Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

BOQ Pricing

Download as pdf or txt
Download as pdf or txt
You are on page 1of 12

d/15/1

ITEM ITEM DESCRIPTION UNIT QUANTITY RATE AMOUNT


UAE. Dhs.

BILL NO. 9 STREET LIGHTING WORKS

PIPE WORK: MANHOLES AND PIPE WORKS


ANCILLARIES

Ducts

uPVC cable ducts to BS 3536 class C laid and


jointed in trench beneath carriage ways
inckuding end caps, 8mm dua cords, studs and
concrete ducts markers as specified

A 2 Way; 100mm dia depth not exceeding 1.5m nr 525

B 4 Way; 100mm dia depth not exceeding 1.5m nr 506

PIPE WORK: SUPPORTS AND PROTECTION


ANCILLARIES TO LAYING AND EXCAVATON
Beds and Surround including warning tape

Imported sand bed and surround to 2 way duct


G nr 315
100mm dia

Imported sand bed and surround to 4 way duct


H nr 304
100mm dia

Mass concrete bed and surround to 2 way duct


nr 210
100mm dia

Mass concrete bed and surround to 4 way duct


nr 202
100mm dia

To Part Summary Dhs.

BILL NO. 9 STREET LIGHTING WORKS


(Cont'd…)

MISCELLANEOUS WORKS

Carefuly remove and set aside the existing


lighting pole: including excavation of
foundation, disposal backfilling and compacting
with selected excavated material and making
good the surface, reusable materials to be
retained by contractor for possible reuse on

Existing 10m to 14m high lighting pole with


A nr 25 563.00 14,075.00
luminaires

Remove of Existing cable


d/15/2

ITEM ITEM DESCRIPTION UNIT QUANTITY RATE AMOUNT


UAE. Dhs.

BILL NO. 9 STREET LIGHTING WORKS

Carefully remove existig cables including


disconnections, excavation backfilling of voids,
complete as per local authority (FEWA)
requirements ans dilever to FEWA -ED

5 1 way 6.6/11 KV cable m 50 8.00 400.00


Size not indicated, considered 3C 300
2 way 6.6/11 KV cable m 75 17.00 1,275.00
Size not indicated, considered 3C 300
Lowering of existing cable

Carefully remove existing cables including


desconnection, excavation, backfilling of voids
m 80 10.00 800.00
complete as per local authority / FEWA
requirements and lowering

Size not indicated, considered 4C 35 and 1 C 25


Carefully remove and diversion of existing cables
including excavation laying protection, cleaning
backfilling and disposal excavated material to
A m 70 10.00 700.00
approved tip, bed and surround and all related
works complete as per local authority / FEWA
standard
Size not indicated, considered 4C 35 and 1 C 25

To Part Summary Dhs. 17,250.00

BILL NO. 9 STREET LIGHTING WORKS


(Cont'd…)
MISCELLANEOUS WORKS

Mass concrete high lighting column bases


complete as detailed on drawing including
excavation backfilling, compaction formwork,
concete, holding down with 12mm rebar link
protection of holdng down bolts nuts and
washer with densotape (before casting and after
erection) bitumen paint etc.

A Foundation for 10m lighting column nr 355


d/15/3

ITEM ITEM DESCRIPTION UNIT QUANTITY RATE AMOUNT


UAE. Dhs.

BILL NO. 9 STREET LIGHTING WORKS

B Foundation for 14m lighting column nr 321

Foundation for existing 10m Height lighting column nr 6

Mass concrete foundation for feeder pillar as


detailed on dwg, including excavation backfillinh
concrete, formwork, holding down chemical anchor
C nr 20
bolts, stainledd steel cover plate, protection of
holding down bolts nuts and washers awith
densotape, bitumen paint etc

To Part Summary Dhs.

BILL NO. 9 STREET LIGHTING WORKS


(Cont'd…)

MISCELLANEOUS WORKS (Cont'd)

Supply and Install LED Luminaires and


accessories complete with brackets, lamps and
cutouts termination cables, commission and
handling as shown on dwg and specification

A Existing Lighting pole retained with 1 new Luminary nr 88 63.00 5,544.00

B Existing Lighting pole retained with 1 new Luminary nr 44 63.00 2,772.00

C Existing Lighting pole retained with 2 new Luminary nr 177 125.00 22,125.00

D Existing Lighting pole replacing with 1 new Luminary nr 6 63.00 378.00


d/15/4

ITEM ITEM DESCRIPTION UNIT QUANTITY RATE AMOUNT


UAE. Dhs.

