Tunnel Design Basis Report PDF
Tunnel Design Basis Report PDF
Tunnel Design Basis Report PDF
5094704/D7003 Rev. BC
EAST WEST METRO PROJECT:
CONTRACT - UG1
TUNNEL DESIGN BASIS REPORT
UG1 WSA 200 NST REP 201 Rev. BC 27/10/11
Sequential
Project No. Origin Area Discipline Doc Code
number Page : 2 / 23
REVISION NOTE
NOTES:
5094704/D7003 Rev. BC
EAST WEST METRO PROJECT:
CONTRACT - UG1
TUNNEL DESIGN BASIS REPORT
UG1 WSA 200 NST REP 201 Rev. BC 27/10/11
Sequential
Project No. Origin Area Discipline Doc Code
number Page : 3 / 23
2. TTAJV TTAJV
NOTE:
1. CONTROLLED COPY HOLDERS WILL RECEIVE THE LATEST ISSUE OF THE DOCUMENT AND
THE SUCCESSIVE ISSUES. HE SHALL BE RESPONSIBLE FOR DESTROYING THE OLD
REVISION OR OTHERWISE MARKING THE SAME AS “SUPERSEDED”.
5094704/D7003 Rev. BC
EAST WEST METRO PROJECT:
CONTRACT - UG1
TUNNEL DESIGN BASIS REPORT
UG1 WSA 200 NST REP 201 Rev. BC 27/10/11
Sequential
Project No. Origin Area Discipline Doc Code
number Page : 4 / 23
TABLE OF CONTENTS
1 INTRODUCTION ........................................................................................................................................... 6
1.1 Purpose of this Report........................................................................................................................... 6
1.2 Related Documents ............................................................................................................................... 6
1.3 Project Description ................................................................................................................................ 6
1.4 Relevant Codes & References .............................................................................................................. 7
2 TUNNEL ELEMENTS ................................................................................................................................... 8
2.1 Bored Tunnel Segmental Lining ............................................................................................................ 8
2.2 Cross Passages .................................................................................................................................... 8
2.3 Bored Tunnel to Underground Structure Interfaces .............................................................................. 9
3 MATERIAL PROPERTIES .......................................................................................................................... 10
3.1 Structural Material Properties for Permanent Works .......................................................................... 10
3.1.1 Pre-cast concrete .............................................................................................................................. 10
3.1.2 Cast In-Situ Concrete ........................................................................................................................ 10
3.1.3 Bar Reinforcement ............................................................................................................................ 10
3.2 Geotechnical Parameters .................................................................................................................... 10
4 DESIGN LOADS ......................................................................................................................................... 11
4.1 General Load Cases ........................................................................................................................... 11
4.1.1 Dead Loads (G) ................................................................................................................................. 11
4.1.2 Imposed Loads (Q)............................................................................................................................ 11
4.1.3 Hydrostatic Loads (H)........................................................................................................................ 12
4.1.4 Earth Loads (E) ................................................................................................................................. 12
4.1.5 Seismic Loads (EQ) .......................................................................................................................... 12
4.1.6 Fire Loading ...................................................................................................................................... 13
4.1.7 Internal Loading................................................................................................................................. 13
4.1.8 Dispersal on Wheel Point Loads ....................................................................................................... 13
4.1.9 Accident Load from Train Derailment................................................................................................ 13
4.2 Other Loads Considered for Segment Design .................................................................................... 13
4.3 Load Factors ....................................................................................................................................... 14
5 OVERALL STABILITY OF TUNNEL .......................................................................................................... 15
5.1 Permanent Conditions ......................................................................................................................... 15
5.1.1 Flotation Uplift due to Water Pressure .............................................................................................. 15
