Centrifugal Liquid Chillers: Installation and Reassembly
Centrifugal Liquid Chillers: Installation and Reassembly
Centrifugal Liquid Chillers: Installation and Reassembly
YMC2 MODEL B
WITH OPTIVIEW™ CONTROL CENTER
LD17194
R-134a
Issue Date:
October 25, 2015
FORM 160.84-N1
ISSUE DATE: 10/25/2015
IMPORTANT!
READ BEFORE PROCEEDING!
GENERAL SAFETY GUIDELINES
This equipment is a relatively complicated apparatus. which it is situated, as well as severe personal injury or
During rigging, installation, operation, maintenance, death to themselves and people at the site.
or service, individuals may be exposed to certain com-
ponents or conditions including, but not limited to: This document is intended for use by owner-authorized
heavy objects, refrigerants, materials under pressure, rigging, installation, and operating/service personnel. It
rotating components, and both high and low voltage. is expected that these individuals possess independent
Each of these items has the potential, if misused or training that will enable them to perform their assigned
handled improperly, to cause bodily injury or death. It tasks properly and safely. It is essential that, prior to
is the obligation and responsibility of rigging, instal- performing any task on this equipment, this individual
lation, and operating/service personnel to identify and shall have read and understood the on-product labels,
recognize these inherent hazards, protect themselves, this document and any referenced materials. This in-
and proceed safely in completing their tasks. Failure dividual shall also be familiar with and comply with
to comply with any of these requirements could result all applicable industry and governmental standards and
in serious damage to the equipment and the property in regulations pertaining to the task in question.
SAFETY SYMBOLS
The following symbols are used in this document to alert the reader to specific situations:
External wiring, unless specified as an optional connection in the manufacturer’s product line, is
not to be connected inside the OptiViewTM cabinet. Devices such as relays, switches, transducers and
controls and any external wiring must not be installed inside the cabinet. All wiring must be in ac-
cordance with Johnson Controls’ published specifications and must be performed only by a qualified
electrician. Johnson Controls will NOT be responsible for damage/problems resulting from improper
connections to the controls or application of improper control signals. Failure to follow this warning
will void the manufacturer’s warranty and could cause serious damage to property or personal injury.
2 JOHNSON CONTROLS
FORM 160.84-N1
ISSUE DATE: 10/25/2015
ASSOCIATED LITERATURE
JOHNSON CONTROLS 3
FORM 160.84-N1
ISSUE DATE: 10/25/2015
SYSTEM NOMENCLATURE
Y M C 2 - S 0756 A B
YORK Mod Level
Magnetic Bearing Refrigerant R-134a
Centrifugal Chiller Capacity in KW
S = Single Stage
T = Two Stage
COMPRESSOR NOMENCLATURE
M2 B - 197 F A C D
Motor Down Discharge
Motor Design Level Gas Path Revision Level
Impeller Tip Diameter (mm) Impeller Design Revision Level
Rotation
F = Forward
R = Reverse
VESSEL NOMENCLATURE
E A 25 14 271 B R 1 1 F C R
Inlet from Front View
Vessel
R = Right
E = Evaporator
L = Left
C = Condenser
Heat Exchanger Mod Level Waterbox Type
C = Compact
Nominal Inside Diameter (Inches)
M = Marine
Nominal Length (Feet) Water Connection Type
Marketing Tube Number F = Flanges
Tube Code G = Grooved Standard
B = 3/4" Code 1 A = Victaulic AGS
C = 3/4" Code 2 Number of Passes
D = 3/4" Code 3 Vessel Refrigerant Pressure Code Water Side Pressure Code
E = 3/4" Code 4 R = Code 180 1 = 150 psi
2 = 1" Code 1 S = Code 235 3 = 300 psi
3 = 1" Code 2 T = Code 300
4 = 1" Code 3 U = Code 350
5 = 1" Code 4 V = Code 400
4 JOHNSON CONTROLS
FORM 160.84-N1
ISSUE DATE: 10/25/2015
TABLE OF CONTENTS
SECTION 1 - OVERVIEW..........................................................................................................................................9
General.............................................................................................................................................................. 9
Component Combinations................................................................................................................................. 9
Inspection – Damage – Shortage.................................................................................................................... 10
Chiller Data Plate............................................................................................................................................ 10
YMC2 Shipment Forms....................................................................................................................................10
Form 1.................................................................................................................................................... 11
Form 2.................................................................................................................................................... 11
Form 3.................................................................................................................................................... 11
Form 7....................................................................................................................................................12
Form 9....................................................................................................................................................12
Form 10 .................................................................................................................................................13
Form 11..................................................................................................................................................14
JOHNSON CONTROLS 5
FORM 160.84-N1
ISSUE DATE: 10/25/2015
SECTION 3 - INSTALLATION.................................................................................................................................31
Overview......................................................................................................................................................... 31
Determine Location......................................................................................................................................... 31
Foundation Requirements......................................................................................................................31
Clearance Requirements........................................................................................................................31
Rig Unit To Final Location............................................................................................................................... 31
Install Isolators................................................................................................................................................ 31
Neoprene Isolator Pads..........................................................................................................................31
Install Optional Spring Isolators.............................................................................................................. 34
Make Connections........................................................................................................................................... 35
Piping Connections................................................................................................................................35
Refrigerant Relief Piping........................................................................................................................38
Unit Piping..............................................................................................................................................39
Control Wiring.........................................................................................................................................39
Power Wiring..........................................................................................................................................39
Supplied Variable Speed Drive............................................................................................................... 39
Apply Insulation............................................................................................................................................... 39
Installation Check – Request For Startup Service...........................................................................................39
SECTION 4 - REASSEMBLY...................................................................................................................................41
Form 3 and Form 7 Reassembly............................................................................................................ 41
Form 9 and Form 10 Reassembly.......................................................................................................... 48
Form 11 Reassembly.............................................................................................................................50
Refrigerant Tubing Reassembly...................................................................................................................... 52
Assembly of Straight Thread O-ring Port Fittings................................................................................... 52
Assembly of O-ring Face Seal Fittings................................................................................................... 53
6 JOHNSON CONTROLS
FORM 160.84-N1
ISSUE DATE: 10/25/2015
LIST OF FIGURES
JOHNSON CONTROLS 7
FORM 160.84-N1
ISSUE DATE: 10/25/2015
LIST OF TABLES
8 JOHNSON CONTROLS
FORM 160.84-N1
ISSUE DATE: 10/25/2015
SECTION 1 - OVERVIEW 1
GENERAL They can also be shipped dismantled when required by
rigging conditions, but it is generally more economical
This manual provides instructions for rigging and in-
to enlarge access openings to accommodate the factory
stalling a YMC2 Liquid Chilling Unit.
