discharge rates of stormwater runoff for rainfall events over a 24-hour period. Runoff volumes
and rates are calculated by determining the curve numbers (CN) and calculating the time of
concentration (Tc) for each drainage area depending on the given rainfall value.
General Permit for Concentrated Animal Feeding Operations
An additional stormwater-related permit will be required from NYSDEC related to the
housing/feeding of horses on-site as part of the harness racing component included in Phase 1 of
Proposed Project. This permit is the SPDES General Permit for Concentrated Animal Feeding
Operations (CAFOs) - General Permit GP-0-09-001 and is issued pursuant to the Environmental
Conservation Law for CAFO operations. Because the proposed horse facility would not
discharge or propose to discharge as a point source, but would instead conform to the best
management and Comprehensive Nutrient Management Plan requirements of the CAFO General
Permit, it would not require coverage under SPDES General Permit GP-04-02 for point source
discharges.
EXISTING CONDITIONS
The Project Site is comprised of approximately 1,538 aces in mostly contiguous parcels located
at the crossroads of Joyland Road and Thompsonville Road generally bound by Kiamesha Lake
Road, NYS Route 17, Concord Road, and County Route 161.
The Project Site’s topography is characterized by the lowland valley of Kiamesha Creek that
runs from south to north through the center of the Site, and its higher elevation uplands to the
east and west. The Project Site is located within a subwatershed of the Neversink River, which is
tributary to the Delaware River. Elevations range from a low point of 1,340 feet above sea level
near the center of the Site to a high point of 1,660 feet above sea level on the western side.
Drainage on the Project Site generally flows from four high points within the Project Site to the
low-lying wetlands, lakes, and Kiamesha Creek.
The Project Site is predominantly forested or occupied by golf course. The Project Site presently
contains minimal impervious cover from the existing roadways traversing the Project Site (i.e.,
Thompsonville Road, Joyland Road, and Chalet Road), unpaved vehicle trails, golf cart paths,
portions of the developed golf courses, and the various buildings and residences which remain
on the Project Site from previous uses. In addition to the two golf courses that occupy the
Project Site, the active Monster Golf Course and the inactive International Golf Course, it also
includes the abandoned ski areas/runs, a spring and pump house, and the Chalet Golf Clubhouse.
At the present time, the Project Site contains no purpose-built stormwater management practices.
However, the open water ponds and the interconnecting drainage system that occupies the golf
courses on the Project Site serve to detain and convey surface flows from portions of the Project
Site east and west of Kiamesha Creek to the lowlands at the center of the Project Site. These
drainage features include a network of culverts and swales built on the golf courses to channel
water away from the fairways. The ponds also provide water features for the golf courses. The
golf courses’ existing drainage network adequately conveys smaller design flows. However, due
to the low elevations of many of the fairways and greens located within the floodplain of
Kiamesha Creek, the Monster Golf Course experiences considerable flooding during larger
storm events.
Since there is minimal stormwater infrastructure located within the roadway network, the
majority of the Project Site runoff travels to the existing wetlands and waterbodies via overland
flow, and through tributary streams and brooks. In some areas, man-made swales parallel to the
roadways collect and convey the stormwater through culvert crossings. These small (in the range
of 8-inch to 24-inch) culverts channel stormwater flows under roadways and driveway crossings.
They also serve, in some instances, to maintain the hydrologic connections between wetlands.
The existing stormwater runoff on the Project Site presently discharges to approximately 23
design points. While some of these design points are directed to a structural element such as a
culvert, the majority of the points are defined as the locations at which overland flow enters a
wetland or waterbody.
To perform the required calculations, a “curve number” (CN) was assigned to each drainage area
under existing and proposed conditions based on the ground surface cover and percentage
imperviousness. The CNs used for the existing condition assumes 100 percent wooded and
vegetative cover for all the areas, corresponding to 0 percent impervious coverage. This is a
conservative strategy, commonly used in the conceptual design phase, which generates a larger-
than-actual runoff volume to be detained, and consequently the design of a conservatively-sized
stormwater storage system.