BILL NO. 9 STREET LIGHTING WORKS

Supply and Install lighting column and


accessories complete with brackets, LED
E Luminaries lamps and cutouts termination
cables, commision and grouting of base plate
and andling as shown on dwg and specification

G 10m high lighting column with 1 luminary nr 306 563.00 172,278.00

H 10m high lighting column with 2 luminary nr 42 625.00 26,250.00

J 14m high lighting column with 1 luminary nr 43 563.00 24,209.00

K 14m high lighting column with 2 luminary nr 270 625.00 168,750.00

L 14m high lighting column with 3 luminary nr 8 688.00 5,504.00

Relocation of existing set aside lighting pole as


M nr 6 563.00 3,378.00
detailed on drawing and specification

To Part Summary Dhs. 431,188.00

BILL NO. 9 STREET LIGHTING WORKS


(Cont'd…)

MISCELLANEOUS WORKS (Cont'd)

Feeder Pillar
Supply and Install of feeder pillar including with
accessories including termination of cables and
commisioning and all related works complete as
directed by the engineer and as per the
SEWA/FEWA standard specification

A 2 way Feeder Pillar nr 10 500.00 5,000.00

B 4 way Feeder Pillar nr 5 1,000.00 5,000.00


d/15/5

ITEM ITEM DESCRIPTION UNIT QUANTITY RATE AMOUNT


UAE. Dhs.

BILL NO. 9 STREET LIGHTING WORKS

C 6 way Feeder Pillar nr 4 1,000.00 4,000.00

D 8 way Feeder Pillar nr 1 1,000.00 1,000.00

E Lighting Panel

Supply and Install of Underbridge lighting panel


including with accessoried including termination of
F cables and commissioning and all related works
complete as directed by the engineer and as per the
SEWA/FEWA standard specification

Underbridge Lighting Panel nr 5 500.00 2,500.00

To Part Summary Dhs. 17,500.00

BILL NO. 9 STREET LIGHTING WORKS


(Cont'd…)

MISCELLANEOUS WORKS (Cont'd)

Excavate for cable trenches

Trench not exceeding 1.5m deep width varying


B m 20,111
between 0.4-0.8 for varying number of cables
d/15/6

ITEM ITEM DESCRIPTION UNIT QUANTITY RATE AMOUNT


UAE. Dhs.

BILL NO. 9 STREET LIGHTING WORKS

Supply and Intall the following power supply cabling


C in trench including warning tape etc, as shown on
the drawings and specification

4C 16mm2 Cu/XLPE/SWA/PVC + 1C 16mm2


D m 15,111 38.00 574,218.00
Cu/PVC 1way

4C 25mm2 Cu/XLPE/SWA/PVC + 1C 25mm2


E m 10,439 57.00 595,023.00
Cu/PVC 1way

4C 50mm2 Cu/XLPE/SWA/PVC + 1C 25mm2


F m 5,000 174.00 870,000.00
Cu/PVC 2way

Warning Tape 250mm wide with English and Arabic


G m 20,111
written as approved by Road Lighting Department

Termination Item 1 58,476.00 58,476.00

To Part Summary Dhs. 2,097,717.00

BILL NO. 9 STREET LIGHTING WORKS


(Cont'd…)

MISCELLANEOUS WORKS (Cont'd)

Supply and Install the following power supply


cabling not in trech as shown on the drawings and
specification

A 4C 50mm2 cable + 1C 25mm2 earth cable 1 way m 50 79.00 3,950.00

B 4C 75mm2 cable + 1C 50mm2 earth cable 1 way m 50 113.00 5,650.00

Earthing System

Supply and Install complete earthing system


including excavation backfilling, compaction and nr 128
handling as shown in dwg and specification
d/15/7

ITEM ITEM DESCRIPTION UNIT QUANTITY RATE AMOUNT


UAE. Dhs.