assembled unit. Chillers that are shipped dismantled
Chillers can be shipped as a single factory assembled, MUST be field-assembled under the supervision of a
piped, wired package, requiring a minimum of field la- Johnson Controls representative, but otherwise instal-
bor to make chilled water connections, condenser wa- lation will be as described in this manual.
ter connections, refrigerant atmospheric relief connec-
tions, and electrical power connections. (Refrigerant COMPONENT COMBINATIONS
charges shipped separately unless optional condenser Figure 1 identifies the major components of the YMC2
isolation valves are ordered.) Chiller. The chiller is customized based on the selected
combination of Motor, Compressor, Evaporator, and
Condenser. Section 5 - Dimensions, Nozzle Arrange-
ments And Weights lists all of the allowable YMC2
Chiller combinations.
LIFTING
OPENINGS
COMPACT
WATERBOXES
CONDENSER
EVAPORATOR
LD14022b
JOHNSON CONTROLS 9
FORM 160.84-N1
Section 1 - Overview
ISSUE DATE: 10/25/2015
INSPECTION – DAMAGE – SHORTAGE 3. When units are shipped dismantled, notify the
nearest Johnson Controls office in ample time for
The unit shipment should be checked on arrival to see
a Johnson Controls representative to supervise
that all major pieces, boxes and crates are received.
rigging the unit to its operating position and the
Each unit should be checked on the trailer or rail car
assembly of components.
when received, before unloading, for any visible signs
of damage. Any damage or signs of possible damage 4. Do not make final power supply connections to
must be reported to the transportation company imme- the compressor motor drive or control center.
diately for their inspection. 5. Do not charge the unit with refrigerant.
JOHNSON CONTROLS WILL NOT BE RESPON- 6. Do not attempt to start the system.
SIBLE FOR ANY DAMAGE IN SHIPMENT OR AT 7. Do not run hot water (>110°F / 43°C max) or
JOB SITE OR LOSS OF PARTS. (Refer to Shipping steam through the evaporator or condenser at any
Damage Claims Form (Form 50.15-NM). time.
When received at the job site all containers should be
CHILLER DATA PLATE
opened and contents checked against the packing list.
Any material shortage should be reported to Johnson A unit data plate is mounted on the control center as-
Controls immediately. (Refer to Shipping Damage sembly of each unit, giving unit model number; design
Claims Form (Form 50.15-NM). working pressure; water passes; refrigerant charge; se-
rial numbers; and motor power characteristics and con-
YMC2 Chillers are not intended to be stored outdoors, nection diagrams.
exposed to rain and moisture. The shipping wrap is for
shipping, not for extended outdoor storage. The chiller Additional information may be found on the compres-
should be tarped during any delays to get indoors and sor and motor data plates. This information should be
moisture desiccant, available for purchase for inside included when contacting the factory on any problem.
electrical panels should be used for damp areas.
YMC2 SHIPMENT FORMS
If the chiller was not shipped complete (as shown in
Form 1 or 2) use the Section 4 - Reassembly in con- The chiller may be ordered and shipped in any of the
junction with this installation manual. following forms:
The services of a Johnson Controls representative will • Form 1 (shipped complete with refrigerant charge)
be furnished to check the installation, supervise the • Form 2 (shipped complete with refrigerant charge
initial start-up and operation of all chillers installed shipped separately)
within the Continental United States.
• Form 3 (shipped in three assemblies)
The Johnson Controls Warranty may be • Form 7 (shipped in four assemblies)
voided if the following restrictions are not
adhered to. • Form 9 (shipped in two assemblies with refriger-
ant charge shipped separately)
• Form 10 (shipped in two assemblies with refriger-
ant charge)
1. No valves or connections should be opened under
• Form 11 (shipped as split shells with refrigerant
any circumstances because such action will result
charge)
in loss of the factory refrigerant (Form 1) or nitro-
gen charge (Form 2). Units that are shipped dismantled MUST
2. Do not dismantle or open the chiller for any rea- be reassembled by, or under the supervi-
son except under the supervision of a Johnson sion of a Johnson Controls representative.
Controls representative. Refer to Section 4 - Reassembly for de-
tailed reassembly instructions.
10 JOHNSON CONTROLS
FORM 160.84-N1
Section 1 - Overview
ISSUE DATE: 10/25/2015
When more than one chiller is involved, • The complete unit is factory leak-tested, evacu-
the major parts of each unit will be ated, and shipped charged with a 3 to 7 PSIG (20 1
marked to prevent mixing of assemblies. to 50 kPa) holding charge of dry nitrogen.
Piping and wiring drawings to be fur-
• The OptiView™ Control Center is mounted on
nished by Johnson Controls.
the unit.
• The Variable Speed Drive (VSD) and Power Pan-
Form 1
el are mounted, wired, and shipped with Glycol.
The chiller is shipped complete with miscellaneous
loose items shipped together and refrigerant charges Miscellaneous Items
are included. The following items are shipped together:
Chiller Unit • Four (4) vibration isolation pads (or optional
The unit is completely assembled at the factory. spring isolators and brackets).
• Other shipped loose items, including piping, wa-
• The driveline (compressor/motor assembly) is
ter temperature controls, wiring, etc.
mounted and all the necessary interconnecting
piping is assembled. • VSD operating coolant (inhibited water)
• The complete unit is factory leak-tested, evacuat- Form 3
ed, and shipped charged with R-134A refrigerant.
Prior to shipping, the unit is completely assembled at
• The OptiView™ Control Center is mounted on the factory. Interconnecting piping is assembled and
the unit. the complete unit is wired and leak-tested.
• The Variable Speed Drive (VSD) and Power Pan- The unit is dismantled and shipped as follows:
el are mounted, wired, and shipped with glycol.
1. The driveline (compressor/motor assembly).
Miscellaneous Items
2. The evaporator/condenser shell assembly.
The following items are shipped together:
3. The Variable Speed Drive (VSD).
• Four (4) vibration isolation pads (or optional
spring isolators and brackets). 4. Miscellaneous shipped loose items.
• Other shipped loose items, including piping, wa- Arrangements with the local service office must be
ter temperature controls, wiring, etc. made to ensure refrigerant is on-site when the unit is
ready to be charged.
