EIA LNG - Executive Summary PDF
EIA LNG - Executive Summary PDF
EIA LNG - Executive Summary PDF
Executive Summary
nd
22 December 2006
!
www.erm.com
nd
22 December 2006
nd
22 December 2006
LNG RECEIVING TERMINAL AND ASSOCIATED FACILITIES EXECUTIVE SUMMARY
EXECUTIVE SUMMARY
LNG RECEIVING TERMINAL AND ASSOCIATED FACILITIES EXECUTIVE SUMMARY
CONTENTS
FOREWORD i
1 INTRODUCTION 1
1.1 BACKGROUND 1
1.2 PURPOSE AND NATURE OF THE PROJECT 1
1.3 PURPOSE AND SCOPE OF THIS EIA 1
1.4 WHAT IS LNG? 3
1.5 THE NEED FOR A LNG RECEIVING TERMINAL IN HONG KONG 3
1.6 REPLACEMENT GAS SUPPLY ALTERNATIVES 6
1.7 CONSIDERATION OF ALTERNATIVE SITE LOCATIONS 10
1.8 WHAT IS REQUIRED TO BRING LNG TO HONG KONG 11
FOREWORD
Hong Kong currently obtains approximately 25% of its electricity requirements from
the Castle Peak Power Company’s (CAPCO) Black Point Power station (BPPS).
This power plant is fuelled by natural gas supplied via pipeline from the Yacheng gas
field off Hainan Island. The gas supply from the Yacheng field is expected to be
depleted by early in the next decade. In 2003, CAPCO commenced studies to identify
a replacement source of natural gas.
The replacement studies examined importing gas from nearby gas fields, similar to the
current arrangement, importing Natural Gas (NG) via the Guangdong Dapeng
Liquefied Natural Gas (LNG) terminal or one of the proposed LNG terminals in
mainland China, or by importing LNG via a new terminal in Hong Kong. The
studies concluded that a LNG terminal located in Hong Kong is the only viable means
of providing an adequate, secure and reliable supply of gas within the necessary time
frame to meet Hong Kong's requirements.
To find a suitable location, CAPCO undertook a site search throughout Hong Kong,
which included 29 possible locations, and identified two sites having the best potential
overall; Black Point in the western New Territories, and South Soko Island, located to
the south of Lantau Island.
The overall conclusion of the EIA and this report is that there is a clear need for a
LNG terminal in Hong Kong and that, of all the potential alternatives examined,
South Soko is the preferred option. In accordance with the EIAO, CAPCO considers
that this EIA provides a suitable basis for the Director of Environmental Protection to
consider granting the Environmental Permit to allow the construction and operation
of this project at the South Soko Island site.
i
0018180_EXEC SUMM_TEXT_FORMAL_V27_7 DEC 06.DOC 11 DEC 2006
LNG RECEIVING TERMINAL AND ASSOCIATED FACILITIES EXECUTIVE SUMMARY
1 INTRODUCTION
1.1 BACKGROUND
Castle Peak Power Company Limited (CAPCO), a joint venture between CLP
Power Hong Kong Limited (CLP) and ExxonMobil Energy Limited (EMEL), is
proposing the development of a Liquefied Natural Gas (LNG) Receiving
Terminal in the Hong Kong SAR. The facility will provide the infrastructure
for a sustainable supply of natural gas (NG), primarily to fuel CAPCO’s
power plant at Black Point. CAPCO initiated preliminary site search and
environmental studies in 2003. Subsequent meetings and discussions with
Government and other stakeholders commenced in 2004. The EIA report for
the project, which is covered by this Executive Summary, is the outcome of
several years’ of informal and formal discussion between CAPCO,
Government and non Government stakeholders. To ensure adequate public
input, more than 350 seminars, meetings, workshops and exhibitions have
been held with key stakeholders and the community.
The Project will provide a replacement for the gas currently supplied to
CAPCO from the Yacheng gas field, which is expected to be depleted by early
in the next decade. The project involves the construction and operation of a
LNG receiving terminal and associated facilities at either South Soko Island or
Black Point. The receiving terminal will provide a facility for receiving and
unloading of LNG carriers, onshore LNG storage, LNG regasification, and a
pipeline for transporting natural gas (regasified LNG) to the existing Black
Point Power Station (BPPS). For the South Soko option, the natural gas will
be sent via a submarine gas pipeline to a Gas Receiving Station (GRS) at BPPS.
For the Black Point option the connection to BPPS will be via a short onshore
pipeline within the boundaries of the proposed terminal and the power
station. For both site locations, the principal natural gas user will be CAPCO.
The following elements of the Project addressed in this EIA Report are
classified as Designated Projects under the Environmental Impact Assessment
Ordinance (Cap. 499) (EIAO).
For both the South Soko Island and Black Point options:
• Dredging operation for the approach channel and turning circle that
exceeds 500,000 m3 (item C.12 of Part I of Schedule 2 of EIAO).
1
0018180_EXEC SUMM_TEXT_FORMAL_V27_7 DEC 06.DOC 11 DEC 2006
LNG RECEIVING TERMINAL AND ASSOCIATED FACILITIES EXECUTIVE SUMMARY
The EIA has been prepared by ERM-Hong Kong, Ltd (ERM) for CAPCO in
accordance with the EIA Study Brief (No. ESB-126/2005) , issued in June 2005,
and the Technical Memorandum of the Environmental Impact Assessment Process
(EIAO-TM).
The purpose of this EIA Study has been to provide information on the nature
and extent of environmental impacts arising from the construction and
operation of the Project and related activities that take place concurrently.
This information will contribute to decisions by the Director of the
Environmental Protection Department (EPD) on:
• the conditions and requirements for the detailed design, construction and
operation of the Project to mitigate against adverse environmental
consequences; and
The detailed requirements of the EIA studies of each site are set out in the EIA
Study Brief.
2
0018180_EXEC SUMM_TEXT_FORMAL_V27_7 DEC 06.DOC 11 DEC 2006
LNG RECEIVING TERMINAL AND ASSOCIATED FACILITIES EXECUTIVE SUMMARY
Liquefied Natural Gas (LNG) is the liquid form of natural gas, the main
component of which is methane. In the liquefied form, at atmospheric
pressure, LNG occupies only 1/600th of its volume at gaseous state under
normal temperature and atmospheric pressure and is therefore more
economical to store and transport over long distances in contrast to the
traditional pipeline delivery of natural gas.