5.2 Temporary Conditions ......................................................................................................................... 15
5.2.1 Heave of Relatively Shallow Tunnels in Clay .................................................................................... 15
5.2.2 Tunnel Face Stability ......................................................................................................................... 15
6 DESIGN APPROACH FOR SEGMENTAL LINING ................................................................................... 16
6.1 Safety Factors For Segment Design ................................................................................................... 16
6.1.1 Ultimate Limit State (ULS) ................................................................................................................. 16
6.1.2 Serviceability Limit State (SLS) ......................................................................................................... 16
6.2 Design Approach ................................................................................................................................. 16
6.2.1 Static Lining Force............................................................................................................................. 16
6.2.2 Numerical Soil-Structure Interaction Analysis ................................................................................... 17
6.2.3 Analysis of the effects of Imposed Distortion .................................................................................... 17
6.2.4 Seismic Lining Forces ....................................................................................................................... 17
6.2.5 Analysis of the Effects of Poor Ring Build ......................................................................................... 19
6.2.6 Design of Radial Joints...................................................................................................................... 19
6.2.7 Analysis of the Effects of Jacking For Propulsion at the Circumferential Joint .............................. 19
6.2.8 Effects of Uneven Shield Shoving Loads .......................................................................................... 20
6.2.9 Grouting Loads .................................................................................................................................. 20
6.2.10 Analysis of the Handling and Stacking .............................................................................................. 20
6.3 Reinforcement Design ......................................................................................................................... 21
6.3.1 Design for Moments and Axial Force ................................................................................................ 21
6.3.2 Crack Control .................................................................................................................................... 21
5094704/D7003 Rev. BC
EAST WEST METRO PROJECT:
CONTRACT - UG1
TUNNEL DESIGN BASIS REPORT
UG1 WSA 200 NST REP 201 Rev. BC 27/10/11
Sequential
Project No. Origin Area Discipline Doc Code
number Page : 5 / 23
5094704/D7003 Rev. BC
EAST WEST METRO PROJECT:
CONTRACT - UG1
TUNNEL DESIGN BASIS REPORT
UG1 WSA 200 NST REP 201 Rev. BC 27/10/11
Sequential
Project No. Origin Area Discipline Doc Code
number Page : 6 / 23
1 INTRODUCTION
1.1 Purpose of this Report
This document provides the design basis for the tunnel works including:
The design of TBM tunnel segmental lining is compatible with KMRC requirements, the
Contract Documents and Specification and conditions in the local environment.
- Reports
Geotechnical Reports
Design Reports
The Contract UG1 comprises approximately 3.7km of railway tunnels and 3 stations with
the following major elements:
• TBM tunnel between Howrah Maidan Station and Howrah Station (east bound and
west bound);
• Howrah Station;
• TBM tunnel between Howrah Station and Mahakaran Station (east bound and west
bound) underpassing the Hooghly River;
• Vent shaft and connecting adits at midway between Howrah and Mahakaran
Station
• Mahakaran Station
• TBM tunnel between Mahakaran Station and Central Station (by others)
The TBM tunnels will be constructed between proposed cut and cover stations and no
additional temporary shafts are required.
5094704/D7003 Rev. BC
EAST WEST METRO PROJECT:
CONTRACT - UG1
TUNNEL DESIGN BASIS REPORT
UG1 WSA 200 NST REP 201 Rev. BC 27/10/11
Sequential
Project No. Origin Area Discipline Doc Code
number Page : 7 / 23
Additional proposed structural design codes and references are detailed within this report
are summarized in Appendix 1.
5094704/D7003 Rev. BC
EAST WEST METRO PROJECT:
CONTRACT - UG1
TUNNEL DESIGN BASIS REPORT
UG1 WSA 200 NST REP 201 Rev. BC 27/10/11
Sequential
Project No. Origin Area Discipline Doc Code
number Page : 8 / 23
2 TUNNEL ELEMENTS
2.1 Bored Tunnel Segmental Lining
The pre-cast concrete segmental lining forms part of the permanent support of the tunnel
and is installed inside the shield of the Tunnel Boring Machine (TBM), as the tunnel
excavation progresses. The TBM shield will be larger than the lining outer diameter. The
void between the ground and the tunnel lining will be continuously filled with grout from the
shield tail.
The segment lining consists of five large segments plus one key segment for each ring.