Form 2
Driveline
The chiller is shipped complete with refrigerant charg-
es shipped separately and miscellaneous loose items The driveline (compressor/motor assembly) is re-
shipped together. moved from the shells and skidded.
Arrangements with the local service office must be • All integral wiring is left on the compressor.
made to ensure refrigerant is on-site when the unit is • All openings on the compressor are closed and
ready to be charged. shipped charged with a 3 to 7 PSIG (20 to 50 kPa)
holding charge of dry nitrogen.
Chiller Unit
The unit is completely assembled at the factory.
• The driveline (compressor/motor assembly) is
mounted and all the necessary interconnecting
piping is assembled.
JOHNSON CONTROLS 11
FORM 160.84-N1
Section 1 - Overview
ISSUE DATE: 10/25/2015
Shells Driveline
The evaporator and condenser are assembled prepared The driveline (compressor/motor assembly) is removed
for shipping but not skidded. from shells and skidded.
• All conduit is left on the shells. • All integral wiring is left on the compressor.
• All openings the shells are closed and charged • All wiring harnesses on shells are removed.
with a 3 to 7 PSIG (20 to 50 kPa) holding charge
• All openings on the compressor are closed and
of dry nitrogen.
shipped charged with a 3 to 7 PSIG (20 to 50 kPa)
Variable Speed Drive (VSD) holding charge of dry nitrogen.
The VSD is skidded and shipped separately from the Shells
assembled chiller.
The evaporator and condenser are separated at the tube
• The VSD is filled with glycol for shipping. The sheets and prepared for shipping separately but not
VSD operating coolant (inhibited water) is skidded.
shipped with the other loose items.
• All conduit is left on the shells.
Miscellaneous Material • Refrigerant lines between shells are flanged and
The following assemblies and items are shipped to- capped, requiring no welding.
gether:
• All openings the shells are closed and charged
• OptiView™ Control Center with a 3 to 7 PSIG (20 to 50 kPa) holding charge
of dry nitrogen.
• Power Panel
Variable Speed Drive (VSD)
• Four (4) vibration isolation pads (or optional
spring isolators and brackets). The VSD is skidded and shipped separately from the
assembled chiller.
• Other shipped loose items, including piping, wa-
ter temperature controls, wiring, etc. • The VSD is filled with glycol for shipping. The
VSD operating coolant (inhibited water) is shipped
• VSD operating coolant (inhibited water)
with the other loose items.
Form 7
Miscellaneous Items
Prior to shipping, the unit is completely assembled at
The following assemblies and items are shipped to-
the factory. Interconnecting piping is assembled and
gether:
the complete unit is wired and leak-tested.
• OptiView™ Control Center
The unit is dismantled and shipped as follows:
• Power Panel
1. The driveline (compressor/motor assembly).
• Four (4) vibration isolation pads (or optional
2. The evaporator. spring isolators and brackets).
3. The condenser. • Operating coolant (inhibited water)
4. The Variable Speed Drive (VSD). • Other shipped loose items, including piping, wa-
5. Refrigerant charges shipped separately. ter temperature controls, wiring, isolators, etc.
6. Miscellaneous shipped loose items. Form 9
Arrangements with the local service office must be Prior to shipping, the unit is completely assembled at
made to ensure refrigerant is on-site when the unit is the factory. Interconnecting piping is assembled and
ready to be charged. the complete unit is wired and leak-tested.
12 JOHNSON CONTROLS
FORM 160.84-N1
Section 1 - Overview
ISSUE DATE: 10/25/2015
JOHNSON CONTROLS 13
FORM 160.84-N1
Section 1 - Overview
ISSUE DATE: 10/25/2015
14 JOHNSON CONTROLS
FORM 160.84-N1
ISSUE DATE: 10/25/2015
JOHNSON CONTROLS 15
FORM 160.84-N1
Section 2 - Rigging and Lifting
ISSUE DATE: 10/25/2015
Side
Spreader
Bar
90°+/-10°
Lifting
Holes Lifting
Holes
Lifting
Holes
LD16719b
65°
Min.
Lifting
Holes Lifting
Holes
Lifting
Holes
LD16719c
16 JOHNSON CONTROLS
FORM 160.84-N1
Section 2 - Rigging and Lifting
ISSUE DATE: 10/25/2015
JOHNSON CONTROLS 17
FORM 160.84-N1
Section 2 - Rigging and Lifting
ISSUE DATE: 10/25/2015
Shells
1. Attach rigging chains to an adequate lifting device.
2. Attach chains to the lifting holes at the corner of
each end sheet as shown on Figure 5 on page 19.
45°
3. If necessary to avoid contact with chiller compo- Min.
nents install side spreader bars between the Evap- 45°
orator and Condenser end sheet lifting chains. Min.
18 JOHNSON CONTROLS
FORM 160.84-N1
Section 2 - Rigging and Lifting
ISSUE DATE: 10/25/2015
Lifting 2
Holes
65°
Min.
90°+/-10°
Lifting
Holes
Lifting
Holes
Lifting
Holes
LD16732a
Figure 5 - FORM 3 RIGGING WITHOUT SIDE SPREADER BARS
5. Fasten the VSD to the condenser and to the motor Figure 6 - VARIABLE SPEED DRIVE RIGGING
terminal box duct. Remove the rigging chains.
JOHNSON CONTROLS 19
FORM 160.84-N1
Section 2 - Rigging and Lifting
ISSUE DATE: 10/25/2015
Lifting
Holes
45°
Min.
Lifting
Holes
LD16738
LD17275a
20 JOHNSON CONTROLS
FORM 160.84-N1
Section 2 - Rigging and Lifting
ISSUE DATE: 10/25/2015
Lifting
Holes
45°
Min.
90°+/-10°
Lifting
Lifting
Holes
Holes
Lifting
Holes
CON
DEN EVA
SER POR
ATO
R
LD17059b
JOHNSON CONTROLS 21
FORM 160.84-N1
Section 2 - Rigging and Lifting
ISSUE DATE: 10/25/2015
3. If necessary to maintain minimum angles in- 1. Attach rigging chains to each end of the compres-
stall spreader bars between the condenser lifting sor/motor assembly as shown in Figure 10 on
chains to have the chains as shown in Figure 9 on page 22.
page 21.
2. Lift the compressor/motor assembly off the
The angle of the lifting chains is critical ground to check for center of gravity. Make ad-
and damage to the unit may occur if the justments as necessary.
rigging is not completed as described.