Large scale LNG trade began in 1964, with the UK as the importing country.
Since then, the LNG industry has built up globally and in 2005 there were 13
countries producing (liquefying) LNG and 15 importing/receiving (re-
gasifying) LNG. The world’s four largest producers in 2005 were Indonesia
(17% global production), Malaysia (15%), Qatar (14%) and Algeria (13%).
1.5.1 Introduction
Since 1996 with the commissioning of the Black Point Power Station (BPPS),
natural gas has been an important component of CAPCO's fuel supply. Use
of natural gas has delivered significant environmental benefits as well as
added diversity to the fuel mix used for electricity generation, thereby
enhancing the security of electricity generation.
• Proven Use in Power Generation: Natural gas has been employed in the
combined cycle gas turbines (CCGT) at BPPS which has enabled this
facility to have higher thermal efficiency than coal or oil fired power
stations with the same generating capacity.
3
0018180_EXEC SUMM_TEXT_FORMAL_V27_7 DEC 06.DOC 11 DEC 2006
LNG RECEIVING TERMINAL AND ASSOCIATED FACILITIES EXECUTIVE SUMMARY
• Adequate Reserves Available: World gas reserves are large and LNG
technology makes them available to consumers in locations remote from
existing sources. This, along with coal and nuclear capabilities,
continues to provide a diverse fuel supply to CAPCO.
“61. To fully achieve the emissions reduction targets in 2010, we have asked the power
companies to … use natural gas for power generation as much as possible.
As Black Point Power Station (BPPS) provides about 25% of Hong Kong’s total
electricity needs, having a reliable supply of natural gas that fuels this power
station is critical for maintaining Hong Kong’s electricity supply. In the event
that gas is not available to BPPS, CAPCO will need to meet electricity demand
by a higher reliance on coal-fired generation , which will increase emissions
beyond existing levels and Government's targets. Although the BPPS is able
to use diesel as a fuel, this capability is designed only for short term
emergency backup use (2).
(1) The 2005-06 Policy Address, Strong Governance For the People, Paragraph 61.
(2) Long term diesel use would require additional investment in infrastructure, higher fuel cost, and would increase
emissions beyond existing levels and Government’s targets.
4
0018180_EXEC SUMM_TEXT_FORMAL_V27_7 DEC 06.DOC 11 DEC 2006
LNG RECEIVING TERMINAL AND ASSOCIATED FACILITIES EXECUTIVE SUMMARY
Given Hong Kong’s total dependence on imported fuel and the necessity of a
quality replacement gas supply, it is vital to have a clear understanding of the
requirements for supply of this important fuel in order to assess the various
replacement options. There are five fundamental requirements of the
replacement gas supply, namely
5
0018180_EXEC SUMM_TEXT_FORMAL_V27_7 DEC 06.DOC 11 DEC 2006
LNG RECEIVING TERMINAL AND ASSOCIATED FACILITIES EXECUTIVE SUMMARY
1. Import gas via pipeline from a nearby gas field: The South China Sea
contains only limited discovered reserves of natural gas, with the majority
of these gas reserves being exploited. These fields are significantly
smaller than Yacheng, are of varying qualities, and have been committed
to identified customers (Dongfang and Ledong – committed to Hainan,
Panyu and Huizhou – targeted to Zhuhai). Given the above, importing
gas from any of the proven South China Sea fields is not feasible because
there is insufficient supply available to meet CAPCO’s and Hong Kong’s
long-term needs. In 2006, there are reports of what could be a significant
deep water gas discovery in the South China Sea At present, information
is very preliminary and insufficient to assess whether this deep water
field is commercially viable and can play a role in CAPCO’s future gas
supply. However, historically progressing a deepwater gas project from
discovery to production has taken 8 to 14 years. For example, although
not a deepwater project, the Yacheng 13-1 gas field took 12 years from
discovery to start-up. This would be an unacceptably long timeframe for
CAPCO's replacement gas supply.
2. Import Natural Gas (NG) via the Guangdong Dapeng LNG terminal
(GDLNG): The GDLNG terminal in Shenzhen, China’s first LNG
terminal, was commissioned this year. GDLNG's initial capacity of
3.7MTA and supply are fully committed to its founding shareholders,
including Guangdong gas users, Hong Kong Electric and Hong Kong &
China Gas. CAPCO assessed the option and understands that the
additional capacity from expansion of the terminal will be dedicated to
Guangdong gas users with unknown timing.
6
0018180_EXEC SUMM_TEXT_FORMAL_V27_7 DEC 06.DOC 11 DEC 2006
LNG RECEIVING TERMINAL AND ASSOCIATED FACILITIES EXECUTIVE SUMMARY
4. Importing LNG via a new terminal in Hong Kong: CAPCO has been
progressing development activities for a LNG terminal in Hong Kong
since 2003. Having completed engineering and environmental feasibility
studies, CAPCO has concluded that constructing a LNG receiving
terminal in Hong Kong will be able to meet CAPCO’s timing and supply
requirements in order to replace the depleting Yacheng field. For
example, extensive site investigation work, preliminary engineering as
well as the pipeline route survey have been completed. The 18-month
EIA process has also reached a major milestone with the submission of
this EIA study. Consultation with Government and the public has been
ongoing since 2004. Discussions with LNG suppliers and LNG shipping
providers are also underway. In short, CAPCO’s development of the
Hong Kong LNG terminal is now at an advanced stage to meet the 2011
timing. An LNG terminal located entirely within Hong Kong enables
smoother and faster project development under a single jurisdiction with
clear policy and regulations. Similar advantages are offered by CAPCO’s
well established commercial structure under the Scheme of Control (SoC).
Given the expected gas depletion by early in the next decade and an LNG
Terminal requirement date of 2011, CAPCO is progressing the
development of a Hong Kong terminal as the only viable alternative.
7
0018180_EXEC SUMM_TEXT_FORMAL_V27_7 DEC 06.DOC 11 DEC 2006
LNG RECEIVING TERMINAL AND ASSOCIATED FACILITIES EXECUTIVE SUMMARY
In summary, the absence or delay of a replacement gas supply will not only
entail an environmental impact but will also compromise Hong Kong’s
electricity supply reliability.