The lining thickness is 275mm with internal diameter of 5.55m. The same universal
segment ring will be used for the whole contract in the following sections:
• Running tunnels between Howrah Maidan Station and Howrah Station (east bound
and west bound);
• Running tunnels between Howrah Station and Mahakaran Station (east bound and
west bound); and
• Running tunnels between Mahakaran Station and the perimeter wall of Central
Station (east bound and west bound.
The segments are bolted together during erection inside the tunnel shield, with bolts on the
circumferential joint of each ring edge and bolts on the radial joints of each ring.
The bored tunnel waterproofing is provided by a hydrophilic seal and EPDM (Ethylene
Propylene Diane Monomer) gasket on the segment circumferential joints. The hoop load
induced into the bored tunnel as a result of the ground water pressure and soil loads will be
sufficient to compress the gaskets to prevent groundwater intrusion in combination with the
hydrophilic swelling properties. Gaskets on the circumferential joints will be compressed by
the TBM jacking pressure and locked by the bolts connecting segments. No membranes
will be used due to the tunnelling construction method.
The cross passages will be constructed by mining (NATM) excavation and temporary
support using reinforced shotcrete linings and lattice girders. The design of the temporary
support will encompass issues such as:
These issues will be developed in the relevant Design Reports. Design analysis will be
undertaken using analytical and numerical methods.
In order to facilitate the opening of the running tunnel segmental lining for cross passage
connection, a temporary support frame of steel ring beams and beams will be adopted.
This will be designed as a structural frame to accommodate tunnel lining loads that will
develop during breaking of the tunnel wall. The temporary steel members and permanent
steel jamb frame to be placed in the tunnel wall will be designed in accordance with
relevant steelwork codes compliant with the Contract specifications.
5094704/D7003 Rev. BC
EAST WEST METRO PROJECT:
CONTRACT - UG1
TUNNEL DESIGN BASIS REPORT
UG1 WSA 200 NST REP 201 Rev. BC 27/10/11
Sequential
Project No. Origin Area Discipline Doc Code
number Page : 9 / 23
The permanent support lining to the cross passages will comprise non-circular cast in-situ
concrete lining. The design of the lining will be undertaken using numerical modelling
methods and detailed in line with the Structures Design Basis Report.
Where the TBM drives terminate at the Central Station headwalls, it is proposed that the
TBM shield will be abandoned in-situ (i.e. removing all other TBM components) and the
tunnel completed between the segmental lining rings and the headwall by a cast in-situ
lining with the abandoned shield incorporated within the lining.
For both of the above cases, the joint details will be designed to provide:
• Capacity to carry soil, water and other loads including seismic impacts.
These details will be developed in the relevant Design Reports and the design will be
governed by the criteria given in the Structures Design Basis Report.
5094704/D7003 Rev. BC
EAST WEST METRO PROJECT:
CONTRACT - UG1
TUNNEL DESIGN BASIS REPORT
UG1 WSA 200 NST REP 201 Rev. BC 27/10/11
Sequential
Project No. Origin Area Discipline Doc Code
number Page : 10 / 23
3 MATERIAL PROPERTIES
3.1 Structural Material Properties for Permanent Works
Note 2: The lining stiffness is reduced according to the Muir Wood [Ref. 9] approach
to account for the effect of radial joints. This is based on the number of joints for each
ring and the reduction of lining thickness at joints:
Ir=Ij + (4/n)2 x I
For permanent cast in-situ elements, structural materials will be as those described in
the Structures Design Basis Report.
The bar reinforcement for segments are high yield steel deformed bar and the
material properties are listed below:
5094704/D7003 Rev. BC
EAST WEST METRO PROJECT:
CONTRACT - UG1
TUNNEL DESIGN BASIS REPORT
UG1 WSA 200 NST REP 201 Rev. BC 27/10/11
Sequential
Project No. Origin Area Discipline Doc Code
number Page : 11 / 23
4 DESIGN LOADS
This section summarises general loads to be considered for the design of bored tunnels
and non-TBM tunnels. If for particular structures or conditions where loads deviate from
those specified herein, the related assumptions will be given in the respective Design
Reports.