The M2C and M6C Compressor/Motor
has metric lifting lugs
22 JOHNSON CONTROLS
FORM 160.84-N1
Section 2 - Rigging and Lifting
ISSUE DATE: 10/25/2015
1. Attach rigging chains from an adequate lifting de- Use lifting chains with working load limit
vice to the four lifting holes at the top of the VSD each 70% of the Power Panel weight.
as shown in Figure 11 on page 23.
2. Lift the VSD slightly off the ground to check for
center of gravity. Make adjustments as necessary
to level the VSD. 2
3. Lift the VSD and remove all packing material, for
VSD weight refer to Table 6 on page 22.
Use lifting chains with working load limit Lifting
each 35% of total VSD weight. Holes
45°
Min.
Lifting
Holes
65°
Min.
65°
Min.
Lifting
Holes LD17275a
JOHNSON CONTROLS 23
FORM 160.84-N1
Section 2 - Rigging and Lifting
ISSUE DATE: 10/25/2015
FORM 9 SHIPMENT
The chiller is shipped in two assemblies:
• The chiller unit (less the VSD).
• The VSD.
• Miscellaneous shipped loose items.
The unit is first factory assembled, refrigerant piped,
wired and leak tested; then dismantled for shipment.
All wiring integral with compressor is left on it, and
all conduit is left on shell. All openings on compressor
and shell are closed and charged with dry nitrogen (3 to
7 PSIG (20 to 50 kPa).
Refrigerant charges are shipped separately.
LD16738 Arrangements with the local service of-
Figure 13 - OPTIVIEW CONTROL CENTER
fice must be made to ensure refrigerant is
on-site when unit is ready to be charged.
Side
Spreader
Bars
65°
Min.
90°+/-10°
Lifting
Holes
Lifting
Holes
Lifting
Holes
LD16739b
24 JOHNSON CONTROLS
FORM 160.84-N1
Section 2 - Rigging and Lifting
ISSUE DATE: 10/25/2015
65° 2
Min.
90°+/-10°
Lifting
Holes
Lifting
Holes
Lifting
Holes
LD16739c
Unit Rigging 5. With an adequate lifting device lift the unit slight-
ly off the ground to determine adjustments neces-
One lifting chain is required for each lift- sary to keep the unit level. Make adjustments as
ing point and each chain having a work- necessary to level the unit.
ing load limit 40% of unit total weight.
Variable Speed Drive (VSD)
The lifting chains traversing the evapora-
tor/condenser shells should remain 90° Table 9 - VARIABLE SPEED DRIVE WEIGHTS
+/- 10° from horizontal. A spreader bar
may be required to achieve the +/- 10°. Model Pounds Kilograms
HYP0490XH 1,226 556
HYP0612XH 1,954 886
HYP0774XH 2,060 934
1. Attach rigging chains to an adequate lifting device.
2. Attach chains to the lifting holes at the corner The VSD is shipped with glycol in the
of each end sheet as shown on Figure 15 on cooling system. The VSD coolant must
page 25. be changed to the inhibitor provided with
the shipped loose items prior to starting
3. If necessary to avoid contact with chiller compo- the unit or a VSD over temperature fault
nents install side spreader bars between the Evap- may occur.
orator and Condenser end sheet lifting chains.
4. The angle of the lifting chains traversing the en 1. Attach rigging chains from an adequate lifting de-
sheet should not be less than 65° as shown on Fig- vice to the four lifting holes at the top of the VSD
ure 15 on page 25. as shown in Figure 16 on page 26.
2. Lift the VSD slightly off the ground to check for
center of gravity. Make adjustments as necessary
to level the VSD.
JOHNSON CONTROLS 25
FORM 160.84-N1
Section 2 - Rigging and Lifting
ISSUE DATE: 10/25/2015
3. Lift the VSD and remove all packing material, for Unit Rigging
VSD weight refer to Table 10 on page 26. One lifting chain is required for each lift-
4. Carefully lower the VSD on to the supports on the ing point and each chain having a work-
condenser. ing load limit 30% of unit total weight or
heat exchanger being lifted.
5. Fasten the VSD to the condenser and to the motor
terminal box duct. Remove the rigging chains. The lifting chains traversing the evapora-
tor/condenser shells should remain 90°
Use lifting chains with working load limit +/- 10° from horizontal. A spreader bar
each 35% of total VSD weight. may be required to achieve the +/- 10°.
The unit is first factory assembled, refrigerant piped, 1. Attach rigging chains from an adequate lifting de-
wired and leak tested; then dismantled for shipment. vice to the four lifting holes at the top of the VSD
Evaporator/condenser is not skidded. All wiring inte- as shown in Figure 17 on page 27.
gral with compressor is left on it, and all conduit is left 2. Lift the VSD slightly off the ground to check for
on shell. center of gravity. Make adjustments as necessary
to level the VSD.
26 JOHNSON CONTROLS
FORM 160.84-N1
Section 2 - Rigging and Lifting
ISSUE DATE: 10/25/2015
3. Lift the VSD and remove all packing material, for Refrigerant charges are shipped separately.
VSD weight refer to Table 10 on page 26. Arrangements with the local service of-
fice must be made to ensure refrigerant is
4. Carefully lower the VSD on to the supports on the
on-site when unit is ready to be charged.
condenser.
5. Fasten the VSD to the condenser and to the motor 2
terminal box duct. Remove the rigging chains.
Condenser Assembly
Use lifting chains with working load limit The lifting chains along the axis of the
each 35% of total VSD weight. condenser shell should not exceed 90°
+/- 10°. A spreader bar may be required
to achieve the +/- 10°.
FORM 11 SHIPMENT
The chiller is split down the middle and shipped in
three assemblies: 4. With an adequate lifting device lift the unit slight-
• The condenser-side assembly. ly off the ground to check for center of gravity.
Make adjustments as necessary to level the unit.
• The evaporator-side assembly.
• The OptiView™ Control Center assembly.
• Miscellaneous shipped loose items.
The unit is first factory assembled, refrigerant piped,
wired and leak tested; then dismantled for shipment.
All wiring integral with compressor is left on it, and all
conduit is left on shell.
All openings on compressor and shell are closed and
3 to 7 PSIG (20 to 50 kPa) holding charge of dry ni-
trogen.
JOHNSON CONTROLS 27
FORM 160.84-N1
Section 2 - Rigging and Lifting
ISSUE DATE: 10/25/2015
90°+/-10°
Lifting
Side Holes
Spreader
Bar 65°
Min.