The analysis reveals that a Hong Kong LNG receiving terminal is the only
option that is capable of fully meeting the requirement of a replacement gas
supply with respect to timing, security of supply, volume adequacy and
flexibility, and competitiveness (Table 1). Moreover, there are other external
benefits to Hong Kong flowing from the project as a Hong Kong terminal will
provide construction and operation jobs in Hong Kong as well as tax and land
grant revenues for the Government. With energy issues high on government
agendas internationally, the LNG terminal will be a strategic asset for Hong
Kong as it will provide the means of access to global natural gas supplies.
Now that engineering and environmental feasibility studies have been
completed, and with timely progress on regulatory regime resolution and
other key approvals, a terminal in Hong Kong can be completed by 2011 to
meet CAPCO’s requirements. CAPCO believes the Hong Kong LNG
receiving terminal is the only viable solution available to ensure a reliable
electricity supply for Hong Kong.
8
0018180_EXEC SUMM_TEXT_FORMAL_V27_7 DEC 06.DOC 11 DEC 2006
LNG RECEIVING TERMINAL AND ASSOCIATED FACILITIES EXECUTIVE SUMMARY
2. Supply Security Moderate – May serve as one Low – Additional long-term Unknown - No project to meet High. - Priority for None – Any indecision or
for Hong Kong of the multiple sources capacity not available to CAPCO / HK's needs within CAPCO/HK is ensured. deferral will not provide the
required for Hong Kong. CAPCO / HK. Also, the time frame. Supply Additional security with required gas supply for Hong
imprudent to have the entire source also uncertain. multiple LNG sources. Kong.
HK and Guangdong demand
supplied through a single
terminal
3. Adequate Volume Low - No credible gas field Low – Additional long-term Unknown - No project to meet High - Terminal designed to None – No gas supply is
and Flexibility with adequate capacity and capacity not available to CAPCO / HK's volume and meet HK’s increasing gas available to serve Hong Kong’s
volume available. CAPCO / HK. flexibility requirements. demand. Capacity will be needs.
assured for Hong Kong’s
needs.
4. Competitive Low – Commercial structure Low – Long-term capacity Unknown - No credible High – Competes in None – No gas supply is
Supply of Gas and competitiveness of and supply not available to supply source identified. international LNG markets to available to serve Hong Kong’s
procurement process yet to be HK. Presence of third party Presence of third party allow a transparent process needs.
determined. operator as middleman adds operator as middleman with competitive market
No supplier with credible cost for their profit in the increases cost and complexity. pricing on supply terms.
proven reserves to contract supply chain.
with.
5. Environmental Issues and Standards not Issues and Standards not Issues and Standards not High - Environmental issues None - Increased emissions
and Safety known at this time. known at this time. The known at this time. The are understood and can be from more coal burn
Standards required pipeline is longer required pipeline is longer mitigated.
with its later part traversing with its later part traversing
same marine area as HK same marine area as HK
terminal. terminal.
Certainty of each of the five alternatives to meet Hong Kong's gas requirements is ranked as none, low, moderate, or high.
9
0018180_EXEC SUMM_TEXT_FORMAL_V27_7 DEC 06.DOC 11 DEC 2006
LNG RECEIVING TERMINAL AND ASSOCIATED FACILITIES EXECUTIVE SUMMARY
Over the following twenty four months, an alternative site location study
encompassing 29 sites was conducted to determine the most suitable coastal
site(s) in Hong Kong for the LNG terminal. A phased approach to the
screening and assessment of sites within Hong Kong was conducted,
including periodic consultation with Government via an Environmental Study
Management Group (ESMG). Environmental sensitive receivers (e.g.,
existing Country Parks, Marine Parks, Fish Culture Zones, Gazetted Beaches)
were screened out in the early phases to aid in avoiding environmental
impacts. The results of this Hong Kong wide site location study indicated
that, from a long list of 29 locations across Hong Kong, two sites offered the
best potential for further analysis based on environmental, risk, planning,
social, marine traffic and engineering criteria. The two preferred sites were
South Soko Island, at the location of the former Detention Centre, and Black
Point, on the headland adjacent to the existing power station (BPPS) (Figure
1.1).
Figure 1.1 Location of South Soko and Black Point Candidate Sites for the LNG
Terminal
10
0018180_EXEC SUMM_TEXT_FORMAL_V27_7 DEC 06.DOC 11 DEC 2006
LNG RECEIVING TERMINAL AND ASSOCIATED FACILITIES EXECUTIVE SUMMARY
The LNG industry can be described by an LNG value chain consisting of 5 key
elements (Figure 1.2):
• Exploration, development and production of gas
• Liquefaction
• Shipping
• Storage and Regasification
• End use (e.g. power generation)
Near the end of the supply chain is the receiving terminal. The key
components of the proposed LNG terminal include marine jetty facilities for
unloading LNG, special tanks for LNG storage, equipment for converting the
LNG back to gas, utilities and other infrastructure. LNG tanks are specially
designed to contain the LNG at a temperature of approximately -162 °C near
atmospheric pressure (Figure 1.3).
11
0018180_EXEC SUMM_TEXT_FORMAL_V27_7 DEC 06.DOC 11 DEC 2006
LNG RECEIVING TERMINAL AND ASSOCIATED FACILITIES EXECUTIVE SUMMARY
12
0018180_EXEC SUMM_TEXT_FORMAL_V27_7 DEC 06.DOC 11 DEC 2006
LNG RECEIVING TERMINAL AND ASSOCIATED FACILITIES EXECUTIVE SUMMARY
LNG carriers have insulated cargo tanks and are of double-hull design. The
double hull provides the location for the segregated ballast and provides
optimum protection for the integrity of the cargo tank containment in the
unlikely event of collision or grounding. There are two types of LNG
carriers: Moss and Membrane. Moss LNG carriers have four or five
spherical tanks contained in the hull, with a substantial proportion of each
tank above the weather deck. In a membrane design the larger proportion of
each tank is below the weather deck (Figures 1.4). Both carrier types are
commonly utilized for LNG transit with no significant operational difference
between them.