For the calculation of dead loads the following unit weights (γ) apply:
Steel 77
Water 10
The surcharge from existing buildings will be calculated and added where the
total load from the building is greater than 50kPa as per the Structures Design
Basis Report.
5094704/D7003 Rev. BC
EAST WEST METRO PROJECT:
CONTRACT - UG1
TUNNEL DESIGN BASIS REPORT
UG1 WSA 200 NST REP 201 Rev. BC 27/10/11
Sequential
Project No. Origin Area Discipline Doc Code
number Page : 12 / 23
The railway loading applied to the structures shall be as per “Modern Rolling
Stock”. The standard gauge is 1435mm. Maximum axle load of the train, P =
160kN, see the diagram below for the details of loading configuration. The type
and position of the vehicle will be chosen to produce the most adverse effect on
the structure.
The loading from maintenance vehicles and low loaders carrying equipment
required along the route will not be of a magnitude to be critical for the design.
The upper or lower bound of the groundwater level should be taken into account in
deriving hydrostatic loads, whichever is more critical for the structure or condition
being considered.
In general, full overburden loads will be considered for the design of permanent
tunnel structures. For temporary structures the earth pressure considered may
be less than the full overburden. Situations that justify the assumption of less
than the full overburden pressure will be explained in the respective Design
Reports.
5094704/D7003 Rev. BC
EAST WEST METRO PROJECT:
CONTRACT - UG1
TUNNEL DESIGN BASIS REPORT
UG1 WSA 200 NST REP 201 Rev. BC 27/10/11
Sequential
Project No. Origin Area Discipline Doc Code
number Page : 13 / 23
For a 4 hour FRP rating, cover to steel bar reinforcement will not be less than
• 75mm as defined in IS1642:1989 Table 13 for the lintel beam in the tunnel
lining above the entrance to the cross passage.
Additional stresses in the tunnel lining will be assessed according to BS8110, Part 2
[Ref: 1].
The effects of internal loads, especially loads imposed by services fixed to the tunnel
walls and roof will be taken into account in the segmental lining design and/or cast in-
situ tunnel linings.
Dispersal on wheel point loads follows the approach as outlined in Section 14.8 and
Appendix C of the Structures Design Basis Report Ref: UG1-WSA-000-ENG-REP-
001
Within the bored tunnel, the segmental ring will be designed to take the full impact
load, which will be resisted by the passive resistance of the ground behind the wall.
The horizontal derailment load shall be taken as 50% of the maximum car weight: for
the most heavily loaded car which has 4 axles of 160 kN each, this amounts to a
nominal force of 320 kN applied over a 5m horizontal length for the SLS case, where
the serviceability requirement is that there should be no permanent damage and the
structure should remain within the elastic range in accordance with IRS bridge rules.
• TBM shoving/ Ram Load (Q4) for a maximum TBM shoving force of 42,560kN.
Further comments on assessment of load cases Q4 and Q5 are given in the next sections.
5094704/D7003 Rev. BC
EAST WEST METRO PROJECT:
CONTRACT - UG1
TUNNEL DESIGN BASIS REPORT
UG1 WSA 200 NST REP 201 Rev. BC 27/10/11
Sequential
Project No. Origin Area Discipline Doc Code
number Page : 14 / 23
Note that for the purposes of numerical soil-structure interaction analysis, partial safety
factors (ULS factor =1.4, SLS factor =1.0) will be applied to computed bending moment
and forces for use in structural design, rather than input into initial parameters and load
cases.
5094704/D7003 Rev. BC
EAST WEST METRO PROJECT:
CONTRACT - UG1
TUNNEL DESIGN BASIS REPORT
UG1 WSA 200 NST REP 201 Rev. BC 27/10/11
Sequential
Project No. Origin Area Discipline Doc Code
number Page : 15 / 23
Where tunnels are relatively shallow, they should be checked for flotation due to
differential water pressure as follows:
Where:
In deriving the restraining and uplift force, the following partial safety factors need to
be considered:
Table 4-1: Partial safety factors for uplift due to water pressure
Where applicable for relatively shallow tunnels in clay, checking for heave due to
shear failure of the ground at tunnel invert level (for example, for mining operations)
will be undertaken following the method derived from the base heave analysis after
Bjerrum & Eide (1956) [Ref: 5]. Where:
For partial safety factors for soil shear strength and unit weight, refer to the table
above.