Lifting
Holes
CO
ND
Lifting
EN
SE Holes
R
LD17057a
65°
Min.
Side
Spreader 90°+/-10°
Bar
Lifting
Holes
Lifting
Holes
LD17058a
28 JOHNSON CONTROLS
FORM 160.84-N1
Section 2 - Rigging and Lifting
ISSUE DATE: 10/25/2015
One chain is required per each lifting Table 11 - CONTROL PANEL WEIGHTS
point. Description Pounds Kilograms
Use lifting chains with working load limit OptiView 75 34
each at least 40% of the total shell and
installed component weight. 1. Lift the OptiView™ Control Center and remove
all packing material.
1. Attach rigging chains to an adequate lifting device. 2. Carefully lower the OptiView™ Control Center
2. Attach chains to the lifting holes at the corner of on to the supports on the condenser.
the end sheets as shown in Figure 19 on page 28. 3. Attach the OptiView™ Control Center to the con-
3. If necessary to maintain minimum angles install denser with the proper hardware.
side spreader bars between the evaporator end 4. Connect all unit wiring and harnesses (refer to
sheets to have the chains at 90° as shown in Fig- YMC2 Unit Wiring and Field Control Modifica-
ure 19 on page 28. tions (Form 160.78-PW2).
The angle of the lifting chains is critical
and damage to the unit may occur if the
rigging is not completed as described.
LD16738
JOHNSON CONTROLS 29
FORM 160.84-N1
ISSUE DATE: 10/25/2015
30 JOHNSON CONTROLS
FORM 160.84-N1
ISSUE DATE: 10/25/2015
SECTION 3 - INSTALLATION
JOHNSON CONTROLS 31
FORM 160.84-N1
Section 3 - Installation
ISSUE DATE: 10/25/2015
SHELL SHELL
DIA.
END SHEET HOLE END SHEET
DIA.
HOLE
LD12638a LD12639a
UNIT WEIGHT UP TO 16,365 Lbs (7,423 Kgs) UNIT WEIGHT 16,366 - 28,835 Lbs (7,424 - 13,080 Kgs)
SHELL
See Detail A
LD12640a
32 JOHNSON CONTROLS
FORM 160.84-N1
Section 3 - Installation
ISSUE DATE: 10/25/2015
*
*
A
D E
LD12642
OPERATING UNIT WEIGHT DIM "A" DIM "B" DIM "C" DIM "D" DIM "E"
15,001 - 29,000 Lbs
62" (1575) 31" (787) 31" (787) 10" (254) 8" (203)
(6,805 - 13,154 Kgs)
JOHNSON CONTROLS 33
FORM 160.84-N1
Section 3 - Installation
ISSUE DATE: 10/25/2015
off the bolts on the overloaded isolator and adjusting 4-SPRING ISOLATORS LD19573
UNIT WEIGHT
opposite isolators as required. 19,564 Lbs UP TO 24, 457 Lbs (8874 Kgs UP TO 11093 Kgs)
SHELL
END
5 1/2” 1 3/8” SHEET
(140) (35)
CAP
SCREW
ADJUSTING
BOLT
1
(25”
)
(15 6”
2)
(1 6”
)
52
UNIT WEIGHT
30,827 Lbs UP TO 35,009 Lbs (13,983 Kgs UP TO 15,880 Kgs)
34 JOHNSON CONTROLS
FORM 160.84-N1
Section 3 - Installation
ISSUE DATE: 10/25/2015
JOHNSON CONTROLS 35
FORM 160.84-N1
Section 3 - Installation
ISSUE DATE: 10/25/2015
Evaporator And Condenser Water Piping The nozzles and water pass arrangements are furnished
The evaporator and condenser liquid heads of chiller in accordance with the job requirements (see Product
have nozzles which are grooved, but also suitable for Drawings furnished with the job.) Standard units are
welding 150 psig DWP flanges or the use of flexible designed for 150 psig DWP on the water side. If job
couplings. Factory mounted flanges are optional. If requirements are for greater than 150 psig DWP, check
welding is done on the nozzles, flow switches, con- the unit data plate before applying pressure to evapora-
denser level sensor, and water temperature thermistors tor or condenser to determine if the chiller has provi-
should be disconnected and the welding ground MUST sions for the required DWP.
be good contact located at the head to prevent current Inlet and outlet connections are identified by labels
damage to the devices. placed adjacent to each nozzle.
COOLING
TOWER
CONTROLLED COOLING
TOWER BYPASS VALVE
(IF NECESSARY)
C = Compressor
STRAINER M = Motor
CONDENSER
C M
COOLING TOWER
PUMP
COOLING
EVAPORATOR LOAD
CHILLER STRAINER
CHILLED WATER PUMP
LD08529a
36 JOHNSON CONTROLS
FORM 160.84-N1
Section 3 - Installation
ISSUE DATE: 10/25/2015
JOHNSON CONTROLS 37
FORM 160.84-N1
Section 3 - Installation
ISSUE DATE: 10/25/2015
VENT TO ATMOSPHERE
CONDENSATION
TRAP
CONDENSER
DUAL RELIEF
SEE NOTE
VALVES
EVAPORATOR
38 JOHNSON CONTROLS
FORM 160.84-N1
Section 3 - Installation
ISSUE DATE: 10/25/2015
Control Wiring
Insulation of the type specified for the job, or mini-
On units shipped disassembled, after installation of
mum thickness to prevent sweating of 30°F (-1°C)
the control center, control wiring must be completed
surfaces should be furnished (by others) and applied 3
between unit components and control center, variable
to the evaporator shell, end sheets, liquid feed line to
speed drive and using wiring harness furnished. Refer
flow chamber, compressor suction connection, and
to YMC2 Field Connections Manual (Form 160.84-
evaporator liquid heads and connections (see Figure
PW1).
9). The liquid head flange insulation must be remov-
Field wiring connections for commonly encountered able, to allow head removal for the tube maintenance.
control modifications (by others) if required, are shown
Units are furnished factory anti-sweat insulated on or-
in the YMC2 Unit Wiring and Field Control Modifica-
der at additional cost. This includes all low tempera-
tions Manual (Form 160.84-PW2).
ture surfaces except the two (2) cooler liquid heads.