“Curve number” and “time of concentration” were determined for each drainage area and used
to calculate peak discharge for the 100-year, 24-hour storm event. Once the peak discharge was
determined for pre-and post-construction conditions, the required storage volume was calculated
in acre-feet by multiplying the Vs/Vr factor by the proposed drainage area and the post-
developed runoff depth (in inches) for the design storm.
The conceptual size (surface area) of the proposed detention basins was determined by assuming
a 4-foot average depth of storage volume. This is the basis for the conceptual design of the
stormwater management facilities for future phases of the Proposed Project. The locations of the
conceptual detention basins (excluding Phase 1, which is considered in greater detail below) are
shown in Figure 7-1.
Tables 7-2 to 7-5 show the drainage computations used to size the stormwater detention basins.
Table 7-2
Existing Conditions
Existing Drainage
Drainage Area # Area (ac) Flowrate (cfs) Runoff Volume (af) Runoff Depth (in)
1 52 93.26 15.57 3.60
2 28 60.58 8.36 3.63
3 31 46.23 9.29 3.57
4 37 96.05 11.14 3.64
5 43 91.21 12.86 3.62
6A 9 13.96 2.62 3.58
6B 28 45.07 8.47 3.58
7A 8 17.89 2.29 3.63
7B 18 42.16 5.39 3.63
8 23 42.40 6.86 3.61
9 22 52.35 6.79 3.63
10 57 128.25 17.16 3.63
11A 24 48.70 7.30 3.62
11B 63 127.16 19.06 3.62
12 48 92.01 14.47 3.61
13 52 100.44 15.78 3.61
14 104 183.33 31.20 3.60
15 24 51.95 7.15 3.63
Notes: acre (ac), acre feet (af), cubic feet per second (cfs), inches (in)
Table 7-3
Proposed Conditions
Proposed Drainage
Drainage Area # Area (ac) Flowrate (cfs) Runoff Volume (af) Runoff Depth (in.)
1 56 195.71 19.98 4.28
2 41 186.86 14.34 4.19
3 32 140.61 11.09 4.19
4 41 182.44 14.03 4.09
5 43 185.33 14.62 4.08
6A 9 41.29 3.15 4.30
6B 28 147.03 11.45 4.84
7A 8 41.47 2.98 4.74
7B 18 97.72 7.02 4.74
8 23 97.77 7.98 4.19
9 22 121.74 9.26 4.96
10 62 200.22 20.45 3.96
11A 24 118.72 8.05 3.99
11B 63 317.34 21.56 4.09
12 44 206.78 14.54 3.98
13 52 252.15 17.42 3.98
14 106 499.10 39.77 4.51
15 37 177.02 14.81 4.84
Notes: acre (ac), acre feet (af), cubic feet per second (cfs), inches (in)
Table 7-4
Existing and Proposed Flowrate and Volume Comparison
Proposed Difference
Existing Proposed Existing Runoff Runoff Volume Runoff Volume
DA Flowrate (cfs) Flowrate (cfs) Volume (af) (af) (af)
1 93.26 195.71 15.57 19.98 4.41
2 60.58 186.86 8.36 14.34 5.97
3 46.23 140.61 9.29 11.09 1.80
4 96.05 182.44 11.14 14.03 2.89
5 91.21 185.33 12.86 14.62 1.76
6A 13.96 41.29 2.62 3.15 0.53
6B 45.07 147.03 8.47 11.45 2.98
7A 17.89 41.47 2.29 2.98 0.70
7B 42.16 97.72 5.39 7.02 1.64
8 42.40 97.77 6.86 7.98 1.11
9 52.35 121.74 6.79 9.26 2.47
10 128.25 200.22 17.16 20.45 3.29
11A 48.70 118.72 7.30 8.05 0.75
11B 127.16 317.34 19.06 21.56 2.51
12 92.01 206.78 14.47 14.54 0.08
13 100.44 252.15 15.78 17.42 1.64
14 183.33 499.10 31.20 39.77 8.57
15 51.95 177.02 7.15 14.81 7.66
Notes: acre feet (af), cubic feet per second (cfs)
Kiame
sha La
ke Roa
d
d
Roa
cord
Con
Ro
ad
ute
e Ro
16
1
Ridg
Road
Rock
Chalet
Thompsonville Road