BILL NO. 9 STREET LIGHTING WORKS

To Part Summary Dhs. 9,600.00

BILL NO. 9 STREET LIGHTING WORKS


(Cont'd…)

MISCELLANEOUS WORKS (Cont'd)

WIRELESS CENTRALISED STREET LIGHTING


CONTROL SYSTEMS (CMS)

Supply and Installation, testing and


commissioning of street lighting management
system (CMS) including node controllers, base
staton , servers, software and internet interface
and interface with MOID central system and all
other necessary accessories as per MOID
requirement.

A Control node per each pole as specified nr 622

GSM dual sim WAN/LAN, WIFI interface Base


B nr 2
station, location to be proposed by supplier

GSM Base station post complete with pole


foundation, ducting, ducts crossing and all
C accessories for power supply. Base station shall be nr 2
powered for nearest feeder pillar (Power cable
measured elsewhere).

D High grade industrial inter based servers as nr 2

Life time licensed, upgrade supported software,


license shall be in accordance with total numbers of
nodes specified or as per client requirement.
E sum 1
Hosting of server at local service provider data
center and clouding of the software costs to be
included

Traffic Detection sencor (Traffic volume


measurement) completeincluding posts, foundation,
F nr 3
cabling, testing and commissioning (Traffic volume
measurement).

2 Years technical support for all the CMS


G components including control nodes base station sum 1
software update.. Etc

H Training of client engineers as specified. nr 1


d/15/8

ITEM ITEM DESCRIPTION UNIT QUANTITY RATE AMOUNT


UAE. Dhs.

BILL NO. 9 STREET LIGHTING WORKS

To Part Summary Dhs.

BILL NO. 9 STREET LIGHTING WORKS


(Cont'd…)

MISCELLANEOUS WORKS (Cont'd)

WIRELESS CENTRALISED STREET LIGHTING


CONTROL SYSTEMS (CMS) (Cont'd)

Drawings, O&M Manuals (Hard & Soft copies in


PDF Format, approvals and nstruction books for
A sum 1
central lighting amanagement system supplied as
specified and as per client's / Engineers Approval.

Spare Parts for 2 Years trouble free operaion as per


manufacturer recommendation & supplier records of
B sum 1
system components failure in precious installation /
Project

Integration of CMS with central lighting


C management system. Location & Interface sum 1
requirement to be coordinated with MOID

System Testing validation and output report


D sum 1
Evaluation as specified
d/15/9

ITEM ITEM DESCRIPTION UNIT QUANTITY RATE AMOUNT


UAE. Dhs.

BILL NO. 9 STREET LIGHTING WORKS

Other accessories, provisions etc to make the


E system effeciently operation as per employer's & sum 1
Engineers Instruction

To Part Summary Dhs.

BILL NO. 9 STREET LIGHTING WORKS


(Cont'd…)

Additional Items
d/15/10

ITEM ITEM DESCRIPTION UNIT QUANTITY RATE AMOUNT


UAE. Dhs.

BILL NO. 9 STREET LIGHTING WORKS

The tendered is to identify here below any other


items which he may consider applicable yet not
given in the BOQ, quantifued and priced to
ensure the sufficiency and completenss of the
lump sum price includes all items whether
shown on the drawings or implied by
interpretation, or described in the specifications
or deemed necessary by the tenderer based on
their field inspection or to cover any other
obligation / risk allocated to the contractor. the
lumpsum price shall represent the entire value
of the works and no subsequent clain for any
additional items wil be entertained.
d/15/11

ITEM ITEM DESCRIPTION UNIT QUANTITY RATE AMOUNT


UAE. Dhs.

BILL NO. 9 STREET LIGHTING WORKS

To Part Summary Dhs.

PART SUMMARY

Page

Page 17,250.00

Page

Page 431,188.00

Page 17,500.00

Page 2,097,717.00

Page 9,600.00

Page

Page

Page

Page

Page

Page

Page

Page

Page
d/15/12

ITEM ITEM DESCRIPTION UNIT QUANTITY RATE AMOUNT


UAE. Dhs.

BILL NO. 9 STREET LIGHTING WORKS

Page

Total for Part 15 - RTA - Road Lighting Works


Carried to Grand Summary Dhs. 2,573,255.00