No deviations in unit wiring from that
INSTALLATION CHECK – REQUEST FOR
shown on drawings furnished shall be
STARTUP SERVICE
made without prior approval of the John-
son Controls representative. The services of a Johnson Controls representative will
be furnished to check the installation and supervise the
initial start-up and operation on all chillers installed
within the Continental United States.
Power Wiring
After the unit is installed, piped and wired as described
DO NOT cut wires to final length or make in this Instruction, but before any attempt is made to
final connections to starter power input start the unit, the Johnson Controls District Office
terminals until approved by the Johnson should be advised so that the start-up service, includ-
Controls representative. ed in the contract price, can be scheduled. Notify the
Johnson Controls office using the Installation Check-
list and Request Form (Form 160.84-CL1).
Supplied Variable Speed Drive.
The factory mounted Variable Speed Drive does not
require wiring to the compressor motor. The mo-
tor power wiring is factory connected to the Variable
Speed Drive (refer to the YMC2 Unit Wiring and Field
Control Modifications Manual (Form 160.84-PW2)).
All wiring to the control panel is completed by the fac-
tory. A control transformer is factory furnished with
the Variable Speed Drive.
JOHNSON CONTROLS 39
FORM 160.84-N1
Section 3 - Installation
ISSUE DATE: 10/25/2015
HOT GAS
LINE LIQUID
LINE
SIGHT GLASS
Tape Insulation
around flanges to
allow for removal.
HOT GAS
CONNECTION
SIGHT GLASS
LD03827a
Bold lines and shaded components
represent insulation.
40 JOHNSON CONTROLS
FORM 160.84-N1
ISSUE DATE: 10/25/2015
SECTION 4 - REASSEMBLY
1. Rig shells according to the rigging section to final 7. Bolt the suction line between the compressor and
location. See Section 2 - Rigging and Lifting. the evaporator using proper gaskets and hardware.
2. Bolt the tube sheets together as shown in Figure 8. Complete the refrigerant liquid line piping be-
28 on page 41. Note that the outside surfaces of tween the evaporator and condenser. Be sure
hardware are all properly installed. 4
the tube sheets must be flush.
9. Tighten all hardware installed in steps 3 through
6 above to the specified torque values provided in
the reassembly figure.
CONDENSER
10. Install refrigerant piping (Refer to Refrigerant
Tubing Reassembly on page 52).
11. Pressure test the unit with nitrogen per Form
160.84-O1.
12. Lift the Variable Speed Drive in accordance with
rigging instructions and remove all packing ma-
terial. Carefully lower the Variable Speed Drive
EVAPORATOR
on to the supports on the condenser. Fasten the
5/8” x 2-1/2” Variable Speed Drive to the condenser. Make all
Bolts, Lockwashers,
and Hex Nuts necessary connections for the VSD cooling loop
LD14812
to be complete.
Figure 28 - SHELL REASSEMBLY The Variable Speed Drive will be shipped with
glycol in the cooling system. The Variable Speed
3. Assemble vibration isolators to unit. Refer to In- Drive coolant must be changed to the inhibitor
stall Isolators on page 31. provided with the shipped loose items prior to
4. Level shells in both directions. The longitudi- starting the unit or a VSD over temperature fault
nal alignment of the shell should be checked by may occur.
placing a level on the top of the shell, next to the 13. Lift the OptiView Control Center in accordance
discharge connection. The transverse alignment with rigging instructions and remove all pack-
should be checked by placing a level on the tops ing material. Carefully lower the control panel on
of both end sheets. Refer to Section 3 - Installa- to the supports provided on the condenser. Fas-
tion on page 31 for additional instructions to ten the Control Center to the condenser with the
level the unit. After shell is leveled, wedge and proper hardware.
shim each corner of the shell to solidly support it
while assembling the other parts. 14. Re-connect motor power leads in the Variable
Speed Drive to T1, T2, and T3 terminals and
5. Install the discharge piece and optional isolation torque to 18-20 Ft-lbs. per the labels in the VSD.
valve between the compressor and the condenser
using proper gaskets and hardware. 15. Connect the motor terminal box flex duct to the
drive.
JOHNSON CONTROLS 41
FORM 160.84-N1
Section 4 - Reassembly
ISSUE DATE: 10/25/2015
16. Lift the Power Panel in accordance with rigging Table 12 - ASSEMBLY TORQUE METRIC FOR
instructions and remove all packing material. METRIC TUBE FITTINGS
Carefully lower the Power Panel on to the evapo- PORT- TORQUE
FITTING
rator. Assemble the Power Panel to the evaporator. SIZE
THREAD FT-LB N-M
SIZE
17. Re-connect all unit wiring and harnesses (refer to M10 M10 x 1 17 23
YMC2 Unit Wiring and Field Control Modifica- M12 M12 x1.5 24 33
tions (Form 160.84-PW2).
M14 M14 x 1.5 34 46
18. Remove Nitrogen and charge unit with Refriger- M16 M16 x 1.5 46 63
ant. (Refer to Form 160.84-O1). M18 M18 x 1.5 61 83
19. All Units – Complete installation and finally M22 M22 x 1.5 94 127
level the unit. (Refer Section 3 - Installation on M27 M27 x 2 139 189
page 31). M30 M30 x 2 167 226
M33 M33 x 2 194 263
M42 M42 x 2 265 359
M48 M48 x 2 302 410
M60 M60 x 2 359 487
42 JOHNSON CONTROLS
FORM 160.84-N1
Section 4 - Reassembly
ISSUE DATE: 10/25/2015
NOTES:
Unless otherwise specified, all screw must be tightened to the follow-
ing torque values with lightly oiled threads.
** Lubricated with oil and graphite on male and female threads and
under bolt heads. Do NOT use Moly-kote.
N
3/8”
K PIPING
3/8”
PIPING
N
LD17283
JOHNSON CONTROLS 43
FORM 160.84-N1
Section 4 - Reassembly
ISSUE DATE: 10/25/2015
F D
K
B
LD17303
LD17303
44 JOHNSON CONTROLS
FORM 160.84-N1
Section 4 - Reassembly
ISSUE DATE: 10/25/2015
F D
C 4
A
G
K B
LD17282
LD17283
JOHNSON CONTROLS 45
FORM 160.84-N1
Section 4 - Reassembly
ISSUE DATE: 10/25/2015
LD17284
46 JOHNSON CONTROLS
FORM 160.84-N1
Section 4 - Reassembly
ISSUE DATE: 10/25/2015
LD17285
JOHNSON CONTROLS 47
FORM 160.84-N1
Section 4 - Reassembly
ISSUE DATE: 10/25/2015
48 JOHNSON CONTROLS
FORM 160.84-N1
Section 4 - Reassembly
ISSUE DATE: 10/25/2015
LD17497
JOHNSON CONTROLS 49
FORM 160.84-N1
Section 4 - Reassembly
ISSUE DATE: 10/25/2015
Form 11 Reassembly
1. Bolt the tube sheets together as shown in Figure 7. The Variable Speed Drive will be shipped with
35 on page 50. Note that the outside surfaces of glycol in the cooling system. The Variable Speed
the tube sheets must be flush. Drive coolant must be changed to the inhibitor
provided with the shipped loose items prior to
starting the unit or a VSD over temperature fault
may occur.