Table 7-5
Storage Volume Estimation
Proposed Existing Surface
Volume Volume Area (4 ft
DA (af) (af) Vr (af) qo (cfs) qI (cfs) Vs/Vr Qd (in) A (ac) Vs (af) deep pond)
1 19.98 15.57 19.98 93.26 195.70 0.29 4.28 55.97 5.71 62,167.17
2 14.34 8.36 14.34 60.58 186.86 0.36 4.28 41.10 5.33 58,007.24
3 11.09 9.29 11.09 46.23 140.61 0.36 4.28 31.80 4.09 44,532.79
4 14.03 11.14 14.03 96.05 182.44 0.27 4.28 41.30 3.92 42,731.67
5 14.62 12.86 14.62 91.21 185.33 0.28 4.28 43.00 4.29 46,699.85
6A 3.15 2.62 3.15 13.96 41.29 0.35 4.30 30.40 3.87 42,103.19
6B 11.45 8.47 11.45 45.07 147.03 0.37 4.84 30.40 4.59 50,018.41
7A 2.98 2.29 2.98 17.89 41.47 0.31 4.74 29.30 3.54 38,537.03
7B 7.02 5.39 7.02 42.16 97.72 0.31 4.74 29.30 3.54 38,534.66
8 7.98 6.86 7.98 42.40 97.77 0.30 4.19 21.70 2.31 25,142.54
9 9.26 6.79 9.26 52.35 121.74 0.31 4.28 22.50 2.46 26,777.47
10 20.45 17.16 20.45 128.25 200.22 0.23 4.28 61.90 5.03 54,722.45
11A 8.05 7.30 8.05 48.70 118.72 0.32 3.99 63.30 6.65 72,398.62
11B 21.56 19.06 21.56 127.16 317.34 0.32 4.28 63.30 7.24 78,821.05
12 14.54 14.47 14.54 92.01 206.78 0.30 4.28 43.90 4.69 51,081.47
13 17.42 18.12 17.42 115.34 252.15 0.29 4.28 52.50 5.51 59,967.44
14 39.77 31.20 39.77 183.33 499.10 0.34 4.28 105.8 12.76 138,962.97
15 14.81 7.15 14.81 51.95 177.02 0.38 4.28 36.8 5.03 54,781.43
Notes: acre (ac), acre feet (af), cubic feet per second (cfs), inches (in)
Filtering Systems
Surface Sand Filter
Underground Sand Filter
Perimeter Sand Filter
Organic Filter
Bioretention
In accordance with NYSDEC runoff reduction volume requirements, green infrastructure will be
incorporated into the stormwater management design where feasible to further reduce runoff and
provide water quality treatment. Green infrastructure practices are now a required element of
stormwater management design intended to enable the post-developed condition to closely
replicate pre-development conditions.
Some of the green infrastructure practices which may be employed include:
Rain garden/bioretention basin
Porous pavement/pervious pavers
Rain barrels/cistern
Vegetated swales
Tree planting/tree box
Disconnection of rooftop runoff
Green roof
Stormwater planter
Conservation of natural areas
KIAMESHA CREEK FLOODING ABATEMENT
The Proposed Project proposes to redesign the existing Monster Golf Course in the center of the
Project Site to retain a wide central green space on either side of Kiamesha Creek. Development
of new buildings, roadways, and related impervious surfaces is not proposed in close proximity
to Kiamesha Creek so that the stream resource can be protected and enhanced. In the past, the
low-lying topography of the course resulted in frequent flooding, which has likely been
exacerbated by upstream development along the Kiamesha Creek corridor. Proposed Project
components intended to remedy this situation include:
Implementation of stormwater management practices to capture, detain, and recharge the
groundwater close to the source of the runoff so that the Creek is not overburdened with
Proposed Project-generated runoff.