For TBM bored tunnelling works, the tunnel face stability is to be managed through
the application of appropriate face pressure. Definition of appropriate face pressure
magnitude and use will be dealt with in later design stages.
For cross passage mining works the tunnel face stability during excavation is of
particular concern. Face stability will be evaluated on the basis of ground parameters
adopted excavation and temporary support methods.
Where ground conditions are relatively poor and instability or severe ground
movement is likely then mitigation works such as ground treatment or pre-support
measures will be developed. Definition of appropriate measures will be dealt with in
later design stages.
5094704/D7003 Rev. BC
EAST WEST METRO PROJECT:
CONTRACT - UG1
TUNNEL DESIGN BASIS REPORT
UG1 WSA 200 NST REP 201 Rev. BC 27/10/11
Sequential
Project No. Origin Area Discipline Doc Code
number Page : 16 / 23
Segments are designed for the ULS in accordance with IS-456:2000. Partial safety
factors for loads and materials are in accordance with the Contract documents, IS-
456:2000 or BS8110 [Ref: 1] where relevant.
In addition, the following partial safety factors are used for specific conditions:
Tensile stresses due to demoulding, stacking, rotating, transport and handling for
erection of ring are to be checked as per the load factors below.
Dynamic factor for demoulding, stacking, rotating, transport, handling (as 5.0
per Contract document Volume 4 Section 2.7.10(d))
The closed form analysis model after Duddeck & Erdmann [Ref: 8] or similar
internationally recognised method, such as the Curtis-Muir Wood method [Ref: 9, 10],
is used for the structural analysis of the segment lining. A full bond between the
lining and the subsoil is assumed.
Calculations will be carried out for the average effective unit weight (γ‘av) of soil,
considering the soil layers and groundwater table.
The effect of differential hydrostatic pressure along the circumference of the tunnel
will be considered in the analysis. This is based on a general plane frame analysis
that will be carried out for varying soil stiffness and differential hydrostatic load.
5094704/D7003 Rev. BC
EAST WEST METRO PROJECT:
CONTRACT - UG1
TUNNEL DESIGN BASIS REPORT
UG1 WSA 200 NST REP 201 Rev. BC 27/10/11
Sequential
Project No. Origin Area Discipline Doc Code
number Page : 17 / 23
A volume loss of 1.5% is assumed for the PLAXIS analysis. This is conservative
compared to typical values for earth pressure balance tunnelling with tail-skin
grouting in soft clay.
The maximum allowable deflection of the tunnel lining is 25mm on radius of the
tunnel. The induced bending moment by applying this distortion is derived by using
the method of Morgan [Ref 14] for jointed lining cases with reduction of lining moment
of inertia based on the recommendation by Muir Wood [Ref. 9]. The predicted
bending moment coupled with minimum thrust force will be input for reinforcement
calculation.
1. Preliminary design and member sizing is based upon static design (G, Q, E, H).
Two numerical models shall be developed, one for the DBE and one for the MCE
seismic events, with the following section properties:
Notes:
5094704/D7003 Rev. BC
EAST WEST METRO PROJECT:
CONTRACT - UG1
TUNNEL DESIGN BASIS REPORT
UG1 WSA 200 NST REP 201 Rev. BC 27/10/11
Sequential
Project No. Origin Area Discipline Doc Code
number Page : 18 / 23
1) Stiffness values are the same as for the static, short-term model
2) 70% reduction of EI due to cracking of a member subject to
compression.