CONDENSER 8. Re-connect motor power leads in the Variable
Speed Drive to T1, T2, and T3 terminals and
torque to 18-20 Ft-lbs. per the labels in the VSD.
9. Re-connect all unit wiring and harnesses (refer to
YMC2 Unit Wiring and Field Control Modifica-
tions (Form 160.84-PW2).
10. Install refrigerant piping (refer to Refrigerant Tub-
ing Reassembly section of this manual for proper
EVAPORATOR connection of O-ring fittings).
5/8” x 2-1/2”
Bolts, Lockwashers,
and Hex Nuts 11. Pressure test the unit with nitrogen per Form
LD14812
160.84-O1.
Figure 35 - SHELL REASSEMBLY 12. Remove Nitrogen and charge unit with refrigerant
(refer Form 160.84-OM1).
2. Assemble vibration isolators to unit. Refer Sec-
tion 3 - Installation on page 31.
3. Level shells in both directions. The longitudi-
nal alignment of the shell should be checked by
placing a level on the top of the shell, next to the
discharge connection. The transverse alignment
should be checked by placing a level on the tops
of both end sheets. Refer Section 3 - Installation
on page 31 for additional instructions to level
the unit. After shell is leveled, wedge and shim
each corner of the shell to solidly support it while
assembling the other parts.
4. Install the discharge piece and optional isolation 3/8”
Steel
valve between the compressor and the condenser Piping
using proper gaskets and hardware. LD17280
50 JOHNSON CONTROLS
FORM 160.84-N1
Section 4 - Reassembly
ISSUE DATE: 10/25/2015
F
4
E
LD17498
JOHNSON CONTROLS 51
FORM 160.84-N1
Section 4 - Reassembly
ISSUE DATE: 10/25/2015
thus affected and maintained by the O-ring compres- Figure 39 - BACK OFF LOCKNUT
sion which results from the clamping force generated
by tightening. The straight threads do NOT offer seal- 5. Screw fitting into port until the back-up washer
ing action; they provide the resistance (holding power) contacts the face of the port. Light wrenching may
for service pressure. be necessary.
BACK-UP
WASHER
LOCKNUT CONTACTS
BACK-UP
FACE
WASHER
O-RING
LD17271
LD17269
Figure 40 - SCREW FITTING INTO PORT
Figure 38 - ADJUSTABLE END FITTING
6. To align the tube end of fitting to accept incom-
1. Inspect to ensure that both matching parts are free ing tube or hose assembly, unscrew by required
of burrs, nicks, scratches or any foreign particles. amount, but NOT more than one full turn. More
then one turn makes the locknut push the O-ring
2. Install O-ring on port end of fitting, if it is NOT into the machine threads beyond the fitting land
pre-installed, take care NOT to nick the O-ring. area during step 7.
3. Lubricate O-ring with a light coat of synthetic 7. Using two wrenches, hold fitting in desired posi-
Polyolester (POE) oil or POE grease. tion and tighten locknut to the appropriate torque
4. Back off locknut as far as possible. Make sure value shown in Table 13 on page 42 or Table 12
back-up washer is NOT loose and is pushed up on page 42.
as far as possible. This ensures the O-ring is com- 8. Inspect to ensure that O-ring is NOT pinched and
pletely at the back of the land so it remains in the the back-up washer seats flat on face of port.
land area when the fitting is turned out at Step 6.
52 JOHNSON CONTROLS
FORM 160.84-N1
Section 4 - Reassembly
ISSUE DATE: 10/25/2015
SEALED
WITH
O-RING
THREADED
FOR
HOLDING POWER
LD17273
JOHNSON CONTROLS 53
FORM 160.84-N1
ISSUE DATE: 10/25/2015
54 JOHNSON CONTROLS
FORM 160.84-N1
ISSUE DATE: 10/25/2015
NOTES:
1. See Figure 43 on page 56 for dimension location points as designated on this table.
2. All dimensions are approximate. Certified dimensions are available on request.
3. S tandard water nozzles are Schedule 40 pipe size, furnished as welding stub-outs with ANSI/AWWA C-606 grooves, allowing the option
of welding, flanges, or use of ANSI/AWWA C-606 couplings. Factory-installed, class 150 (ANSI B16.5, round slip-on forged carbon steel
with 1/16" raised face), water flanged nozzles are optional (add 1/2" to nozzle length). Companion flanges, nuts, bolts, and gaskets are not
furnished.
4. O ne, two, and three-pass nozzle arrangements are available only in pairs shown for all shell codes. Any pair of evaporator nozzles may
be used in combination with any pair of condenser nozzles Compact water boxes on one heat exchanger may be used with Marine Water
Boxes on the other heat exchangers.
5. Condenser water must enter the water box through the bottom connection for proper operation of the sub-cooler to achieve rated performance.
6. To determine overall height, add dimension "M" for the appropriate isolator type.
JOHNSON CONTROLS 55
FORM 160.84-N1
Section 5 - Dimensions, Nozzle Arrangements And Weights
ISSUE DATE: 10/25/2015
VSD
CONTROL
PANEL
M
C D
A 3-3/8”
VSD
COMPRESSOR
MOTOR
CONTROL
PANEL
LD17200
Figure 43 - DIMENSIONS - 197 & 246 COMPRESSOR UNITS FT-IN (MM)
56 JOHNSON CONTROLS
FORM 160.84-N1
Section 5 - Dimensions, Nozzle Arrangements And Weights
ISSUE DATE: 10/25/2015
JOHNSON CONTROLS 57
FORM 160.84-N1
Section 5 - Dimensions, Nozzle Arrangements And Weights
ISSUE DATE: 10/25/2015
ONE - PASS
TWO - PASS
THREE - PASS
LD14020
NOTES:
1. All dimensions shown in Ft/In (mm)
2. Standard water nozzles are furnished as welding stub-outs with ANSI/AWWA C-606 grooves, allowing the option of welding, flanges, or
use of ANSI/AWWA C-606 couplings. Factory-installed, class 150 (ANSI B16.5, round slip-on, forged carbon steel with 1.6mm raised face),
water flanged nozzles are optional (add 13mm to nozzle length). Companion flanges, nuts, bolts, and gaskets are not furnished.