The redesigned golf course would improve course irrigation and drainage systems to reduce
weather-related course closings.
CUMULATIVE STORMWATER IMPACTS
As noted previously, several approved development projects, “No Build projects,” within the
study area have been identified and are analyzed in this DGEIS. While some of these projects
may be within the drainage area contributing surface water runoff to the Project Site, these No
Build projects must all conform to the NYSDEC SPDES General Permit No. GP-0-10-001 and
MITIGATION
Based on the information and analysis presented above, the Proposed Project will not result in
any significant adverse impacts from stormwater runoff. Sufficient space and locations have
been incorporated in the future development phases of the Proposed Project to allow for all of
the necessary stormwater infrastructure that will be required.
For each phase of the Proposed Project, changes in stormwater runoff characteristics will be
evaluated and a SWPPP would be developed in accordance with NYSDEC design guidelines
and SPDES General Permit No. GP-0-10-001 to mitigate potential impacts identified. The
resulting SWPPP will require review and approval by the NYSDEC in advance of the
development of each future phase of the Proposed Project. Therefore, potential impacts from
stormwater runoff, including flooding and erosion impacts, will be avoided. No further
mitigation will be required.
Based on the preliminary geotechnical report the predominant soil type throughout the project
site is silty sand, or a sandy silt mixture. Only three of the 50 samples collected were inorganic
silts and very fine sands, or soil that has more than 50% passing the 200 sieve. However, as a
precautionary method, soil stabilization procedures will include the spray application of soil
stabilizers in addition to the standard erosion and sediment control measures. This method of
soil stabilization will reduce soil erosion. Most stormwater runoff will be conveyed to
temporary sediment basins where flocculant would be added to the temporary sediment basin as
necessary. All necessary DEC permits would be obtained prior to the use of any chemicals
within the ponds.
EXISTING CONDITIONS
The following section provides a summary of the stormwater conditions and stormwater
management plan developed for the Phase 1 Site. Additional information on the hydrologic
analysis for the Phase 1 Site is contained in the Draft SWPPP found in Appendix G.
The Phase 1 Site is approximately 125 acres in size and is located in the southern portion of the
Project Site. It is bordered by Thompsonville Road on the north and Joyland Road on the east.
At present, there are no structures or built features on the Phase 1 Site. The Site consists of
forested land and manicured lawns within the existing Monster Golf Course.
Substantive stormwater infrastructure does not exist within the Phase 1 Site. Drainage on the
Phase 1 Site generally flows from the high area located along the western side of Joyland Road
to the low-lying wetlands and lakes to the west. Stormwater runoff travels via overland flow
across the Phase 1 Site toward the Tannery Brook which ultimately discharges into Kiamesha
Creek. The elevations on the Phase 1 Site range from a high of approximately 1,455 feet along
the eastern property line to a low of approximately 1,342 feet in the southwestern corner of the
Site at the pond adjacent to Thompsonville Road.
Since there is minimal stormwater infrastructure located within the roadway network, the
majority of the existing Phase 1 Site runoff travels via overland flow, natural channels, and
through tributary streams and brooks. In some areas, such as along the southern side of
Thompsonville Road, man-made swales parallel to the roadway collect and convey the
stormwater through culvert crossings. These small (in the range of 8-inch to 24-inch) culverts
channel stormwater flows under roadways and driveway crossings. They also serve, in some
instances, to maintain the hydrologic connections between wetlands.
