Arc Flash Exercise 1: Purpose & Description
Arc Flash Exercise 1: Purpose & Description
Arc Flash Exercise 1: Purpose & Description
System1 and System2 are almost identical, each without transformer primary side protection. There are four TCC
views included in the project, which allow you to see the current protective device settings for the secondary
protective devices.
Add the primary protective devices to the one-line diagram and after to the corresponding TCCs. After adding the
devices, compare and adjust their settings with respect to the 4.16 kV secondary side PDs. Please adjust the
settings as you feel necessary while trying to reduce incident energy. You may also plot the primary protection by
itself if needed, or you can use the TCC 2nd axis feature to show a second axis plotted on the primary side base
kV (plot kV = 12).
Setup
Load the project file named “AF-Example1”. (The solution to this example is located in a directory
called “Solution1”. Open the solution project only to compare against your exercise once completed.)
Utilize the Library from C:\ETAP xxx\lib (xxx= ETAP version currently being used)
Procedure
Step1
In Arc Flash Mode, open study case “AF MV”. Take a look at the Info page and the AF Method pages.
1.1 Why has the option “Symm. 1.5 to 4 Cycle” been selected? (Clue: Look at the faulted bus’ nominal kV)
____________________________________________________________________________________
1.2 What is the incident energy limit for Level B based on NFPA 70E 2012~2015? (Clue: Go to the AF Study
Case/Parameters page/ “Edit/Approve PPE” button under the PPE Requirements section.)
_____________________________________________________________________________________
Step2
Select study case called “AF MV”, run AF and name the report “AF MV”.
Observe the arc flash results displayed on the one-line diagram (OLD)
Double click on Bus A and then Bus2. Navigate to the Arc Flash page of each.
Open the Arc Flash Analysis report as well, and answer the following questions:
Step3
Add a fuse for the transformer primary winding protective devices in System1.
The fuse can be of any type within the ETAP library and it is strongly suggested that you try different types. Run
the AF calculation and check the TCCs to see if your solution is acceptable.
1. Standard = ANSI
2. Manufacturer = Southern States
3. Model = BPA-PF
4. Slow Speed
5. Interrupting current = 10 kA
6. Size = 100A (100 Amp continuous current)
3.1 What is the Incident energy released for a fault at line side of Main CBA?
(Clue: Go to the SC Display Options and select Source PDs under the Arc Fault Location)
3.2 What is the Fault Clearing Time for a fault at line side of Main CBA?
(Clue: Go to the SC Display Options and select FCT under the Arc-Flash section)
4.1 What is the Incident energy released for a fault at line side of Main CB1?
4.2 What is the Fault Clearing Time for a fault at line side of Main CB1?