LNG shipping has an outstanding safety record, with over 60,000 LNG carrier
voyages, covering more than 90 million miles, and over 40 years of operation
without a failure or loss of cargo. This excellent safety record can be
attributed to the high technical standards employed in the design,
construction and operation of LNG facilities and carriers and also the physical
properties of LNG. In part, the safety record is a result of the adoption
worldwide of a series of standards, codes, regulations, and operating
procedures and practices. For example, these extra measures that will be
applied in Hong Kong include daylight only transit, use of two local pilots in
13
0018180_EXEC SUMM_TEXT_FORMAL_V27_7 DEC 06.DOC 11 DEC 2006
LNG RECEIVING TERMINAL AND ASSOCIATED FACILITIES EXECUTIVE SUMMARY
addition to the Ship's Master while transiting in Hong Kong, and between two
and four escort tugs at all times.
14
0018180_EXEC SUMM_TEXT_FORMAL_V27_7 DEC 06.DOC 11 DEC 2006
LNG RECEIVING TERMINAL AND ASSOCIATED FACILITIES EXECUTIVE SUMMARY
It is proposed that the LNG terminal will be located on 36.5 ha of land located
in the centre of South Soko Island. The majority of the terminal’s facilities
will be located on land that was developed in the late 1980s as a Detention
Centre. The Detention Centre was demolished in the mid 1990s and what
remains is a series of cut slopes, access roads and paths coming from the large
concrete platform in the centre of the island. In order to locate all of the
necessary equipment for the terminal, reclamation totalling less than 0.6
hectares will be required in Sai Wan. Seawall modifications will also be
required at South Soko which will occupy 1.1 ha of artificial and natural
coastline. The key elements of the LNG terminal are presented in the
preliminary layout on Figure 2.1 and include:
• Process Area;
• In order to deliver the regasified natural gas from the terminal to BPPS, a
38 km long submarine gas pipeline (provisional alignment as shown in
Figure 2.2) will be constructed;
• A gas receiving station is required at the BPPS to receive the gas and send
it on to the power station;
15
0018180_EXEC SUMM_TEXT_FORMAL_V27_7 DEC 06.DOC 11 DEC 2006
Storage Tanks
on Formed Land
Jetty &
Construction Equipment Berthing Area
Stores and Access Road
Present only during
Construction Phase
Project Area 36.5ha
Turning Basin Reclamation Area 0.6ha
Dredging Volume
Approach (Project Total) 3.89Mm
3
Channel
Figure 2.1 Preliminary Indicative Layout for the Proposed South Soko LNG Terminal Environmental
(Aerial photograph source: Lands Department) Resources
FILE: c2662(0018180)eia_docu-set2_95g_3.cdr Management
EIA_0018180_Jpg_output-soko.mxd
DATE: 15/11/2006
795000 800000 805000 810000 815000
)
Black Point
830000
830000
Power Station
KEY
) Black Point GRS
Tuen Mun
Proposed Water Pipe Route Lung Kwu
Ur m
Proposed Cable Circuit Route Chau
sto
Hong Kong SAR Boundary
n
LNG Terminal
Ro
825000
825000
ad
Proposed Gas Pipeline Route
Sha Chau
820000
820000
Chek Lap Kok
Tai Ho
Tung Chung
New Town
815000
815000
Sham
Wat
Lantau Island
Tai O
810000
810000
Tong Fuk
Yi O Shek Pik
Shui Hau
Peaked
Hill
Fan Lau
North Soko
805000
805000
0 2
´
Kilometers
4 8
South Soko
Figure 2.2
Environmental
Locations of Works Resources
File: EIA/0018180_Prelim_Pipeline_1.mxd Management
Date: 17/10/2006
LNG RECEIVING TERMINAL AND ASSOCIATED FACILITIES EXECUTIVE SUMMARY
The LNG terminal will be designed and operated according to the European
Standard EN 1473 – Installation and Equipment for Liquefied Natural Gas - Design
of Onshore Installations.
The LNG carrier will access the site via the southern approaches to Hong
Kong waters before berthing at South Soko. Dredging work (approximately 1
Mm3) will be required to provide the necessary approach to the jetty and for a
turning circle for the LNG carrier. The marine transit route is presented in
Figure 2.3.
16
0018180_EXEC SUMM_TEXT_FORMAL_V27_7 DEC 06.DOC 11 DEC 2006
LNG RECEIVING TERMINAL AND ASSOCIATED FACILITIES EXECUTIVE SUMMARY
• By locating the terminal facilities in the centre of the island the disturbance
to natural habitats on the island has been reduced and the view of the
storage tanks from visual sensitive receivers on Lantau Island is in part
obscured.
Various route options for the South Soko-BPPS gas pipeline have been
examined. The assessment concluded overland routes across Lantau will
have the greatest potential impacts for water quality, ecological and landscape
impacts within the Country Parks (North Lantau and South Lantau) and along
the roads in Lantau and are not preferred. A tunnel option through Lantau
has been examined and although it will avoid most of the land-based sensitive
17
0018180_EXEC SUMM_TEXT_FORMAL_V27_7 DEC 06.DOC 11 DEC 2006
LNG RECEIVING TERMINAL AND ASSOCIATED FACILITIES EXECUTIVE SUMMARY
receivers, it also presents more drawbacks with respect to the offshore option
(Base Case). These include:
• potential impacts on the Tai Long Wan and Sham Wat archaeological
sites;
• water quality impacts due to the dredging and reclamation of the tunnel
portal working areas; and,
The assessment concluded that due to the short-term and transient nature of
the water quality and marine ecological impacts, a completely marine route is
preferred. The marine route also avoids additional ecological, noise, air,
cultural heritage, waste, landscape and visual impacts to land based sensitive
receivers. In addition, construction methods have been designed to reduce
the impacts in sensitive marine mammal habitat, including restricted working
hours, controlling construction rates, and avoiding peak calving periods for
specific works.
Two (2) Air Sensitive Receivers (ASR) were identified (Shek Pik Prison and the
administration building for the Black Point Power Station) and the potential
impacts arising from the construction and operation phases of the LNG
terminal to these ASRs have been evaluated. No exceedance of the Air
Quality Objective (AQO) is anticipated at the ASRs and therefore no air
quality monitoring will be required for either the construction or operational
phase.
2.5 NOISE
No Noise Sensitive Receivers (NSRs) have been found on South Soko and the
nearest NSR has been identified on Lantau Island (Shek Pik Prison) which is
located approximately 6 km away from the site. The predicted construction
noise levels are within the stipulated noise criterion of 75 dB(A). The noise
levels generated from the equipment during the operation of the LNG
terminal are within daytime and night-time noise criteria.