2. The free field deformation of the soil during a seismic event is derived using the
SHAKE2000 software. The design inputs include ground motions obtained from the
SHAKE2000 software library and from publically available ground motion libraries. The
latter include strong ground motions from the Chamoli (1999), Diphu (1988) and Burma
(1995) events. The input data includes soil profile, ground acceleration due to 0.08g
(DBE) and 0.16g (MCE) and dynamic shear modulus derived from the ground
investigation.
3. Obtain Lining-soil racking ratio (R) for the structures and the soil mass by the equation.
4(1 − υ m ) Δd lining
R=± =
(α + 1) Δd free− field
, where Δdlining = lining diametric deflection
Δdfree-field = free-field diametric deflection
νm = Poisson’s ratio of the soil medium
α = coefficient used in calculation of lining-soil racking ration of circular tunnels
dependent on whether slip is permitted between the soil medium and the tunnel lining.
R is used to derive the lining diametric deflection Δdlining for input into thrust and
bending moment expressions below.
4. The circumferential thrust and bending moment in the lining as a function of the
angular location of the tunnel lining is obtained using the expressions by Hashash et al
[Ref 17].
5. Superimpose the seismically induced thrust and bending moment distributions to the
results obtained from the numerical model.
The circular tunnel shall also be designed to resist vertical components of the seismic
motion, with the vertical component, Av, taken as 2/3 of the horizontal component, Ah.
Where two or three component motions are considered, then these shall be combined
in accordance with Section 6.3.4 of IS-1893: 2002.
Since the permanent structure is designed for the ‘at rest’ condition’, no net additional
dynamic loading need be applied to the structure either before or after the seismic
event.
6. The following design combinations shall be considered for the section design under
seismic load:
For the DBE case, the load factor of 1.4 is applied in accordance with:
1.4 x (1.0 (G + Q) + 1.0E + 1.0 H +/- 1.0 EQH +/- 1.0 EQV)
The MCE is an extreme event and is not explicitly a design requirement of the Indian
code. Hashash et al [Ref. 17] recommend that for the MCE event, the partial safety
factors for all loads should be unity.
5094704/D7003 Rev. BC
EAST WEST METRO PROJECT:
CONTRACT - UG1
TUNNEL DESIGN BASIS REPORT
UG1 WSA 200 NST REP 201 Rev. BC 27/10/11
Sequential
Project No. Origin Area Discipline Doc Code
number Page : 19 / 23
Note that combined DL and LL allows for the 50kPa minimum surcharge at the ground
surface for both DBE and MCE.
7. If the results from (7) show that the structure has adequate capacity then the design is
considered to be satisfactory.
The key construction tolerances for ring build are a maximum of 25mm on radius of
ring due to ovalisation and the limitation on stepping of segments at the
circumferential and radial joints (5mm). Poor ring build can induce significant loading
and therefore, the following are checked:
Due to the width of the bearing faces being less than the lining section thickness,
transverse tensile stresses occur at the joints. This bearing area is further reduced
where joint rotations occur due ring deflection or ring building defects, causing
increasingly concentrated loads.
The joint design for splitting tensile effects due to concentrated loads are based on
BS 8110 [Ref 1].
Steel link bars will be placed between the main reinforcement to counter tensile
forces beyond the capacity of the concrete as required.
The jacking loads imposed by the hydraulic propulsion jacks onto the leading edge
circumferential joint of the segmental lining ring are a significant load case. These
loads are in the longitudinal direction.
Due to their localisation and jack eccentricity to the lining (possibly exacerbated by
ring build defects), significant additional stresses may be induced in the lining.
Particular attention is given to the induced tensile stresses that may cause cracking
and spalling. Reinforcement of the segment to accommodate these stresses will be
included as required.
5094704/D7003 Rev. BC
EAST WEST METRO PROJECT:
CONTRACT - UG1
TUNNEL DESIGN BASIS REPORT
UG1 WSA 200 NST REP 201 Rev. BC 27/10/11
Sequential
Project No. Origin Area Discipline Doc Code
number Page : 20 / 23
The effect of these forces will be assessed using BS 8110 [Ref 1]. The required
reinforcement to accommodate tension under compressive loads and bending
moment will be determined.