DESIGN POINTS
The existing stormwater runoff from the Phase 1 Site presently discharges to five “design
points” - points of discharge at the periphery of the Phase 1 Site used to analyze changes in
runoff from development. While some of these design points are pinpointed to a structural
element such as a culvert, the majority of the points are defined as the locations at which
overland flow enters a wetland or waterbody. Figure 7-2 shows the location of the pre-
development design points and contributing drainage areas.
PHASE 1 BOUNDARY
SCALE
Phase 1 Stormwater Pre-Development
EPT CONCORD RESORT Draft Environmental Impact Statement Figure 7-2
Chapter 7: Stormwater Management
Table 7-7
Comparison of Pre- and Post-Development Conditions – Design Point 3
Pre-Development DP-3 Post-Development DP-3
Flow (cfs) 21.13 14.02
1 – Year Storm
Volume (CF) 153,810 358,586
Flow (cfs) 113.57 68.96
10 – Year Storm
Volume (CF) 736,381 1,088,303
Flow (cfs) 175.38 107.49
100 – Year Storm
Volume (CF) 1,138,876 1,560,581
Table 7-8
Comparison of Pre- and Post-Development Conditions – Design Point 4
Pre-Development DP-4 Post-Development DP-4
Flow (cfs) 10.46 9.41
1 – Year Storm
Volume (CF) 54,668 70,524
Flow (cfs) 53.58 52.94
10 – Year Storm
Volume (CF) 252,866 268,112
Flow (cfs) 82.18 75.29
100 – Year Storm
Volume (CF) 388,425 397,659
Phase 1 Boundary
Raingarden/Bioretention Basin
Porous Pavement
SCALE
Phase 1 Green Infrastructure
EPT CONCORD RESORT Draft Environmental Impact Statement Figure 7-3
6.14.12
PHASE 1 BOUNDARY
SCALE
Phase 1 Stormwater Post-Development
EPT CONCORD RESORT Draft Environmental Impact Statement Figure 7-4
Chapter 7: Stormwater Management
Table 7-9
Comparison of Pre- and Post-Development Conditions – Design Point 5
Pre-Development DP-5 Post-Development DP-5
Flow (cfs) 4.08 0.16
1 – Year Storm
Volume (CF) 22,041 23,174
Flow (cfs) 19.85 2.58
10 – Year Storm
Volume (CF) 98,489 88,950
Flow (cfs) 30.16 3.72
100 – Year Storm
Volume (CF) 150,282 131,594
need for modifications to the Erosion and Sediment Control Plan will be identified and
implemented immediately.
All maintenance will be completed in accordance with the New York State Standards and
Specifications for Erosion and Sediment Control.
MITIGATION
Peak flows have been reduced through the implementation of green infrastructure and standard
stormwater management practices. Post-development peak flows are less than the pre-
development conditions. Therefore, it has been demonstrated that the proposed stormwater
drainage and treatment system described above mitigates the impacts associated with the
development of Phase 1.
The preparation of the SWPPP and Erosion and Sediment Control Plan (described above) in
accordance with SPDES GP 0-10-001 will also satisfy the requirements of the Delaware River
Basin Commission. The Commission will have the opportunity to review the SWPPP concurrent
with review by the NYSDEC. Once found satisfactory by both agencies, this will finalize review
and approval of the stormwater management-related components of Phase 1.
Separately, as part of the horse housing/feeding operation conducted for the harness horse
racetrack component of Phase 1, the General Permit for Concentrated Animal Feeding
Operations (CAFOs) - General Permit GP-0-09-001, will be submitted for review and approval
by the NYSDEC. The harness horse racetrack component of Phase 1 will be permitted once
NYSDEC accepts the best management and Comprehensive Nutrient Management Plan. These
elements of the harness horse racetrack operation will be completed during the site plan approval
process for Phase 1. Monticello Raceway Management, Inc.’s existing CAFO permit will be
modified to include the operations at the Phase 1 Site.
Implementation of the State-approved SWPPP for Phase 1 will avoid potential adverse impacts
caused by surface water runoff. Therefore, no further mitigation will be required.