18
0018180_EXEC SUMM_TEXT_FORMAL_V27_7 DEC 06.DOC 11 DEC 2006
LNG RECEIVING TERMINAL AND ASSOCIATED FACILITIES EXECUTIVE SUMMARY
Potential impacts arising from the proposed dredging, backfilling and jetting
works are predicted to be mainly confined to the specific works areas.
Modelling results indicate that the suspended solids elevations as a result of
dredging and jetting for the installation of the submarine utilities are expected
to be compliant with the assessment criteria at all point specific sensitive
receivers in both seasons. In the few exceptions in which the modelling
results indicate elevations above the criteria (i.e. open waters in western part
of Lantau and open waters around South Soko during dredging activities)
these are of short duration (typically less than one day) and not considered
sufficient to cause an unacceptable deterioration of water quality. The
elevation predicted at Pak Tso Wan beach and at the False Pillow Coral
location can be mitigated through the adoption of silt curtains. Hence it is
anticipated that such elevations above the criteria would be temporary and
unacceptable impacts would be unlikely to arise. Overall the predicted
elevations of suspended sediment concentrations during the construction
phase are transient in nature and not predicted to cause adverse impacts to
water quality at the sensitive receivers.
During the operation phase, adverse impacts to water quality are not expected
to occur as the area affected by the cooled water and antifoulants discharge is
extremely small and in the direct vicinity of the discharge point.
19
0018180_EXEC SUMM_TEXT_FORMAL_V27_7 DEC 06.DOC 11 DEC 2006
LNG RECEIVING TERMINAL AND ASSOCIATED FACILITIES EXECUTIVE SUMMARY
The LNG terminal and its associated facilities will be located mainly in
habitats of low ecological value such as the already disturbed areas which
were formerly part of the now demolished Detention Centre. The
construction impact on the natural habitats and associated wildlife is
considered to be manageable, and no adverse residual impact is expected after
the implementation of the recommended mitigation measures.
20
0018180_EXEC SUMM_TEXT_FORMAL_V27_7 DEC 06.DOC 11 DEC 2006
LNG RECEIVING TERMINAL AND ASSOCIATED FACILITIES EXECUTIVE SUMMARY
During the operational phase, adverse impacts are not expected to occur.
Therefore, no terrestrial ecology monitoring will be required.
The waters and coastal areas of West Lantau and Southwest Lantau including
the Soko Island group, which are located away from the major population
centres of Hong Kong, have been considered by some academics, government
and green groups to be a general area of high ecological value including from
a marine perspective. However, it is important to note that there are
significant spatial variations in the ecological values and characteristics within
this large area which encompasses the smaller Study Area.
Ecologically sensitive receivers have been identified and the potential impacts
arising from the construction and operation phases of the LNG terminal on
them have been evaluated. The key sensitive receivers include habitats of the
Indo-pacific Humpback Dolphin (Sousa chinensis) and Finless Porpoise
(Neophocaena phocaenoides), the Sha Chau and Lung Kwu Chau Marine Park
and other ecologically sensitive areas such as spawning and nursery grounds
and coral habitat.
As previously discussed, the layout selected for South Soko Island reduces
reclamation to approximately 0.6 ha of Sai Wan bay. Coastline disturbance
for modification of the seawalls is limited to approximately 300 m of natural
coastline. The area of seawall modification is 1.1 ha which includes both
natural and artificial coastlines. As a result of the small size of habitat
directly affected by the works and the previous history of reclamation along
this particular coastline, the impacts are classified as acceptable.
The results of the water quality modelling activities indicate that indirect
impacts arising from the marine works will generally be transient and
confined to the works areas and compliant with the assessment criteria after
implementation of mitigation measures. It is therefore predicted that there
will be no unacceptable impacts to the marine ecology (including marine
mammals) of the Study Area as a result of the LNG terminal’s construction
activities.
21
0018180_EXEC SUMM_TEXT_FORMAL_V27_7 DEC 06.DOC 11 DEC 2006
LNG RECEIVING TERMINAL AND ASSOCIATED FACILITIES EXECUTIVE SUMMARY
2.10 FISHERIES
The Water Quality modelling activities indicate that the impacts arising from
the proposed dredging or jetting works are predicted to be largely confined to
the specific works areas and the predicted elevations in suspended sediment
concentrations are not predicted to cause large area exceedances of the
assessment criterion. Adverse impacts to fishing grounds or species of
importance to the fisheries are therefore not expected to occur.
The potential impacts to the landscape and visual sensitive receivers caused
by the presence of the LNG terminal at South Soko have been assessed. The
assessment has covered a wide range of potential landscape impacts including
the alteration of the landscape caused by the excavation and reclamation, and
the introduction of the LNG terminal in South Soko Island’s natural
landscape. The baseline Landscape Resources are generally of low to
moderate sensitivity and there will be no significant impacts on any of the
Landscape Resources. The baseline Landscape Character of the Soko Islands
is of generally high quality. There will be varied impacts on the landscape
22
0018180_EXEC SUMM_TEXT_FORMAL_V27_7 DEC 06.DOC 11 DEC 2006
LNG RECEIVING TERMINAL AND ASSOCIATED FACILITIES EXECUTIVE SUMMARY
The assessment has evaluated the hazards to life associated with the LNG
terminal, the submarine gas pipeline and the Gas Receiving Station as well as
the marine transit of LNG. The assessment has concluded that the risks
23
0018180_EXEC SUMM_TEXT_FORMAL_V27_7 DEC 06.DOC 11 DEC 2006
LNG RECEIVING TERMINAL AND ASSOCIATED FACILITIES EXECUTIVE SUMMARY
related to transit of LNG to South Soko, the operation of the terminal, the
submarine gas pipeline and the Gas Receiving Station are acceptable as per
the individual and societal risk criteria set out in Annex 4 of the EIAO-TM.
A summary of the key design and environmental aspects of the South Soko
option, with a comparison against the Black Point option, is presented in Table
4.1
24
0018180_EXEC SUMM_TEXT_FORMAL_V27_7 DEC 06.DOC 11 DEC 2006
LNG RECEIVING TERMINAL AND ASSOCIATED FACILITIES EXECUTIVE SUMMARY
• Process Area
The LNG terminal will be designed and operated according to the European
Standard EN 1473 – Installation and Equipment for Liquefied Natural Gas - Design
of Onshore Installations.