TBM shoving loads acting at circumferential joints cause bursting stresses, as the
bearing width of the rams and joint packing are less than the segment thickness.
Additional flexure and torsion may generally be induced on segments, when shoving
loads are not equally distributed, due to steps along the circumferential joints. In
order to minimise damage during shoving, accurate ring build is crucial. The use of
joint packing will further help to mitigate such effects by reducing load concentration.
Segments will be designed for stresses during demoulding, stacking and erection of
the segments.
Stresses are generally calculated by elastic methods to ensure that the modulus of
rupture of the unreinforced concrete is not exceeded and thus the segments remain
uncracked.
Calculation of the allowable flexural strength of concrete fcr, shall be obtained from the
compressive strength using the following expression from IS456:2000.
f cr = 0.7 f ck (MPa)
5094704/D7003 Rev. BC
EAST WEST METRO PROJECT:
CONTRACT - UG1
TUNNEL DESIGN BASIS REPORT
UG1 WSA 200 NST REP 201 Rev. BC 27/10/11
Sequential
Project No. Origin Area Discipline Doc Code
number Page : 21 / 23
Concrete mix design will consider and address the aggressiveness of the ground
conditions the segmental lining and other structural concrete will be exposed to.
6.4.2 Bolts
Bolts are used to tie adjacent segments and rings together. The bolts are designed to
keep the sealing gaskets compressed, when part of the shield thrust is relieved during
erection of the rings.
Further behind the shield, the friction between lining and ground is sufficient to keep
the gaskets compressed.
5094704/D7003 Rev. BC
EAST WEST METRO PROJECT:
CONTRACT - UG1
TUNNEL DESIGN BASIS REPORT
UG1 WSA 200 NST REP 201 Rev. BC 27/10/11
Sequential
Project No. Origin Area Discipline Doc Code
number Page : 22 / 23
• Design checking to anticipate any risk of flotation of the tunnels – this has been
checked and it is considered that this is not a significant risk;
5094704/D7003 Rev. BC
EAST WEST METRO PROJECT:
CONTRACT - UG1
TUNNEL DESIGN BASIS REPORT
UG1 WSA 200 NST REP 201 Rev. BC 27/10/11
Sequential
Project No. Origin Area Discipline Doc Code
number Page : 23 / 23
8 REFERENCES
[1] BS8110 (1997): “Structural use of concrete. Code of practice for design and
construction”. British Standard Institution
[2] BS4449 (1997): “Specification for carbon steel bars for the reinforcement of
concrete”. British Standard Institution
[3] EN10025-1 (2004): “Hot rolled products of structural steels – Part 1: General
technical delivery conditions”. British Standard Institution
[6] BS8007 (1987): “Code of practice for design of concrete structures for retaining
aqueous liquids”. British Standard Institution
[8] Duddeck H. and Erdmann J. (1982): “Structural design models for tunnels”.
Proceedings of Conference Tunnelling ’82, pp 83-91, UK
[9] Muir Wood, A.M. (1975). “The circular tunnel in elastic ground”. Geotechnique 25,
No. 1, 115 – 127.
[11] Wang, J.N., (1983): “Seismic design of tunnels: A simple state-of-the-art design
approach” Monograph 7, William Barclay Parsons Fellowship, USA.
[12] Monsees J.E. and Richard D.P. (1994): “Seismic Design of Underground
Structures”. 1st Conference Egyptian Society for Earthquake Engineering, Cairo
[17] Hashash, M.A., Hook, J.J., Schmidt, B. and Yao, J.I. (2001): “Seismic design and
analysis of underground structures”. Tunnelling and Underground Space Technology Vol.
16 p 247-293.
5094704/D7003 Rev. BC
EAST WEST METRO PROJECT:
CONTRACT - UG1
TUNNEL DESIGN BASIS REPORT
UG1 WSA 200 NST REP 201 Rev. BC 27/10/11
Sequential
Project No. Origin Area Discipline Doc Code
number APPENDIX 1
Number
Item Document Ref. Title Revision Added by
of Pages