3. One-, Two- and Three-pass nozzle arrangements are available only in pairs shown and for all shell codes. Any pair of evaporator nozzles
may be used in combination with any pair of condenser nozzles.
4. Evaporator and condenser water must enter the water box through the bottom connection to achieve rated performance.
5. Connected piping should allow for removal of compact water boxes for tube access and cleaning.
6. Add dimension "M" as shown on the unit dimensions page for the appropriate isolator type.
58 JOHNSON CONTROLS
FORM 160.84-N1
Section 5 - Dimensions, Nozzle Arrangements And Weights
ISSUE DATE: 10/25/2015
LD14010
JOHNSON CONTROLS 59
FORM 160.84-N1
Section 5 - Dimensions, Nozzle Arrangements And Weights
ISSUE DATE: 10/25/2015
ONE - PASS
TWO - PASS
THREE - PASS
LD14020
60 JOHNSON CONTROLS
FORM 160.84-N1
Section 5 - Dimensions, Nozzle Arrangements And Weights
ISSUE DATE: 10/25/2015
JOHNSON CONTROLS 61
FORM 160.84-N1
Section 5 - Dimensions, Nozzle Arrangements And Weights
ISSUE DATE: 10/25/2015
1'-4-5/8" 3'-11" 0'-9" 3'-11" 1'-5-1/2" 1'-6" 0'-9" 3'-11" 1'-4" 1'-4-1/2"
EB25 8 6 4 (422) (1194) (229) (1194) (445) (457) (229) (1194) (406) (419)
1'-5-1/2" 4'-3" 0'-10" 4'-3" 1'-6-1/2" 1'-7" 0'-10" 4'-3" 1'-6-1/2" 1'-7"
EB29 10 8 6
(445) (1295) (254) (1295) (470) (483) (254) (1295) (470) (483)
1'-7-1/2" 4'-7" 0'-44" 4'-7" 1'-9-1/2" 1'-10" 0'-11" 4'-7" 1'-9-1/2" 1'-10"
EB33 14 10 8
(495) (1397) (279) (1397) (546) (559) (279) (1397) (546) (559)
62 JOHNSON CONTROLS
FORM 160.84-N1
Section 5 - Dimensions, Nozzle Arrangements And Weights
ISSUE DATE: 10/25/2015
LD14021
NOTES:
1. All dimensions shown in Ft/In (mm)
2. All dimensions are approximate. Certified dimensions are available upon request.
3. S
tandard water nozzles are Schedule 40 pipe size, furnished as welding stub-outs with ANSI/AWWA C-606 grooves, allowing the option of
welding, flanges, or use of ANSI/AWWA C-606 couplings. Factory-installed, class 150 (ANSI B16.5, round slip-on, forged carbon steel with
1.6 mm raised face), water flanged nozzles are optional (add 13 mm to nozzle length). Companion flanges, nuts, bolts, and gaskets are not
furnished.
4. O
ne-, two-, and three-pass nozzle arrangements are available only in pairs shown and for all shell codes. Any pair of evaporator nozzles
may be used in combination with any pair of condenser nozzles. Compact water boxes on one heat exchanger may be used with Marine
Water Boxes on the other heat exchanger.
5. Water must enter the water box through the bottom connection to achieve rated performance.
JOHNSON CONTROLS 63
FORM 160.84-N1
Section 5 - Dimensions, Nozzle Arrangements And Weights
ISSUE DATE: 10/25/2015
LD14021
64 JOHNSON CONTROLS
FORM 160.84-N1
Section 5 - Dimensions, Nozzle Arrangements And Weights
ISSUE DATE: 10/25/2015
JOHNSON CONTROLS 65
FORM 160.84-N1
Section 5 - Dimensions, Nozzle Arrangements And Weights
ISSUE DATE: 10/25/2015
WEIGHTS
Table 15 - APPROXIMATE EVAPORATOR WEIGHTS 150 PSI COMPACT WATER BOXES
EVAPORATOR COMPACT WATER BOX WEIGHT LBS (KG) MARINE WATER BOX WEIGHT LBS (KG)
WEIGHT LBS
CODE 1-PASS 2-PASS 3-PASS 1-PASS 2-PASS 3-PASS
(KG)
EB2508 2830 (1284) 264 (120) 269 (122) 272 (123) 474 (215) 563 (255) 514 (233)
EB2510 3628 (1646) 264 (120) 269 (122) 272 (123) 474 (215) 563 (255) 514 (233)
EB2514 4545 (2062) 264 (120) 269 (122) 272 (123) 474 (215) 563 (255) 514 (233)
EB2910 4338 (1968) 332 (151) 355 (161) 360 (163) 624 (283) 731 (332) 688 (312)
EB2914 5502 (2496) 332 (151) 355 (161) 360 (163) 624 (283) 731 (332) 688 (312)
EB3310 5372 (2437) 402 (182) 421 (191) 432 (196) 776 (352) 851 (386) 826 (375)
EB3314 6779 (3075) 402 (182) 421 (191) 432 (196) 776 (352) 851 (386) 826 (375)
NOTE: Weights based on maximum tube bundle allowed per shell.
66 JOHNSON CONTROLS
FORM 160.84-N1
Section 5 - Dimensions, Nozzle Arrangements And Weights
ISSUE DATE: 10/25/2015
WEIGHTS (CONT'D)
Table 17 - APPROXIMATE VARIABLE SPEED DRIVE (VSD) WEIGHTS
VSD WEIGHT LBS (KG)
HYP0490XH 1226 (556)
HYP0612XH 1954 (886)
HYP0774XH 2060 (934)
JOHNSON CONTROLS 67
P.O. Box 1592, York, Pennsylvania USA 17405-1592 800-861-1001 Subject to change without notice. Printed in USA
Copyright © by Johnson Controls 2015 www.johnsoncontrols.com ALL RIGHTS RESERVED
Form 160.84-N1 (1015)
Issue Date: October 25, 2015
Supersedes: 160.84-N1 (814)