The LNG carrier will access the site via the East Lamma Channel, transit the
Ma Wan Channel, Urmston road before berthing at Black Point (Figure 3.2).
Dredging work (approximately 2.5 Mm3) will be involved to provide the
necessary approach to the jetty and for a turning circle for the LNG carrier.
25
0018180_EXEC SUMM_TEXT_FORMAL_V27_7 DEC 06.DOC 11 DEC 2006
Project Area 32ha Turning Basin
Admin Area
Approach
Channel
Process Area
Laydown Area
Project Boundary
Storage Tanks
Figure 3.1 Layout for the Proposed Black Point LNG Terminal Environmental
(Aerial photograph source: Lands Department) Resources
FILE: c2662(0018180)eia_docu-set2_96d_2.cdr Management
EIA/0018180_Jpg_output-BK.mxd
DATE: 05/10/2006
LNG RECEIVING TERMINAL AND ASSOCIATED FACILITIES EXECUTIVE SUMMARY
26
0018180_EXEC SUMM_TEXT_FORMAL_V27_7 DEC 06.DOC 11 DEC 2006
LNG RECEIVING TERMINAL AND ASSOCIATED FACILITIES EXECUTIVE SUMMARY
Two construction options were considered, the Fully Dredged Option and the
Partially Dredged Option. The Partially Dredged Option is adopted to
minimise the volume of dredged material for disposal.
For the construction of the LNG Jetty, two alternatives for the installation of
marine piles have been assessed (bored or percussive). The assessment
proposed that either method would be suitable for the construction of the
LNG Jetty as part of the Black Point terminal. In addition to the above,
construction methods will be adopted including the use of a bubble jacket to
reduce underwater sound levels during marine percussive piling work for the
construction of the jetty.
Two dredging plants have been assessed: grab dredgers and trailing suction
hopper dredgers (TSHD). Both are commonly used in Hong Kong and as
such have been considered as viable options.
3.4 NOISE
27
0018180_EXEC SUMM_TEXT_FORMAL_V27_7 DEC 06.DOC 11 DEC 2006
LNG RECEIVING TERMINAL AND ASSOCIATED FACILITIES EXECUTIVE SUMMARY
28
0018180_EXEC SUMM_TEXT_FORMAL_V27_7 DEC 06.DOC 11 DEC 2006
LNG RECEIVING TERMINAL AND ASSOCIATED FACILITIES EXECUTIVE SUMMARY
The terrestrial ecological resources recorded within the Study Area include
plantation, shrubland, shrubby grassland, stream/channel, orchard and
developed areas, with their associated wildlife. Of these habitats, shrubland
located at the western part of the headland is of moderate ecological
importance, shrubland located at the southern part of the headland and the
stream are low to moderate in ecological importance, while the remaining
habitats are of low or negligible ecological importance.
During the operation phase of the LNG terminal at Black Point, adverse
impacts to terrestrial ecological resources are not expected to occur.
A series of detailed seasonal field surveys were conducted during 2004, 2005
and 2006 examining the organisms present on intertidal and subtidal shores
and within the soft seabed around Black Point. Land (12 months in 2004 -
2005) and vessel (July 2005 to May 2006) based marine mammal surveys were
also conducted around Black Point. Ecologically sensitive receivers have
been identified and the potential impacts arising from the construction and
operation phases of the LNG terminal to these have been evaluated. The key
sensitive receivers include the Indo-pacific Humpback Dolphin (Sousa
chinensis) habitat of Northwest Lantau, the Sha Chau and Lung Kwu Chau
Marine Park and ecologically sensitive areas (mangroves, horseshoe crab
habitat, seagrass beds and intertidal mudflats).
The results of the water quality modelling activities indicate that indirect
impacts arising from the marine works will generally be transient and
confined to the works areas and compliant with the assessment criteria. It is
therefore predicted that there will be no unacceptable impacts to the marine
29
0018180_EXEC SUMM_TEXT_FORMAL_V27_7 DEC 06.DOC 11 DEC 2006
LNG RECEIVING TERMINAL AND ASSOCIATED FACILITIES EXECUTIVE SUMMARY
ecology (including marine mammals) of the Study Area as a result of the LNG
terminal’s construction activities.
All marine vessels involved in the Project will be required to observe a speed
limit in areas where marine mammals are present. The mitigation measures
designed to mitigate impacts to water quality to acceptable levels (compliance
with assessment criteria) are also expected to mitigate impacts to marine
ecological resources.
3.9 FISHERIES
The potential impacts to the landscape and visual sensitive receivers caused
by the presence of the LNG terminal at Black Point have been assessed. The
assessment has covered a wide range of potential landscape impacts including
the alteration of the landscape caused by the reclamation and the introduction
of the LNG terminal in Black Point’s natural landscape. The baseline
Landscape Resources are generally of varying sensitivity and there will be no
significant impacts on any of the Landscape Resources. The LNG terminal will
only be visible from a limited number of locations, and these impacts will only
be significant at close proximity (< 1,260m) to the Black Point Terminal. As
30
0018180_EXEC SUMM_TEXT_FORMAL_V27_7 DEC 06.DOC 11 DEC 2006
LNG RECEIVING TERMINAL AND ASSOCIATED FACILITIES EXECUTIVE SUMMARY
most of the VSRs within this distance are located in ocean areas, the impact is
greatly reduced as all visitors will experience this impact from marine vessels.
There will be a moderate to significant visual impact from the publicly
accessible lookout of Lung Kwu Chau on clear days. However there will be
low visitor numbers to experience this impact. The presence of LNG terminal
will have a moderate to significant negative impact on the existing Landscape
Character of Black Point, particularly the hill slope area, however the impacts
on the other LCA's will range from moderate to negligible
The assessment has evaluated the hazards to life associated with the LNG
terminal as well as the marine transit of LNG. Based on the risk criteria set
out in Annex 4 of the EIAO-TM, the assessment has concluded that the
individual risk for the marine transit and the LNG terminal are acceptable.
However, the societal risk of the marine transit to Black Point is As Low As
Reasonably Practicable (ALARP) (1 for some areas of the marine transit; the
difference in risk for these areas is due to busy marine traffic and high
population density particularly through the Ma Wan channel. Measures to
(1 ) Under Hong Kong EIAO-TM guidelines, there are three regions of risk categorisation: "Acceptable" requires no
further action; risk within "ALARP" should be mitigated to as low as reasonably practicable; and, "Unacceptable"
cannot be permitted.
31
0018180_EXEC SUMM_TEXT_FORMAL_V27_7 DEC 06.DOC 11 DEC 2006
LNG RECEIVING TERMINAL AND ASSOCIATED FACILITIES EXECUTIVE SUMMARY
mitigate the marine societal risk through these areas from ALARP to
Acceptable are not considered to be implementable at this time by the relevant
Authority due to their impact on other marine traffic in the busy Hong Kong
environment. LNG transit through these areas is avoided by the selection of
the South Soko site, where the risk of the marine transit has been assessed as
Acceptable along the entire route.
3.14 SUMMARY
A summary of the key design and environmental aspects of the Black Point
option, with a comparison against the South Soko option, is presented in Table
4.1.
32
0018180_EXEC SUMM_TEXT_FORMAL_V27_7 DEC 06.DOC 11 DEC 2006
LNG RECEIVING TERMINAL AND ASSOCIATED FACILITIES EXECUTIVE SUMMARY
As noted previously with BPPS providing about 25% of Hong Kong’s total
electricity needs, having a reliable supply of natural gas that fuels this power
station is critical for maintaining Hong Kong’s electricity supply. In the event
that gas is not available to BPPS, CAPCO will need to meet electricity demand
by a higher reliance on coal-fired generation, with increased emissions as a
result. Under such circumstances, Hong Kong consumers could be exposed
to supply interruptions or power rationing.
For each of the components assessed in the South Soko EIA Report, the
assessments and the residual impacts have all been shown to be acceptable
within the relevant standards/criteria of the EIAO-TM and the associated
Annexes.
The marine risk for the transit of LNG carriers to Black Point is in the As Low
As reasonably Practicable (ALARP) (1) region for some areas of the marine
transit of the LNG carrier but for all other aspects of the Black Point EIA
Report, the assessments and the residual impact have all been shown to be
acceptable within the relevant standards/criteria of the EIAO-TM and the
associated Annexes.
(1 ) Under Hong Kong EIAO-TM guidelines, there are three regions of risk categorisation: "Acceptable" requires no
further action; risk within "ALARP" should be mitigated to as low as reasonably practicable; and, "Unacceptable"
cannot be permitted.
33
0018180_EXEC SUMM_TEXT_FORMAL_V27_7 DEC 06.DOC 11 DEC 2006
LNG RECEIVING TERMINAL AND ASSOCIATED FACILITIES EXECUTIVE SUMMARY
34
0018180_EXEC SUMM_TEXT_FORMAL_V27_7 DEC 06.DOC 11 DEC 2006
LNG RECEIVING TERMINAL AND ASSOCIATED FACILITIES EXECUTIVE SUMMARY
Table 4.1 Summary of the Key Findings of the Environmental Performance Comparison – (site parameters are based on the preliminary indicative site
design and are approximate)
• Need to dispose of 3.89 Mm3 of marine sediment. • Need to dispose of 3.15 Mm3 of marine sediment.
• Need to dispose of 179,000 m3 of excavation waste off site • 0 m3 of excavation waste (assuming all material accommodated within
WASTE assuming 1.30 Mm3 is used to rock armour the submarine gas the reclamation site)
pipeline.
• South Soko: permanent loss of approximately 0.2 ha of secondary • Permanent loss of approximately 4.2 ha of shrubland considered to be of
woodland, 2.8 ha of plantation, 7.3 ha of shrubland, 0.5 ha of moderate ecological value and 1.0 ha of disturbed area
abandoned wet agricultural land, 1.8 ha of grassland and 5.3 ha of • Although the terrestrial ecology at Black Point is mainly dominated by
disturbed area. The affected areas are considered to be generally moderate-low value shrubland/grass habitat typical of Hong Kong, it
low to moderate quality habitats. must be noted that the Project Area is relatively undisturbed with no
• Shek Pik: permanent loss of approximately 0.004 ha of plantation significant human alterations.
TERRESTRIAL
and 0.02 ha of developed area. The affected areas are considered
ECOLOGY
to be generally low/negligible quality habitats.
• Many of the habitats on South Soko Island are highly modified
and disturbed as a result of village developments up to the 1960s,
the construction of a Detention Centre in 1980s and its subsequent
demolition in the 1990s.
• Permanent loss of approximately 265 m of natural rocky • Permanent loss of approximately 600 m of natural rocky shore/intertidal
shore/natural subtidal habitat and approximately 35 m of sandy habitat which are of low ecological value. The residual impact is
shore which are of low to medium ecological value. The residual acceptable, as the loss will be compensated by the provision of approx. 1.1
impact is considered to be acceptable, as the loss of these habitats km of sloping rubble mound/rock or concrete armour seawalls.
MARINE ECOLOGY
will be compensated by the provision of 0.6 km of sloping rubble • Permanent loss of approximately 16 ha of subtidal soft bottom
mound/rock or concrete armour seawalls. assemblages within the reclamation sites. The residual impact is
• Permanent loss of approximately 0.6 ha of subtidal soft bottom acceptable as even though the size of habitat lost is relatively large it is of
assemblages and marine waters within the reclamation site. The relatively low ecological value.
35
• Acceptable residual impact is loss of 0.6 ha of seabed used for • Residual impact is loss of 16 ha of fishing grounds. Considered
FISHERIES small-scale fishing operations. acceptable despite relatively large size as production values are low.
• Overall the residual impacts on the Landscape Resources would • There will be a residual impact on the Shrubland. However, the impacts
be slight. on the Landscape Resources will overall be slight-moderate.
• The principal visual change will be for those few viewers who • LNG terminal only visible from limited viewpoints, including visitors to
visit the surrounding area and particularly the ocean between the remote island of Lung Kwu Chau in the Marine Park and the transient
South and North Soko. passengers on ferry routes.
LANDSCAPE & VISUAL • Land based VSRs will experience negligible to moderate adverse • Visitors to Lung Kwu Chau may experience a moderate to significant
impacts. visual impact during clear days. However there are low user numbers to
• VSRs on South Soko and on waters around South Soko will this area. The users of the ferry routes may experience a moderate visual
experience significant adverse impacts. However, there are low impact.
visitors numbers in this area, and no residents, to experience this • Potential glare and lighting impacts will be low due to the distances
impact. between the site and viewers and careful lighting selection and
36
• Direct loss of archaeological deposits areas Sites A to E. Given • Loss of two building structures at Terrace 1, a WWII cave at Terrace 2
the construction of underground utilities making in-situ and a stone structure at Terrace 3 of low cultural resource value.
preservation impossible, as a last resort, an archaeological action • The loss is considered acceptable provided that a photographic and
plan has been recommended which is a separate document cartographic recording is undertaken for the sites following AMO’s
containing the detailed rescue excavation plan, archaeological requirements.
watching brief plan and contingency plan to preserve impacted
archaeological deposits by record.
• Impact on the Tai A Chau Tin Hau Temple, 21 graves and the
CULTURAL HERITAGE associated tablet and 7 earthshrines is expected. These sites will
be relocated with the provision of photographic and cartographic
records to preserve them by record prior to their removal. An
archaeological survey will be undertaken at the suitable relocation
site for the Tai A Chau Tin Hau Temple to confirm if any
archaeological deposits will be impacted at the relocation site. If
archaeological deposits are identified, appropriate mitigation
measures will be implemented to mitigate the impact.
37
• The results of the Marine Quantitative Risk Assessment of the • The results of the Marine Quantitative Risk Assessment of the transit of
transit of the LNG carrier to South Soko indicated that individual the LNG carrier to Black Point indicated that individual risk is acceptable
and societal risk levels are acceptable as per the HKSARG risk and the societal risk is as low as reasonably practicable (ALARP) as set
guidelines presented in Annex 4 of the EIAO-TM. out in HKSARG risk guidelines presented in Annex 4 of the EIAO-TM.
• The results of the Terminal and Pipeline Quantitative Risk • The results of the Terminal Quantitative Risk Assessments of the LNG
Assessments of the LNG terminal at South Soko indicated that terminal at Black Point indicated that individual and societal risk levels
individual and societal risk levels comply with the HKSARG risk comply with the HKSARG risk guidelines presented in Annex 4 of the
guidelines presented in Annex 4 of the EIAO-TM. EIAO-TM.
• The location of the South Soko Island provides for very low
HAZARD TO LIFE numbers of surrounding land and marine-based populations with • Access to the Black Point site today requires marine transit through busy
exposure to both the terminal site and the marine transit. harbour traffic, and along densely populated areas, of:
38
CAPCO has identified a preference for the South Soko option for the
following reasons:
• South Soko allows an earlier replacement of natural gas supply and can
provide flexibility for higher gas off-take depending on certainty of
remaining Yacheng gas availability which would result in CAPCO
burning less coal, and avoiding the associated emissions;
• South Soko enables CAPCO to meet the Hong Kong SAR Government’s
emission targets sooner than the Black Point option;
• South Soko requires less land reclamation, while its offshore pipeline to
Black Point results in only temporary environmental impacts of short
duration;
• The location of South Soko provides for very low numbers of surrounding
land and marine-based populations with exposure to both the terminal
and the marine transit and all aspects of the marine transit are acceptable
from a societal risk standpoint.
CAPCO believes that siting the LNG terminal on South Soko Island provides
an opportunity to enhance the island's marine and terrestrial environments
for the benefit of the community and would support a Soko Islands and
Southwest Lantau Marine Park. By assisting government through the
provision of initial funding for education and research to support the
establishment of the Parks, CAPCO believes it can create the necessary
stimulus to bring this conservation area to fruition.
39
0018180_EXEC SUMM_TEXT_FORMAL_V27_7 DEC 06.DOC 11 DEC 2006
LNG RECEIVING TERMINAL AND ASSOCIATED FACILITIES EXECUTIVE SUMM ARY
extensive marine studies as part of its EIA process, obtaining expert views
from well known and highly respected specialists in marine conservation.
CAPCO will provide access to those studies as part of any Enhancement Plan.
CAPCO has identified the following key possible enhancements through its
discussions with stakeholders and experts:
40
0018180_EXEC SUMM_TEXT_FORMAL_V27_7 DEC 06.DOC 11 DEC 2006
LNG RECEIVING TERMINAL AND ASSOCIATED FACILITIES EXECUTIVE SUMM ARY
at and around the Soko Islands. Such efforts could include the
production of educational materials that relate to the marine conservation
areas of Fan Lau and Soko Islands as well as the benefits of clean energy.
(1) AAHK's Aviation Fuel Receiving Facility located in the Lung Kwu Chau and Sha Chau Marine Park,
HK
(2) Dominion Cove Point Liquid Natural Gas, LP's LNG terminal operated within the Cove Point Natural
Heritage Trust, Chesapeake Bay, Maryland, USA
This environmental assessment report has been prepared in full compliance with the
requirements of the Study Brief and the EIAO Technical Memorandum. The overall
conclusion of the EIA report is that there is a clear need for a LNG terminal located in
Hong Kong and that, of all the potential alternatives examined, South Soko is the
preferred option. In accordance with the EIAO, CAPCO considers that this EIA
provides a suitable basis for the Director of Environmental Protection to consider
granting the Environmental Permit to allow the construction and operation of this
project at the South Soko Island site.
41
0018180_EXEC SUMM_TEXT_FORMAL_V27_7 DEC 06.DOC 11 DEC 2006
South West
Marine Park
Lantau
at Fan Lau
Marine Park
North
Soko
South
Existing Pier Potential Pier
Soko
Image from ‘Quarterly Bulletin of the Antiquities and
Monuments Office, Vol 4 No. 2’
Access will be maintained through a
replacement to the existing pier Establish a display of recovered artefacts
Education Recreation
Legend
Pier & Relocated Natural Heritage Existing Reservoir
Tin Hau Temple Displays
Provide facilities to support education Heritage Eco Trail
efforts on marine and terrestrial ecology Trail Opportunities for outdoor recreation
and cultural heritage features of Island
Landscape Architecture
SOUTH SOKO
& Urban Design
21 / F Lincoln House
979 Kings Road
Taikoo Place